load flow studies of a grid interfaced w

90
1 LOADFLOW STUDIES OF A GRID INTERFACED WINDFARM USING PSS®E Submitted by WAQAS ALI MEMON (Group Leader) 11EL87 NEELESH KUMAR 11EL78 UMAR MEMON 11EL140 JITENDER KUMAR 11EL132 KHAMISO KHAN 11EL147 ALEEM-UL-HAQUE 11-09EL02 Supervised By ENGR. MOKHI MAAN CHANG Co-Supervised By ENGR. MAHESH KUMAR RATHI DEPARTMENT OF ELECTRICAL ENGINEERING MEHRAN UNIVERSITY OF ENGINEERING & TECHNOLOGY, JAMSHORO Submitted in partial fulfillment of the requirement for the degree of the Bachelor of Electrical Engineering JANUARY 2015

Upload: hassan

Post on 18-Feb-2016

29 views

Category:

Documents


0 download

DESCRIPTION

load flow studies

TRANSCRIPT

Page 1: Load Flow Studies of a Grid Interfaced w

1

LOADFLOW STUDIES OF A GRID INTERFACED

WINDFARM USING PSS®E

Submitted by

WAQAS ALI MEMON (Group Leader) 11EL87

NEELESH KUMAR 11EL78

UMAR MEMON 11EL140

JITENDER KUMAR 11EL132

KHAMISO KHAN 11EL147

ALEEM-UL-HAQUE 11-09EL02

Supervised By

ENGR. MOKHI MAAN CHANG

Co-Supervised By

ENGR. MAHESH KUMAR RATHI

DEPARTMENT OF ELECTRICAL ENGINEERING MEHRAN UNIVERSITY OF ENGINEERING & TECHNOLOGY,

JAMSHORO

Submitted in partial fulfillment of the requirement for the degree of

the Bachelor of Electrical Engineering

JANUARY 2015

Page 2: Load Flow Studies of a Grid Interfaced w

2

CERTIFICATE

This is to certify that the work presented in this project report/thesis report on

“LOADFLOW ANALYSIS OF A GRID INTERFACED WINDFARM USING

PSS®E” is entirely written by the following student/s, themselves under the

supervision of Engr. Mokhi Maan Chang,.

Submitted by

WAQAS ALI MEMON (Group Leader) 11EL87

NEELESH KUMAR 11EL78

UMAR MEMON 11EL140

JITENDER KUMAR 11EL132

KHAMISO KHAN 11EL147

ALEEM-UL-HAQUE 11-09EL02

Project / Thesis Supervisor External / Examiner

________________________________

Chairman

Department of Electrical Engineering

Mehran UET, Jamshoro

Date:___________________

Page 3: Load Flow Studies of a Grid Interfaced w

3

ACKNOWLEDGEMENT

At the outset, I pay homage and guidance to ALLAH ALMIGHTY, the most

merciful, compassionate, gracious and beneficial whose help enabled to complete this

thesis.

We extend our profound sense of gratitude to respected supervisor Engr. Mokhi

Maan Chang, Department of Electrical Engineering MUET Jamshoro under whose

abe guidance this thesis has been completed. We are indeed extremely grateful for her

inspiring guidance and kind sympathetic attitude. Without that thesis would not have

been the light of the day.

We are highly thankful to Dr. Abdul Sattar Larik, Chairman Department of

Electrical Engineering MUET Jamshoro, who always encouraged and advised us to

complete the thesis well on the time. He extended all the possible co-operation in this

regard.

We are also thankful to all our teachers of our department who helped us to fulfill this

thesis.

And finally we are thankful to Engr. Mushtaq Ahmed Kerrio, Plant Manager and

Engr. Shahid Ali, Sub-engineer at Zorlu Wind Power Farm.

Page 4: Load Flow Studies of a Grid Interfaced w

4

ABSTRACT

Wind power has evolved as a significant renewable energy source for the generation

of electrical energy due to the growth of environmental concerns. Large wind farms

with several hundred megawatts of rated power have been connected to grid, fulfilling

the energy demands of a region or a country.

The injection of new produced power into the existing power system resulting

challenges regarding voltage levels, thermal limits, stability and constancy of

frequency. In the same way when wind farms are connected to the existing power

system introducing the new power to the system it also offers some challenges like

reactive power compensation, fluctuations in active and reactive power and control

strategies.

It is therefore necessary to go through steady state and dynamic analysis to map the

impacts of newly injected power of wind farms on the existing system.

Thus the objective of this thesis is to carry out the load flow analysis of the wind farm

integrated to the power grid, in order to study their overall impacts on the power

system.

For this purpose, a wind farm of 110MW having two aggregates of 24MW and three

aggregates of 21MW connected offshore to the power grid by means of a power

cable. Initially the steady state load flow analysis is carried out and then dynamic

simulation is carried out to determine the fault ride through capability of the wind

farm. All this simulation and load flow is performed using a software i.e. PSS/E by

Siemens PTI.

The results of the simulation are analyzed to study the Impacts of grid interfaced wind

farm on the power system.

Page 5: Load Flow Studies of a Grid Interfaced w

5

TABLE OF CONTENTS

Title ................................................................................................................................ i

Certificate ...................................................................................................................... ii

Acknowledgement ....................................................................................................... iii

Abstract ........................................................................................................................ iv

Table of Contents ...........................................................................................................v

List of Figures ............................................................................................................. vii

List of Tables ............................................................................................................. viii

CHAPTER 1

INTRODUCTION

1.1 Introduction ........................................................................................................1

1.2 Problem Statement ............................................................................................1

1.3 Objectives ..........................................................................................................2

1.4 Thesis Outline ....................................................................................................2

CHAPTER 2

LITERATURE REVIEW

2.1 Offshore Wind Farms ........................................................................................3

2.2 Transmission Strategies .....................................................................................4

2.3 LVRT .................................................................................................................6

2.4 Grid Integration ..................................................................................................7

2.5 HVAC Transmission ..........................................................................................9

2.6 Reactive Power Compensation ..........................................................................9

2.7 FACTs Devices ................................................................................................10

2.8 Power Flow Analysis .......................................................................................11

CHAPTER 3

INTRODUCTION TO PSS®E 3.1 Introduction .....................................................................................................19

3.2 What is PSS®E? ..............................................................................................19

3.3 File types used in PSS®E ................................................................................21

3.4 Explanation of Tabs .........................................................................................22

3.5 Major system security tools offered in PSS®E ...............................................27

Page 6: Load Flow Studies of a Grid Interfaced w

6

CHAPTER 4

PSS®E MODEL CONFIGURATION

4.1 Wind Farm Modeling Approach ......................................................................30

4.2 PSS®E Modeling .............................................................................................31

4.3 Grid Structure...................................................................................................32

4.4 Wind Farm Model ............................................................................................37

4.5 Wind Turbines .................................................................................................38

4.6 Layout of the Offshore Wind Farm .................................................................40

4.7 HVAC Transmission System ...........................................................................41

4.8 STATCOM for Steady State Simulation .........................................................42

4.9 Diagram of the Grid .........................................................................................44

4.10 Modeling for Dynamic Analysis ......................................................................45

CHAPTER 5

RESULTS & OBSERVATION

5.1 Introduction ......................................................................................................51

5.2 Power Flow Simulation Results .......................................................................51

Case1 Wind Farm without Reactive Power Compensation ........................................54

Case2 Wind Farm with Shunt Reactor .......................................................................60

Case3 Wind Farm with STATCOM ..........................................................................65

5.3 Dynamic Results ..............................................................................................70

CHAPTER 6

CONCLUSION

6.1 Conclusion .......................................................................................................80

6.2 Recommendations ............................................................................................81

REFERENCES ...............................................................................................82

Page 7: Load Flow Studies of a Grid Interfaced w

7

LIST OF FIGURES

Fig1:Example of the results of a voltage drop test ....................................................................... 7

Fig2: Schematic Diagram of an SVC...........................................................................11

Fig3 – (a) Schematic Diagram of a STATCOM; (b) a STATCOM installation .........11

Fig4: Use of PSS®E in different fields ........................................................................20

Fig5: PV Analysis Curve .............................................................................................28

Fig6: Layout of wind turbines in Wind Farm .............................................................37

Fig7: PSS®E model of the offshore wind farm ...........................................................40

Fig8: HVAC transmission layout in PSS®E ...............................................................41

Fig9: Graphic representation of a STATCOM in PSS®E ...........................................42

Fig10: Single line diagram of the wind Farm connected to the Grid...........................44

Fig11: DFIG Model .....................................................................................................46

Fig12: Power Flow Data File .......................................................................................47

Fig13: PSS®E DFIG Generic Model ..........................................................................48

Fig14: Legend of the values presented in the single-line diagrams .............................51

Fig 15: Power Flow results of Wind Farm without Compensation .............................54

Fig16: color display of voltages at buses .....................................................................57

Fig 17: power Flow results of wind farm with Shunt reactor ......................................60

Fig 18: Color display of Voltages at different buses ...................................................60

Fig 19: Power Flow results of Wind Farm with STATCOM ......................................65

Fig 20: Color display of voltages at different buses ....................................................65

Fig 21: Single line diagram of the grid used for the dynamic simulations. Note: Bus

3005, where the fault occurs is marked in the orange rectangle ......................71

Page 8: Load Flow Studies of a Grid Interfaced w

8

LIST OF TABLES

Table1: 33KV and 220KV Line data ..........................................................................33

Table2: 400KV Line dat .............................................................................................34

Table3: Grid Transformer Data ..................................................................................35

Table4: Load Data........................................................................................................36

Table5: Shunt Compensator Data ................................................................................36

Table6: Wind Turbine Data .........................................................................................39

Table7: Wind Farm Transformer Data ........................................................................39

Table8: 33KV Cable Data ............................................................................................40

Table9: 150KV Cable parameters ................................................................................41

Table10: Onshore and offshore transformer data ........................................................42

Table11: STATCOM Parameters ................................................................................43

Table12: Color Representation of Voltages .................................................................45

Table13: Turbine Model WT3T1.................................................................................49

Table14: Generator Model WT3G1 .............................................................................49

Table15: Pitch Model WT3P1 .....................................................................................49

Table16: Electric Part Model WT3E1 .......................................................................50

Table17: Voltages at different buses............................................................................56

Table18: Data of Active and Reactive power generated .............................................56

Table19: Voltages at different buses including wind farms ........................................62

Table20: Active and Reactive power generated by different generators. ....................62

Table21: Voltages at different buses using STATCOM ..............................................67

Table22: Active and Reactive power generated using STATCOM.............................67

Page 9: Load Flow Studies of a Grid Interfaced w

9

INTRODUCTION

1.1 INTRODUCTION

The utilization of wind turbine to produce electricity is increasing rapidly in different

parts of the world. It has become one of the main alternatives for non pollutant and

environmentally friendly type for power generation all over the world and in Pakistan

also its benefits are being recognized and a large amount of wind power is planned to

be added to the national grid in coming years.

Not until recently, the contribution of wind power generation on the system stability

was considered to be small. However with increasing in the wind farm capacity it is

clear that disconnecting a large wind farm will result in loss of a big part of power

generation in grid, which can aggravate instability problems. Due to increasing

portion of wind power, wind turbines have to contribute in reactive power support

during transient conditions.

The grid connection procedure is changing and adaption to a large scale wind power

expansion is continually made. This adaption will most likely lead to requirements of

information regarding the wind power unit‟s electrical behavior and then to determine

the impact of adding wind generation, and establish how the system can be upgraded.

Therefore a simulator tool (PSS/E) is used to perform the load flow and to study the

dynamic behavior of the grid interfaced wind farm.

1.2 PROBLEM STATEMENT

Wind power industry is developing rapidly, more and more wind farms are being

connected into power systems. Integration of large scale wind farms into power

systems presents some challenges that must be addressed, such as

System operation and control

System stability and power quality

This thesis describes modern wind power systems, presents requirements of wind

turbine connection and analyzes the impacts on grid integrated wind-farm.

1.3 OBJECTIVES

Page 10: Load Flow Studies of a Grid Interfaced w

10

The overall objective for this thesis is to illustrate the dynamic impacts from the wind

farms on the existing power system.

The following elements are included in the studies:

Establish a steady-state and dynamic model of wind-farm integrated power

system

Carryout load flow and transient analysis to study the impacts on grid inter-

connected wind-farm

Introduction to PSSE and Simulation using PSSE software

1.4 THESIS OUTLINE

This thesis consists of six chapters including this chapter. The content of each chapter

are outlined as follows:

Chapter 2 includes Literature Review in which offshore wind farms, LVRT, steady-

state and dynamic analysis, grid codes and compensation devices are discussed and it

mainly focuses on the challenges which are faced to integrate the wind farms to power

grid.

