major water environmental assessment report for …

65
MAJOR WATER ENVIRONMENTAL ASSESSMENT REPORT FOR AN UNDERWATER MEMORIAL PARK ST. THOMAS - ST. JOHN U. S. VIRGIN ISLANDS SUBMITTED TO THE OFFICE OF COASTAL ZONE MANAGEMENT DEPARTMENT OF PLANNING AND NATURAL RESOURCES GOVERNMENT OF THE VIRGIN ISLANDS U.S. ARMY CORPS OF ENGINEERS SUBMITTED BY UNDERWATER MEMORIAL, LLC PREPARED BY BIOIMPACT, INC. P.O. BOX 132 KINGSHILL ST. CROIX, U.S. VIRGIN ISLANDS 00851 AND UNDERWATER MEMORIAL, LLC APRIL 2021

Upload: others

Post on 15-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

MAJOR WATER

ENVIRONMENTAL ASSESSMENT REPORT

FOR

AN UNDERWATER MEMORIAL PARK

ST. THOMAS - ST. JOHN U. S. VIRGIN ISLANDS

SUBMITTED TO

THE OFFICE OF COASTAL ZONE MANAGEMENT

DEPARTMENT OF PLANNING AND NATURAL RESOURCES

GOVERNMENT OF THE VIRGIN ISLANDS

U.S. ARMY CORPS OF ENGINEERS

SUBMITTED BY

UNDERWATER MEMORIAL, LLC

PREPARED BY

BIOIMPACT, INC.

P.O. BOX 132 KINGSHILL

ST. CROIX, U.S. VIRGIN ISLANDS 00851

AND

UNDERWATER MEMORIAL, LLC

APRIL 2021

2

TABLE OF CONTENTS

Contents

1.00 Name and Address of Applicant ................................................................................ 1

2.00 Location of Project ..................................................................................................... 1

3.00 Abstract ...................................................................................................................... 3

4.00 Statement of Objectives Sought by the Proposed Project .......................................... 3

5.00 Description of the Project ........................................................................................... 4

5.01 Summary of Proposed Activity .............................................................................. 4

5.01a Purpose of Project ............................................................................................ 4

5.01b Presence and Location of Any Critical Areas and Possible Trouble Spots ..... 4

5.01c Proposed Methods of Construction ................................................................. 5

5.01d Provisions to Limit Site Disturbance ............................................................... 5

5.01e Sediment Control Methods to be Implemented ............................................... 5

5.01f Schedule for Construction Activities and Implementation of Sediment Control

Measures ................................................................................................................................ 5

5.01g Maintenance of Sediment and Siltation Control Measures ............................. 5

5.02 Exhibits and Drawings .......................................................................................... 5

5.03 Project Workplan .................................................................................................. 10

6.0 Environmental Setting and Probable Project Impacts ................................................ 10

6.01 Climate and Weather ............................................................................................ 10

6.02 Landforms, Geology, Soils, and Historic Use ................................................... 20

6.03 Drainage, Flooding, and Erosion Control ............................................................ 22

6.03a Impacts on Terrestrial and Shoreline Erosion ............................................... 22

6.03b Relationship of the Project to the Coastal Flood Plain .................................. 22

6.04 Freshwater Resources ........................................................................................... 22

6.05 Oceanography....................................................................................................... 23

6.05a Seabed Alteration........................................................................................... 23

6.05b Tides and Currents ......................................................................................... 23

6.05c Waves ............................................................................................................ 24

6.05d Marine Water Quality .................................................................................... 25

6.06 Marine Resources and Habitat Assessment......................................................... 28

6.07 Terrestrial Resources ............................................................................................ 32

6.08 Wetlands ............................................................................................................... 32

6.09 Rare and Endangered Species .............................................................................. 32

3

6.10 Air Quality............................................................................................................ 36

7.00 Impacts on the Human Environment ........................................................................ 37

7.01 Land and Water Use Plans ................................................................................... 37

7.02 Visual Impact ....................................................................................................... 37

7.03 Impact on Public Services .................................................................................... 37

7.03a Water............................................................................................................... 37

7.03b Sewage Treatment and Disposal .................................................................... 37

7.03c Solid Waste Disposal ...................................................................................... 37

7.03d Roads, Traffic and Parking ............................................................................. 37

7.03e Electricity ........................................................................................................ 37

7.03f Schools ............................................................................................................ 37

7.03g Fire and Police Protection .............................................................................. 38

7.03h Health ............................................................................................................. 38

7.04 Social Impacts ...................................................................................................... 38

7.05 Economic Impact.................................................................................................. 38

7.06 Impacts on Historical and Archeological Resources............................................ 38

7.07 Recreational Use .................................................................................................. 38

7.08 Waste Disposal ..................................................................................................... 38

7.09 Accidental Spills .................................................................................................. 38

7.10 Potential Adverse Effects Which Cannot Be Avoided......................................... 39

8.00 Mitigation Plans ....................................................................................................... 39

9.00 Alternatives to Proposed Action .............................................................................. 39

10.00 Relationship Between Short Term and Long Term Uses of Man’s Environment . 39

11.00 REFERENCES ....................................................................................................... 39

Appendix I

Qualification Statement

Bioimpact, Inc.

Appendix II

Inspection Plan

1

1.00 Name and Address of Applicant

Underwater Memorial, LLC

4600 Estate Charlotte Amalie, Suite 201

Charlotte Amalie, U.S. Virgin Islands 00802

P.O. Box 8058

Charlotte Amalie, U.S. Virgin Islands 00801

2.00 Location of Project

The Underwater Memorial Park is proposed to encompass a 40-acre area to the north

of Lovango Cay and to the east of Congo Cay encompassing areas of reef and open

sand. The parks boundaries would be:

Latitude Longitude

18.3668764°N -64.809037°W

18.363296°N -64.808984°W

18.363256°N -64.813114°W

18.366840°N -64.813018°W

Marker buoys will be place at the locations shown above. The mooring buoys would be

placed at:

Latitude Longitude

18.366178°N -64.809838°W

18.364582°N -64.809578°W

The following location maps depict the mooring site in reference to adjacent cays, and

vicinity in the U.S. Virgin Islands.

2

Figure 2.00.1 Location of Proposed Memorial Park

Figure 2.00.1 Location of Boundary Markers and Moorings

Congo

Lovango

3

Figure 2.00.3 Location of Project in the U.S. Virgin Islands

3.00 Abstract

Underwater Memorial, LLC is proposing to create a Virgin Islands Underwater Memorial Park.

The idea is to create a beautiful underwater memorial park where people can have their ashes

incorporated into small structures which will serve as hard substrate for coral colonization and as

attachment points for coral propagation. The area requested is 40 acres, however the actual

“interment” will be less than 20 acres. The reason for the size of the requested is so that the park

can be eligible for inclusion in several organization which specialize in low impact natural

burials. This provides Underwater Memorial, LLC to project coral reef resources within the 40-

acre park.

Ashes would be incorporated into coral shaped markers which would be installed by divers.

The structures would be place in an area of open sand and no closer than 20ft from any

hardbottom or coral. There are no seagrass resources within the area of open sand. The park

boundary would be approximately 250’ off Congo Cay and 250’ off Lovango. The actual

interment area is located amid the surrounding coral reefs. The area would prohibit anchoring

and would provide two moorings for families wishing to visit their loved ones.

4.00 Statement of Objectives Sought by the Proposed Project

The objective of the application is to provide Virgin Islanders and others with an

affordable alternative to burial which help enhance the marine environment by

providing substates for coral propagation.

4

5.00 Description of the Project

5.01 Summary of Proposed Activity

Ashes will be incorporated into a variety of structural shapes which will be attached to a

screw anchor and have a hole through it which will allow for easy installation. The

structure will be made so the eye of the screw anchor is within the turning access.

Structures would only be deployed every several months based on demand to minimize

cost and seafloor disturbance so it is probable that several structures will be installed at

the same time. Prior to any deployment the two mooring buoys and boundary markers

would be installed using helix anchors and floating lines. Both the boundary markers and

the mooring buoys will state that the area is a memorial park, and no anchoring is

allowed.

Divers will carry the prepared internment structures to the site and install them within the

park. If the individual or the family would like coral to be planted on the structure,

Underwater Memorial, LLC is developing an MOU with the University of the Virgin

Islands to plant corals being raised by the University of the Virgin Islands on to the

structures. The structures have been designed so that they will extend up from the sand

to provide suitable substrate, and a study conducted over the last 6 months has shown

there is adequate sand depth and sand movement in the open sand area is minimal during

normal sea conditions. An Inspection Plan is proposed that will provide periodic

inspection to ensure that markers remain stable and to make any repairs and adjustments

which may be required, and to collect any debris which may have been deposited in the

area.

5.01a Purpose of Project

The objective of the application is to provide Virgin Islanders and others who wish to be

interned in beautiful clear offshore water with an affordable alternative to burial.

5.01b Presence and Location of Any Critical Areas and Possible Trouble Spots

There are coral reefs within the proposed Memorial Park which contain ESA listed coral

species, when boundary markers are proposed, since these will be in reef areas, they will

be placed so they avoid all corals, including ESA species and so that their floated lines

will not impact soft or hard corals.

The actual interment area is an area of uncolonized open sand. A concern has been raised

related to the movement of sand within the area. A six month survey has found that

minimal sand movement occurs under normal sea conditions, including through the

heavy winter swells.

It is possible more significant sand movement may occur during major storm events. An

Inspection plan is proposed to conduct any necessary maintenance which may be required

and to pick up any debris which may end up in the area.

5

5.01c Proposed Methods of Construction

The structures will be constructed on land and then installed every several months

depending on need. Moorings, marker buoys and structures will be installed by divers.

5.01d Provisions to Limit Site Disturbance

The internment structures will be placed no closer than 20ft to adjacent reefs or corals.

A marker buoys, and moorings will use helix type anchors with floated lines to prevent

bottom disturbance.

Installation will occur every few months based on demand to minimize bottom

disturbance.

5.01e Sediment Control Methods to be Implemented

The proposed moorings, markers and interment structures will have negligible short-term

turbidity impacts during diver installation therefore no sediment controls are necessary.

