CONSULTING ASSOCIATES Consulting Engineers & Project Planners Near Deans Complex Apartments, Behind Gul CNG, Board Bazaar, Jamrud Road, Peshawar. Ph: +92-91-570 17 74, Fax: +92-91-570 17 75, Email: [email protected] CONSTRUCTION OF 356 MINI/MICRO HYDROPOWER PROJECTS IN NORTHERN DISTRICTS OF KHYBER-PAKHTUNKHWA PAKHTUNKHWA ENERGY DEVELOPMENT ORGANIZATION ENERGY AND POWER DEPARTMENT GOVERNMENT OF KHYBER PAKHTUNKHWA P E D O

Upload: jazvell

Post on 11-Feb-2016

769 views

Category:

Documents


0 download

DESCRIPTION

Monthly progress report Aug 2015. Construction of 356 MINI/MICRO HYDROPOWER. Projects in Nothern Districts of Khyber-Pakhtunkhwa.

TRANSCRIPT

Page 1: KP MHPs Progress Report (Aug 2015)

CONSULTING ASSOCIATES

PESHAWAR

C o n s u l t i n g E n g i n e e r s & P r o j e c t P l a n n e r s

N e a r D e a n s C o m p l e x A p a r t m e n t s , B e h i n d G u l C N G , B o a r d B a z a a r ,

J a m r u d R o a d , P e s h a w a r .

P h : + 9 2 - 9 1 - 5 7 0 1 7 7 4 , F a x : + 9 2 - 9 1 - 5 7 0 1 7 7 5 ,

E m a i l : c o n s u l t i n g a s s o c i a t e 1 2 7 @ g m a i l . c o m

CONSTRUCTION OF 356 MINI/MICRO HYDROPOWER

PROJECTS IN NORTHERN DISTRICTS OF KHYBER-PAKHTUNKHWA

PAKHTUNKHWA ENERGY DEVELOPMENT ORGANIZATION ENERGY AND POWER DEPARTMENT

GOVERNMENT OF KHYBER PAKHTUNKHWA

P E D O

Page 2: KP MHPs Progress Report (Aug 2015)

TABLE OF CONTENTS

EXECUTIVE SUMMARY………………………………………………………………………………………………1

1.1. INTRODUCTION ............................................................................................................................... 1

1.2. PHYSICAL STATUS .......................................................................................................................... 2

1.3. FINANCIAL STATUS ....................................................................................................................... 3

1.4. CONSTRAINTS .................................................................................................................................. 4

1.5. LOCATION MAP................................................................................................................................ 4

PROGRESS BY NGOS /CONTRACTORS ................................................................................................ 5

AGA KHAN RURAL SUPPORT PROGRAMME (AKRSP) ................................................................ 6

2.1. CONTRACT DETAILS ...................................................................................................................... 7

2.2. PERFORMANCE OF THE CONTRACTOR ................................................................................. 7

2.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015) ....................... 7

2.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015) ...................................... 7

JV GAP/HASHAAR/HYDROLINK/ZOMO ASHRO ............................................................................ 8

3.1. CONTRACT DETAILS ...................................................................................................................... 9

3.2. PERFORMANCE OF THE CONTRACTOR ................................................................................. 9

3.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015) ....................... 9

3.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015) ................................... 10

JV DADO / CCDP........................................................................................................................................... 11

4.1. CONTRACT DETAILS ................................................................................................................... 12

4.2. PERFORMANCE OF THE CONTRACTOR .............................................................................. 12

4.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015) .................... 12

4.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015) ................................... 13

JV ZAIF FOUNDATION / FWF ................................................................................................................ 14

5.1. CONTRACT DETAILS ................................................................................................................... 15

5.2. PERFORMANCE OF THE CONTRACTOR .............................................................................. 15

5.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015) .................... 15

Page 3: KP MHPs Progress Report (Aug 2015)

5.4. PROGRESS OF WORK DURING THIS MONTH (AUGUST 2015) .................................. 16

SARHAD RURAL SUPPORT PROGRAMME (SRSP) ...................................................................... 17

6.1. CONTRACT DETAILS ................................................................................................................... 18

6.2. PERFORMANCE OF THE CONTRACTOR .............................................................................. 18

6.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015) .................... 18

6.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015) ................................... 19

JV CEMCO/ PCRET ...................................................................................................................................... 20

7.1. CONTRACT DETAILS ................................................................................................................... 21

ANNEXURE-I

Page 4: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

1

EXECUTIVE SUMMARY

1.1. INTRODUCTION

The main objective of the development of Mini/ Micro Hydropower is to utilize cheap

hydropower potential and to provide reliable and consistent power to local areas specially

those which are deprived of electricity. It will also provide opportunities to local

communities for enhancements of economic activities through establishments of small scale

industries.