Chapter 3 includes the Introduction to PSS/E software introducing to the files,

windows and components used for simulation and explaining different security

analysis functions offered by it.

Chapter 4 includes PSS/E modeling approach, discussing the Grid and wind farm data

for the analysis and establishing a model in order to perform the desired analysis.

Chapter 5 includes the steady-state and dynamic analysis results of a power system

connected with 110MW wind farm. Analysis is performed and results are discussed.

Chapter 6 contains conclusion and recommendations regarding the future work on

PSS/E.

Page 11: Load Flow Studies of a Grid Interfaced w

11

CHAPTER 2

LITERATURE REVIEW

2.1 OFFSHORE WIND FARMS

Among the available types of renewable energy, wind power generation offers the

advantages of mat u re technological systems and a rich track record, as well as

lower generation costs. For these reasons, the introduction and popularization of

wind power is advancing.

The challenges involved in offshore wind power development may be divided into

three key categories.

The first is that of cost. Because offshore wind turbines are installed within ocean

environments, the cost is said to run roughly twice that of onshore facilities. This

includes the wind turbines themselves, the foundations (bases submerged in the

waters), submarine cable installation work and other project aspects. In addition, the

operation and maintenance (O&M; referring to parts replacement and other upkeep)

work also differs from onshore wind turbines insofar as the demand for heavy

expenditures [12,13].

Costs likewise vary by distances from the shore, water depth and other elements.

Because recent offshore wind farms in Europe are steadily moving further away

from continental areas and into deeper waters, installation costs are also on the rise.

The second challenge category is technology. With early offshore wind turbines

suffering frequent breakdowns in their step-up gears, generators, development of

technology was advanced for means of raising reliability involving salt damage

countermeasures and monitoring of wind turbine conditions. In addition, when

moving installation locations from shallow to deeper waters, there is a need to

increase per-turbine power generation in order to lower cost. This makes increased

size and improved reliability a major theme in developing the technology for offshore

wind turbines.

The third challenge concerns social acceptance. Clearly, offshore wind power

generation will never be realized without the understanding of fisheries

Page 12: Load Flow Studies of a Grid Interfaced w

12

operators and other marine users. To earn their supports, environmental assessments

are a must.

The extension of wind power can have severe impacts on the transmission system

because of the remote sitting and the possible problems for system security.

Due to the fact that electrical energy cannot be stored in a substantial way, the need

for short and long term power balancing can require an adjustment of the operational

strategy of power systems with a high wind power penetration level. Besides, in case

of windstorms or system disturbances (such as voltage drops), there exists the

increased risk of a sudden and uncontrolled shutdown of the wind farms, which can

severely affect the security of the system.

Wind generation also has an influence on the network‟s Voltage control capability.

On one hand, wind turbine generators (WTG) can demand a large amount of reactive

power (depending on the technology) and on the other hand they replace conventional

thermal power plants that have excellent voltage control capabilities.

In order to reduce the impact of wind generation on the transmission system, the

connection through HVDC based on voltage source converters (VSC) seems a

promising solution. The major benefit of this technology is its ability to vary the

reactive power supplied and, as a consequence, to help in supporting the voltage at the

point of common coupling with the transmission network [12,13].

2.2 TRANSMISSION STRATEGIES

The transmission link to the shore can be HVAC; line- commutated thyristor-based

HVDC or VSC-HVDC.

The AC connection is the solution adopted mostly by existing wind farms and has the

following features:

The submarine AC cable generates a considerable reactive current due

to its high capacitance (typically in the range of 100-150 KVAR/km for 33 kV

XLPE (cross- linked polyethylene) cables, 1000 KVAR/km for 132 kV XLPE

cables, and 6–8 MVAR/km for 400 kV XLPE cables). This reduces the active

current carrying capacity of the cable and, for large distances, requires

compensation devices;

Page 13: Load Flow Studies of a Grid Interfaced w

13

because of the high capacitance of the cable, resonances between the onshore

and the offshore grid can occur, leading to distortion of the shape of the

voltage;

The AC local wind turbine grid and the main grid are synchronously coupled

and all faults in either grid are noticed in the other;

The major advantage is the low costs for substations when compared to

DC solutions. On the other hand, costs for cables are higher than for DC

alternatives.

The main advantages of the DC link with respect to the AC link are the

following:

The losses and the voltage drop in the DC link are very low and there is no

charging current in the DC cable. There is virtually no limitation of the

connection distance, only practical restraints of cable manufacturing and

laying put a maximum to this distance;

There is no resonance between the cables and other AC equipment

Since the collection system and the main grid are not synchronously coupled,

the WTG‟s do not contribute significantly to short-circuit currents in the main

grid;

The DC link provides faster control of active and reactive power than the AC

link. Voltage source converters are able to control reactive power over the

complete operation range, for „classical‟ thyristor-based HVDC this is

somewhat limited. This control capability makes it easier to comply with

connection requirements.

The thyristor-based HVDC solution is a technology that has proven itself on land but

seems not particularly well suited for offshore applications. Converter stations and

auxiliary equipments have demanding space requirements, which will lead to

enormous offshore converter platforms. Moreover this technology is highly

susceptible to AC network disturbances (resulting in commutation failures in the

inverter station), which can cause a temporary shutdown of the HVDC system; for

these reasons this technology has not been considered further in this paper.

On the contrary HVDC technology based on VSC‟s seems to be very promising for

offshore applications because it requires less auxiliary equipment and the converters

themselves take less space than the thyristor-based version. The VSC‟s are able to

Page 14: Load Flow Studies of a Grid Interfaced w

14

independently control both the active and reactive power exchanged with the AC grid

and therefore they can take part in voltage regulation. The major drawback of this

technology is the high converter losses, caused mainly by switching losses that

depend on the switching frequency of the semiconductor devices [9].

2.3 LOW VOLTAGE RIDE THROUGH CAPABILITY (LVRT)

Grid stability and security of supply are two important aspects for energy supply. In

order to avoid power outages it is necessary that power generating plants should have

control capabilities and protection mechanisms. In the past, these requirements were

mainly fulfilled by conventional power plants. In the meantime, however, the share of

re­newable energy sources in the total electricity generation has become so significant

that these sources too must con­ tribute to the grid stability. Therefore the transmission

sys­ tem operators have established so called grid codes with certain critical values

and control characteristics that the generating plants have to fulfill. An important part

of these requirements is the so-called LVRT capability of generating plants.

LVRT is short for Low Voltage Ride Through and describes the requirement that

generating plants must continue to operate through short periods of low grid voltage

and not disconnect from the grid.

Short term voltage dips may occur, for example, when large loads are connected to the

grid or as a result of grid faults like lightning strikes or short circuits. In the past,

renew­ able generating plants such as wind turbines were allowed to disconnect from

the grid during such a fault and try to reconnect after a certain period of time.

Today, because of the significant share of renewable, such a procedure would be

fatal. If too many generating plants disconnect at the same time the complete network

could break down, a scenario which is also called a “blackout”. For this reason the

LVRT requirement has been established which is meant to guarantee that the

generating plants stay connected to the grid. Additionally many grid codes demand

that the grid should be supported during voltage drops. Generating plants can support

the grid by feeding reactive current into the network and so raise the voltage.

Immediately after fault clearance, the active power output must be increased again to

the value prior to the occurrence of the fault with­ in a specified period of time.

Page 15: Load Flow Studies of a Grid Interfaced w

15

These requirements which at the beginning only applied to wind turbines, now also

have to be fulfilled by photo­ voltaic systems (PV) and most recently, by combined

heat and power plants (CHP).

Fig 1: Example of the results of a voltage drop test.

Figure 1 shows the result of a voltage drop test at a PV system. In this diagram the

voltage drops to about 20% of the nominal voltage for a time of approx. 550ms. The

PV inverter recognizes the voltage drop and feeds a reactive current of approx.

100% of the nominal voltage into the system for the duration of the fault in order to

support the grid. After fault clearance the active power output is increased to the

value prior to the occurrence of the fault within 160ms [10].

2.4 GRID INTEGRATION

Integrating a wind farm in an electrical network poses a significant challenge to the

grid. The impact varies with the strength of the grid and the size of the wind farm. As

the wind farm capacity grows, grid integration issues may arise, as increasingly large

amounts of electricity are fed into networks, either in distribution or transmission

systems.

Page 16: Load Flow Studies of a Grid Interfaced w

16

2.4.1 Grid Connection Requirements

Until some years ago wind farms were allowed to disconnect from the grid during a

disturbance in the grid. This has changed significantly, due to the addition of large

amounts of installed wind power capacity. The disconnection of a large wind farm

would result in a significant loss of generation that could cause some stability

problems to the network. Transmission system operators require nowadays for wind

farms to stay connected under certain disturbances in the grid. These requirements are

known as the fault ride through capability of the wind farm and are generally

regulated in grid codes. As established in most grid codes, only under certain

circumstances shall wind farms be disconnected from the grid following a grid fault,

remaining otherwise connected in order to assist in the stabilization of the grid

frequency or the voltage during fault, providing voltage back-up [7].

Apart from the fault ride through capability, other technical requirements must be

fulfilled by the wind farm, since the increasing size of wind farms means that the

rating of such installations will be comparable to that of traditional generating plants

on the grid. These requirements include:

Control of active and reactive power (operation under a specified range for

power factor);

Frequency range (with time durations for extreme conditions, permissible

reduction at frequency extremes)

Contribution to network stability;

AC voltage control capability.

As the proliferation of wind power increases, wind farms will be bound to meet these

demands, which may prove difficult depending, to greater extent, on the transmission

system used between the wind farm and grid. The charging currents affecting AC

cables represent a limitation for the HVAC cables and so some form of compensation

for the surplus reactive power generated by the cable is necessary to met grid

requirements [7].

Page 17: Load Flow Studies of a Grid Interfaced w

17

2.5 HVAC TRANSMISSION

2.5.1 General Aspects

Connecting the wind farm to the grid by an AC cable is the most straightforward

technical solution, as both the power generated by the wind farm and the onshore

transmission grid are AC. The HVAC transmission offers some advantages:

Proven and low-cost technology;

Easy to integrate in existing power systems

Low losses over small distances

On the other hand there are some limitations of the HVAC system

There is an excessive amount of reactive power produced in the AC

transmission cables

Increase in the cable length means increase in its capacitance which results in

a reactive power increase, resulting in a transmission distance limit for AC

systems

Necessary use of compensation systems (shunt reactors, STATCOMS, SVC,

etc) at the ends of the cable [7]

2.5.2 Main Components of HVAC Transmission

A transmission system based on HVAC technology includes the following

main components

AC based collector system within the wind farm known as point of common

coupling.

Three core HVAC transmission cable

Offshore transformer

Reactive power compensation (onshore and/or offshore)

Onshore transformer

2.6 REACTIVE POWER COMPENSATION

The solution for the large amounts of reactive power at the cable is to compensate the

reactive power produced by absorbing reactive power, thus reducing the additional

losses and increasing the maximum transmitting distance. The compensation is

usually done by fixed or electronically controlled shunt reactors. The fixed shunt

Page 18: Load Flow Studies of a Grid Interfaced w

18

reactor is the simplest device but the progress in FACTS (Flexible AC transmission

system) devices, such as SVC (Static VAR compensator) or STATCOM (Static

Synchronous Compensator), considerably extends the reactive power and voltage

control possibilities offered by the switched shunt reactors.

The voltage on a transmission network is determined by the reactive power flows.

DFIG wind turbines have the capability of controlling reactive power flow through

the connection network and supporting the voltage network which they are connected.

However, in a large wind farm controlling individual DFIG wind turbine to regulate

reactive power flow is not feasible. It may not be able to control the voltage in the

grid. On many occasion, the reactive power and voltage control at the grid is achieved

by using reactive power compensation [7].

2.7 FACTS DEVICES

The SVC and the STATCOM are part of the FACTS device family, used for voltage

regulation and power system stabilization, based on power electronics. These devices

are capable of both generating and absorbing reactive power. The flexibility of use is

the main advantage of these equipments, since they allow the continuous variable

reactive power absorption (or supply). The reactive power is not proportional to the

voltage at the bus is another advantage of FACTS devices. The FACTS devices also

contribute in the improvement of the voltage stability and the recovery from network

faults.

The similarity of the SVC and STATCOM devices led to them being sometimes

referred generally as “Static VAR Compensators”. These are, however, different

equipments. The SVC is based on conventional capacitor banks together with parallel

thyristor controlled inductive branches. These inductive branches can either be TCR

(Thyristor Controlled Reactor), used for linear injection of reactive power or TSC

(Thyristor Switched Capacitor), used for stepwise injection of reactive power. A SVC

device is represented in Figure where a linear diagram and an SVC installation (in an

offshore wind farm) are represented [7].