5.01f Schedule for Construction Activities and Implementation of Sediment Control

Measures

The proposed activity will have negligible turbidity impacts therefore no sediment

controls are necessary.

5.01g Maintenance of Sediment and Siltation Control Measures

The proposed activity will have negligible short-term turbidity impacts therefore no

sediment controls are necessary.

5.02 Exhibits and Drawings

Drawing Page

Location Plan 6

Bathymetric Map 7

Structure Examples 8

Mooring and Marker Details 9

6

7

8

Potential Structures and Anchoring Configuration

9

10

5.03 Project Workplan

• Divers Install boundary buoys and moorings

• Interment Structures are installed every few months based on demand

• Corals are transplanted on to structures if desired

6.0 Environmental Setting and Probable Project Impacts

6.01 Climate and Weather

Prevailing Winds

The Virgin Islands lie in the "Easterlies" or "Trade Winds" which traverse the southern

part of the "Bermuda High" pressure area, thus the predominant winds are usually from

the east-northeast and east (IRF, 1977). These trade winds vary seasonally and are

broadly divided into 4 seasonal modes: 1) December to February; 2) March to May; 3)

June to August; and 4) September to November. Below are the characteristics of these

modes as taken from Marine Environments of the Virgin Islands Technical Supplement

No. 1 (IRF, 1977).

December - February

During the winter the trade winds reach a maximum and blow with great regularity from

the east-northeast. Wind speeds range from eleven to twenty-one knots about sixty

percent of the time in January. This is a period when the Bermuda High is intensified

with only nominal compensation pressure changes in the Equatorial Trough. The trade

winds during this period are interrupted by "Northerners" or "Christmas Winds" which

blow more than twenty knots from a northerly direction in gusts from one to three days.

Such outbreaks average about thirty each year. They are created by strengthening of

high-pressure cells over the North American continent, which, in turn, allow weak cold

fronts to move southeastward over the entire Caribbean region. These storms are

accompanied by intermittent rains, clouds and low visibility.

March - May

During the spring, the trade winds are reduced in speed and blow mainly from the east.

Winds exceed twenty knots only thirteen percent of the time in April. The change in

speed and direction is the result of a decrease of the Equatorial Trough.

June - August

Trade winds reach a secondary maximum during this period and blow predominantly

from the east to east-southeast. Speeds exceed twenty knots twenty-three percent of the

time during July. The trend for increasing winds results from the strengthening of the

Bermuda High and a concurrent lowering of the pressure in the Equatorial Trough. Trade

winds during this period are interrupted by occasional hurricanes.

11

September - November

During the fall, winds blow mainly from the east or southeast and speeds reach an annual

minimum. Only seven percent of the winds exceed twenty knots in October. The low

wind speeds result from a decrease in the Equatorial Trough. During this period,

especially during late August through mid-October, the normal trade wind regime is often

broken down by easterly waves, tropical storms and hurricanes.

Storm and Hurricanes

There are numerous disturbances during the year, especially squalls and thunderstorms.

These occur most frequently during the summer, lasting only a few hours and causing no

pronounced change in the trade winds.

A tropical cyclone whose winds exceed 74 miles per hour is termed a hurricane in the

northern hemisphere, and significantly affects the area. These hurricanes occur most

frequently between August and mid-October with their peak activity occurring in

September. The annual probability of a cyclone used to be one in sixteen years (Bowden,

1974). However, the Virgin Islands were hit with two Category V hurricanes within a

two-week period in 2017 and a category 1 hurricane in 2019.

Hurricane wind data for the barge site was obtained from the HURDAT2, which contains

tropical storm and hurricane information from 1851 to 2019, and the NOAA hurricanes

website (https://coast.noaa.gov/hurricanes/26.03). According to the NOAA Historical

Hurricane Tracks Tool, a total of 258 storms (hurricanes, tropical storms, and tropical

depressions) have passed within 200 nautical miles of the barge location dating back to

1867 as shown in the figure below. Of the 258 storms, 38 were considered Major

Hurricanes (Cat 3 or greater) and are presented in the figure below.

12

Figure 6.01.1. Tidal Datums and extreme water levels Station relative to VIVD09 -

Station 9751639

Figure 6.01.2. Tidal Datums and extreme water levels Station relative to VIVD09 -

Station 9751639

13

Table 6.01.3 Return frequency of storms

Climate

The average annual rainfall on St. Thomas and St. John is approximately 45 inches,

ranging from 35 inches toward the eastern end of the islands to more than 55 inches at the

higher elevation to the west. Rainfall usually occurs in brief, intense showers of less

than a few tenths of an inch and major rainfall events are associated with weather systems

(USGS 1998). The Virgin Islands have no sharply defined wet season. The wettest

period generally is from September to November, and the driest period is from January to

June (USGS 1998).

Return Period, years

Wind Speed, kt Hurricane Category

Best-fit 95% non-exc. 5% non-exc. Saffir-

Simpson

5 95.68 101.27 90.09 3

10 117.20 124.22 110.19 4

25 135.41 144.88 125.94 5

50 146.30 157.49 135.12 5

100 155.81 168.57 143.05 5

14

Figure 6.01.4 Total Precipitation East End St. Thomas 1981-2010, 3.22 miles from

proposed Memorial Park site. (https://www.weather.gov)

The difference between the mean temperatures of the coolest and warmest month is only

5 to 7 degrees F. The highest temperatures August or September and the lowest are in

January or February. The highest average daytime temperature in the warmest months is

about 88 degrees F, and in the coolest months is in the low 80’s. Nighttime lows are

usually in the mid 70’s during the warmer months and in the high 60’s during the cooler

months (USGS 1998). In general, air temperature in the Virgin Islands ranges between

77 degrees and 85 degrees.

15

Figure 6.01.5 Wind Roses from the USACE showing the predominant easterly trade

winds from the two closest buoys.

16

Figure 6.01.6Wind averages (https://weatherspark.com/y/28234/Average-Weather-

inCharlotte-Amalie-U.S.-Virgin-Islands)

Figure 6.01.7 Tropical Cyclone Frequencies in the Atlantic (National Weather Service)

17

Figure 6.01.8 Tropical Storm and Hurricane Occurrences in the Atlantic (National

Weather Service)

18

19

Figure 6.01.9 Climate averages (https://weatherspark.com/y/28234/Average-Weather-

inCharlotte-Amalie-U.S.-Virgin-Islands)

Impact on Project

The project is at a depth of 40ft and therefore there should be negligible impact from

storms except for the most severe sea conditions. An Inspection Plan is proposed to

check on the site after storm events to make any repairs or cleanup necessary.

20

6.02 Landforms, Geology, Soils, and Historic Use

GEOLOGY OF ST. THOMAS

The Virgin Islands are near the northeastern corner of the present Caribbean Plate, a

relatively small trapezoidal-shaped plate that is moving eastward relative to the North and

South American continents carried on the American plate. The arc of the Lesser Antilles

is an active volcanic arc above a subduction zone in which the Atlantic oceanic crust of

the American Plate is carried downward under the Caribbean Plate. The closest volcano

to the Virgin Islands that is still active is Saba, about 160 km. to the east.

St. Thomas is composed of stratified volcanic and volcaniclastic rocks with minor

limestone of the Early Cretaceous (Albain) to possibly the late Cretaceous Age (Donnelly

1966). These rocks are granitic composition, some of which may be as young as Tertiary

(Kesler and Sutter, 1979). The oldest rocks of St. John are submarine lavas (keratophyre

and spilite), beds of volcanic debris and chert. Associated intrusive rocks of the Water

Island Formation is overlain by andesitic volcanic and volcaniclastic rocks of the

Louisenhoj Formation which underlies the island of St. Thomas to the east and much of

the northwestern portion of St. John. Donnelly (1966) suggested that the Louisenhoj

Formation was deposited unconformably on the Water Island Formation after a period of

emergence, tilting and erosion, on the slopes and environs of a subaerial volcanic island

located roughly between St. Thomas and St. John, an area now occupied by Pillsbury

Sound. The youngest layered deposits on St. Thomas are volcaniclastic rocks of the Tutu

Formation. Fossils contained in the Tutu Formation suggest that those deposits are of the

Early Cretaceous (Albain) Age (Donnelly et. al. 1971). It appears that all of the

volcaniclastic rocks of St. Thomas were deposited in a relatively short period of time

spanning 10 to 15 million years approximately 100 million years ago (D. Rankin 1988).

GEOLOGY OF PROPOSED PARK SITE

The project site is located offshore in what is considered the Altantic Ocean since it is

north of Lovango Cay. The site lies to the north of Lovango and to the southeast and

east of Congo. The adjacent cays are both steep and rocky and water depths at the

proposed project site are approximately 40ft, The seafloor is sandy in the proposed

internment location and coral reefs surround the area to the north, south, east and west.

An assessment was made in the proposed footprint of the interment area to look at sand

depth and change over time.

Tag

Lat

Lon

Dep

th (

ft.)

