PROJECT BACKGROUND

2008 Bond Authorization

October 2010: Council Appointed Advisory Group

June 2011–June 2012: Facility Programming

June 2012: Council Presentation

September 2012: Council Presentation

January 2013: Council Presentation

April 2013: Design Contract

Page 3: Lick Creek Nature Center
Page 4: Lick Creek Nature Center
Page 5: Lick Creek Nature Center
Page 6: Lick Creek Nature Center
Page 7: Lick Creek Nature Center
Page 8: Lick Creek Nature Center
Page 9: Lick Creek Nature Center

PROJECT SCHEDULE

Bid documents complete in July 2014

Bid in August 2014

Construction contract award in September 2014

Preconstruction conference in October 2014

Notice to Proceed in November 2014

Final Completion in November 2015

Page 10: Lick Creek Nature Center

PROJECT BUDGET

Budget: $2,495,000

Encumbered: $ 401,210

Balance: $2,093,790

Cost Estimate w/ 5% Contingency: $2,000,000

Alternates: Solar Panels, Amphitheater, Outdoor Classroom

Page 11: Lick Creek Nature Center

Questions ?

Page 12: Lick Creek Nature Center

REFERENCE INFORMATION

Page 13: Lick Creek Nature Center
Page 14: Lick Creek Nature Center
Page 15: Lick Creek Nature Center
Page 16: Lick Creek Nature Center