Page 19: Load Flow Studies of a Grid Interfaced w

19

Fig 2: Schematic Diagram of an SVC

The STATCOM device uses a power electronic voltage source (VSC). The converter

uses semiconductors with turn-off capability, such as Insulated Gate Bipolar

Transistors (IGBTs). The benefits of the STATCOM (commercially known as “SVC

Light” by ABB or “SVC Plus” by Siemens), compared with the SVC, are the fact that

the capacitor banks used are smaller and also there is no need for big air-cored

inductors. Further advantages of the STATCOM are also found in the dynamic

behavior (such as faster transient response). A simplified schematic diagram of a

STATCOM is shown in Figure 3(a & b).

Fig 3 – (a) Schematic Diagram of a STATCOM; (b) a STATCOM installation

2.8 POWER FLOW ANALYSIS

In power engineering, the power flow analysis (also known as load-flow study) is an

importance tool involving numerical analysis applied to a power system. Unlike

traditional circuit analysis, a power flow study usually uses simplified notation such

as a one-line diagram and per-unit system, and focuses on various form of AC power

(ie: reactive, real and apparent) rather than voltage and current. The advantage in

studying power flow analysis is in planning the future expansion of power systems as

well as in determining the best operation of existing systems. Power flow analysis is

being used for solving power flow problem. There are three methods can be used to

Page 20: Load Flow Studies of a Grid Interfaced w

20

solve power flow analysis. The methods are Newton-Raphson method, Fast-

Decoupled method and Gauss-Seidel method. This sub-chapter will discuss all three

methods generally on formula or mathematical step in order to solve power flow

problem [15].

2.8.1 Newton-Raphson Method

Newton-Raphson method is commonly use and introduce in most text book. This

method widely used for solving simultaneous nonlinear algebraic equations. A

Newton-Raphson method is a successive approximation procedure based on an initial

estimate of the one-dimensional equation given by series expansion.

The Newton-Raphson method using the bus admittance matrix in either first or second

– order expansion of Taylor series has been evaluate as a best solution for the

reliability and the rapid convergence.

f(x)=c (1)

If x(0)

is an initial estimate of the solution, and ∆ x(0)

is a small deviation from the

correct solution, we must have

f(x(0)

+ ∆ x(0)

)=c (2)

Expanding the left-hand side of the above equation in Taylor‟s series about x(0)

yields

f(x(0)

) + (df/dx)(0)

∆ x(0)

+1/2! (d2f/dx

2)

(0 ) (∆ x

(0))2+...=c (3)

Assuming the error ∆ x(0)

is very small, the higher-order terms can be neglected,

which result in

∆ c(0)

≈ (df/dx)(0)

∆ x(0)

where

∆ c(0)

=c - f(x(0)

)

Adding ∆ x(0)

to the initial estimate will result in the second approximation

x(1)

= x(0)

+ ∆ c(0)

/ (df/dx)(0)

(5)

Page 21: Load Flow Studies of a Grid Interfaced w

21

Successive use of this procedure yields the Newton-Raphson algorithm

∆ c(k)

=c - f(x(k)

) (6)

∆ x(k)

= ∆ c(k)

/ (df/dx)(k

(7)

x(k+1)= x(k )+ ∆ x(k) (8)

(7) can be rearranged as

∆ c(k)

= j(k)

∆ x(k)

where j(k)

= (df/dx)(k)

(9)

In power system analysis, J(k)

is called the Jacobian matrix. Element of this matrix are

the partial derivatives evaluated at X(k)

. It is assumed that J(k)

has an inverse during

each iteration. Newton‟s method, as applied to a set of nonlinear equations reduces

the problem to solving a set of linear equations in order to determine the values that

improve the accuracy of the estimates [15].

2.8.2 Gauss-Seidel Method

Gauss-Seidel method is also known as the method of successive displacements.

To illustrate the technique, consider the solution of the nonlinear equation given by

F(x)=0 (10)

Above function is rearrange and writes as

x=g(x) (11)

If x=(k) is an initial estimate of the variable x, the following iterative sequence is

formed

X(k+1)= g(x(k)) (12)

A solution is obtained when the difference between the absolute value of the

successive iteration is less than a specified accuracy, i.e.,

| x(+k1)- x(k)|≤ ε (13)

Where ε is the desire accuracy

Page 22: Load Flow Studies of a Grid Interfaced w

22

The process is repeated until the change in variable is within the desired accuracy. So

the Gauss-Seidel method needs much iteration to achieve the desired accuracy, and

there is no guarantee for the convergence [15].

2.8.3 Fast Decoupled Method

When solving large scale power transmission systems, an alternative strategy for

improving computational efficiency and reducing computer storage requirements is

the decoupled power flow method, which makes use of an approximate version of the

Newton-Raphson procedure.

The Fast decoupled power flow solution requires more iterations than the Newton-

Raphson method, but requires considerably less time per iteration and a power flow

solution is obtained very rapidly. This technique is very useful in contingency

analysis where numerous outages are to be simulated or a power flow solution is

required for on-line control [15].

For large scale power system, usually the transmission lines have a very high X/R

ratio. For such a system, real power changes ∆P are less sensitive to changes in

voltage magnitude and are most sensitive to changes in phase angle ∆δ. Similarly,

reactive power is less sensitive to changes in angle and most sensitive on changes in

voltage magnitude. Incorporate of these approximations into the Jacobian matrix in

Newton-Raphson power flow solution makes the elements of the sub-matrices J12 and

J21 zero.

We are then left with two separated systems of equations,

Page 23: Load Flow Studies of a Grid Interfaced w

23

In well-designed and properly operated power transmission system:

i) Angular differences between typical buses of the system are usually so small.

δ ij = (δi −δ j ) very small that results,

cosδij ≈1

sin δij ≈ 0.0

ii) The line susceptances Bij are many times larger than the line conductances Gij

so that Gij sin δij << Bij .

iii) The reactive power Qi injected into any bus i of the system during normal

operation is much less than the reactive power which would flow if all lines

from that bus were short circuited to reference.

That is Qi << Vi 2 Bii .

∂Pi

= −

Y V

V

j

sin (θ i

j

j

−δ )

(16)

∂δ j

ij i i

∂Qi

sin(θ

)=

∂Pi

V

j

= −

V

j

Y

V

i

i

j

j

−δ (17)

∂V j

ij i

∂δ j

In Eq.(16) and Eq.(17), the off diagonal elements of J11 and J22 are given by

V

j

∂Qi

= −

V

j

Y

V

i

sin(θ

Ij

j

−δ

)=

∂Pi

(18)

∂V j ij i ∂δ j

Page 24: Load Flow Studies of a Grid Interfaced w

24

Using the identity sin(α + β)= sinα cos β + cosα sin β in Eq.(18) gives us

∂Pi

=

V

j

∂Qi

= −

V

V

j

B

i

j

cos(δ

j

−δ ) + G

i

j

sin(δ

j

−δ ) (19)

∂δ j

V

j

i i i

The approximation listed above then yield the off diagonal elements

∂Pi

=

V

j

∂Qi

= −

V V

j

B

i

j

(20)

∂δ j

V

j

i

∂Pi

= ∑n

Yij

ViV j

sin(θ ij

+δ j −δi )

(21)

∂δi

j=1

j≠i

V

∂Qi

= −

∂Pi

− 2

V

2

B

= Q −

V

2 B

(22)

i

∂V

∂δ i

i

ii

i

i

ii

Page 25: Load Flow Studies of a Grid Interfaced w

25

The diagonal elements of J11 and J22

Applying the inequality Qi << Vi 2 Bii

∂Pi

V

∂Qi

≅ −

V

2 B

∂δ

i

i

∂δ

i

i

ii

are shown in Eq. (8) and Eq. (9) respectively. to those expressions yields (23)

Substitute Eq. (19) and Eq. (20) into Eq. (14) and Eq. (15), we obtain

We can also modify Eq. (24) and Eq. (25) to two decoupled systems of equations for

n-bus network.

Page 26: Load Flow Studies of a Grid Interfaced w

26

And

Bij are the imaginary parts of the corresponding Ybus elements.

These were the basic introduction to all the related literature to understand the further

work of our thesis in chapter 4 and 5.

Page 27: Load Flow Studies of a Grid Interfaced w

27

CHAPTER 3

INTRODUCTION TO PSS®E

3.1 INTRODUCTION

The software tool PSS®E (Power Systems Simulation for Engineering) made by

Siemens is heavily utilized to perform system studies. This software is used by many

power companies. The reason that so many companies rely on PSS®E is because of

the many features and abilities that it has to offer. The functionality and performance

of PSS®E doesn‟t come at a cheap price. The software costs roughly $90,000 per

computer. Luckily for our thesis studies we have got university version of this

software limited up to 50 buses.

The hardest part of our thesis was actually learning how to use PSS®E. We spent

numerous hours outside of PSS®E just reading the help files that in our opinion are

somewhat difficult to apply to create a power-flow study. We learned how to use

PSS®E to perform power-flow study. Our study involves adding a wind farm to the

existing power grid. We were able to draw several conclusions about the feasibility of

this addition [6].

3.2 WHAT IS PSS®E?

Power System Simulation for Engineering (PSS®E) is composed of a comprehensive

set of programs for studies of power system transmission network and generation

performance in both steady-state and dynamic conditions. Currently two primary

simulations are used, one for steady-state analysis and one for dynamic simulations.

PSS®E can be utilized to facilitate calculations for a variety of analyses, including:

Power flow and related network functions

Optimal power flow

Balanced and unbalanced faults

Network equivalent construction

Dynamic simulation

In this chapter our focus will primarily be on power flow, steady-state and dynamic

simulations. PSS®E uses a graphical user interface that is comprised of all the

functionality of state analysis; including load flow, fault analysis, optimal power flow,

equivalency, and switching studies.

Page 28: Load Flow Studies of a Grid Interfaced w

28

In addition, to the steady-state and dynamic analyses, PSS®E also provides the user

with a wide range of auxiliary programs for installation, data input, output,

manipulation and preparation [6].

Fig 4: Use of PSS®E in different fields.

3.2.1 Power Flow

A power flow study (also known as load-flow study) is a steady-state analysis whose

target is to determine the voltages, currents, and real and reactive power flows in a

system under a given load conditions.

It is an important tool involving numerical analysis applied to a power system. Unlike

traditional circuit analysis, a power flow study usually uses simplified notation such

as a one-line diagram and per-unit system, and focuses on various forms of AC power

( i-e: reactive, real, and apparent).

Power flow studies are important because they allow for planning and future

expansion of existing as well as non-existing power systems. A power flow study also

can be used to determine the best and most effective design of power systems [6].

3.2.2 Dynamic Simulation

Page 29: Load Flow Studies of a Grid Interfaced w

29

The dynamic simulation program includes all the functionality for transient, dynamic

and long term stability analysis. The purpose of the dynamics is to facilitate operation

of all dynamic stability analytical functions.

The dynamic modeling simulation is used to ensure the reliability of electricity supply

and to predict the performance of the system under a wide range of conditions and to

identify any problems and scope measures needed for reliability [6].

3.3 FILE TYPES USED IN PSS®E

PSS®E uses many types of files. Here is a brief description of important file types

that may be used by PSS®E:

*.sav – Saved case file

The saved case file is a binary image of the load flow working case. To conserve disk

space and minimize the time required for storage and retrieval, saved cases (*.sav) are

compressed in the sense that unoccupied parts of the data structure are not stored

when the system model is smaller than the capacity limits of the program.

*.raw – Power flow raw data file (input data file)

A raw file is a collection of unprocessed data. This means the file has not been

altered, Compressed, or manipulated in any way by the computer. Raw files are often

used as data files by software programs that load and process the data. These files

contain power flow system specification data for the establishment of an initial

working case.

*.sld – Slider file (Single Line Diagram)

This file allows for performing network analysis studies on the grid.

Sliders are visual displays of the grid. It includes buses, branches, lines, loads,

Generators, transformers etc... All components should be color coded based on

voltage flow. The slider file can also show the operational ratings (power flowing

across the component relative to the capacity) of the listed components.

*.txt – Text file

A text file (or plain text file) is a computer file which contains only ordinary textual

characters with essentially no formatting.

Page 30: Load Flow Studies of a Grid Interfaced w

30

*.dat – Input data file

PSS®E accepts large volumes of data from external sources time to time. Such large

volumes of data could be typed directly into the PSS®E working case using the

Spreadsheet View but this could be an onerous task. Voluminous data is best

assembled in an input data file independent of PSS®E before PSS®E is started up.

This file may then be used as the input source for PSS®E to feed the data through the

appropriate input activity into the PSS®E working case [6].

2.4 EXPLANATION OF TABS

After opening the *.sav file, there are 19 tabs to choose from at the bottom of the data

file (shown below). Each tab can be accessed by clicking on it. Few tabs will be

focused over here:

2.4.1 Buses

Followind are few important parameters of Buses used in PSS®E:

Displays the number assigned to a specific bus.