Dat

e

Mea

sure

(in)

Dat

e

Mea

sure

(in)

Chan

ge (i

n)

Chan

ge (c

m)

Dat

e

Mea

sure

(in)

Chan

ge (

in)

Chan

ge fr

om la

st m

onito

ring

(cm

)

Chan

ge fr

om M

onth

1 (i

n)

Chan

ge fr

om M

onth

1 (c

m)

Dat

e

Mea

sure

(in)

Chan

ge fr

om la

st m

onito

ring

(in)

Chan

ge fr

om la

st m

onito

ring

(cm

)

Chan

ge fr

om M

onth

1 (i

n)

Chan

ge fr

om M

onth

1 (c

m)

6 18.36578 64.8089 2.1 11/20/2020 55.375 12/9/2020 54.2 1.175 2.9845 1/20/2020 53 1.2 3.048 2.375 6.0325 4/12/2021 53.5 -0.5 -1.27 1.875 4.7625

10 18.36561 64.80879 3.9 11/20/2020 56.75 12/9/2020 57.7 -0.95 -2.413 1/20/2020 57.1 0.6 1.524 -0.35 -0.889 4/12/2021 56.2 0.9 2.286 0.55 1.397

no tag 18.36536 64.80886 2.5 11/20/2020 55.25 12/9/2020 57 -1.75 -4.445 1/20/2020 58 -1 -2.54 -2.75 -6.985 4/12/2021 57.4 0.6 1.524 -2.15 -5.461

11 18.36546 64.80866 2.8 11/20/2020 57.5 12/9/2020 61.2 -3.7 -9.398 1/20/2020 60 1.2 3.048 -2.5 -6.35 4/12/2021 59.6 0.4 1.016 -2.1 -5.334

12 18.36578 64.80928 3.8 11/20/2020 52.5 12/9/2020 54.3 -1.8 -4.572 1/20/2020 55 -0.7 -1.778 -2.5 -6.35 4/12/2021 54.5 0.5 1.27 -2 -5.08

13 18.36547 64.80913 4.5 11/20/2020 54.375 12/9/2020 55 -0.625 -1.5875 1/20/2020 55.9 -0.9 -2.286 -1.525 -3.8735 4/12/2021 56.2 -0.3 -0.762 -1.825 -4.6355

14 18.36562 64.80921 4.6 11/20/2020 57 12/9/2020 56.4 0.6 1.524 1/20/2020 55.2 1.2 3.048 1.8 4.572 4/12/2021 56 -0.8 -2.032 1 2.54

15 18.3657 64.80906 5 11/20/2020 56 12/9/2020 55.3 0.7 1.778 1/20/2020 54.7 0.6 1.524 1.3 3.302 4/12/2021 55.4 -0.7 -1.778 0.6 1.524

no tag 18.36593 64.80916 4.1 11/20/2020 54.25 12/9/2020 54 0.25 0.635 1/20/2020 54.5 -0.5 -1.27 -0.25 -0.635 4/12/2021 53.7 0.8 2.032 0.55 1.397

21

HISTORIC USE

The area is within a passage which is used by boaters.

ADVERSE SITE CONDITIONS

The project site has a direct northern exposure and is protected from seas from the south.

The project site is within flood zone VE10 where it has been determined that the 100-

year flood elevation with velocity will be 10ft as shown on FIRM map 16 of 94.

Figure 6.02.1. FEMA FIRM Map Panels 16 of 94.

Coastal flooding will have no impact on impact the project.

The U.S. Virgin Islands lie in one of the most earthquake prone areas of the world, and

are susceptible to ground shaking, earthquake-induced ground failures, surface fault

ruptures and tsunamis (tidal waves) (Hays, 1984). The activity is mostly associated with

large-scale tectonic activity or faulting, originating in the Anegada Trough to the

northeast of the islands. The trough and its related scarp apparently were thrown up by

block faulting during the late Pliocene or early Pleistocene. It is oriented generally

northeast to southwest, separating St. Croix from Puerto Rico and the other Virgin

Islands. Based on shallow focus earthquakes, the Anegada Fault Trough is estimated to

22

be more than 400 miles in length. There are indications that strike slip movement is

occurring, with St. Croix shifting northeast relative to Puerto Rico (Puerto Rico Water

Authority 1970). The year 2021 marks the 154th anniversary of the last major

earthquake in the islands. This quake, which occurred on November 18, 1867 had an

identified intensity of VIII on the Modified Mercalli Scale. Earthquakes of this

magnitude have generally been associated with epicentral ground accelerations of

between 0.05 and 0.35 gravities. Since the 1868 quake, there has been continuous low

intensity activity, all below 6.5 Richter. Thousands of tiny earthquakes are encountered

every year on the island.

IMPACT OF PROJECT

The project will utilize sand screws and helix type screws to install buoy markers,

moorings and the internment structures. Measurements were made of the sand within the

proposed interment site and depths were between 25” nearest the reef, and between 30”-

60” in the interment area and mooring buoy locations. The boundary marker buoys will

be placed in small sand patches within the area of reef and may require rock pins due to

the shallowness of the sand veneer over rock.

Measurement were taken over 6 months at 9 locations to look at sand movement in the

interment area. The greatest gain was 1.875” and the greatest loss was 2.15”. This study

encompassed the winter months which typically has large northern swell.

6.03 Drainage, Flooding, and Erosion Control

6.03a Impacts on Terrestrial and Shoreline Erosion

The proposed Memorial Park is offshore and does not involve the installation of any

significant structures which would have any impact on coastal processes.

6.03b Relationship of the Project to the Coastal Flood Plain

The memorial park site is within flood zone VE10 where it has been determined that the

100-year flood elevation with velocity will be 10ft as shown on FIRM map 16 of 94

(Figure 6.02.1). This should have no impact on the proposed project.

6.04 Freshwater Resources

The proposed memorial park will have no impact on freshwater resources due to its

location in the marine environment.

23

6.05 Oceanography

6.05a Seabed Alteration

The project involves the installation of 6 helix type anchors for the placement of two

moorings and 4 boundary markers. The interment structures which will be installed by

divers will utilize screw anchors.

6.05b Tides and Currents

The Virgin Islands coastal areas are not subject to significant tidal ranges or tidal currents.

Due to the small size of the cays, the sea flows around the cays causing an average tidal

height of only a few inches and maximum change of only a little over a foot. Only very

narrow intertidal zones are found because of this lack of tidal amplitude and the steepness

of the cays rising out of the sea. The tides at the proposed Memorial Park site are primarily

semi-diurnal in nature, with two cycles of high and two of low water every 24 hours. The

second cycle is often indistinguishable. The mean tides range from 0.8f. to 1.0 ft and the

spring tidal ranges reach up to 1.3ft (IRF 1977). NOAA operated a tide gauge at Lovango

Cay (VI 9751467) which is the cay just south of the proposed park. The tide gauge was

installed on April 20, 2011 and maintained the station until August 30, 2011. The mean

tidal range was 0.61 ft. and the diurnal range 1.06ft.

The Charlotte Amalie Station has been recording water levels since 1975. The high tide

recorded on September 18, 1989 (Hurricane Hugo) was +3.35ft, and in 1995 during

Hurricane Marilyn the Charlotte Amalie tide station recorded the highest tide height 3.98ft

above Mean Lower Low Water (MLLW). The lowest tide recorded was on February 6,

1985 and was -1.44ft. The tidal ranges of the Charlotte Amalie station are as follows:

Mean Higher High Water 1.09ft

Mean High Water 0.94ft

Mean Tide Level 0.54ft

Mean Sea Level 0.52ft

Mean Low Water 0.13ft

Mean Lower Low Water 0.0ft

The nearest active Tide Station is Leinster Point, Leinster Bay, St. John (Station ID:

9751309) the station is located at latitude 18° 22.1N and longitude 64° 43.2’ W and has a

mean tidal range of 0.78 ft and a diurnal range of 1.12 ft.

24

Figure 6.05.1. Tidal data from the Leinster Point, Leinster Bay Tidal Station (NOAA

Buoys)

The surface currents throughout the Caribbean are driven by the North Equatorial Current

that runs through the islands west-northwest and then joins the Gulf. These currents

change very little from season to season with the currents coming more from the south

during the summer months. Because of the shallowness of the Caribbean basin of less

than 1000m, mainly surface water from the Atlantic flows through the islands. The

westerly drift of the Caribbean Current sweeps into Pillsbury Sound from the Southeast,

seeking a way North through the barrier set up by the Cays to discharge along the North

Shore of St. Thomas and out into the Atlantic. The current flows past the north side of

Lovango in a westerly direction year-round.

There are often strong currents between Congo and Lovango Cay. This will not affect

the proposed project.

6.05c Waves

The deep-water waves at the memorial park site are primarily driven by the northeast

trade winds that blow most of the year (Figure 6.05.1). Waves average from 1 to 3ft from

the east, 42% of the time throughout the year (IRF, 1977). For 0.6% of the time easterly

waves reach 12ft in height. The southeasterly swell with waves one to twelve feet high

become significant in late summer and fall when the trade winds blow from the east or

when tropical storms and hurricanes pass the islands at a distance to the south. During

the winter months, long length, long period northern swells develop to a height of 1 to 5

feet. The USACE Hindcast Studies for buoy 61020, the buoy whose waves patterns

should be most similar to the memorial park site, show that a majority of the waves

which occurred approach from easterly directions. Congo Cay provides protection from

this direction.

25

6.05d Marine Water Quality

Water quality at the proposed park site is pristine. The area enjoys excellent water

quality and receives good circulation from currents running through the scattered islands

and cays.

Turbidity in the area is affected by wave approach and during periods of rough sea there

can be areas of turbidity extending off shore due to the re-suspension of sand in the

shallows.

Turbidity measurements were taken at the site during the monitoring of the sand stakes.

The readings were all low, ranging from a low of 0.19NTU to a high of 0.36NTU. The

bottom at 40ft was visible on all visits to the site.

The offshore waters are classified as Class B and the best usage of the water is listed as

the propagation of desirable species of marine life and for primary contact recreation

(swimming, water skiing, etc.). The quality criteria include, dissolved oxygen not less

than 5.5mg/l from other than natural conditions. The pH must not vary by more than 0.1

pH unit from ambient; at no time, shall the pH be less than 7.0 or greater than 8.3.

Bacteria (fecal coliform) cannot exceed 70 per ml, and turbidity should not exceed a

maximum nephelometric turbidity unit of three (3) NTU.

IMPACT OF PROPOSED PROJECT

Installation of the boundary markers and moorings will have a negligible short-term

impact due to divers disturbing the seafloor. Sand will be suspended and will quickly

settle.

The interment structures will be installed every several months based on demand, and

during the diver installation sand will be suspended and will quickly settle. The project

will have no impact on water quality.

26

Figure 6.05.1. Prevailing currents in the Caribbean, IRF 1975.

Figure 6.05.2 Prevailing currents off St. John, IRF 1975.

27

Figure 6.05.3. Wave Roses from the USACE Wave Information Studies for buoy 61020.

28

6.06 Marine Resources and Habitat Assessment

The proposed Memorial Park encompasses 40 acres to the north of Lovango Cay and

southeast of Congo Cay. It encompasses approximately 20 acres of reef and 20 acres of

open sand. The interments will occur in areas of open sand a minimum of 10ft from the

adjacent reef areas. The reefs have a large variety of corals including ESA listed

species.

