Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO Diretoria de Operação SM.O Superintendência de Manutenção Preparado por: Luciano Junqueira Calixto Email: [email protected]

Upload: phamdung

Post on 04-Jun-2018

242 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Lessons learned from Angra 1

& Angra 2 NPP’s Outages

DO – Diretoria de Operação

SM.O – Superintendência de Manutenção

Preparado por: Luciano Junqueira Calixto

Email: [email protected]

Page 2: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Angra 1 & Angra 2 Data Angra 1:

• PWR – Westinghouse Design; • 121 Fuel Elements (33 control rods) – 12 months cycle;

• 2 loops (2 Steam Generators – 2 RCP’s);

• 1 HP and 2 LP turbines;

• Installed capacity: 640 MWe (1809 MWth);

• First criticality: 1981 - Commercial Operation since 1983;

Angra 2:

• PWR – Siemens / KWU design;

• 193 Fuel Elements (61 control rods) – 12 months cycle;

• 4 loops (4 Steam Generators – 4 RCP’s);

• 1 HP and 3 LP turbines;

• Installed capacity: 1350 MWe (3765 MWth);

• First Criticality: 2000 - Commercial Operation since Jan/2001;

Page 3: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Basic Outage Planning Milestones

Page 4: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Basic Outage Planning Milestones

Page 5: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

General Outage Coordination Structure

Plant Manager

Or Deputy

Maintenance Coordinator

Operation Coordinator

System Engineer

Coordinator

RadiologicalProtection

Coordinator

Design Engineering Coordinator

Outage Coordinator

Quality Assurance

Coordinator

Page 6: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Outage Control Center Main Tasks

• Follow-up of Outage Activities, specially the critical path;

• Evaluate deviations and look for each Area Coordinator to

expedite the solution, in order to return to the original

schedule;

• Deliberate about changes on the critical path;

• Evaluate Nuclear Safety;

Page 7: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Angra 1 & Angra 2 basic Outage plan

Angra 2 Pre outage (10-12 days prior to outage):

• Inspection of safety components of Outage main redundancy,

such as 1 Safety Injection, 1 Component Cooling and 1 RHR

pumps, according to Preventive Maintenance plan or due to

Condition Based Monitoring;

Angra 1 & Angra 2 Major Maintenance Plan (30 day outage):

• Reactor unload and refueling (Exchange 1/3 of Fuel Elements);

• Review of 1 turbine item (HP, LP or Electric Generator);

• RCP seal inspection and Exchange of 1 motor;

• Inspection of 1 redundancy of Main Steam valves;

• SG inspection (Sludge Lancing and/or ECT);

• Major Design Modifications implementation;

• Inservice Inspections and safety MOV actuators revision;

• Electrical and I&C Tests / Inspections (such as Reactor

Protection);

• Circulating Water Motor inspection / exchange;

• Corrective and Elective Maintenance;

Page 8: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Maintenance during operating cycle

• Diesel Engine maintenance and associated Electric Generator

inspection;

• Limitation system - I&C tests (Angra 2);

• Predictive maintenance (vibration, oil analysis and termography)

of main componentes and electric panels;

• Minor Design Modifications;

• Water intake structure cleaning and material condition

maintenance;

• MOV current measurement and profile analysis / trend;

• Radiation detector tests (electronic and with rad. source);

• Corrective, Elective and minor Maintenance;

• Chill water turbocharger revision;

• Air compressor revision;

• Important to safety redundant instrumentation loop tests;

• Fan belt tension evaluation / adjustment;

• Lubricating;

Page 9: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Past Outages results

Angra 1:

Days

# T

asks

Page 10: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Past Outages results

Angra 2:

0

1000

2000

3000

4000

5000

6000

0

5

10

15

20

25

30

35

40

2P5 (2007) RCP 2P6 (2008) 2P7 (2009) 2P8 (2010) 2P9 (2012) 2P10 (2013) 2P11 (2014)

Days

# T

asks

Page 11: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção

Recent Challenges and Lessons Learned

• Angra 1 1P21 (2015) outage delayed 23 days due to an employee

Union’s strike;

• Spare parts and consumables import and Customs clearance

times;

• Temporary tools import and export time;

• Angra 2 2P11 (2014) delayed mainly due to Electric Generator test

equipment 6 days shipment delay;

• Manpower qualification during outages. Around 1000 temporary

contractors during outage (per plant);

• Stablishment of a long term (3-5 year) TG-set manufacturer

contract;

• Inservice inspection control prior and during outage, specially of

tests required for changing of “operation modes”;

• Stablishment of “Service Coordinators” for the critical path and

main inspection tasks;

• Preparation of a “Containment Arrangement” due to multiple /

concurrent task demanding polar crane inside containment;

Page 12: Lessons learned from Angra 1 & Angra 2 NPP’s Outages · Lessons learned from Angra 1 & Angra 2 NPP’s Outages DO – Diretoria de Operação SM.O – Superintendência de Manutenção