For the said purpose a PC-I for “Construction of 356 Mini/ Micro Hydropower Projects in

Northern Districts of Khyber Pakhtunkhwa” amounting to Rs. 5,524.832 Million was

approved by the PDWP on 1st January 2015.

PEDO has awarded contract for the execution of work to six (6) no. of NGOs covering twelve

(12) districts of Khyber Pakhtunkhwa, following is the detail.

Sr. District Date of

Award Name of NGO/Contractor

Contract Amount

(Rs. Million)

1. Chitral

1st Sept,

2014

Aga Khan Rural Support

Programme (AKRSP)

1059.6

2. Upper Dir JV Dir Area Development

Organization/CCDP

699.97 3. Lower Dir

4. Batagram JV Green Alternative

Power/HASHAAR/ZOMO ASHRO/

HYDROLINK

728.35

5. Abottabad

6. Swat Sarhad Rural Support Programme

(SRSP) 1570.57 7. Shangla

8. Kohistan

9. Buner JV Zaif Foundation/ Fatma Welfare

Foundation

437.81

10. Malakand

11. Mansehra JV CEMCO / PCRET 863.35

12. Torghar

Page 5: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

2

The consultancy agreement was signed for “Construction of 356 Mini/ Micro Hydropower

Projects in Northern Districts of Khyber Pakhtunkhwa” between Project Director MHP PEDO

and Consulting Associates Peshawar on 24th March, 2014.

This report has been produced under the sub clause 3.7 (consultants obligations) of the

consultancy contract agreement.

1.2. PHYSICAL STATUS

Till the month of July 2015, out of the total 356 awarded projects 275 were identified.

Whereas 174 were approved for construction, out of the 174 approved projects,

construction work was in progress on 94 sites.

Now during the reporting month i.e. August 2015 the no. of identified sites has increased

from 275 to 276, projects approved by MC from 174 to 187, whereas projects in construction

phase remains 94.

15 projects were expected to complete in the month of August 2015 however due to weather

conditions and financial constraints contractors failed to do so.

Figure 1: Physical Progress of the Project

Page 6: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

3

1.3. FINANCIAL STATUS

Till July 2015, Rs. 294.604 Million were released to the contractors, this amount remained

same in the reporting month.

Sr. NGO/Contractor Bid Price

(Rs. Million) Payment

(Rs. Million) %age

Utilization

1. Aga Khan Rural Support Programme (AKRSP)

1059.6 130.62 12.32

2. JV Dir Area Development Organization/CCDP

699.97 14.93 2.13

3. JV GAP/HASHAAR/ZOMO ASHRO/ HYDROLINK

728.35 78.306 10.75

4. Sarhad Rural Support Programme (SRSP)

1570.57 55.537 3.53

5. JV Zaif Foundation/ Fatma Welfare Foundation

437.81 15.211 3.47

6. JV CEMCO / PCRET 863.35 -- --

Figure 2: Financial Progress of the Project

Page 7: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

4

1.4. CONSTRAINTS

Low production capacity of local manufacturers of E&M equipment causing delay in

completion of project.

Inaccessibility of sites (lack of infrastructure).

NGOs’ inability to handle the large no. of sites.

Stay order from contractor in two (Torghar & Mansehra) districts.

Reversal of the decision of not to develop 10-15kw sites.

Weather constraints.

Complications in contractual interpretations.

Key challenge is to address capacity gap of +9MW.