Benthic Community Survey Methods

Benthic surveys were undertaken starting in July of 2020 with periodic surveys occur

through April 2021. Belt transects were swam and species identified within both the

reef and open sand areas. The sandy area was measured for sand depth to ensure

enough depth to install the memorial markers. Divers in combination with a vessel

mounted GPS were used to confirm reef/hardbottom edges.

Figure 6.06.1 provides the Benthic Habitat Map provided by NOS, NOAA. The NOS

Benthic Habitat Map shows the mooring as open sand and reef colonized pavement.

Figure 6.06.1 NOS Benthic Habitat Map

29

Figure 6.06.2 Transects and benthic habitats found within the vicinity of the

barge mooring.

The Benthic Community

Sand

There is a large area of open sand which have scattered diatom coats. The sand is 99%

uncolonized. Because of changes in the topography of the rock beneath the sand there

are an occasional hard coral near the edges as well as soft corals species. Seen were

Diploria labyrinthiformis, Porites astreoides, Psuedodiploria strigosa,

Pseudopterogorgia americana, Pseudopterogorgia rigida, Pterogorgia anceps,

Pterogorgia citrina, Pterogorgia guadalupensis, Pseudopterogorgia bipinnata and

Eunicea mammosa.

The sand is uncolonized with scattered diatoms on the surface.

Reefs

The surrounding reefs are coral colonized emergent pavement, more so the reefs rise

approximately1 ft above the seafloor and their relief is added to by the colonizing corals.

Soft corals are very abundant and are more abundant than hard coral species. There are

30

scattered sand channels within the pavement, but most are relatively narrow. The table

below list the corals which were noted on the hardbottom habitat.

Some of the soft corals extend into surrounding sand. The soft corals form a forest in

many areas of the reef.

Nurse sharks were seen frequently during surveys. Scattered hard corals are found amid

the soft corals.

The soft corals cover most of the emergent rock.

31

Xestospongia muta (basket sponges) were found amid the soft corals.

There is a small emergent hardbottom in the largest sand area.

Species noted Species noted

Stony Corals Soft Corals (cont.)

Acropora cervicornis Eucinea spp.

Orbicella annularis Pterogorgia guadalupensis

Orbicella franksi Pseudopterogorgia americana

Orbicella faveolata Pseudopterogorgia rigida

Dendrogyra cylindrus Pterogorgia anceps

Siderastrea siderea Eunicea mammosa

Agaricia fragilis Pseudopterogorgia bipinnata

Porites astreoides Pterogorgia citrina

Meandrina meandrites Pterogorgia guadalupensis

Pseudodiploria strigosa Gorgonia ventalina

Diploria labyrinthiformis Gorgonia flabellum

Agarica agaricites Palythoa caribbaeorum

Porites porites Erythropodium caribaeorum

Sephanocenia intersepta Sponges

Siderastrea radians Xestospongia muta

Montastrea cavernosa Ircinia strobilina

Dichocoenia stokesii Callispongia vaginalis

Eusmilia fastigiata Agelas confera

Madracis decactis Aplysina fulva

Soft Corals Aplysina cauliformis

Pseudoplexaura flagellosa Verongula gigantea

Plexaurella nutans Callyspongia plicifera

Plexaura flexuosa Neofibularia nolitangere

32

Impact of Interment Structures, Boundary Markers, and Moorings

The selected location for the internment structures and the boat moorings are uncolonized

There should be no negative impacts. The structures will be introducing hard substrate

which will in time become colonized and there will be the opportunity to have corals

transplanted on to the structures by UVI from their coral nursery. The project will also

be encompassing large areas of reef in an area where anchoring will be restricted and this

should help minimize coral impacts in the future.

6.07 Terrestrial Resources

All project components are located offshore and therefore the project will have no direct

impact on the terrestrial environment. The project will also be lessening the need for

burial sites and therefore has a positive impact on the terrestrial environment

6.08 Wetlands

The U.S. Army Corps of Engineers defines wetlands as "those areas that are periodically

inundated or saturated by surface or groundwater at a frequency and duration sufficient

to support, and under normal circumstances do support, a prevalence of vegetation

typically adapted for life in saturated soil conditions. Wetlands generally include

swamps, bogs, marshes and similar areas." (U.S. Army Corps of Engineers, 1986).

The project is located offshore and will have no impact on any terrestrial wetlands.

6.09 Rare and Endangered Species

Three rare or endangered sea turtle species; hawksbill turtles (Eretmochelys imbricata)

green turtles (Chelonia mydas) and leatherback turtles (Ermochelys coriacea) occur in

the area. NOAA’s Vessel Strike Avoidance Measures and Reporting for Mariners will be

implemented by all vessels associated with the project.

The surrounding reefs and the marine habitats in the wider area have abundant coral

resources. There are numerous ESA listed corals species offshore of both Lovango and

Congo Cay.

Acropora palmata, A. cervicornis, Orbicella annularis, O. franksi and O. faveolata as

well as Dendrogyra cylindrus are present in the wider area.

The Nassau grouper (Epinephelus striatus) was seen during the surveys and a Humpback

whales (Megaptera novaeangliae) have also been seen off Lovango.

33

Table 6.09.1. ESA Threatened and Endangered Species Potentially Occurring in the

Greater Project Area

Scientific Name Common Name Status

Acropora palmata Elkhorn coral T

Acropora cervicornis Staghorn coral T

Orbicella annularis Lobbed Star coral T

Orbicella faveolata Mountainous star coral T

Orbicella franksi Boulder star coral,

Dendrogyra cylindrus Pillar coral T

Mycetophyllia ferox Rough Cactus Corals T

Eretmochelys imbricata Hawksbill sea turtle E

Dermochelys coriacea Leatherback sea turtle E

Chelonia mydas Green sea turtle T

Caretta caretta Loggerhead sea turtle T

Trichechus manatus manatus West Indian manatee E

Megaptera novaeangliae Humpback whale E/D2

Balaenoptera physalus Finback whale E

Epinephelus striatus Nassua grouper T

Manta birostris Giant Manta Ray T

Sphyma lewini Scalloped

Hammerhead T

Carcharhinus longimanus Oceanic Whitetip

Shark T

Coastal waters and waters within the Virgin Islands are frequented by whales (Megaptera

novaeangliae, Balaenoptera physalus) during winter for mating and birthing and dolphins

(Tursiops truncates) are year-round residents.

Four species of sea turtles occur in the Virgin Islands and all four have been seen during

surveys for other projects in the greater project area. These include two threatened species,

the green turtle (Chelonia mydas) and the loggerhead (Caretta caretta), and two

endangered species, the hawksbill turtle (Eretmochelys imbricata) and the leatherback

turtle (Dermochelys coriacea).

The endangered Antillean manatee (Trichechus manatus manatus) has recently been seen

in the U.S. Virgin Islands after not being seen for many years so it is included in this

assessment.

The greater project contains areas considered Essential Fish Habitat (EFH) and species

managed by the Caribbean Fisheries Management Council (CFMC) occur within the

greater Project Area (see Table 6.09.2).

34

Table 6.09.2 Species managed by CFMC occurring in the nearshore area in the Virgin Islands.

Scientific Name Common Name

Cnidarians All corals

Strombus gigas Queen conch

Panulirus argus Spiny lobster

Epinephelus struiatus Nassau grouper

E. guttatus Red hind

E. fulvus Coney

Ocyurus chrysurus Yellowtail snapper

Lutjanus analis Mutton snapper

L. apodus Schoolmaster

L. gruiseus Grey snapper

L. vivanus Silk snapper

Chaetodon striatus Butterflyfish

Holocentrus ascensionis Squirrel fish

Haemulon plumieri White grunt

Balistes vetula Queen triggerfish

Malacanthus plumieri Sandtilefish

Sparisoma chrysopterum Redtail parrotfish

Lactophrys quadricornis Trunkfish

- Sharks and Tunas

- Swordfish and Billfishes

POTENTIAL PROJECT IMPACTS

The selected location for the internment structures and boat moorings are uncolonized

sand and the boundary moorings will be placed so that they avoid hard bottom and any

corals.

The project should not directly impact any endangered species. Anchoring will be

prohibited in the park and this should help protect resources.

Sea Turtles - Hawksbill (Eretmochelys imbricata), Leatherbacks (Dermochelys coriacea)

and Green turtles (Chelonia mydas), Loggerheads (Caretta caretta)

Potential Impacts

Turtles are present in the project area, but no nesting beaches will be impacted.

35

Mitigation Measures

Project vessels will also observe turtle avoidance protocols (NOAA guidance). Impacts to

turtles are not expected to occur with the application of avoidance and mitigation

measures.

Nassau Grouper (Epinephelus striatus)

These fish occur in the project impact area but will not be directly or indirectly impacted.

Sharks and Rays: Giant Manta Ray (Manta birostris), Scalloped Hammerhead (Sphyma

lewini), Oceanic Whitetip Shark (Carcharhinus longimanus)

These species are unlikely to occur in the project area, and if any of these animals are

seen during the mooring or internment structure installation, it is probable that they will

move away from the activities. There should be no impacts to these animals.

Marine Mammals: Whales, Dolphins, and West Indian Manatee (Trichechus manatus)

These species may occur in the impact area, and if any of these animals are seen during

the mooring or internment structure installation it is probable that they will move away

from the activities. Therefore, impacts to marine mammals will be avoided.

CONCLUSIONS – EFFECTS DETERMINATIONS

Corals

Elkhorn (Acropora palmata) Staghorn (Acropora cervicornis): The project avoids all

Acropora colonies and their critical habitat. The project will have no effect acropoid

corals. Lobbed Star coral (Orbicella annularis) Mountainous star coral (Orbicella

faveolata), Pillar coral (Dendrogyra cylindrus), Boulder star coral (Orbicella franksi),

Rough cactus coral (Mycetophyllia ferox): The project avoids all Lobbed Star coral,

Mountainous star coral, Boulder star coral, Rough cactus coral and Pillar coral. The

project will have no effect these corals.

Nassau Grouper (Epinephelus striatus)

The project will have no effect on Nassau groupers.