Alphanumeric identifier assigned to bus "#". The name may be up

to twelve characters.

Bus base voltage; entered in kV.

Bus type code:

1 - Load bus (no generator boundary condition)

Page 31: Load Flow Studies of a Grid Interfaced w

31

2 - Generator or plant bus (either voltage regulating or fixed Mvar)

3 - Swing bus

4 - Disconnected (isolated) bus

5 – Same as type 1, but located on the boundary of an area in which an

equivalent is to be constructed.

Bus voltage magnitude; entered in per unit, V = 1.0 by default.

3.4.2 Branches: Following are few important parameters of Branches

Branch "from bus" number outside brackets with bus name

and bus kV enclosed in brackets.

Branch "to bus" number outside brackets with bus name

and bus kV enclosed in brackets.

Line R (pu): Branch resistance; entered in per unit. A value

of R must be entered for each branch.

Line X (pu): Branch reactance; entered in per unit. A

nonzero value of X must be entered for each branch.

Charging (pu): Total branch charging susceptance (imaginary

part of admittance); entered in per unit. B = 0.0 by default.

Length: Length of line entered in user-selected units.

3.4.3 Load

Following are few important parameters of the Load:

Page 32: Load Flow Studies of a Grid Interfaced w

32

This displays the Bus Number (where the load resides) outside

of the brackets and displays the bus name as well as the bus

voltage in kV inside the brackets.

This is a alphanumeric load identifier. It is used to distinguish among multiple

loads at the same "Bus Number/Name".

At buses in which there is a single load present, the ID = 1.

A check mark indicates that a certain load at a "Bus Number/Name" is

fully operational. If for any reason a certain load at a "Bus

Number/Name" needs to be taken out of service, simply un-check that

particular one.

Active power component of constant MVA load; entered in MW.

Reactive power component of constant MVA load; entered in MVAR.

3.4.4 Machines

The machines tab can be used to:

1. Add machines at an existing generator bus (i.e., at a plant).

2. Enter the specifications of machines into the working case.

3. To divide and distribute the total plant output power limits proportionally

among the machines at the plant. The important parameters for the machines

tab are described below:

Page 33: Load Flow Studies of a Grid Interfaced w

33

This displays the Bus Number (where the machine is located)

outside of the brackets and displays the bus name as well as the

bus voltage in kV inside the brackets.

This is a alphanumeric machine identifier. It is used to

distinguish among multiple machines at a plant (i.e., at a

generator bus). At buses in which there is a single machine

present, ID = 1.

A check mark indicates that a certain machine at a "Bus

Number/Name" is fully operational or out of service.

This shows the active power that the generator is putting out;

entered in MW.

This shows the minimum active power that the generator can

output; entered in MW.

This shows the maximum active power that the generator can

output; entered in MW.

This shows the reactive power that the generator is putting out;

entered in MVAR.

This shows the minimum reactive power that the generator can

output entered in MVAR.

This shows the maximum reactive power that the generator can

output; entered in MVAR.

3.4.5 Two Winding Transformers

Each transformer to be represented in PSS®E is introduced by reading a transformer

data record block.

Page 34: Load Flow Studies of a Grid Interfaced w

34

The transformer data record block can be accessed by clicking on the two Winding

transformer tab. The important parameters for this tab are explained below:

This states the first bus number outside of the brackets with the

bus name and bus kV enclosed in brackets. It is connected to

winding one of the transformers included in the system. The

transformer‟s magnetizing admittance is modeled on winding

one. No default is allowed.

This states the second bus number outside of the brackets with

the bus name and bus kV enclosed in brackets. It is connected

to winding two of the transformers included in the system. No

default is allowed.

A check mark indicates that a certain two winding transformer

between two buses is fully operational. If for any reason a

transformer needs to be taken out of service, simply un-check

that particular one. The default is in service [6].

Page 35: Load Flow Studies of a Grid Interfaced w

35

3.5 MAJOR POWER SYSTEM SECURITY TOOLS OFFERED BY PSS®E

This section briefly describes three power system topics that are usually covered at

the undergraduate level which are offered b PSS®E. The three topics are: load flow

analysis, transient stability analysis, and short circuit analysis.

3.5.1 Load Flow Analysis

The main purpose of load flow analysis is to calculate bus voltages and transmission

line MW and MVAR flows for a power grid. There are two types of power flow

analysis:

AC power flow and

DC power flow calculation.

AC Power Flow: By solving the AC power flow problem, effectiveness of various

voltage control strategies could be identified.

After performing the load flow concepts, the maximum power transfer capability of

any system could be determined.

DC Power Flow: PSSE offers DC power flow options which could be used to

perform fast contingency analysis to identify potential thermal overloads on the

system. They can also compare the accuracy between the AC and DC load flow

calculations [14].

3.5.2 Voltage Stability Analysis

In addition to solving for bus voltages and line flows, PSSE can also be used to derive

PV and VQ curves for different contingency scenarios, a process commonly used to

assess power grid voltage stability. Through PV and VQ analysis, maximum power

transfer capability of a transmission path could be determined while preserving

voltage stability of the system. PSSE produces PV curves for each monitored bus so

that the weakest node of the system can be identified. Figure presents a typical output

of a PV analysis from PSSE for different contingency scenarios [14].

Page 36: Load Flow Studies of a Grid Interfaced w

36

Fig 5: PV Analysis Curve

3.5.3 Transient Stability Analysis

Transient stability, also known as large signal stability, is a measure of the ability of

synchronous generators to remain in synchronism when the power system suffers

from a disturbance. The disturbance could be a fault successfully cleared by

protective relays, tripping of a major generator, or loss of a large load. These types of

disturbances can cause rotors to accelerate, resulting in an increase in internal angle

and the potential loss of transient stability.

For a single-machine-infinite-bus system (SMIB), the electrical power output of the

generator is significantly reduced during the fault-on period, so that the mechanical

input of the generator exceeds its electrical output. As a result, the transient kinetic

energy of the generator increases rapidly as the rotor accelerates. When the fault is

finally cleared, the generator needs to dissipate all the excess transient kinetic energy

into the power system. If proper protection schemes are not in place to isolate the fault

fast enough, the generator can lose synchronization (i.e. falling out of step) and suffer

severe damages. Transient stability is affected by many factors such as the mechanical

inertia of the generator, pre-contingency generator output level, and the excitation

control of the generator.

The Equal Area Criterion can be used to determine the transient stability of a SMIB if

the synchronous machine is represented as a classical generator, i.e., a constant

voltage source behind a transient reactance. The Equal Area Criterion states that for a

Page 37: Load Flow Studies of a Grid Interfaced w

37

given contingency, the area corresponding to the destabilizing effect of the fault must

not exceed the area corresponding to the restorative strength of the post-fault system.

The critical clearing time is defined when the fault is cleared so that the generator is

just marginally stable. The generator angle at the critical clearing time is known as the

critical clearing angle.

The Equal Area Criterion is, however, only applicable for a single-machine-infinite-

bus system. When there are multiple generators, the time domain simulation

technique must be used. This is the method which is used by PSSE.

The interactive structure of PSSE guides through a step-by-step process which

provides a greater understanding of the major factors which influence the transient

stability of a system.

PSSE exposes to analysis that cannot practically be done by hand calculations.

Furthermore, the interactive nature of PSSE is conducive to sensitivity analysis, that

is, different elements or variables of the system can be changed and the observer can

immediately see how these changes affect system stability (e.g. varying the length or

location of a fault) [14].

3.5.4 Short Circuit Calculation

For the purpose of power system protection, it is important to introduce fault

calculation which is also known as short circuit calculation. For the short circuit

calculation, introduction to the concept of symmetrical components and the formation

of positive, negative, and zero sequence networks is necessary. Then interconnection

of the sequence networks depending on the type of fault under consideration is

performed, in order to calculate the fault current levels.

This short circuit calculation facility is offered by PSSE [14].

Page 38: Load Flow Studies of a Grid Interfaced w

38

CHAPTER 4

PSS®E MODEL CONFIGURATION

4.1 WIND FARM MODELLING APPROACH:

The modeling approach of wind farms is based on Wind Grid Code Requirements.

The aim of Wind Grid Code is to provide a description of the technical and

operational requirements that are to be met by the developers and operators of Wind-

Powered Generating Stations (WPGS) that wish to connect to the national grid. The

Wind Code applies to all WPGSs that are or have applied to be connected to the

transmission grid. Before the interconnection of wind farm to transmission grid the

impact and design study is performed which covers:

Impact of the Wind Farm connection on the power system security and

reliability of supply.

Design of the appropriate direct assets from the commercial boundary.

Design of the necessary Infrastructure Reinforcement of the Transmission

System.

Based on grid code and wind grid code requirements a new connection (a generator or

load) could be connected into the transmission network if the following conditions are

fulfilled:

System operation security after the connection shall not be negatively affected.

The quality and reliability of demand supply shall comply with grid code

requirements

The steady state and transient stability of power system should have sufficient

security margin.

All relevant planning data will be used for detailed modeling of Wind Farms using

PSS®E simulation platform. In this case two common calculations are essential for

assessing the impact of Wind Farm on security and reliability of power system:

Power flow calculation

Transient stability

Page 39: Load Flow Studies of a Grid Interfaced w

39

4.1.1 Power Flow Calculations

A power flow calculation is to determine the power flows on transmission lines and

transformers and the voltage profile of system bus bars. This calculation is

fundamentally important for the planning and design of the connection of wind farms

to the transmission grid. N-1 Security criterion (system should be able to withstand

the loss of any single components like lines, transformers, cables or generators) is

essential for the proper design of transmission networks to ensure the security and

reliability of power supply. System performance is compared to operating limits and

criteria. Short Circuit calculations also play a very significant role for the proper

selection of high voltage equipment and the setting of protection relays [8].

4.1.2 Transient Stability Studies

The objective of transient stability studies is to examine whether wind farms will have

a negative effect on the transient stability of power system. The power system

response for a defined set of disturbances, typically three phase and single phase

faults cleared by tripping of transmission elements such as lines, transformers,

generators or bus bars. The response of conventional or wind turbine generators is

checked to see that all machines have an adequate stability margin, damping of power

system oscillations is acceptable and that the voltage recovery following fault clearing

is adequate [8].

4.2 PSS®E MODELING

In order to simulate the behavior of a wind farm, appropriate models of the wind

farm, the transmission system and the electrical grid have to be constructed. Only then

is it possible to analyze the steady-state and the transient behavior of the power

system.

The software used to model the system and perform the simulations in the work of

this thesis is the PSS®E software. PSS®E stands for Power System

Simulator/Engineering and it is a software tool provided by Siemens Power

Technologies International (PTI). It is used by most utilities in the world to perform

power system simulations, as it allows the performance of power flow analysis,

dynamic simulations and stability studies, among other features. PSS®E is composed

of a comprehensive set of programs for studies of power system transmission network

Page 40: Load Flow Studies of a Grid Interfaced w

40

performance in both steady-state and dynamic conditions, which is an obvious reason

for its widespread use by transmission and distribution systems operators [1].

4.3 GRID STRUCTURE

The electrical grid that will be used for steady-state analysis in which the wind farm

will be integrated is the “savnw” network, provided by PSS®E as an example of a

relatively large grid, as it has 23 buses, 6 generators and 7 loads. In order to properly

use this grid, a few changes were made, namely to the operating frequency and

voltage levels. These changes were made taking into account values used in the Asian

electrical grid [1].

Additional changes to the original “savnw” network were performed since the wind

farm rated at 110MW will be placed in a bus where the existing generation is of 750

MW.

Therefore, adjustments in active and reactive power of the network are required,

which can be made by adapting the power of the loads and the shunt compensators.

As so, the changes made to the original network can be summarized:

The frequency was changed to 50 Hz (the frequency in use in most parts of

the world, including Pakistan) since the frequency of original example grid is

60 Hz (typical of American grids)

The voltage levels were changed from 500 kV, 230 kV and 22 kV to,

respectively, 400 kV, 220 kV and 33 kV. These voltage levels are common in

most Asian Grids, including Pakistan

The 110 MW offshore wind farm was added, replacing an existing power

plant of 750 MW

Most of the parameters of the grid are presented in detail:

4.3.1 Lines

As a result of changing the grid frequency to 50 Hz, the reactance and the susceptance

of the branches have to be converted, since these parameters depend on the grid

frequency. So new parameters (except those of 400kv lines) are given in table 1 using

following equations [1]

Page 41: Load Flow Studies of a Grid Interfaced w

41

X50Hz = X60HZ × (ω50Hz / ω60Hz)

B50Hz = B60HZ × (ω50Hz / ω60Hz)

Table1: 33KV and 220KV Line data

Line X50Hz

[p.u.]

