king edward memorial park foreshore community liaison ... · pdf fileking edward memorial park...

43
King Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017

Upload: votuong

Post on 22-Feb-2018

223 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

King Edward Memorial Park Foreshore

Community Liaison Working Group

5 June 2017

Page 2: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

2

CONTENTS

Progress report

Upcoming works

Focus on hoarding works

Focus on sheet piling

Mitigation

LBTH presentation

Permanent and temporary artwork

Page 3: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

3

KEMPF

Page 4: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

4

Playground

Page 5: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

5

Site hoarding

Page 6: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

6

Upcoming works

Page 7: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

7

Focus on hoarding works

Free Trade

Wharf

KEMPF Site

Page 8: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

8

Site hoarding

Page 9: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

9

Cofferdam Impact Piling Works

• Total Number of Piles: 278

• Total Number of Driven Piles: 45 approx. (16%)

• Average amount of driving time per pile: 17 Minutes continuous

• Average amount of driving time per pile: 22 Minutes intermittent

• 1600 hours of general piling works, with approximately 13 hours of impact piling

• June, 2 Piles

• July, 9 Piles

• Aug, 12 Piles

• Sep, 6 Piles

• Oct, 2 Piles

• Nov, 2 Piles

• Dec, 10 Piles

Indicative

Page 10: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

10

Cofferdam – Chambers Wharf

Page 11: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

11

Noise and Vibration – Best Practice

‘Super silent’ generators Giken Super crush

Re-designed pressure

washersAcoustic panels

Page 12: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

12

Shadwell Basin – slipway

Page 13: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

13

Mitigation

Page 14: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

14

Mitigation

• ‘Special Case’ procedure – Non-statutory off-site mitigation &

compensation policy

• ‘Standard Case’ procedure – discretionary offer made by Tideway

Page 15: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

15

Special Case Procedure

• ‘Special Case’ procedure is in accordance with the Non-statutory off-site mitigation and compensation policy.

• Offers a mechanism for residents to apply for additional mitigation if they have special circumstances which are exacerbated by exposure to the effects of construction, eg.noise and/or vibration.

• Special circumstances could include night shift workers, vulnerable persons who are housebound or those with a recognised medical condition.

• Mitigation could include:- secondary glazing for habitable rooms, eg living rooms or bedrooms

- respite periods away from the works during more intrusive construction activities or,

- temporary rehousing for the duration of the construction works.

• Special circumstances could also include those who have a demonstrable loss as a direct result of the construction, e.g loss of rent or business.

• All Special Case applications are assessed by the Independent Compensation Panel (ICP) and are assessed individually on a case by case basis.

Page 16: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

16

Special Case Procedure – How To Apply

• Apply and make yourself known to the project, either by email,

phone or verbally to one of the team.

Email - helpdesk@tideway-london

Phone – 08000 30 80 80

• Tideway’s TAPs and Mitigation Lead will contact you and talk you

through the process, either over the phone or in person.

• Your application needs to include:

- Clear statement / description of how the works are affecting you.

- Supporting documentation eg. evidence of being a nightshift worker, or

evidence from a GP or medical consultant

- Clear identification of what specific mitigation you are applying for, e.g

secondary glazing, temporary respite / rehousing etc.

• Your supporting documentation will then be reviewed by the

Independent Compensation Panel (ICP).

Page 17: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

17

Standard Case procedure

• New mitigation procedure which will run in parallel to the existing Special Case & TAPs mitigation

• Discretionary offer by Tideway available for days when impact piling of cofferdam sheet piles at King Edward Memorial Park Foreshore site may occur.

• Qualifying residents can select mitigation without needing to submit an application to be considered a Special Case by the Independent Compensation Panel (ICP).

• Only for impact piling days, not available for days when sheet piles are installed by push piling or vibration piling.

• Impact piling days will be notified in advance by email.

• In order to qualify for the Standard Case mitigation, residents must fulfil both the following criteria:

a) Residents must permanently live within the Geographical Area, and

b) Residents must have one of the identified Characteristics

• The new Standard Case procedure was initially developed for Chambers Wharf site with input from the local agencies.

• Only available to residential, not available to commercial properties.

Page 18: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

18

Standard Case – Geographical Area

Geographical Area For Standard Case Zone – Version dated 5th June 2017

Standard Case Zone

Approximate Cofferdam

Page 19: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

19

Standard Case – Characteristics

• In order to qualify for the Standard Case, residents must fulfil at

least one of the following criteria:

• Residents with children of a pre-school age

• Residents with children of a school age

• Residents in full time education who live at the property during term

time

• Residents who are over state retirement age and are fully retired

• Residents who have retired early due to ill health

• Residents who work from home

• Residents with a recognised medical condition.