Sea Turtles - Hawksbill (Eretmochelys imbricata), Leatherbacks (Dermochelys coriacea)

and Green turtles (Chelonia mydas)

The project should not have a direct impact on these species. During mooring and

internment structure installation there is the potential for vessel strikes, NOAA guidelines

will be implemented to minimize this potential. The project has been designed no impact

to their foraging habitat.

36

Spotters will be used on the vessels during mooring installation operations to minimize

potential strikes.

The project may affect, but is not likely to adversely affect sea turtle species.

Sharks and Rays: Giant Manta Ray (Manta birostris), Scalloped Hammerhead (Sphyma

lewini), Oceanic Whitetip Shark (Carcharhinus longimanus)

The project should not have a direct impact on these species. These are large open water

species which should move away from the areas of any activity. Spotters will be used on

the vessels during mooring installation to minimize potential strikes.

The project will have no effect on shark or ray species.

Marine Mammals-Whales and Dolphins

The project should not have a direct impact on these species. During mooring

installation and operations there is a potential for vessel strikes. NOAA guidelines will be

implemented to minimize this potential.

The project may affect, but is not likely to adversely affect whales or dolphins.

West Indian manatee (Trichechus manatus)

The project is not expected to impact this species. During mooring installation there is a

potential for vessel strikes. NOAA guidelines will be implemented to minimize this

potential. The project has been designed to avoid impacts to their foraging habitat.

The project may affect, but is not likely to adversely affect the West Indian manatee.

Essential Fish Habitat

Essential Fish Habitat is present around both cays, and the project is in a sandy bottom

area. The project involves the placement of helix anchors and screw anchors.

The project should have no effect on Essential Fish Habitat.

6.10 Air Quality

All of St. John and St. Thomas is designated Class II by the Environmental Protection

Agency in compliance with National Ambient Air Quality Standards. In Class II air

quality regions the following air pollutants are regulated; open burning, visible air

37

contaminants, particulate matter emissions, volatile petroleum products, sulfur

compounds, and internal combustion engine exhaust (Virgin Islands Code Rules and

Regulations).

The project will utilize small vessels for the installation of the moorings and internment

structures, the project will have a negligible impact on air quality.

7.00 Impacts on the Human Environment

7.01 Land and Water Use Plans

In the U.S. Virgin Islands offshore water are not zoned. Lovango Cay is zoned R-1.

Congo Cay is not zoned since it is a wildlife sanctuary.

7.02 Visual Impact

The above landscape is currently an open viewshed of the cays with a couple of mooring

buoys. The project will be introducing 6 buoys (2 mooring, 4 boundary markers) and

therefore will have a negligible impact on the above water viewshed. Underwater the

area of open sand will slowly become an area with small scattered structures and corals.

7.03 Impact on Public Services

7.03a Water

The project has no impact on water resources or use.

7.03b Sewage Treatment and Disposal

The project has no impact on sewage treatment and disposal.

7.03c Solid Waste Disposal

The project will have no impact on solid waste disposal.

7.03d Roads, Traffic and Parking

The project will have no impact on roads, traffic and parking.

7.03e Electricity

The project will have no impact on electricity use.

7.03f Schools

The project will have no impact on schools.

38

7.03g Fire and Police Protection

The barge should have no impact on fire or police protection.

7.03h Health

The project will have no impact on local health care.

7.04 Social Impacts

The project will have a positive social impact by offering an alternative internment

option. People will have the opportunity to choose to have their ashes placed into

structures which will become colonized by marine organisms overtime. This alternative

will also help alleviate pressure on Graveyards as they become more crowded overtime.

This allows family members to have a place to come visit by vessel to visit a lost loved

one if they wish.

7.05 Economic Impact

The Underwater Memorial Park offers an affordable alternative to burial which has

become more and more costly.

7.06 Impacts on Historical and Archeological Resources

The project involves the installation of 6 helix anchors and an unknown number of screw

anchors into the sand bottom where no debris or wreckage was noted. The installation of

the anchors will have no impact on archeological resources.

7.07 Recreational Use

The project is offshore in an area used for boating. This activity will continue

unimpeded.

7.08 Waste Disposal

The project will have no impact on waste disposal.

7.09 Accidental Spills

The project will only use small gasoline power vessels for the buoy installations and

periodic structure placements. Chances for spills will be negligible. All vessels will

follow standard USCG spill procedures.

39

7.10 Potential Adverse Effects Which Cannot Be Avoided

The project has been designed to avoid impact to resources by is location. The most

significant change will be a change of use from an area of unoccupied sand to a Memorial

park.

8.00 Mitigation Plans

The moorings and buoys will be utilize type helix anchors and floating lines to minimize

bottom impacts.

The installations will all be done by divers and will have minimal impact.

9.00 Alternatives to Proposed Action

The project could not be done and there would be no change in use of the area and there

would continue to be limited options for internment.

Another location could be chosen which would have more impacts by impact seagrass or

corals. The chosen location has no impact on coral or seagrass resources.

10.00 Relationship Between Short Term and Long Term Uses of Man’s Environment

The project proposes an alternative option from burial or scattering ashes at sea. It

creates an area where people can visit lost loved ones and relieves pressure on the limited

burial space on the island on St. Thomas. It is a beneficial use of the environment with

minimal impact.

11.00 REFERENCES

Literature Cited

Bowden, M.J. et. al., 1969. Climate, water balance and climatic change in the north-west

Virgin Islands. Caribbean Research Institute, CVI,, St. Thomas, Virgin Islands.

Bucher, K. E., D.S. Littler, M. M. Littler, J. N. Norris. 1989. Marine Plants of the

Caribbean A Field Guide From Florida to Brazil. Smithsonian Institution Press,

Washington, D.C.

Donnelly,T. 1966. Geology of St. Thomas and St. John, U.S. Virgin Islands. In: Hess, H.

(ed.) Caribbean geological investigations. Geol Soc. Amer. Mem. 98:85-176.

Donnelly, T., et al. 1971. Chemical evolution of the igneous rocks of the Eastern West

Indies. In: Donnely, t. (ed.) Caribbean geophysical, tectonic and petrologic studies. Geol.

Soc. Amer. Mem. 130:181-224.

40

Humann, Paul. 1992. Reef Creature Identification. New World Publications, Inc.,

Jacksonville, FL.

Humann, Paul. 1993. Reef Coral Identification. New World Publications, Inc.,

Jacksonville, FL.

Humann, Paul. 1989. Reef Fish Identification. New World Publications, Inc.,

Jacksonville, FL.

Island Resources Foundation. 1977. Marine environments of the Virgin Islands.

Technical Supplement No.1 1976. Prepared for the Virgin Islands Planning Office.

STEER (2011) St. Thomas East End Reserve Management Plan. St. Thomas, USVI.

USACE Wave Information Studies

On line Resources Referenced:

http://www.nmfs.noaa.gov

http://www.surf-forecast.com/weather_maps/US-Virgin-Islands

http://coralpedia.bio.warwick.ac.uk/

https://msc.fema.gov/portal/advanceSearch

http://www.sercc.com/climateinfo/historical/historical_pr.html

http://oceancurrents.rsmas.miami.edu/data.html

http://www.spongeguide.org/

http://tidesandcurrents.noaa.gov/tide_predictions

http://websoilsurvey.nrcs.usda.gov/app/WebSoilSurvey.aspx

http://www.ndbc.noaa.gov/

http://wis.usace.army.mil/hindcasts.html?dmn=atlantic

41

APPENDIX I

42

BIOIMPACT, INC. Page 1

BBIIOOIIMMPPAACCTT,, IINNCC

P.O. BOX 132

KINGSHILL, ST. CROIX

U.S. VIRGIN ISLANDS 00851

PHONE NUMBER 340 690-8445 FAX NUMBER 340 718-3800

EMAIL [email protected], [email protected]

BIOIMPACT, INC. Page 2

BIOIMPACT, INC. QUALIFICATION STATEMENT

Bioimpact, Inc. is a Virgin Islands Corporation licensed to do business in the Virgin Islands

Since 1986.

Bioimpact, Inc. is qualified to conduct and prepare both terrestrial and marine Environmental

Assessment Report required by the Department of Planning and Natural Resources, Division of

Coastal Zone Management, and the U.S. Army Corps of Engineers.

Amy Claire Dempsey, principal of Bioimpact, Inc. is certified in wetland delineation by the

National Wetland Science Training Cooperative to establish wetland jurisdictional limits for the

U.S. Army Corps of Engineers.

Bioimpact, Inc. is experienced in the creation and implementation of wetland mitigation

programs.

Bioimpact, Inc. is experienced in developing and implementing marine water quality monitoring

programs and long-term photographic monitoring of the benthic environment. Amy Claire

Dempsey, principal of Bioimpact, Inc. is an EPA certified water sampler and analyst.

Bioimpact, Inc. has successfully designed and implemented large scale coral and seagrass

transplant programs.

Bioimpact, Inc. is experienced in cable landfall studies and the establishment of routes for

undersea cables and monitoring of cable installations to minimize impact.

Bioimpact, Inc. is experienced in endangered species surveys included the endangered coral, as

well as terrestrial flora and fauna species and is experienced in preparing Biological Assessments

for National Marine Fisheries and Fish and Wildlife Service.

Bioimpact, Inc. is experienced in the transplant and monitoring of Environmental Protection Act

(ESA) listed coral species as authorized under “take permits” from National Marine Fisheries

Service.

Bioimpact, Inc. is experienced in preparing Environmental Assessments for federal permitting

and the issuance of Findings of No Significant Impact.

Bioimpact, Inc. is experienced in the preparations of Phase I Environmental Site Assessments as

set forth in the ASTM Standard Practice Designation E 1527-13 and All Appropriate Inquires

and Phase II Environmental Site Assessments as set for in ASTM E1903 – 11.

Bioimpact, Inc. is experience in the development and implementation of sampling plans to

detect and delineation hazardous materials and petroleum products.

BIOIMPACT, INC. Page 3

Bioimpact, Inc. is experience in conducting deep water ROV surveys up to 1000ft and has all

the necessary equipment to undertake these studies.

Bioimpact, Inc. has conducted environmental studies in the U.S. Virgin Islands, Puerto Rico,

British Virgin Islands, throughout the Caribbean and in the Florida Keys.