B50Hz

[p.u.] From

Bus

To

Bus

153 154 0.0375 0.08333

153 154 0.045 0.125

153 3006 0.01 0.025

154 203 0.0333 0.08333

154 205 0.00278 0.075

154 3008 0.01833 0.25

203 205 0.0375 0.006667

203 3003 0.0375 0.06667

3001 3004 0.00667 0

3002 3005 0.045 0.075

3003 3005 0.045 0.075

3003 3005 0.045 0.075

3005 3006 0.025 0.05833

3005 3007 0.02083 0.05

3005 3008 0.04167 0.1

3007 3008 0.02083 0.05

Page 42: Load Flow Studies of a Grid Interfaced w

42

4.3.2 400KV Line Parameters

The values for the 400 kV line parameters calculated are shown in Table 2

Line

R [p.u] X [p.u] B [p.u] From

bus To bus

151 152 0.00183 0.0201 0.5623

151 152 0.00183 0.0201 0.5623

151 201 0.00091 0.01005 0.2811

152 202 0.00146 0.01608 0.4498

152 3004 0.00128 0.01407 0.39361

201 202 0.00091 0.01005 0.28115

201 204 0.00091 0.01005 0.28115

Table2: 400KV Line data

Page 43: Load Flow Studies of a Grid Interfaced w

43

4.3.3 Transformers

For the two-winding transformers in the “savnw” grid, the transformer reactance is

frequency dependent, so their values also have to be adapted to the 50 Hz frequency,

according to Equation

X50Hz = X60HZ × (ω50Hz / ω60Hz)

B50Hz = B60HZ × (ω50Hz / ω60Hz)

The values of the results of the calculations for the transformers in the grid are shown

in Table 3

Table3: Grid Transformer Data

Buses X50Hz

[p.u.] From

Bus

To

Bus

101 151 0.01133

152 153 0.00417

201 211 0.01771

202 203 0.01354

204 205 0.0125

205 206 0.01111

3001 3002 0.0125

3001 3011 0.00833

3004 3005 0.01354

3008 3018 0.07083

Page 44: Load Flow Studies of a Grid Interfaced w

44

4.3.4 Loads and Shunt Compensators

Addition of the wind farm rated at 110 MW to bus 102 of the grid in the place of the

existing 750 MW conventional power plant leads to an imbalance of active and

reactive powers. This imbalance can be compensated by reducing the consumed

power in the loads.

As so, the values of the load powers of the grid are presented in Table 4.

The shunt compensators are also regulated in order to maintain the voltage in the

buses at values within reasonable values (between 0.95p.u and 1.05p.u). Table 5

outlines the values of the shunt compensators of the grid [1].

Bus Pload

[MW]

Qload

[Mvar]

153 200 100

154 500 450

154 400 350

203 200 100

205 1000 700

3005 100 50

3007 200 75

3008 100 50

Table 4: Load Data

Table 5: Shunt Compensator Data

Bus Bshunt

[Mvar]

151 0

153 150

154 300

201 300

203 100

205 300

Page 45: Load Flow Studies of a Grid Interfaced w

45

4.4 WIND FARM MODEL

The model for the offshore wind farm is based in an existing installation: the

Lillgrund Wind Farm.

This wind farm is located off the coast of Sweden, at a distance of 9 km from the

Point of Connection in the onshore grid and the transmission is achieved by a

combination of an AC sea cable (7 km long) and an AC land cable (2 km long). With

48 wind turbines, rated at 2, 3 MW each, the total capacity of the wind farm is 110

MW. Figure 6 depicts the layout of the wind turbines in the Lillgrund wind farm, used

as a reference here.

Fig 6: Layout of wind turbines in Wind Farm

As can be seen in Figure 6, the internal grid of the Lillgrund wind farm consists of 33

kV sea cables divided in five feeders and each of these feeders connects 9 or 10 wind

turbines to the offshore substation. The total is 48 wind turbines rated at 2, 3 MW.

The modeled wind farm is based on this layout. The turbines are joined in aggregates

and then connected to the offshore substation bus via 33 kV AC cables [1].

Page 46: Load Flow Studies of a Grid Interfaced w

46

4.5 WIND TURBINES

The wind turbines used are the GE 1.5 MW model, available in the PSS®E Wind

package. This model is of a DFIG (Doubly Fed Induction Generator) wind turbine

developed by General Electric and released for PSS®E simulation and testing.

In order to match the 110 MW of the reference wind farm, a total of 74 1.5 MW wind

turbines were used in the model. These are joined in five aggregates: two aggregates

of 24 MW (16 wind turbines for each aggregate) and three of 21 MW (14 wind

turbines per aggregate). This actually adds up to 111 MW, which is the value assumed

hereby for the wind farm power.

For PSS®E simulation of the wind farm, two distinct models are designed for the

wind turbines: the

Steady-state model (which allows the power flow simulations) and the transient

model (used for Dynamic simulations) [1].

4.6 STEADY-STATE MODEL

The load flow provides initial conditions for dynamic simulations. In the Load Flow

parameters of the PSS®E, the wind turbines were modeled as five conventional

generators, rated at 24 MW and 21 MW. The values specified on the existing

generator record are outlined in Table 6.

Note that the values in Table were calculated considering the values in the Individual

WTG Power

Flow Data of the PSS®E Wind User Guide and multiplying by the number of lumped

elements, as recommended by the PSS®E guide.

Since the model used is of a DFIG wind turbine, both the active and reactive power

can be controlled. As so, for the wind turbine aggregates, for the HVAC transmission

system, the wind turbines were regulated for a unit power factor, which means no

reactive power is generated by the wind turbines. The reason is that the AC cable

already produces a significant amount of reactive power, so an additional quantity of

reactive power generated by wind farm would deteriorate the system behavior [1].

Page 47: Load Flow Studies of a Grid Interfaced w

47

24MW

Aggregates

21MW

Aggregates

PgenMW 24 21

PmaxMW 24 21

PminMW 1.1 1

QgenMvar 0 0

QmaxMvar 0 0

QminMvar 0 0

MbaseMVA 26 23

Xsourcep.u 08 08

Table 6: Wind Turbine Data

4.6.1 Step-Up Transformers

The 0.69/33 kV transformers that adapt the voltage at the generation buses (690 V) to

the voltage of the internal grid of the wind farm (33 kV) have the parameters

presented in Table 7.

As each aggregate contains 14 or 16 wind turbines, the rated power of the

transformers is respectively, 24.5 MVA and 28 MVA [1].

Transformer Parameters Value

Unit Rating MVA 175

Unit Rated Voltage kV/kv 0.69/33

Unit Impedance% 5.75

Unit X/R 7.5

Table 7: Wind Farm Transformer Data

Page 48: Load Flow Studies of a Grid Interfaced w

48

4.6.2 33 kV Cables

The cables used to link the five buses where the wind turbines are connected to the

offshore bus are 33 kV AC cables. The cable parameters are presented in Table 8

Cable Length

[km] Rp.u Xp.u Bp.u

From

Bus

To

Bus

1 102 1 0.003857 0.010101 0.000957

2 102 0.8 0.003085 0.008081 0.000766

3 102 0.6 0.002314 0.006061 0.000574

4 102 0.4 0.001543 0.00404 0.000383

5 102 0.2 0.000771 0.00202 0.000191

Table 8: 33KV Cable Data

4.7 LAYOUT OF THE OFFSHORE WIND FARM

Figure illustrates the wind farm designed in PSS®E, where the wind turbines, the

step-up transformers and the 33 kV cables mentioned above are represented [1].

Fig 7: PSS®E model of the offshore wind farm

Page 49: Load Flow Studies of a Grid Interfaced w

49

4.8 HVAC TRANSMISSION

The HVAC transmission is the simplest alternative for the transmission of the

electrical power of the offshore wind farm to the onshore grid. The main components

are the AC transmission cable and the two transformers: onshore and offshore. Figure

8 illustrates the HVAC transmission scheme, with the AC cable and both

transformers. For proper compensation of the reactive power generated in the cable,

shunt reactors (or a STATCOM device) were applied to one or both ends of the cable.

They are not however represented here [1].

Fig 8: HVAC transmission layout in PSS®E

4.8.1 150KV Power Cable

The power cable chosen is a 100Km, 150 kV XLPE cable. 150 kV is a typical option

for offshore wind farms, used in, for example, the Horns Rev wind farm, in Denmark.

Hence using the parameters of the power cable in Horns Rev

Cable Rkm

[Ω/km]

Xkm

[Ω/km]

Ckm

[µF/km]

Length

[km] Rp.u Xp.u Bp.u

From

Bus

To

Bus

20 21 0.039 0.12 0.19 100 0.0173 0.053 1.34235

Table 9: 150KV Cable parameters

Page 50: Load Flow Studies of a Grid Interfaced w

50

4.8.2 Onshore and Offshore Transformers

The offshore transformer adapts the voltage from the 33 kV of the internal grid to the

150 kV of the power cable. As for the onshore transformer, it is used to increase the

voltage from the 150 kV of the cable to the 400 kV of the onshore grid. Table10

shows the offshore and onshore transformers data [1].

Buses

Location

Rated

Voltage

KV

Rated

Voltage

Impedance

%

Rating

MVA

Xp.u.

100MVA

Based From

Bus To Bus

20 102 Offshore 33/150 13.8 160 0.08625

21 151 Onshore 150/400 15 200 0.075

Table 10: Onshore and offshore transformer data

4.9 STATCOM FOR STEADY-STATE SIMULATION

For power flow analysis, the STATCOM is modeled as a FACTS device with the

parameters adjusted as to simulate the behavior of this device. In both cases of the use

of the STATCOM (in HVAC transmission) it was modeled with the same parameters.

Fig 9: Graphic representation of a Statcom in PSS®E

The parameters presented in Table 11 are the most important values used in power

flow analysis of the STATCOM and they are obtained using PSS®E Manual for

FACTS devices

Page 51: Load Flow Studies of a Grid Interfaced w

51

Parameter Rectifier

Device Number 1

Terminal Bus 0

Control Mode Normal

P Setpoint MW 0.00

Q Setpoint MVAR 0.00

V Send Setpoint 1.02

Shunt Max MVA 64

RMPCT % 100

Bridge Max 0

V term max pu 1.1

V term min pu 0.9

V Series Max pu 1

I Series Max MVA 64

Dummy Series Xpu 0.05

V Series Reference Sending end voltage

Table 11: STATCOM Parameters

Page 52: Load Flow Studies of a Grid Interfaced w

52

4.10 DIAGRAM OF THE GRID

The resulting grid, after the changes performed, is presented in the single-line diagram

shown in Figure, in which the offshore wind farm is already included. Bus 102

referred above, is marked in the figure 10. The legend of the colors used in the figure

for each voltage value is presented in Table 12

Fig 10: Single line diagram of the wind Farm connected to the Grid

Page 53: Load Flow Studies of a Grid Interfaced w

53

Color Rated

Voltage KV

RED 440

BLACK 220

PURPLE 150

DARK GREEN 33

BLUE 20

ORANGE 13.8

BORDEAUX RED 0.7

Table 12: Color Representation of Voltages

4.11 MODELING FOR DYNAMIC ANALYSIS

The dynamic data file so called (.dyr) file in PSS®E consist of dynamic parameter

data for all conventional synchronous generators, turbines, exciters governors and

other devices. The first step in dynamic simulation using initial dynamic file is to

enter the detailed dynamic model data for Wind Farm, which is saved in a file. This

file contains a group of records, each of which defines the location of a dynamic

WTG model in the grid along with the constant parameters of the model. The PSS®E

university version 33 provides a dynamic model for a DFIG wind turbine. The model

includes generator, electrical control, wind turbine and pitch control. Dynamic

simulation is performed based on the load flow data that provide the transmission

grid, load, and generator data. In this study, dynamic analysis is performed to

investigate the WTGs model response subjected to grid disturbances. The most

relevant disturbance for the study case is a three-phase symmetrical short-circuit fault

on an onshore bus. Additional fault events can be simulated on the different buses of

the Wind Turbine Generation Station (WTGS) to see the behavior of the wind farm

but here our focus will only be on the simulation of fault on the 400KV onshore bus

named as 3005 [8].

Page 54: Load Flow Studies of a Grid Interfaced w

54

4.11.1 PSS®E Dynamic model of DFIG

The variable speed wind turbine using DFIG are more popular technology which is

used word-wide due to advantages such as high energy efficiency and controllability.

DFIG is basically a standard, wound rotor induction generator with a voltage source

converter connected to the slip-rings of the rotor. The stator winding are coupled

directly to the grid and the rotor winding is connected to power converter as shown in

figure 11.