1.5. LOCATION MAP

Page 8: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

5

PROGRESS BY NGOs /CONTRACTORS

Page 9: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

6

AGA KHAN RURAL SUPPORT PROGRAMME (AKRSP)

Page 10: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

7

2.1. CONTRACT DETAILS

Name of NGO/Contractor: Aga Khan Rural Support Programme (AKRSP)

Date of Contract Award: 1st September, 2014

Date of Effectiveness Of Contract: 19th Feburary,2015

Total Projects Awarded 55

Duration of Contract 18 months

District Chitral

2.2. PERFORMANCE OF THE CONTRACTOR

55 no. of projects are awarded to AKRSP with total capacity of 6.27MW. Contractor is able to

get approval of all the 55 no. of projects. Out of 55 approved projects, contractor has initiated

construction work on 30 projects only.

2.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015)

Till the month of July 2015 AKRSP had achieved the progress stated below.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

55 55 30 -- --

Financial Progress: Rs. 130.62 Million (cumulative) for Feasibility Study

2.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015)

In the month of August 2015, AKRSP achieved the following progress.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

55 55 30 -- --

Financial Progress: No Change

See Annexure-I of the report for details.

Page 11: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

8

JV GAP/HASHAAR/HYDROLINK/ZOMO ASHRO

Page 12: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

9

3.1. CONTRACT DETAILS

Name of NGO/Contractor: JV GAP/HASHAAR/HYDROLINK/ZOMO ASHRO

Date of Contract Award: 1st September, 2014

Date of Effectiveness Of Contract: 19th Feburary,2015

Total Projects Awarded 73

Duration of Contract 18 months

District Abbottabad Batagram

Total No. of Projects Awarded 34 39

3.2. PERFORMANCE OF THE CONTRACTOR

73 no. of projects are awarded to JV GAP/HASHAAR/HYDROLINK/ZOMO ASHRO with total

capacity of 5.42MW. However till the reporting month contractor is able to get approval for

52 no. of projects with capacity of 4.51 MW. Out of 52 approved projects, contractor has

initiated construction work on 19 projects.

3.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015)

Till the month of July 2015 JV GAP/Hashaar/Hydrolink/Zomo Ashro had achieved the

progress stated below.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Abottabad

34 18 6 -- --

Financial Progress: Rs. 27.12 Million(cumulative) for Feasibility Study and E&M

Equipment

District Batagram

39 35 13 1 --

Financial Progress: Rs. 51.197 Million(cumulative) for Feasibility Study

Page 13: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

10

3.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015)

Two (2) approved sites in district Abottabad have been dropped due to inconformity with

the contract agreement. In the month of August 2015, JV GAP/Hashaar/Hydrolink/Zomo

Ashro achieved the following progress.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Abottabad

34 16 6 -- --

Financial Progress: No change

District Batagram

39 36 13 1 --

Financial Progress: No change

See Annexure-I of the report for details.

Page 14: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

11

JV DADO / CCDP

Page 15: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

12

4.1. CONTRACT DETAILS

Name of NGO/Contractor: JV DADO / CCDP

Date of Contract Award: 1st September, 2014

Date of Effectiveness Of Contract: 19th Feburary,2015

Total Projects Awarded 55

Duration of Contract 18 months

District Upper Dir Lower Dir

Total No. of Projects Awarded 44 11

4.2. PERFORMANCE OF THE CONTRACTOR

55 no. of projects are awarded to JV DADO/CCDP with total capacity of 4.72MW. However

till the reporting month contractor is able to get approval for 16 no. of projects with capacity

of 705KW (0.705MW). Contractor has initiated construction work on 4 projects only.

4.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015)

Till the month of July 2015 JV DADO/CCDP had achieved the progress stated below.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Upper Dir

44 8 4 18 8

Financial Progress: Rs. 13.13(cumulative) for Feasibility Study

District Lower Dir

11 1 -- 10 --

Financial Progress: Rs. 1.76 Million for Feasibility Study

Page 16: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

13

4.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015)

In the month of August 2015, JV DADO/CCDP achieved the following progress.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Upper Dir

44 14 4 13 --

Financial Progress: No Change

District Lower Dir

11 2 -- 10 --

Financial Progress: No Change

See Annexure-I of the report for details.