PARTIAL JOB LIST

UP-DATED March 2018

MONITORING PROGRAMS

2019- Development and Implementation of the Water Quality and Environmental Monitoring

Plan for the installation of a Single Point Mooring at Limetree Marine Terminals, St.

Croix.

2018- Development and Implementation of the Water Quality and Environmental Monitoring

Plan for the Construction of the Veterans Drive Project on St. Thomas for Virgin Islands

Department of Public Works.

2014-2018 Development and Implementation of the Environmental Monitoring Plans for the

Conversion of VIWAPA to LPG for Vitol, St. Croix and St. Thomas.

2014-2018 Development and Implementation of the Environmental Monitoring Plans for the

Development of a Dolphin Exhibit for Coral World (VI), Inc., St. Thomas.

2013-2018 Development and Implementation of the Water Quality and Environmental

Monitoring related to the dredging of the Crown Bay Marine Terminal and Turning

Basin, St. Thomas.

2016 Development and Implementation of the Water Quality Monitoring Plan for the WICO

Emergency Bulkhead replacement, St. Thomas.

2013 –2015 Environmental Monitoring of the wetland created as mitigation for the

development of VIWMA’s St.Croix Transfer Station

2013-2018 Development and Implementation of the Monitoring Plans for VIDPW’s

Improvements to Veterans Drive St. Thomas

2013-2018 Development and Implementation of the Monitoring Plans for VIPA’s Maintenance

Dredging of Crown Bay Marina, St. Thomas

2013-2018 Development and Implementation of the Monitoring Plans for Westin Resorts

Permitting of the dock and Improvements of Drainage, St. John

BIOIMPACT, INC. Page 4

2012 –2018 Development and Implementation of the Monitoring Plans for viNGN’s Cable

System in the USVI.

2011-20198 Water Quality and Environmental Monitoring Program for the increase in

discharge from the Frenchman’s Reef Hotel, St. Thomas

2010-2012 Development of the Water Quality and Environmental Monitoring Program for the

development of Thatch Cay, with special emphasize on the ESA listed coral species

2009 Establishment of the baseline for the dredging of Charlotte Amalie Harbor and entrance

channel and the filling of the dredged hole in Lindbergh Bay, St. Thomas for

West Indies Company

2009 – 2010 Water Quality Monitoring Plan for the Construction of the dock at Frenchman’s

Cove, St. Thomas for Marriott Vacation Club, Inc.

2009-2015 Environmental Monitoring for the development of Oil Nut Bay, and YCCS Yacht

Club, Virgin Gorda, BVI, for Victor International

2008-2009 Environmental Monitoring of the development of Scrub Island, BVI, for MainSail

Development, LLC

2007 – 2010 Water Quality Monitoring for the development of the Calabash Boom Affordable

Housing Complex in Calabash Boom, St. John for Reliance Housing

2007 - 2009 Water Quality and Environmental Monitoring for the Subdivision of 77 acres in

Hansen Bay, St. John, for Flamboyant

2006- 2008 Water Quality Monitoring for the dredging of the Sand Channel for the V.I. Water

and Power Authority

2006-2007 Water Quality Monitoring for the renovations to the Ritz Carlton Hotel, St. Thomas

for Ritz Carlton

2006 - 2010 Environmental monitoring for the placement of undersea cables at the Global

Crossing Cable Station in St. Croix for Global Crossing Network, ALCATEL and TYCO

2005-2007 Water Quality Monitoring for the dredging of Crown Bay, St. Thomas for the V.I.

Port Authority

2005- 2006 Water Quality and Environmental Monitoring for Improvements to the Redhook

Marine Terminal for the V.I. Port Authority

2004 - 2011 Water Quality and Environmental Monitoring for the construction of the Pond

BIOIMPACT, INC. Page 5

Bay Resort, St. John for First American Development Group

2003 - 2006 Water Quality Monitoring for the construction of the Enighed Pond Marine

Terminal, St. John, for the V.I. Port Authority

2002 - 2008 Water Quality and Environmental Monitoring for the development of Marine

Amenities on the island of Lovango, St. John, for the Joseph Markus Trust

2003 - 2004 Water Quality Monitoring for the development of the Crown Bay Marine Terminal,

St. Thomas for the V.I. Port Authority

2002-2005 Water Quality Monitoring for the improvements to the Gallows Bay Marine

Terminal, St. Croix, for the V.I. Port Authority

1999-2006 Water Quality Monitoring for repairs to the Frederiksted Pier, St. Croix, for the

V.I. Port Authority

2001-2008 Coral Transplant Monitoring for the Enighed Pond Marine Terminal, St. John, for the

V.I. Port Authority

2001- 2007 Coral Transplant Monitoring for the Mangrove Lagoon Sewage Treatment Plant

Outfall, St. Thomas for the V.I. Department of Public Works

2000 - 2003 Water Quality Monitoring for the dredging of Charlotte Amalie Harbor, St. Thomas,

for the V.I. Port Authority

2001 - 2002 Water Quality Monitoring for Improvements to the Tropical Shipping Dock in

Crown Bay, St. Thomas for Misener Marine

2000 - 2006 Seagrass Transplant Monitoring for the Seagrass Transplant for the Dredging of

Charlotte Amalie Harbor for the V.I. Port Authority

1999- 2002 Water quality monitoring for Construction of Cable Stations at Estate Northside for

Global Crossings

1997-2002 Wetland monitoring of the Airport Mitigation Site at the Henry E. Rohlsen Airport

for the V.I. Port Authority

1997 - 2002 Wetland monitoring for the Fairplains Mitigation Site at the Henry E. Rohlsen

Airport for the V.I. Port Authority

1997- 2005 Water quality monitoring program for Construction of the Christiansted Boardwalk

in St. Croix prepared for the Government of the Virgin Islands

BIOIMPACT, INC. Page 6

1997-2005 Wetland monitoring of Tren Urbano, PR 5 and PR 22 Mitigation *Sites in Puerto

Rico under subcontract to Nutter and Associates for the Puerto Rico Highway Authority

1996 Water quality monitoring program for Expansion and Improvements to the Redhook

Marine Terminal in St. Thomas prepared for the V.I. Port Authority

1996 Water quality monitoring program for the creation of The Enighed Pond Marine Terminal

in St. John prepared for Maguire Group, Inc. for the V.I. Port Authority

1996-1998 Water quality monitoring for the Expansion of the Molasses Pier at the Third Port St.

Croix conducted for the V.I. Port Authority

1995 Water quality for the Construction of the AT&T Cable Landing Facility, Estate Northside

St. Croix, conducted for AT&T Submarine Systems

1992-1994 Water quality monitoring program for the Reconstruction of the Frederiksted Pier,

conducted for the V.I. Port Authority, St. Croix

1992-1993 Establishment of a baseline and long term monitoring of the benthic community

potentially impacted by the Water and Power Authority Outfall from the Richmond

Power Plant, conducted for the V.I. Water and Power Authority, St. Croix

1992-1993 Preparation of a biological monitoring study for the Cooling Pond Discharge, and

monitoring of the algal bloom within the cooling ponds; development of management

strategies to alleviate algal and runoff problems, the V.I. Alumina Corporation, St. Croix

1990-1992 Water quality monitoring for The Dredging Project and Related Activities in

Christiansted Harbor, conducted for the V.I. Port Authority, St. Croix

1989 Turtle Monitoring Program for Manchineel Beach, St. Croix

LARGE SCALE MITIGATION PROGRAMS

UPDATED AUGUST 2019

Development and Implementation of the Compensatory Mitigation Plan for the transplant of

approximately 1700 corals, repair of 500 corals of opportunity and outplanting of 3000

ESA listed corals for Limetree Bay Terminal’s Single Point Mooring on St. Croix.

Development and Implementation of a Compensatory Mitigation Plan for the relocation of 1.25

acres of seagrass and transplant of 631 corals from the impact footprint of the Veterans

Drive Project in St. Thomas.

Development and Implementation of the Mitigation Plan for the relocation of 10,000 corals off

the WICO bulkhead in Havensight for West Indies Company in St. Thomas.

BIOIMPACT, INC. Page 7

Development and Implementation of a coral transplant for the Stabilization of the Seawater

Intake line for Marriott Frenchman’s Reef, St. Thomas.

Development and Implementation of a coral transplant to minimize construction impacts for

LPG Improvements at the VIWAPA facilities on St. Croix and St. Thomas.

Development and Implementation of a coral transplant for Coral World (VI), Inc. in

Association with the development of the dolphin exhibit in St. Thomas.

Development and Implementation of the Mitigation Plans for VIDPW’s Improvements to

Veterans Drive St. Thomas

Development and Implementation of the Mitigation Plans for VIPA’s Dredging of Crown Bay

Marine Terminal and Turning Basin, St. Thomas

Development and Implementation of the Mitigation Plans for VIPA’s Maintenance Dredging of

Crown Bay Marina, St. Thomas

Development and Implementation of the Mitigation Plans for Westin Resorts Permitting of the

dock and Improvements of Drainage, St. John

Virgin Islands Waste Management Authority creation of an Herbaceous Wetland as mitigation

for the construction of the Transfer Station at the Anguilla Landfill, St. Croix

Mainsail Coral Transplant/Seagrass Transplant for impacts associated with the development of

the Scrub Island Resort BVI, Bioimpact, Inc. came in and completed the transplant and

monitoring began by others (Approximately 3000 Corals)

Victor International Coral Transplant for impacts associated by the development of an access

ramp and dock at Oil Nut Bay, BVI (Approximately 300 corals)

V.I. Port Authority Mangrove Mitigation for the construction of the Enighed Pond Terminal in

St. John (2.8 Acres of Mangrove Wetland)

Joseph Markus Trust Creation of Acropora Thickets and Artificial Reefs as mitigation for the

construction of a barge landing facility on the island of Lovango

V.I. Port Authority Transplanting of coral out of the area of impact for the development of the

Crown Bay Marine Terminal, St. Thomas (Approximately 3000 Corals)

Department of Public Works Mangrove Mitigation Project for the construction of the Mangrove

Lagoon Sewage Treatment Plant, St. Thomas (Approximately 1 Acre of Mangrove

Wetland)

BIOIMPACT, INC. Page 8

V.I. Port Authority Transplanting of Coral out of the area of impact for the Enighed Pond Marine