The steady-state and dynamic characteristics of DFIG are dominated by the power

converter. The converters allow the machine to operate over a wider range of speed,

and control active and reactive power independently. This means that DFIG have the

capability to participate in steady-state and dynamic VOLT/VAR control. In some

DFIG designs, a crow-bar or DC chopper circuit may be used to short the rotor-side

converter during a close-in transmission fault to avoid excessively high DC link

voltage and keep the machine running. If the rotor-side converter is shorted, the

dynamic behavior is similar to an induction generator. During a low voltage event, the

converter tries to retain full in control of active and reactive currents. DFIG can be

designed to meet low voltage ride-through requirements without external reactive

power support. Converters are current-limited devices, and this plays a major role in

the dynamic response of DFIGs to grid disturbances. DFIGs also have a pitch control

to optimize energy capture [8].

Fig 11: DFIG Model

The PSS®E wind turbine model WT3 was used for the dynamic simulation study with

the objective of simulating the dynamic performance of a wind Farm employing

DFIG technology. The generic WT3 model is included as a standard model in the

Dynamic Model Library of PSS®E version 33. The WT3 model can only be used

Page 55: Load Flow Studies of a Grid Interfaced w

55

when the generator is specified as a wind generator and not as conventional generator

in the power flow data file. As shown in the fig 12

Fig 12: Power Flow Data File

0 if this is not a wind machine (this is the default value).

1 if this is a wind machine which participates in voltage control, with the

values of QT and QB on the data record specifying the machine‟s reactive

power limits.

2 if this is a wind machine which participates in voltage control, with the

specified power factor and the machine‟s active power setting (PG on the data

record) used to set the machine‟s reactive power limits.

3 if this is a wind machine which operates at a fixed power, with the

machine‟s reactive power output and reactive power upper and lower limits all

equal, and set based on the specified power factor and the machine‟s active

power setting [8].

4.11.2 Power Factor

ignored if the wind control mode is 0

is used in setting the machine‟s reactive power limits when the wind control

mode is 2 or 3

Negative value may be specified when the wind control mode is 3, and is

interpreted as a leading power factor (i.e., the wind machine produces active

power and absorbs reactive power).

The WT3 generic wind turbine model consists of the following main modules:

WT3G generator/converter module

WT3E electrical control module

WT3T turbine module and

WT3P pitch control module.

Page 56: Load Flow Studies of a Grid Interfaced w

56

Figure 13 shows the interaction between these modules.

Fig 13: PSS®E DFIG Generic Model

The DFIG includes 4 modules which are responsible for:

WT3G1, doubly-fed induction generator which is mostly an algebraic model

to calculate the current injection to the grid based on commands from controls,

with or without the PLL control.

WT3E1, electrical control including the torque control and a voltage control.

WT3T1, the turbine model including a two-mass shaft mechanical system and

a simplified method of aerodynamic conversion, namely ΔP=Kaero*θ*Δθ

where P is mechanical power, θ is a pitch angle; this method was validated

against results obtained when using the Cp matrix

WT3P1, the pitch control.

Tables 13, 14, 15, 16, show the dynamic data for Double Fed Inductive Generator

based on WT3 Generic Wind Model. Values for the parameters of these models were

based on typical values given in the PSS®E Wind manual. The number of aggregated

wind turbines was changed in the models to 14 for the 21 MW aggregates and 16 for

the 24 MW aggregates [8].

Page 57: Load Flow Studies of a Grid Interfaced w

57

Symbol Value Unit

Vw 1.25 p.u

H 4.95 MW*sec/MVA

DAMP 0 p.u P/pu

Kaero 0.007 Const.

Theta 2 21.98 Deg.

Htfac 0.875 Hturb.h

Freq 1.8 HZ

DSHAFT 1.5 P.U P/pu

Table 13: Turbine Model WT3T1

Symbol Value Unit

Xeq 0.8 p.u

Pll gain 30 Con

Pll integrator gain 1 Con

Pll maximum 0.1 Cons

Turbine MW rating 0.5 MW

No.of lumped WT-s number of turbines

for each feeder Integer

Table 14: Generator Model WT3G1

Table 15: Pitch Model WT3P1

Symbol Value Unit

Tp 0.3 Sec

Kpp 150 p.u

Kip 25 p.u

Kpc 3 p.u

Kik 30 p.u

Tetamin 0 Deg

Tetamax 27 Deg

RTetamax 10 Deg/sec

PMX 1 p.u on Mbase

Page 58: Load Flow Studies of a Grid Interfaced w

58

Symbol Value Unit Symbol Value Unit

Tfv 0.15 Sec T_Power 5 sec

Kpv 18 p.u Koi 0.05 Con

Kiv 5 p.u VMNCL 0.9 Con

Xc 0 p.u VMAXCL 1.2 Con

Tfp 0.05 Sec Kqv 40 Con

Kpp 3 p.u X1Qmin -0.5 Con

Kip 0.6 p.u X1QMax 0.4 Con

PMX 1.12 p.u Tv 0.05 Con

PMN 0.1 p.u Fn 1 con

QMX 0.309 p.u Wpmin 0.69 p.u

QMN -0.309 p.u Wp20 0.78 p.u

IPMAX 1.1 p.u Wp40 0.98 p.u

TRV 0.05 Sec Wp60 1.12 p.u

RPMX 0.45 p.u pwp 0.74 p.u

RPMN -0.45 p.u Wp100 1.2 p.u

Table16: Electric Part Model WT3E1

Page 59: Load Flow Studies of a Grid Interfaced w

59

CHAPTER 5

RESULTS & OBSERVATIONS

This chapter presents the results of the steady-state simulations performed on the grid

with the offshore wind farm, as described in Chapter 4. Results are analyzed and

discussion of the results is also performed.

5.1 INTRODUCTION

The power flow analysis carried out comprehends numerical calculations of active

and reactive power flows and node voltages. PSS/E software is used, in the scope of

this thesis, for the power flow analysis of power grid with an offshore wind farm.

Special attention is given to the Point of Common Coupling (hereby designated as

PCC), i.e., the point of connection of the wind farm with the remaining grid. The

voltage at the PCC, the active power injected and the reactive power

injected/absorbed in the PCC is analyzed as a part of the power flow study. Power

losses for each transmission system are also assessed.

The power flow results are presented by the single-line diagrams of the network (from

the PSS/E load flow software). The active and reactive flows at each end of the

branches and the voltage magnitude and angle at each bus are depicted in each figure

of this chapter. Figure depicts how each of the values from the power flow

calculations are represented in the power flow result figures [1].

Fig 14: Legend of the values presented in the single-line diagrams.

5.2 POWER FLOW SIMULATION RESULTS

For the HVAC transmission system, the power flow analysis focuses on the voltage

level and reactive power flow in the wind farm and the power cable connecting the

wind farm to the grid. Therefore, some reactive power compensation options are

Page 60: Load Flow Studies of a Grid Interfaced w

60

studied with the objective to compensate the reactive power flow at different buses of

Wind farm so as to keep the voltage in to the desires range of 0.95pu to 1.05pu.

The main criteria for the choice of the value of the compensation device is the power

factor at the PCC, which is chosen to be approximately of 0.9, a typical value in grid

integration of wind farms. As so, the shunt reactor chosen for offshore compensation

only absorbs certain amount of reactive power, as the 0.9 power factor at the PCC is

guaranteed with this value.

An estimate of the reactive power produced by the 150 kV AC cable can be made

taking into account Equation. The approximate amount of reactive power produced by

the 100 km cable is given by equation below

Note that, for HVAC power flow, the wind turbine generators supply no reactive

power, since there is already an excess of reactive power, as a consequence of the

shunt capacitance of the AC cable. Therefore, the capability of the DFIG machines of

providing voltage support to the grid, by supplying reactive power, is not considered

for the present study.

Different strategies are made in order to compensate the reactive power produced due

to the power cable that is interconnecting the wind farm to the grid. This reactive

power needs to be compensated in order to keep the voltage profile of all the buses

and generators at the wind farm into desired range of 0.95pu to 1.05pu. It must be

noted that in this study of wind farm, doubly fed induction generators are used which

have the capability to control the reactive power flow but for the wind farms of larger

capacity like 110MW wind farm this approach of compensating the reactive power

seems less effective. Due to which different compensation devices are connected to

keep the control of reactive power flow in order to keep the voltages at all the buses

of the power system into desired limits.

Here in this study three cases are discussed which are as follows:

Wind farm without compensation devices

Wind farm with shunt reactor

Wind farm with STATCOM

Page 61: Load Flow Studies of a Grid Interfaced w

61

These cases are created to analyze the importance of the external compensation

devices into the wind farms.

Each case simulation describes the reactive, active power flows at different buses and

voltages at different branches and buses. It also uses „„Enable contour‟‟ facility of

PSSE to show the voltage level of different buses.

Page 62: Load Flow Studies of a Grid Interfaced w

62

CASE1

WIND FARM WITHOUT REACTIVE POWER COMPENSATION

After developing the steady-state model of the power system having wind farm

connected to it, the load flow analysis is performed in order to carry out the impact

studies. Full Newton-Raphson method is used to perform the power flow studies. In

Case 1 the wind farm can be seen connected to the power system. In this case no

compensation device is connected to the wind farm and the results are obtained as

shown in fig15.

Fig 15: Power Flow results of Wind Farm without Compensation

In table given 17 the result of voltages at different buses can be observed. It can be

seen that at all the buses of the wind farm the voltages are extremely high as

compared to the desired value of the voltages. The voltage is as high as 1.19pu

whereas the desired voltage limit is 1.05pu. The voltage reaches to the extreme value

due to high capacitive reactive power produced by the power cable, which needs to be

compensated in order to bring the voltage under normal ranges.

Page 63: Load Flow Studies of a Grid Interfaced w

63

Bus

Number Bus Name Base KV Code Voltage(p.u)

Angle

(deg)

1 PARK 1 33.0 1 1.1952 8.35

2 PARK 2 33.0 1 1.1950 8.34

3 PARK 3 33.0 1 1.1948 8.31

4 PARK 4 33.0 1 1.1947 8.29

5 PARK 5 33.0 1 1.1945 8.27

20 BUS

OFFSHORE

150.0 1 1.1973 4.42

21 BUS ONSHORE 150.0 1 1.1426 2.60

101 NUC-A 33.0 2 1.0221 3.28

102 NUC-B 33.0 1 1.1944 8.26

151 NUCPANT 400.0 1 1.0343 -1.35

152 MD500 400.0 1 1.0172 -4.46

153 MD230 220.0 1 0.9992 -5.68

154 DOWNTN 220.0 1 0.9705 -9.23

201 HYDRO 400.0 1 1.0400 -2.87

202 EAST500 400.0 1 1.0208 -4.74

203 SUB500 220.0 1 0.9981 -7.65

204 SUB230 400.0 1 1.0142 -4.98

205 URBGEN 220.0 1 0.9800 -8.61

206 HYDRO_G 18.0 2 1.0807 -3.61

211 MINE 20.0 2 1.0307 2.47

3001 E-MINE 220.0 1 1.0279 -1.62

3002 S-MNE 400.0 1 1.0257 -2.31

3003 WEST 220.0 1 1.0121 -2.58

3004 WEST 400.0 1 1.0015 -4.74

3005 UPTOWN 220.0 1 1.0001 -5.78

Page 64: Load Flow Studies of a Grid Interfaced w

64

3006 RURAL 220.0 1 0.9816 -5.71

3007 CATDOG 220.0 1 0.9835 -8.13

3008 MINE_G 220.0 3 1.0400 -8.17

3011 CATDOG_G 220.0 2 1.0360 0.00

3018 GEN BUS1 0.7 2 1.1952 -4.19

90001 GEN BUS2 0.7 2 1.1950 8.64

90002 GEN BUS3 0.7 2 1.1948 8.62

90003 GEN BUS4 0.7 2 1.1947 8.56

90004 GEN BUS5 0.7 2 1.1945 8.54

Table 17: Voltages at different buses

Table 18 shows the active and reactive power generated by different generating units.

It can be seen that power factor of the wind farm is 1, due to which no reactive power

is supplied by the WTGs to the Grid.

Bus

Number Bus Name Code PGen(MW) QGen(MW)

Voltage

(p.u)

101 NUC-A 2 750.0 100.0 1.0221

206 URBGEN 2 800.0 458.8 0.9800

211 HYDRO_GEN 2 600.0 252.2 1.0400

3011 MINE_G 3 367.4 112..3 1.0400

3018 CATDOG_G 2 100.0 80.0 0.9835

90001 GEN BUS1 2 24.0 0.0 1.1952

90002 GEN BUS2 2 24.0 0.0 1.1950

90003 GEN BUS3 2 21.0 0.0 1.1948

90004 GEN BUS4 2 21.0 0.0 1.1947

90005 GEN BUS4 2 21.0 0.0 1.1945

Table 18: Data of Active and Reactive power generated

Page 65: Load Flow Studies of a Grid Interfaced w

65

Figure 16 color display of the voltages at the different parts of the power system. Here

it can be seen that color at all the buses of the wind farm is red which indicates that

voltages at these buses are very high as compared to the normal voltage range.