Page 20: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

20

Standard Case – Mitigation Available

• If a resident permanently lives within the Geographical Area and

they fulfil one of the specified characteristics, then they can select

one of the following discretionary mitigation offer for impact piling

days:

1. Daily Daytime Respite Payment – daily payment to assist resident to go out if they so wish

2. Temporary Office / Working Space – For those who work from home

• Should a resident request alternative mitigation not listed above

(such as respite with overnight accommodation or temporary

rehousing), then they would need to make an application to be

considered a ‘Special Case’.

Page 21: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

21

Standard Case – Next steps

• Residents within the Geographical Area will receive a letter in the

near future.

• Tideway have appointed a Case Support Adviser to assist residents

in applying to be a Standard Case and advising what mitigation is

available.

• Residents outside the Geographical Area can still apply to be

considered a ‘Special Case’ but their case will need to be assessed

by the ICP.

Page 22: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Primary Legislation

Act of Parliament

Planning Act 2008

Secondary Legislation

Secretaries of State

The Thames Water Utilities Limited

(Thames Tideway Tunnel) Order 2014

(S.106 Legal Agreement)

Approved Plans Requirements

Project Wide and Site Specific

Example:

• PW6 (Project Wide 6): Works to be

implemented in accordance with:

Code of Construction Practice Part A

Coder of Construction Practice Part B

Schedule 17

Procedure for

discharge of

Requirements

Draft Submission

28 days – Site

Notice

Main Submission

8 Weeks

Page 23: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

History of the Tideway DCO

• October 2010 – Phase 1 consultation

• May 2011 - CABE Sketch Review

• June 2011 – CABE Scheme Review

• February 2012 – Phase 2 Consultation

• February 2013- Date of submission

• September 2013 - Examination Begins

• September 2014 – Order approved by the Secretary of

State

Page 24: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Summary of Project Wide and Site Specific

Requirements

Project Wide Requirements Site Specific Requirements

PW1: Interpretations/definitions KEMPF1: CoCP Part B

PW2: Time Limits KEMPF2: Location of permanent works

PW3: Phasing of the authorised development – Project wide KEMPF3: Detailed design approval for permanent above-ground structures

PW4: Phasing of the Authorised Development KEMPF4: Detailed design approval for signature ventilation columns

PW5: Drive Strategy KEMPF5: Detailed design approval for river wall and foreshore structure

PW6: CoCP Part A KEMPF6: Landscaping works

PW7: Air Management Plan KEMPF7: Works to reconfigure the multi-purpose sports pitch, relocated the

children’s play area and associated landscaping

PW8: Monitoring of and protective works to listed buildings and structures KEMPF8: Temporary works platform

PW9: Built heritage recording KEMPF9: Contaminated Land

PW10: Signage for temporary footpath diversions KEMPF10: Archaeology

PW11: Interpretation strategy KEMPF11: Construction Traffic Management Plan

PW12 Excavated material and waste KEMFP12: Travel Plan

PW13: Groundwater and dewatering monitoring and management KEMPF13: Specification of accesses (construction and operational)

PW14: Operational Noise KEMPF14: Surface water drainage

PW15: River Transport Strategy KEMPF15: Highway works

PW16: Completion of construction KEMPF16: Section 106 Agreement / Undertaking

PW17: Noise and vibration trigger values KEMPF17: Commissioning Works

PW18: Notice of maintenance works KEMPF18: Working Hours

PW19: Baseline Monitoring

Page 25: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Extract of the DCO

Drawing NumbersRequirements

Page 26: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Adam Hussain

Senior Planning Officer

London Borough of Tower Hamlets

[email protected]

Page 27: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

27

Permanent and Temporary Artwork

Page 28: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

28

Hoarding Commission

The Process

• Following an open call, the three shortlisted artists visited the site prior to

developing their proposals.

• The selection panel was held on 22 February. A representative from the

Community Liaison Working Group (CLWG) participated, along with

representatives from Tideway and CVB (the Main Works Contractor) and

LB Tower Hamlets.

The Proposal

• Artists Matheson Marcault (Holly Gramazio and Sophie Sampson) are

working with local community groups to develop a series of games that can

be played in the park and the surrounding area. The rules for these games

are being developed into a visually striking design for the hoarding area

adjacent to the play area and tennis courts.