Terminal Project, St. John (Approximately 50,000 Corals)

Department of Public Works Transplanting of Coral out of the area of impact for the placement

of the Mangrove Lagoon Sewage Treatment Plant Outfall, St. Thomas (7,000 Corals)

V.I. Port Authority Transplanting of Coral out of the area of impact for the mooring

improvements to the Frederiksted Pier, St. Croix (Approximately 300 corals)

V.I. Port Authority Transplanting of Seagrass from the Dredging footprint for the dredging of

Charlotte Amalie Harbor, St. Thomas (Approximately 2 acres)

V.I. Port Authority/Department of Public Works, Mangrove Mitigation Project for the

construction of the Molasses Dock Road, St. Croix (Approximately ½ acre)

V.I. Port Authority creation of Herbaceous Wetlands for mitigation at the Henry E. Rohlsen

Airport, St. Croix (Approximately 1 acres)

V.I. Port Authority mitigation plan for impact incurred in Fairplains Gut by the VIPA plan for

creation of 16,000 Square Feet of Wetland at the Manning Bay Site, St. Croix

V.I. Water and Power Authority plan for creation of 4.1 Acres of Wetland as mitigation of the

construction of the South Shore Power Plant, Third Port, St. Croix

Green Cay Plan for mitigation for the impacting of 12 Acres of Wetland for the construction of

the Green Cay Resort, St. Croix

ENVIRONMENTAL ASSESSMENT REPORTS 2014-2018

Installation of a Single Point Mooring at the Limetree Bay Terminal, St. Croix, Limetree Bay

Terminals, LLC.

Installation of a Submarine Cable System for the V.I. Water and Power Authority, St. Thomas

Veterans Drive Expansion with Parsons Brinckerhoff, for the Department of Public Works

St. Thomas

Maintenance Dredging of Krause Lagoon Channel for V.I. Port Authority, St. Thomas

Installation of New Reverse Osmosis Discharge and Intake Line, Westin Resorts, St. John

Shoreline Stabilization Project for Buccaneer Hotel, St. Croix

VIWAPA’s conversion to LPG in both St. Croix and St. Thomas.

BIOIMPACT, INC. Page 9

viNGN Submarine Cable Network with Acatel-Lucent for Virgin Islands Next Generation

Network, Virgin Islands

Improvements to the Frederiksted Pier, V.I. Port Authority, St. Croix

Improvements to the Red Hook Marine Terminal, V.I. Port Authority, St. Thomas

Offshore Windmills for Ocean Energy, Inc.

St. John Marina for Summers End Group, St. John

Maintenance Dredging of the Schooner Channel, V.I. Port Authority, St. Croix

Remediation of Hydrocarbon Contamination at the V.I. Seaplane Ramp, V.I. Port Authority, St.

Croix.

Maintenance of the Existing Bulkhead and Maintenance Dredging of Charlotte Amalie Harbor,

with CH2M Hill for West Indies Company, St. Thomas

ENVIRONMENTAL ASSESSMENT REPORS 2009-2013

Dredging of Crown Bay Marine Terminal and Turning Basin, V.I. Port Authority, St. Thomas.

Maintenance Dredging of Crown Bay Marina, V.I. Port Authority, St. Thomas

Improvements to Bordeaux Road, with Parsons Brinkerhoff, for V.I. Department of Public

Works, St. Thomas.

Improvement to Spring Gut Road, with Stanley Engineer, for V.I. Department of Public Works,

St. Croix.

Coral World’s Dolphin Exhibit for Coral World (VI), Inc., St. Thomas.

Expansion of the Spratt Bay Homeowners Dock on Water Island.

Veterans Drive Expansion with Parsons Brinckerhoff, for the Department of Public Works

St. Thomas

Chiller Cooling System, BaHaMar, HDR, Grande Bahama

Reverse Osmosis Facility at V.I. Water and Power Authority’s St. Thomas Power Plant

BIOIMPACT, INC. Page 10

Submarine Cable for V.I. Water and Power Authority between the Islands of St. Thomas and St.

John

Chiller System and Dock repairs at Frenchman’s Reef, St. Thomas

Expansion of Heavy Materials Krum Bay Facility, St. Thomas

33 Mega-Watt Waste to Energy Plant Alpine Energy Group, Inc. St. Thomas

18 Mega-Watt Waste to Energy Plant Alpine Energy Group, Inc. St. Croix

Reverse Osmosis Facility V.I. Water and Power Authority, St. John

Seven Hills Development, Robin Bay Partners, St. Croix

Improvements to the Molasses Dock, V.I. Port Authority, St. Croix

Dredging of the Charlotte Amalie Harbor and the Channel and the Filling of Lindbergh Bay,

West Indies Corporation, St. Thomas

Fueling Station, V.I. Water and Power Authority, St. Croix

ENVIRONMENTAL ASSESSMENT REPORTS 2005 -2008

Port of Mandahl, MSJ Realty, St. Thomas

North Sound Yacht Club, Victor International, Virgin Gorda, BVI

Reconstruction of the Frenchman’s Cove Dock, Marriott Ownership Vacation Club, Inc. St.

Thomas

Thatch Cay Development, Thatch Cay, LLC, St. Thomas

Smith Bay Development Smith Bay Developers, Inc. Smith Bay, St. Thomas

Subdivision of Great St. James Christian Kejer, Great St. James Island, St. Thomas

Subdivision of Inner Brass Green Island Developers, Inner Brass Island, St. Thomas

Subdivision of Inner Brass Byran family, Inner Brass Island, St. Thomas

Cabrita Point Major Land Permit Cabrita Point Partners, Lionstone LLC, Cabrita Point, St.

Thomas

BIOIMPACT, INC. Page 11

Cabrita Point Major Water Permit Cabrita Point Partners, Lionstone, LLC, Cabrita Point, St.

Thomas

Subdivision of 77 Acres in Hansen Bay on the East End of St. John Flamboyant Realty, St.

John

Subdivision of 14 Acres in Hansen Bay on the East End of St. John Hansen Bay Development

Group, St. John

Expansions and Improvements to the Ritz Carlton Hotel William Karr and Associates, St.

Thomas

Modification to Carden Beach Condominiums TK Properties, Inc. St. Croix

Development of Betty’s Hope V.I. Port Authority, St. Croix

Expansion of the Compass Point Marine Margate Management, Benner Bay, St. Thomas

Construction of Maintenance Buildings HOVENSA, St. Croix

Replacement of Existing Stacks HOVENSA, St. Croix

Installation of a Permanent Barge Landing Facility on Lovango Cay Joseph Markus Trust,

Lovango Cay

Relocation of the Existing Barge Landing and Construction of a Swim Dock and Beach

Enhancing Devices on Little St. James LSJ, LLC, Little St. James

Development of Affordable Housing in Calabash Boom, Reliance Housing, St. John

Demineralized Water System and Storage Tank Upgrades, V.I. Water and Power Authority, St.

Croix

Development of a Pizza Bar and Miniature Golf Course, Divi Carina Bay Resort, St. Croix

Placement of Fuel Pipelines on the Ann E. Abramson Pier, Royal Caribbean Cruise Lines, St.

Croix

Development of a Marine and Related Infrastructure, Coral Bay Marina LLC, St. John

Development of a Marine Mammal Encountered Facility, Coral World VI, St. Thomas

Improvements to The “Doc” James Race Track, TRAXCO, St. Croix

BIOIMPACT, INC. Page 12

Maintenance Dredging and the Permitting of Permanent Moorings, Westin Resort, St. John

Construction of the LSF Facility, HOVENSA, St. Croix

Construction of the LSF Project on Uplands, HOVENSA, St. Croix

Construction of the LSF Project on Submerged Lands, HOVENSA, St. Croix

Construction of Modular Buildings, HOVENSA, St. Croix

Construction of Housing in Estate Blessing, HOVENSA, St. Croix

Permitting of an Existing Borrow Pit, HOVENSA, St. Croix

ENVIRONMENTAL ASSESSMENT REPORTS 2000-2004

Compass Point Marina Expansion of the existing marina with Springline Architects, St. Thomas

Emergency Electrical Cable to St. John V.I. Water and Power Authority, St. Thomas/St. John

Richmond Sand Channel Dredging V.I. Water and Power Authority, St. Croix

Hassel Island Electrical Cable Replacement V.I. Water and Power Authority, St. Thomas

Golden Resort Hotel Casino Resort Environmental Assessment Report, St. Croix

Crown Bay Marine Terminal Improvements Environmental Assessment Report with Adams,

Inc., St. Thomas

Global Crossings Environmental Assessment Report for the Placement of a Point of Presence in

Frederiksted, St. Croix

Innovative Telephone Environmental Assessment Report for the Burial of Fiber Optic Cable on

the North Shore of St. Croix

Innovative Telephone Environmental Assessment Report for the Burial of Fiber Optic Cable on

the West End of St. Croix

Callaloo Club Blowing Point Environmental Assessment for the Crasion of a marina on

Anguilla, BWI

V.I. Water and Power Authority Waterline Environmental Assessment for a waterline between

St. Thomas and St. John

BIOIMPACT, INC. Page 13

V.I. Water and Power Authority Powerline Environmental Assessment for a utility line between

St. Thomas and Little St. James

Global Crossings Environmental Assessment Report for the South American Crossing Cable

Station at Estate Northside

Water Island Ferry Dock Environmental Assessment Report for the construction of a ferry dock

on Water Island

Cuisanart Environmental Impact Assessment for Beach Renourishment, Anguilla, BWI

Cinnamon Bay Environmental Impact Assessment for Development of a Marine Facility,

Anguilla, BWI

Crown Bay Benthic Habitat Survey of Crown Bay and Gregerie Channel as a supplement to the

USACOE Feasibility Report

Frederiksted Pier Environmental Assessment Report for the Improvements to the Existing

Frederiksted Pier, St. Croix

Little St. James Environmental Assessment Report for a Private Dock on Little St. James Island

Government of the Virgin Islands Environmental Assessment Report for Phase II of the

Christiansted Boardwalk, St. Croix

Beal Aerospace Environmental Assessment Report for Construction of the World Headquarters

Estate Great Pond, St. Croix

ENVIRONMENTAL ASSESSMENT REPORTS 1988-2000

Divi Hotel Environmental Assessment Report for the reconstruction of a dock, St. Croix

Global Crossing Environmental Assessment Report for the construction of a Cable Terminal

Building and a corridor for 8 submarine fiber optic cables

HOVENSA Environmental Assessment Report for the Construction of a Coker and Coker Dock

at the Existing HOVIC Refinery

V.I. Port Authority Environmental Assessment Report for the construction of a Mooring Dolphin

at the Frederiksted Pier

Seaborne Environmental Assessment Report for the Development of a Seaplane Terminal at the

old Seaplane Ramp, St. Croix

BIOIMPACT, INC. Page 14

Forest Bay Environmental Assessment Report for the Development of a Marina and related

facilities in Forest Bay Anguilla, BWI

META Resorts Environmental Assessment Report for the development of a Dolphin Lagoon at

Meads Bay Anguilla, BWI

Government of the Virgin Islands Environmental Assessment Report for the Construction of a

boardwalk in Christiansted, St. Croix

V.I. Port Authority Environmental Assessment Report for the runway extension at the Henry E.