Fig 16: Color display of voltages at buses

This is the power flow program which shows the convergence of the solution. The

method used was full Newton-Raphson power flow method.

Page 66: Load Flow Studies of a Grid Interfaced w

66

SIEMENS POWER TECHNOLOGIES INTERNATIONAL

50 BUS POWER SYSTEM SIMULATOR--PSS(R)E University-33.4.0

INITIATED ON THU, JAN 08 2015 2:26

PSS(R)E PROGRAM APPLICATION GUIDE EXAMPLE

BASE CASE INCLUDING SEQUENCE DATA

Diagonals = 34 Off-diagonals = 52 Maximum size = 82

ITER DELTAP BUS DELTAQ BUS DELTA/V/ BUS DELTAANG BUS

0 23.1846( 151 ) 11.6593( 211 )

0.33741( 1 ) 0.28003( 90001 )

1 2.6871( 151 ) 13.6337( 211 )

0.14515( 3018 ) 0.11360( 90001 )

2 0.2356( 201 ) 1.0717( 206 )

0.02800( 3018 ) 0.01425( 90001 )

3 0.0015( 20 ) 0.2126( 3018 )

0.00815( 3018 ) 0.00050( 3018 )

4 0.0001( 3008 ) 3.5016( 3018 )

0.15212( 3018 ) 0.01307( 3018 )

5 0.0281( 3018 ) 1.5351( 206 )

0.02969( 3018 ) 0.00413( 3018 )

6 0.0028( 205 ) 0.3256( 206 )

0.00332( 206 ) 0.00043( 206 )

7 0.0001( 205 ) 0.0317( 206 )

0.00032( 206 ) 0.00004( 206 )

8 0.0000( 205 ) 0.0025( 206 )

Page 67: Load Flow Studies of a Grid Interfaced w

67

0.00003( 206 ) 0.00000( 206 )

9 0.0000( 205 ) 0.0002( 206 )

Reached tolerance in 9 iterations

Largest mismatch: -0.00 MW -0.02 Mvar 0.02 MVA at bus 206 [URBGEN 18.000]

System total absolute mismatch: 0.04

MVA

SWING BUS SUMMARY:

BUS# X-- NAME --X BASKV PGEN PMAX PMIN QGEN QMAX QMIN

3011 MINE_G 13.800 367.4 900.0 0.0 112.3 600.0 -100.0

Page 68: Load Flow Studies of a Grid Interfaced w

68

CASE 2

WIND FARM WITH SHUNT REACTOR

In case a shunt reactor is connected to the offshore bus to compensate the reactive

power. As discussed earlier the value of the shunt reactor is chosen so to obtain the

power factor of 0.9 lag at Bus 102 (point of common coupling, PCC). Same Full

Newton-Raphson method is used to perform the load flow and the results are

obtained. The Active and reactive power flows and voltage at all the buses can be

observed.

Fig 17: power Flow results of wind farm with Shunt reactor

Figure 18 shows the color display of the voltages at the different parts of the power

system. Here it can be seen that color at all the buses of the wind farm changed from

dark red to sky blue by the use of the static VAR compensator of proper rating at the

offshore bus, which indicates that the voltages are under the normal ranges.

Fig 18: Color display of Voltages at different buses

Page 69: Load Flow Studies of a Grid Interfaced w

69

The table 19 shows the voltages at different buses of the power system including that

of the wind farm buses. It can be observed that by the use of the shunt reactor at the

offshore bus, the voltages are brought below the max voltage limit of 1.05pu.

Bus

Number

Bus Name Base KV Code Voltage(p.u) Angle

(deg)

1 PARK 1 33.0 1 0.9864 12.99

2 PARK 2 33.0 1 0.9862 12.97

3 PARK 3 33.0 1 0.9860 12.93

4 PARK 4 33.0 1 0.9850 12.90

5 PARK 5 33.0 1 0.9856 12.88

20 BUS

OFFSHORE

150.0 1 0.9908 7.23

21 BUS ONSHORE 150.0 1 1.0132 3.14

101 NUC-A 33.0 2 1.0200 3.35

102 NUC-B 33.0 1 0.9855 12.85

151 NUCPANT 400.0 1 1.0267 1.31

152 MD500 400.0 1 1.0134 4.47

153 MD230 220.0 1 0.9961 5.69

154 DOWNTN 220.0 1 0.9700 9.26

201 HYDRO 400.0 1 1.0400 2.89

202 EAST500 400.0 1 1.0196 4.76

203 SUB500 220.0 1 0.9974 7.68

204 SUB230 400.0 1 1.0142 5.01

205 URBGEN 220.0 1 0.9800 8.64

206 HYDRO_G 18.0 2 1.0303 3.66

211 MINE 20.0 2 1.0597 2.60

3001 E-MINE 220.0 1 1.0301 1.63

3002 S-MNE 400.0 1 1.0268 2.31

3003 WEST 220.0 1 1.0248 1.63

Page 70: Load Flow Studies of a Grid Interfaced w

70

3004 WEST 400.0 1 1.0095 2.31

3005 UPTOWN 220.0 1 0.9995 2.59

3006 RURAL 220.0 1 0.9973 4.75

3007 CATDOG 220.0 1 0.9799 5.80

3008 MINE_G 220.0 3 0.9522 5.72

3011 CATDOG_G 220.0 2 1.0420 8.15

3018 GEN BUS1 0.7 2 1.0340 8.20

90001 GEN BUS2 0.7 2 0.0040 0.00

90002 GEN BUS3 0.7 2 0.0070 4.21

90003 GEN BUS4 0.7 2 0.0056 13.42

90004 GEN BUS5 0.7 2 0.0040 13.39

Table19: Voltages at different buses including wind farms

The table 20 gives details of the active and reactive power generated by different

generators. It is observed that no reactive power is generated by the WTGs and none

of the generator is overloaded.

Bus

Number

Bus Name Code PGen(MW) QGen(MW) Voltage

(p.u)

101 NUC-A 2 750.0 49.3 1.0200

206 URBGEN 2 800.0 481.7 0.9800

211 HYDRO_GEN 2 600.0 122.9 1.0400

3011 MINE_G 3 368 120.6 0.9822

3018 CATDOG_G 2 100.0 80.0 0.9864

90001 GEN BUS1 2 24.0 0.0 0.9864

90002 GEN BUS2 2 24.0 0.0 0.9862

90003 GEN BUS3 2 21.0 0.0 0.9852

90004 GEN BUS4 2 21.0 0.0 0.9859

90005 GEN BUS4 2 21.0 0.0 0.9858

Table 20: Active and Reactive power generated by different generators.

Page 71: Load Flow Studies of a Grid Interfaced w

71

This is the power flow program which shows the convergence of the solution. The

method used was full Newton-Raphson power flow method.

SIEMENS POWER TECHNOLOGIES INTERNATIONAL

50 BUS POWER SYSTEM SIMULATOR--PSS(R)E University-33.4.0

INITIATED ON THU, JAN 08 2015 2:26

PSS(R)E PROGRAM APPLICATION GUIDE EXAMPLE

BASE CASE INCLUDING SEQUENCE DATA

Diagonals = 34 Off-diagonals = 52 Maximum size = 82

ITER DELTAP BUS DELTAQ BUS DELTA/V/ BUS DELTAANG BUS

0 23.1846( 151 ) 9.4961( 211 )

0.15868( 211 ) 0.27989( 90001 )

1 1.5258( 151 ) 12.4269( 211 )

0.15219( 3018 ) 0.04278( 20 )

2 0.2099( 201 ) 1.0471( 206 )

0.02687( 3018 ) 0.00490( 21 )

3 0.0011( 205 ) 0.2050( 3018 )

0.00775( 3018 ) 0.00047( 3018 )

4 0.0001( 3008 ) 3.6260( 3018 )

0.15558( 3018 ) 0.01331( 3018 )

5 0.0295( 3018 ) 1.6009( 206 )

0.03122( 3018 ) 0.00434( 3018 )

6 0.0030( 205 ) 0.3419( 206 )

0.00347( 206 ) 0.00045( 206 )

7 0.0001( 205 ) 0.0349( 206 )

Page 72: Load Flow Studies of a Grid Interfaced w

72

0.00035( 206 ) 0.00004( 206 )

8 0.0000( 205 ) 0.0029( 206 )

0.00003( 206 ) 0.00000( 206 )

9 0.0000( 205 ) 0.0002( 206 )

Reached tolerance in 9 iterations

Largest mismatch: 0.00 MW 0.02 Mvar 0.02 MVA at bus 205 [SUB230 220.00]

System total absolute mismatch: 0.05 MVA

SWING BUS SUMMARY:

BUS# X-- NAME --X BASKV PGEN PMAX PMIN QGEN QMAX QMIN

3011 MINE_G 13.800 368.0 900.0 0.0

120.6 600.0 -100.0

Page 73: Load Flow Studies of a Grid Interfaced w

73

CASE3

WIND FARM WITH STATCOM

In the third case the strategy which is used is the replacement of the shunt reactor with

the STATCOM at the offshore bus for the compensation of the reactive power to keep

the voltages closer to the nominal values. The power flows and voltages can be seen

in the figure 19.

Fig 19: Power Flow results of Wind Farm with STATCOM

Figure 20 shows the color display of the voltages at the different parts of the power

system. Here it can be seen that color at all the buses of the wind farm changed from

dark red to light green by the use of the static synchronous compensator (STSTCOM)

of proper rating at the offshore bus, which indicates that the voltages are under the

normal ranges.

Fig 20: Color display of voltages at different buses

Page 74: Load Flow Studies of a Grid Interfaced w

74

Table 21 shows the voltages at all the buses of the power system after the use of the

STATCOM at the offshore bus for the purpose of reactive power compensation. It can

be observed that voltage at all the buses of the wind farm is in the desired range of

0.95pu to 1.05pu.

Bus

Number Bus Name Base KV Code Voltage(p.u)

Angle

(deg)

1 PARK 1 33.0 1 1.0160 12.25

2 PARK 2 33.0 1 1.0159 12.22

3 PARK 3 33.0 1 0.0156 12..18

4 PARK 4 33.0 1 1.0155 12.16

5 PARK 5 33.0 1 1.0153 12.13

20 BUS OFFSHORE 150.0 1 1.0200 6.81

21 BUS ONSHORE 150.0 1 1.0315 3.09

101 NUC-A 33.0 2 1.0200 3.35

102 NUC-B 33.0 1 1.0151 12.11

151 NUCPANT 400.0 1 1.0276 1.31

152 MD500 400.0 1 1.0139 4.46

153 MD230 220.0 1 0.9964 5.68

154 DOWNTN 220.0 1 0.9701 9.24

201 HYDRO 400.0 1 1.0400 2.87

202 EAST500 400.0 1 1.0197 4.74

203 SUB500 220.0 1 0.9975 7.76

204 SUB230 400.0 1 1.0142 4.99

205 URBGEN 220.0 1 0.9800 8.63

206 HYDRO_G 18.0 2 1.0300 3.64

211 MINE 20.0 2 1.0395 2.77

3001 E-MINE 220.0 1 1.0301 1.62

3002 S-MNE 400.0 1 1.0269 2.31

3003 WEST 220.0 1 1.0249 2.59

3004 WEST 400.0 1 1.0098 4.74

3005 UPTOWN 220.0 1 0.9998 5.76

Page 75: Load Flow Studies of a Grid Interfaced w

75

3006 RURAL 220.0 1 0.9977 5.71

3007 CATDOG 220.0 1 0.9801 8.14

3008 MINE_G 220.0 3 0.9824 8.18

3011 CATDOG_G 220.0 -2 1.0400 0.00

3018 GEN BUS1 0.7 -2 1.0350 4.20

90001 GEN BUS2 0.7 -2 1.0160 12.65

90002 GEN BUS3 0.7 -2 1.0158 12.62

90003 GEN BUS4 0.7 -2 1.0156 12.53

90004 GEN BUS5 0.7 -2 1.0153 12.48

Table 21: Voltages at different buses using STATCOM

The table 22 gives details of the active and reactive power generated by different

generators. It is observed that no reactive power is generated by the WTGs and none

of the generator is overloaded.

Bus

Number Bus Name Code PGen(MW) QGen(MW)

Voltage

(p.u)

101 NUC-A 2 750.0 58.1 1.0200

206 URBGEN 2 800.0 478.8 0.9800

211 HYDRO_GEN 2 600.0 2.9 1.0400

3011 MINE_G 3 368 119.5 1.0200

3018 CATDOG_G 2 100.0 80.0 1.0000

90001 GEN BUS1 2 24.0 0.0 1.0000

90002 GEN BUS2 2 24.0 0.0 1.0000

90003 GEN BUS3 2 21.0 0.0 1.0000

90004 GEN BUS4 2 21.0 0.0 1.0000

90005 GEN BUS4 2 21.0 0.0 1.0000

Table22: Active and Reactive power generated using STATCOM.

