magnet infrastructures and cavern layout

15
Magnet Infrastructures and Cavern Layout CLIC Detector WG5, April 1st 2010 Andrea Gaddi Physics Dept. - CERN

Upload: liluye

Post on 19-Jan-2016

33 views

Category:

Documents


1 download

DESCRIPTION

Magnet Infrastructures and Cavern Layout. CLIC Detector WG5, April 1st 2010. Andrea Gaddi Physics Dept. - CERN. Introduction. The push-pull mode of operation sets specific requirements and challenges for many systems of detector and accelerator, in particular for: the IR magnets - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Magnet Infrastructures and Cavern Layout

Magnet Infrastructures andCavern Layout

CLIC Detector WG5, April 1st 2010

Andrea GaddiPhysics Dept. - CERN

Page 2: Magnet Infrastructures and Cavern Layout

Page 2April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Introduction

The push-pull mode of operation sets specific requirements and challenges for many systems of detector and accelerator, in particular for:• the IR magnets• the cryogenics, vacuum and powering systems of detector magnet• machine and detector alignment system• beam-line shielding

The EA design shall allow the fastest and safest detector switch-over, including:

• detector moving• services reconnections• shielding re-arrangements• machine and detector re-alignment.The actual target is to perform the switch-over in a fewdays.

The push-pull operation includes time from the switch-off the beam until the moment when luminosity is restored to 70% level and at the same energy, after the detector exchange (cfr. ILC).

Page 3: Magnet Infrastructures and Cavern Layout

Page 3April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Detector on-beam

Page 4: Magnet Infrastructures and Cavern Layout

Page 4April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Detector off-beam

Page 5: Magnet Infrastructures and Cavern Layout

Page 5April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Magnet infrastructures & push-pull scenario

The two most challenging magnet services are the cryogenics & vacuumsystem and the powering & protection one. The He liquifier is an heavy and delicate components that cannot move with the detector, neither sit too close, due to the magnetic stray field. Its ideal location is the side service cavern, along with the fore vacuum pumps, that are noisy in terms of vibration and need easy access for maintenance.

The power supply, and its associated breakers, is also a huge and heavy component whose location is better chosen in the service cavern. On the contrary, the dump resistors protecting the coil, should stay as close as possible to the magnet, but consideration on the total energy (> 1GJ) dissipated in the cavern may lead to move them away from the detector.

Page 6: Magnet Infrastructures and Cavern Layout

Page 6April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Cryogenics & vacuum block diagram

Page 7: Magnet Infrastructures and Cavern Layout

Page 7April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Magnet powering block diagram / different solutions

Page 8: Magnet Infrastructures and Cavern Layout

Page 8April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Cavern layout Cable-chain

Page 9: Magnet Infrastructures and Cavern Layout

Page 9April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Flexible cryo & vacuum lines

The detector solenoid has to stay cold during the push-pull period, i.e. liquidHelium and has to be guaranteed via flexible transfer lines. Vacuum inside thecoil cryostat could be kept by simple cryo-pumping during push-pull, but a flexiblerough vacuum line is necessary anyhow.

CMS has 30m long rigid cryo transfer line, vacuum insulated+ 50m long rigid 230mm primary vacuum line (10-3 mbar)Not applicable to push-pull.

Flexible cryolines have been successfully installed to cool Atlas Endcap ToroidsLHe lines diameter 58mmOuter shielding 110mmVacuum envelope 143mm

SiD foresees a flexible cryoline 160mm, vacuum insulated

Page 10: Magnet Infrastructures and Cavern Layout

Page 10April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Flexible HTS bus-bars

Despite the fact that during push-pull, the detector magnet is obviously off,a permanent connection of the solenoid power supply to the coil current leadswould save precious time. This line shall be able to carry 20kA in a self-fieldof about 0.6T, over a length of some 60m. A flexible resistive line would taketoo much space in the cavern and have a significant voltage drop V (in additionto the power dissipated P=VxI).

CERN is actually developing the design of a semi-flexible, vacuum insulated,HTS (MgB2) line for the LHC upgrade.The characteristics of this powering line are the following: Nominal current: 110kA at 20K and 0.8T Maximum current: 130kA at 20K and 0.8T Cooling: GHe, from 5 to 20K Length: 100m Vacuum envelope: 90mm Minimum bending radius: 1.5m

Page 11: Magnet Infrastructures and Cavern Layout

Page 11April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Proposal for powering lines : flexible HTS bus-barsPrototypes of the multi-cables HTS powering line (courtesy A. Ballarino, CERN-TE Dept.)

Page 12: Magnet Infrastructures and Cavern Layout

Page 12April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Proposal for dump-system : compact water-cooled resistorsTotal stored magnetic energy ≈ 2.50 GJEnergy extracted by the dumping system ≈ 1.25 GJSolenoid reference current (I) ≈ 20 kASolenoid inductance (L= 2E/I2) ≈ 12.5 HDump resistance (R) ≈ 30 mDischarge voltage ≈ 300 V wrt groundPeak discharge power (Ppeak=I2R) ≈ 12 MWDischarge time constant (t=L/R) ≈ 416 s

Page 13: Magnet Infrastructures and Cavern Layout

Page 13April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Page 14: Magnet Infrastructures and Cavern Layout

Page 14April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Stray field considerations Requirement for the magnetic field outside of detector is an important factor

which defines the amount of iron in the detector (or degree of compensation for endcap hybrid-design).

Effects of any field outside of detectors on the beam shall be corrected, and the requirements should come from human safety factor, from the limit of field map distortion due to off-beamline detector and from effects on cavern equipment.

Field on any external surface of on-beamline detector shall be less than 2kGs, while its field in non-restricted area (including near the off-beamline detector) to be less than 100Gs (ILC requirements).

The magnetic field effect from the off-beamline detector onto the on-beamline detector must limit distortion of magnetic field map of the latter to less than 0.01% anywhere inside its tracking volume (ILC requirement).

Page 15: Magnet Infrastructures and Cavern Layout

Page 15April 1st, A. Gaddi, Physics Dept. CERN

EA Infrastructures & Push Pull Scenario

Conclusion & work-plan towards the CDR. The push-pull scenario leads to an integrated design of detectors infrastructures.

A compromise between on-board services and a remote “service block” has to be found, making use of cable-chains that assure permanent connections with the service block, allowing a smooth movement of the detector during the push-pull operation. We will focus our work on this.

Cryogenics and vacuum flexible lines have been already successfully used at Atlas. Need to be adapted to CLIC detector magnet. An existing R&D program for a HTS powering line for LHC upgrade could give good indications for a 20kA HTS line cooled with GHe between 5 and 20K, to be employed for detector magnet power-lines.

The problem of a compact on-board dump-system could be solved with a water-cooled resistor-bench. A 1/10 scale prototype could be useful to validate our simulations.

Integration of magnet services with cavern layout requires a closer collaboration with civil engineering group.

The effects of the stray-field have to be carefully looked. Any effort to limit the stray-field via an optimized yoke design has to be pursued.