Rohlsen Airport under subcontract to LPA Group

V.I. Port Authority Environmental Assessment Report for the expansion of the Redhook Marine

Terminal, St. Thomas

V.I. Port Authority Environmental Assessment Report for the creation of the Enighed Pond

Marine Facility, St. John

Coral World (VI), Inc. Environmental Assessment Report for the renewal of the submerged land

lease for the Coral World Facility, St. Thomas

Cowpet Bay Environmental Assessment Report for the modification of the existing permit for

construction of a seawall, St. Thomas

Watergate East Villas Environmental Assessment Report for the Construction of a Rip-Rap

Revetment, St. Thomas

Christiansted Boardwalk Environmental Assessment Report for the construction of a boardwalk

on the Christiansted Waterfront, St. Croix

V.I. Water and Power Authority Environmental Assessment Report for Improvements to the fuel

dock at the Power Generating Facility, St. Thomas

La Domaine Environmental Assessment Report for the subdivision of 40 Acres of Land in Estate

Misngunt, St. Thomas

V.I. Port Authority Environmental Assessment Report for the expansion of the Alexander

Hamilton Airport Terminal and Highway 64 Relocation, St. Croix

AT&T Environmental Assessment Report for the Cable Landing Facility at Estate Northside, St.

Croix

BIOIMPACT, INC. Page 15

DEVCON Environmental Assessment Report for the Dredging of the Christiansted Sand

Channel, St. Croix

VIALCO Environmental Assessment Report for the Expansion of the Red Mud Storage Ponds,

VIALCO Alumina Facility, St. Croix

VIALCO Environmental Assessment Report for the creation of a stormwater drainage system,

VIALCO Alumina Facility, St. Croix

VIALCO Environmental Assessment Report for the Mining of Caliche, VIALCO Alumina

Facility, St. Croix

Molasses Dock/VI Port Authority Consulting on the Environmental Assessment Report for the

Molasses Dock Terminal at the Third Port Facility, subcontracted by Frank Torrez, and

the V.I. Port Authority, St. Croix

SELECTED ENVIRONMENTAL ASSESSMENT REPORTS 1988 -1993

St. Croix by the Sea Environmental Assessment Report for beach renourishment and the

construction of jetties, St. Croix

Vieques Environmental Assessment Report for the creation of a shrimp farm in Puerto Ferro,

Vieques, Puerto Rico

MSRC Dock Environmental Assessment Report for the construction of a pier in the HOVIC

West Turning Basin, St. Croix

Eden Beach Proposed hotel and condominium project Environmental Assessment Report, St.

Croix

Tamarind Reef proposed reconstruction and expansion of the Tamarind Reef Hotel, Hotel, St.

Croix

V.I. Water and Power Authority Environmental Assessment Report and U.S. Corps of Engineers

Application for the construction of two gas turbines at the Third Port Site, St. Croix

Lovango Cay Environmental Assessment Report for the creation of a subdivision on Lovango

Cay Placement of a private dock, St. Thomas

VIALCO Environmental Assessment Report for the construction of a well water gathering

system for wells at the Virgin Islands Alumina Corporation’s Plant, St. Croix

Crawl Cay Environmental Assessment Report, Wetlands Delineation and Hammock Studies of

Crawl Cay, Florida, for Monroe County

BIOIMPACT, INC. Page 16

Jack’s Bay Environmental Assessment Report for the subdivision of Approximately 300 Acres

into 64 lots at Estate Jack’s and Isaac’s Bays, St. Croix

VIALCO Environmental Assessment Report for the Expansion of the Bauxite Building at the

Virgin Islands Alumina Corporation’s Alumina Facility, St. Croix

Carambola Beach Club Environmental Assessment Report for the repair and improvement of the

Carambola Beach Club facility prepared for Danested, St. Croix

Salt River Environmental Impact Statement for the proposed National Park at Salt River, St.

Croix, prepared for the National Park Service

V.I. Water and Power Authority Environmental Assessment Report for the Construction of a

desalination unit on St. John, prepared for the V.I. Water and Power Authority, St. John

Carmel by the Sea Environmental Assessment Report for the Construction of a 95 unit

condominium at Estate Turner’s Hole, St. Croix

VLBA Environmental Assessment Report and Landscaping Plan for the Very Long Baseline

Array, St. Croix

Buccaneer Environmental Assessment Report for 20 room addition to the Buccaneer Hotel, St.

Croix

Ritz Carlton Zoning Application and Environmental Assessment Report for a 350 report for a

350 room Hotel, Estate Davis Bay, St. Croix

Frederiksted Pier Environmental Assessment Report for the construction of a second pier in

Frederiksted, St. Croix

Kingston Environmental Assessment Report for Hotel and Condominium Construction,

Kingston, Tortola

Airport Warehouse Environmental Assessment Report for construction of a Warehouse Facility

at the Alexander Hamilton Airport, St. Croix

Great Pond Environmental Assessment Report, Zoning Application, and COE Permit

Application

for a Hotel and Condominium Project at Estate Great Pond, St. Croix

BIOIMPACT, INC. Page 17

ENVIRONMENTAL ASSESSMENT REPORTS 1986-1988

Southeast Peninsula, St. Kitts

Columbus Landing, St. Croix

Grapetree Beach, St. Croix

Blue Beards Beach, St. Thomas

St. Croix by the Sea, St. Croix

Divi Dive Canal, Nassau, Bahamas

Ensenada, St. Croix

Virgin Grand, St. Croix

Sugar Bay, St. Croix

Turtle Run, St. Croix

Palm Shores, St. Croix

Baobab, St. Croix

Reflection Bay, St. Croix

Coakley Bay, St. Croix

Green Cay, St. Croix

Turquoise Bay St. Croix

Eagle Bay, St. Croix

Granard, St. Croix

Concordia, St. John

ENVIRONMENTAL ASSESSMENTS

Sampling of USTs for Domino Oil on St. Thomas 2016-2017

Sampling of the LUSTs at the VIPA’s Seaplane Ramp, St. Croix 1994, 2011, 2012-2016

Sampling for REC Estate Anna’s Hope, St. Croix 2012-2016

Sampling for petroleum products at gasoline stations and industrial sites in St. Croix 2006-2016

Sampling for chemical contamination in cisterns in St. Croix 2000- 2011

Sampling for mold Renaissance Hotel, St. Thomas

Sampling for REC residential and commercial properties St. Croix, St. Thomas, St. John and

Puerto 1990 - 2018

bioim
Typewriter
APPENDIX B

BIOIMPACT, INC. Page 17

ENVIRONMENTAL ASSESSMENT REPORTS 1986-1988

Southeast Peninsula, St. Kitts

Columbus Landing, St. Croix

Grapetree Beach, St. Croix

Blue Beards Beach, St. Thomas

St. Croix by the Sea, St. Croix

Divi Dive Canal, Nassau, Bahamas

Ensenada, St. Croix

Virgin Grand, St. Croix

Sugar Bay, St. Croix

Turtle Run, St. Croix

Palm Shores, St. Croix

Baobab, St. Croix

Reflection Bay, St. Croix

Coakley Bay, St. Croix

Green Cay, St. Croix

Turquoise Bay St. Croix

Eagle Bay, St. Croix

Granard, St. Croix

Concordia, St. John

ENVIRONMENTAL ASSESSMENTS

Sampling of USTs for Domino Oil on St. Thomas 2016-2017

Sampling of the LUSTs at the VIPA’s Seaplane Ramp, St. Croix 1994, 2011, 2012-2016

Sampling for REC Estate Anna’s Hope, St. Croix 2012-2016

Sampling for petroleum products at gasoline stations and industrial sites in St. Croix 2006-2016

Sampling for chemical contamination in cisterns in St. Croix 2000- 2011

Sampling for mold Renaissance Hotel, St. Thomas

Sampling for REC residential and commercial properties St. Croix, St. Thomas, St. John and

Puerto 1990 - 2018

VIRGIN ISLANDS UNDERWATER MEMORIAL PARK STRUCTURE, MOORING AND SEA FLOOR INSPECTION AND MAINTENANCE PLAN

Underwater Memorial, LLC is proposing to create a Virgin Islands Underwater Memorial Park. The idea is

to create a beautiful underwater memorial park where people can have their ashes incorporated into

small structures which will serve as hard substrate for coral colonization and as attachment points for

coral propagation. The area requested is 40 acres, however the actual “interment” will be less than 20

acres. The reason for the size of the requested is so that the park can be eligible for inclusion in several

organization which specialize in low impact natural burials. This provides Underwater Memorial, LLC to

project coral reef resources within the 40-acre park.

In order to ensure the internment structures, moorings and boundary markers are in good condition and to avoid inadvertent impacts which could occur if debris or trash ends up in the area.

Monitoring and Maintenance

On a quarterly basis each mooring, and marker buoy will be inspected to ensure that they are in good working condition and that there is no damage that needs to be repaired. If shackles or other tackle appears to be worn it will be replaced immediately. Divers will survey the internment structures and ensure that all are in good condition and do not need adjustment. All trash found within the area will be collected and removed and properly disposed of on shore.