Page 76: Load Flow Studies of a Grid Interfaced w

76

This is the power flow program which shows the convergence of the solution. The

method used was full Newton-Raphson power flow method.

SIEMENS POWER TECHNOLOGIES INTERNATIONAL

50 BUS POWER SYSTEM SIMULATOR--PSS(R)E University-33.4.0

INITIATED ON THU, JAN 08 2015 2:21

PSS(R)E PROGRAM APPLICATION GUIDE EXAMPLE

BASE CASE INCLUDING SEQUENCE DATA

Diagonals = 34 Off-diagonals = 52 Maximum size = 82

ITER DELTAP BUS DELTAQ BUS DELTA/V/ BUS DELTAANG BUS

0 23.1846( 151 ) 8.4145( 211 )

0.14079( 211 ) 0.27984( 90001 )

1 1.3339( 151 ) 12.1903( 211 )

0.15348( 3018 ) 0.04093( 20 )

2 0.2089( 201 ) 1.0247( 206 )

0.02622( 3018 ) 0.00786( 90001 )

3 0.0010( 205 ) 0.1963( 3018 )

0.02811( 102 ) 0.01292( 90001 )

4 0.0030( 21 ) 3.6299( 3018 )

0.15556( 3018 ) 0.01327( 3018 )

5 0.0294( 3018 ) 1.5914( 206 )

0.03124( 3018 ) 0.00436( 3018 )

6 0.0029( 205 ) 0.3405( 206 )

Page 77: Load Flow Studies of a Grid Interfaced w

77

0.00346( 206 ) 0.00045( 206 )

7 0.0001( 205 ) 0.0346( 206 )

0.00035( 206 ) 0.00004( 206 )

8 0.0000( 205 ) 0.0029( 206 )

0.00003( 206 ) 0.00000( 206 )

9 0.0000( 205 ) 0.0002( 206 )

Reached tolerance in 9 iterations

Largest mismatch: -0.00 MW -0.02 Mvar 0.02 MVA at bus 206 [URBGEN 18.000]

System total absolute mismatch: 0.05 MVA

SWING BUS SUMMARY:

BUS# X-- NAME --X BASKV PGEN PMAX PMIN QGEN QMAX QMIN

3011 MINE_G 13.800 367.4 900.0 0.0 119.5 600.0 -100.0

Page 78: Load Flow Studies of a Grid Interfaced w

78

5.3 DYNAMIC RESULTS

After undergoing the Steady-state simulation and observing the results of that study,

dynamic simulations are performed on the grid under analysis. The response of the

wind farm and that of the grid to a symmetrical short circuit fault on a grid is analyzed

and results are discussed.

5.3.1 Introduction

The analysis of the dynamic behavior of the offshore wind farm comprehends the

response of the wind farm to voltage and frequency disturbances in the grid.

The study of this work is focused on the response of both the offshore wind farm and

the onshore grid to a three-phase fault in an onshore bus, bus 3005, as marked in

Figure 21

Page 79: Load Flow Studies of a Grid Interfaced w

79

Fig 21: Single line diagram of the grid used for the dynamic simulations. Note: Bus

3005, where the fault occurs is marked in the orange rectangle

Nature of Disturbance and clearance time:

For all simulations, the following conditions were applied:

The fault applied is a bolted symmetrical three-phase applied one second after

the start of the simulation.

The fault clearing time is 1 second (45 cycles) and the simulation time is 20

seconds.

Page 80: Load Flow Studies of a Grid Interfaced w

80

Behavior of the following parameters of the grid and wind farm is analyzed here

during and immediately following the disturbance:

Voltage response at different buses and WTGs.

WTG speed response

WTG active power response

WTG reactive power response

Pitch angle response

The analysis is carried out with the objective of assessing the fault ride through

capability of the offshore wind farm, i.e. the requirement for the wind farm to stay

connected to the grid during the disturbance, thus contributing to the reestablishment

of the normal operation. The fault ride through capability of the wind turbines in the

offshore wind farm is guaranteed by the under/over voltage disconnection relays of

the wind turbine generators. These devices allow the operation of the wind turbines

even when the terminal voltage decreases. This capacity of “riding through” a fault is

limited to defined voltage dips and fault durations. So, and according to the

implemented fault ride through characteristic (as defined in Figure), the wind turbine

will only trip if the fault that occurs across the terminals of the machine are outside

the defined limits.

Following are the results of different parameters during and after the occurrence of

fault:

5.3.2 Response of voltage during the fault at the faulty bus, Bus 9005

After the occurrence of the three-phase short circuit at the Bus 9005, the voltage drop

occurs almost in the entire transmission system. More precisely, the closer the

location of the fault, the greater will the voltage drop be. This transient voltage drop

lasts as long as the time of activity of protective relays in order to isolate the fault. In

graph 1, is shown the impact of short circuit fault at the faulted bus. Response of

voltage could be see during and after the occurrence of Fault. After 1 sec when the

fault occurs, the voltage of bus 9005 drops down to (0 p.u) and after the clearance of

fault the voltage restores to its normal value.

Page 81: Load Flow Studies of a Grid Interfaced w

81

Graph1: Response of voltage during the fault at the faulty bus, Bus 9005

5.3.3 Response of voltage at offshore bus, Bus 20

Graph 2 shows that during the fault on bus 3005, the 150Kv offshore bus voltage

drops to 0.45pu. After fault clearance, the voltage gradually recovers to around

0.98pu.

Graph2: Response of voltage at offshore bus, Bus 20

Page 82: Load Flow Studies of a Grid Interfaced w

82

5.3.4 Response of voltage at 400 KV onshore bus, Bus 21:

Graph 3 shows that during the fault on bus 3005, the 150KV offshore bus voltage

drops to 0.63pu. After fault clearance, the voltage gradually recovers to around 0.98pu

Graph 3: Response of voltage at 400 KV onshore bus, Bus 21

Page 83: Load Flow Studies of a Grid Interfaced w

83

5.3.5 Response of voltage at terminals of WTG1 during the fault:

Graph 4 shows that during the fault at bus 3005, the WTG terminal voltage shows a

similar pattern, except that during the fault the minimum terminal voltage is 0.18pu

approximated to 0.2pu. The range of terminal voltage drop to other WTGs is from

0.2pu to 0.23pu, depending on location of the installed units. The simulation results

indicate that all DFIGs have the ability to ride through the fault, which is in

compliance with Wind Grid Code requirements.

Graph4: Response of voltage at terminals of WTG1 during the fault

Page 84: Load Flow Studies of a Grid Interfaced w

84

5.3.6 WTG1 active power response during the fault:

Graph 5 shows that during the fault the WTG electrical power output suddenly

decreases to a very low value (0.001pu). The difference between the mechanical input

power and electrical output power causes an increase in the rotor speed and therefore

the rotor starts to accelerate. The torsion oscillation in the drive-train model is

reflected in the output power of the wind turbine. Oscillation of power output after the

fault is cleared will cause mechanical stress in the drive train system. Approximately

ten seconds after the fault is cleared, the power output recovers to the pre-fault value

of 16MW.

Graph 5: WTG1 active power response during the fault

Page 85: Load Flow Studies of a Grid Interfaced w

85

5.3.7 WTG1 reactive power response during the fault:

During the fault, the rotor speed increases, giving a larger negative slip. This is

because the electric power has decreased to almost zero whereas the mechanical

power is assumed to be the same. As a result, WT3P module responds by altering the

blade pitch to decrease mechanical power. The reactive power output from selected

wind turbine generator WTG1 is shown in graph 6. Before the fault occurs, the

generated reactive power is near zero and the wind farm operates at unity power

factor. It can be seen that each WTG units during the fault provide reactive power

support to the grid, as is required by the Wind Grid Code.

Graph 6: WTG1 reactive power response during the fault

Page 86: Load Flow Studies of a Grid Interfaced w

86

5.3.8 WTG1 speed response during the fault

Graph 7 shows the generator rotor speed response after the fault occurs. The generator

speed is oscillating for about 5 seconds after the fault. 16 seconds after fault is

cleared, the rotor speed recovers to the pre-fault value after some 16 seconds.

Graph 7: WTG1 speed response during the fault

Page 87: Load Flow Studies of a Grid Interfaced w

87

5.3.9 Pitch angle response after fault event

As can be seen in graph 8, the turbine blade pitch angle is increased during the fault in

order to reduce the power input from the wind turbine. The pitch angle oscillates in

response to the oscillation of the speed of the turbine. For a few seconds after fault

clearance, the turbine shaft speed decreases while the pitch angle increases due to the

effect of pitch compensation controller trying to reduce the input power to the turbine

by increasing the pitch angle.

Graph 8: Pitch angle response after fault event

Page 88: Load Flow Studies of a Grid Interfaced w

88

CHAPTER 6

CONCLUSION & RECOMMENDATIONS

6.1 CONCLUSION

Wind power has evolved as a significant renewable energy source for the generation

of electrical energy due to the growth of environmental concerns. Large wind farms

with several hundred megawatts of rated power have been connected to grid.

When wind farms are connected to the existing power system introducing the new

power to the system, it offers some challenges like reactive power compensation,

fluctuations in active and reactive power and Voltage control strategies.

It is therefore necessary to go through steady state and dynamic analysis to map the

impacts of newly injected power of wind farms on the existing system.

Thus the objective of this thesis is to carry out the load flow analysis of the wind farm

integrated to the power grid, in order to study their overall impacts on the power

system.

For this purpose, a wind farm of 110MW having two aggregates of 24MW and three

aggregates of 21MW connected offshore to the power grid by means of a power

cable. Initially the steady state load flow analysis is carried out considering three

cases which are

Wind Farm without compensation

Wind farm with Shunt Reactor

Wind Farm with STATCOM

On the basis of these three Cases the voltages and power Flows at different buses

were determined and it was ensured that Reactive power and voltages are in the

normal ranges.

Then dynamic simulation is carried out by creating a fault at a grid bus for a second in

order to determine the fault ride through capability of the wind farm. For all this

Steady-State and Dynamic simulation Siemens PTI software Known as PSS®E is

used.

Page 89: Load Flow Studies of a Grid Interfaced w

89

The results of the simulation are analyzed to study the Impacts of grid interfaced wind

farm on the power system.

6.2 RECOMMENDATIONS

In our thesis HVAC transmission system was used to interconnect the offshore wind

farm to the power grid and results were studied. For the future work we would

recommend that DC link converter could be taken in PSS/E and HVDC transmission

model could be developed to interconnect the offshore wind farm to the Grid, and

then the results of both HVAC and HVDC transmission systems could be compared

to see the impacts of each on the power system.

Page 90: Load Flow Studies of a Grid Interfaced w

90

REFERENCES

1. Steady State Analysis of the Interconnection of Offshore Energy Parks

By: Miguel Jorge da Rocha Barros Marques.

https://fenix.tecnico.ulisboa.pt/downloadFile/.../dissertacao.pdf

2. PSS/E Wind Modeling Package for 1.5/3.6/2.5 MW Wind Turbines - User

Guide. 2009.

3. PSS/E 33 Users Manual. 2010

4. PSS/E 33 Program Operation Manual Volume II. 2010

5. PSS/E 33 Program Application Guide Volume II. 2010

6. Creation of a Power Flow Study. BY: Ben Pilato & Bryan Lake (Department

of Electrical and Computer Engineering, Colorado State University)

7. Modeling, Simulation and Analysis of Full Power Converter Wind Turbine

with Permanent Synchronous Generator. By: Skender Kabashi, Gazmend

Kabashi

8. Wind Farm Modeling for Steady State and Dynamic Analysis. By: G. Kabashi

K. Kadriu

http://connection.ebscohost.com/c/articles/60799391/wind-farm-modeling-

steady-state-dynamic-analysis

9. Case Studies of Wind Park Modeling. By: Yuriy Kazachkov, Siemens PTI

10. Power System Analysis. By: Haadi Saadat

11. Low Voltage Ride-Through. By: J. Dirksen; DEWI GmbH; Wilhelmshaven

12. Transmission System for offshore wind farms in the Netherlands. By: Wil

Kling

13. NEDO offshore wind energy progress Edition II

14. Teaching Undergraduate Power System Courses with the help of Siemens PTI

PSS/E-University simulator software. By: Chi Tang, Adam Freeman, Jerome

Spence, Matthew Bradica, and Donge Ren (McMaster School of Engineering

Technology)

15. Power flow analysis using MATLAB. By: Mohammad Shahimi Bin

Mohammad Isa (University Malaysia Pahang)