Page 17: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

14

JV ZAIF FOUNDATION / FWF

Page 18: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

15

5.1. CONTRACT DETAILS

Name of NGO/Contractor: JV ZAIF FOUNDATION / FWF

Date of Contract Award: 1st September, 2014

Date of Effectiveness Of Contract: 19th Feburary,2015

Total Projects Awarded 22

Duration of Contract 18 months

District Buner Malakand

Total No. of Projects Awarded 13 9

5.2. PERFORMANCE OF THE CONTRACTOR

22 no. of projects are awarded to JV Zaif Foundation/FWF with total capacity of 2.98MW.

However till the reporting month contractor is able to get approval for 5 no. of projects with

capacity of 240KW (0.240MW). Contractor has initiated construction work on 5 no. of the

approved projects.

5.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015)

Till the month of July 2015, JV Zaif Foundation/FWF had achieved the progress stated below.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Buner

13 5 5 11 --

Financial Progress: Rs. 15.216 Million(cumulative) for Feasibility Study and E&M

Equipment

District Malakand

9 -- -- 4 --

Financial Progress: None

Page 19: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

16

5.4. PROGRESS OF WORK DURING THIS MONTH (AUGUST 2015)

In the month of August 2015, JV Zaif Foundation/FWF achieved the following progress.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Buner

Financial Progress: No change

13 5 5 11 --

District Malakand

9 -- -- 4 --

Financial Progress: None

See Annexure-I of the report for details.

Page 20: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

17

SARHAD RURAL SUPPORT PROGRAMME (SRSP)

Page 21: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

18

6.1. CONTRACT DETAILS

Name of NGO/Contractor: SARHAD RURAL SUPPORT PROGRAMME (SRSP)

Date of Contract Award: 1st September, 2014

Date of Effectiveness Of Contract: 19th Feburary,2015

Total Projects Awarded 105

Duration of Contract 18 months

District Swat Shangla Kohistan

Total No. of Projects Awarded 45 25 35

6.2. PERFORMANCE OF THE CONTRACTOR

105 no. of projects are awarded to SRSP with total capacity of 5.42MW. However till the

reporting month contractor is able to get approval for 54 no. of projects with capacity of

3.5MW. Out of 54 approved projects, contractor has initiated construction work on 36

projects only.

6.3. PROGRESS OF WORK DURING THE PREVIOUS MONTH (JULY 2015)

Till the month of July 2015, SRSP had achieved the progress stated below.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Swat

45 17 12 17 10

Financial Progress: Rs. 22.04 Million(cumulative) for Feasibility Study

District Shangla

25 13 13 10 9

Financial Progress: Rs. 17.381 Million(cumulative) for Feasibility Study

Page 22: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

19

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Kohistan

35 17 11 17 15

Financial Progress: Rs. 16.113 Million(cumulative) for Feasibility Study

6.4. PROGRESS OF WORK DURING THE MONTH (AUGUST 2015)

In the month of August 2015, SRSP achieved the following progress.

Total Sites

Total Approved Sites

Construction Started

Identified in this Month

Submitted for Approval (out of identified)

District Swat

45 20 12 14 --

Financial Progress: No Change

District Shangla

25 16 13 7 --

Financial Progress: No Change

District Kohistan

35 18 11 17 --

Financial Progress: No Change

See Annexure-I of the report for details.

Page 23: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

20

JV CEMCO/ PCRET

Page 24: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

21

7.1. CONTRACT DETAILS

Name of NGO/Contractor: JV CEMCO/ PCRET

Date of Contract Award: 1st September, 2014

Total Projects Awarded 46

Duration of Contract 18 months

District Torghar Mansehra

Total No. of Projects Awarded 20 26

After the award of contract the contract initiated its work, and had preliminary identified no.

of sites for MHP development. However, The Ministry of Science and Technology vide letter

No 2(1)/JS (A) Government of Pakistan Ministry of Science and Technology dated

03/12/2014 communicated for immediate withdrawal of PCRET from joint venture. CEMCO

was given notice to clarify the position within 07 days as per contract agreement clause No

45.1 and 45.2.

Reply of CEMCO was not satisfactory and PEDO intended to terminate his contract however

CECMO took stay order from Peshawar High Court. Hence the matter is now in Court and

PEDO is not in position to take any action till the decision of the Court.

Page 25: KP MHPs Progress Report (Aug 2015)

Mini/Micro HPP Progress Report: August

22