Page 29: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Games for specific landscaping in the park

Page 30: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Games which reference sport

Page 31: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

31

Hoarding Commission

Methodology / Community involvement

• During April and May the artists met and worked with five different local

groups. Workshops included discussions, game creation and development,

as well as playing games previously developed by Matheson Marcault.

• So far they have worked with:

- young children from Ideas Store Watney Market

- older people from Prime Time Club, Ideas Store Watney Market

- children and young people at Shadwell Basin Outdoor Activity Centre

- children from St Peter’s After School Club

- young people from The Rooted Forum girl’s youth group at Tarling East

Community Centre

• The artists have also met the Tennis Manager to discuss how players might

use and interact with the hoarding adjacent to the tennis courts.

Page 32: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

32

Hoarding Commission

Methodology / Community involvement

• Following the workshops, Holly and Sophie have developed and tried out

games that fit several different themes including games about nature,

monsters and colours.

• The games are simple physical games that can be played on your own or in

small groups, with no special equipment. For example:

- COLOUR SPOTS: When you're about to leave, pick two colours - say, blue and

orange. One player looks for blue things; the other looks for orange. Who can spot

the most things in their colour before you leave the park?

- MONSTER HUNTER: Choose your favourite monster! [image showing a selection

of 8-10 monsters]. Make a face to copy that monster - can everyone else guess

which monster you picked?

Programme

• They will continue with play testing the games on Wednesday 7 June

between 16:00 and 17:00. The games and instructions will be formed into

visual imagery for the hoarding. Installation is anticipated in June.

• The initial designs will be shared with the CLWG and a launch event held

once installed.

Page 33: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

33

Page 34: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

34

East: The Shipping Parishes – Gateway to the World

Page 35: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

Site Narrative: Sailortown, international diaspora and

progressive politics

Page 36: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

36

Permanent Integrated Commission

The Selection Process

• The selection panel was held on the 26 January – representatives were

invited from LBTH (unable to attend due to prior engagement) and the

CLWG (no response), a representative from a local arts organisation

attended with Tideway staff.

• The site specific narratives of the HIS relate to the close historical links with

mercantile and dock communities that have been associated with the

contrasting impact of former British maritime power and trading empire on

different ethnic, social and economic groups, locally and internationally.

Artist & Proposal

• Hew Locke, an artist with an international profile, has been appointed. His

proposal comprises a series of unique cast bronze boats representative of

the history of the Thames and shifting population of the East End, placed

on low plinths around the foreshore site. Creating a trail through the

foreshore site, linking the new public realm with the park.

• These currently include: a Tug, Chinese Junk, Thames 19th Century

Paddle Cruiser, John Hawkins (slave ship), Thames Barge and a

Bangladeshi river boat.

Page 37: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

37

Hew Locke - Previous Work

Page 38: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

38

Permanent Integrated Commission

Methodology and Community Involvement

• Hew has been gathering information on the appropriate heritage of the

boats, their decoration and symbolism. Histories will be suggested by

specific decorative details and cargos which has been the focus of his

consultation.

• Hew has undertaken significant research with guilds and companies

(Watermen & Lightermen, Hudson Co, East India Company, Thames Iron

Works), history from the Elizabethan period – including the various waves

of immigration and different diaspora groups in the area.

• Further research includes visits to St Matthias Church (built by the East

India Co.), St John’s Churchyard Wapping and its sailors’ gravestones, and

St Paul’s Church Shadwell where Captain Cook worshipped.

• Hew has met with and consulted: the Maritime Museum and Museum of

London; the Boitok Group (St Hilda’s East Community Centre), the

Coriander Club (Spitalfields City Farm) and the Chinese Association.

• Future consultation is planned with the Hermitage Community Moorings

and Tarling East Community Centre.

Page 39: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,
Page 40: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,
Page 41: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,
Page 42: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,

42

Permanent Integrated Commission

Design and Approval Process and Timeline

• May/June/July: Design development – creating drawings of the plinths and

drawings, maquettes and collages of the surface details for the sculptures;

security, accessibility and associated costs

• 12th June: Design Council Cabe design review

• June/July/August: further detailed artwork development.

• Completion of design work in September.

• The artwork forms part of the project planning application

• The timescale for fabrication and installation has yet to be confirmed.

Future Community Engagement

• Hew is looking at ways for future engagement during the fabrication stage,

the casting of the bronze, and post installation.

Page 43: King Edward Memorial Park Foreshore Community Liaison ... · PDF fileKing Edward Memorial Park Foreshore Community Liaison Working Group 5 June 2017. 2 ... through the process,