kiln heat-up, optimun kiln operation

42
ONODA ENGINEERING CO., LTD. ENGINEERING JAN. 0 6. i9.97 PROJECT C o KILN HEATING UP TIME oitte-17 '2- 1/-Q- At the time of kiln heating up, it is necessary to pay attention to the following items. (1) To avoid mechanical troubles of kiln shell, tyre, roller metal bearings, etc. (2) To avoid refractory troubles (The refractories protect directly or indirectly the above components against heat). 1 DETERMINATION OF HEATING UP TIME The heating up time is determined taking into account the environment in vicinity of refractory. (1) For new kiln, it is necessary to consider the drying time for castable, burning down time for cardboard spacer (installed for expansion allowance), thermal expansion of refractory, balance of kiln revolution by 180°, etc. (2) Kiln inside temperature at the beginning of start-up (e.g. ambient temperature, high and medium temperature at shut down). (3) Others such as flame pattern, whether or not there is refractory lining in top cyclone, etc. Notwithstanding the above, it is most important to comply with the following. (1) Burning Section (Preheater - Kiln) The heating up should be carried out to achieve the target temperature at outlet of top cyclone, kiln inlet hood and burning zone - 1 -

Upload: joko-dewoto

Post on 19-Jan-2016

649 views

Category:

Documents


100 download

DESCRIPTION

kiln heat-up guidance

TRANSCRIPT

Page 1: Kiln Heat-up, Optimun Kiln Operation

ONODA ENGINEERING CO., LTD.

ENGINEERING JAN. 0 6. i9.97

PROJECT

C o

KILN HEATING UP TIME oitte-17 '2- 1/-Q-

At the time of kiln heating up, it is necessary to pay attention to the following items.

(1) To avoid mechanical troubles of kiln shell, tyre, roller metal bearings,

etc.

(2) To avoid refractory troubles (The refractories protect directly or indirectly the above components against heat).

1 DETERMINATION OF HEATING UP TIME

The heating up time is determined taking into account the environment in vicinity of refractory.

(1) For new kiln, it is necessary to consider the drying time for castable,

burning down time for cardboard spacer (installed for expansion

allowance), thermal expansion of refractory, balance of kiln revolution by 180°, etc.

(2) Kiln inside temperature at the beginning of start-up (e.g. ambient temperature, high and medium temperature at shut down).

(3) Others such as flame pattern, whether or not there is refractory lining in top cyclone, etc.

Notwithstanding the above, it is most important to comply with the following.

(1) Burning Section (Preheater - Kiln)

The heating up should be carried out to achieve the target

temperature at outlet of top cyclone, kiln inlet hood and burning zone

- 1 -

Page 2: Kiln Heat-up, Optimun Kiln Operation

ONODA ENGINEERING CO., LTD.

as well as balance among these temperatures. The raw meal feeding

is started once the temperature of gas at kiln inlet hood reaches the

target temperature. Nonetheless, the temperature at burning zone during heating up should not exceed the target temperature to avoid damage to refractory.

(2) The heating up time should be decided so as to prevent melting down of refractory as well as to avoid damage of refractory due to thermal stress inside refractory.

The non-compliance with the above two items during heating up will lead to refractory troubles and some other troubles (such as unstable condition inside the kiln, raw meal flushing, overheating, clogging of cyclones, etc.) which may occur after raw meal feeding. Even if there

is no apparent refractory trouble during heating up, there is always a danger of causing serious damage to refractory.

If heating up time is too long (24-36 hours) or too short (8 hours), in

either case, it is practically difficult to achieve a continuous balance

among the three temperatures mentioned above both during heating up and after raw meal feeding. If heating up time is too long, the

above troubles will be experienced repeatedly but too short heating time is worse.

Accordingly, the most optimum heating up time is 12-15 hours

which has been decided considering the mechanism of causing damage to refractory (described hereafter) and to achieve a stable kiln operation after raw meal feeding.

2

Page 3: Kiln Heat-up, Optimun Kiln Operation

ONODA ENGINEERING CO., LTD.

2. MECHANISM OF CAUSING DAMAGE TO REFRACTORY

DURING HEATING UP

(1) High temperature of burning zone, highest temperature point, causing melting down of refractory.

- Too short flame causing overheating locally.

- Also, it is not possible to achieve a balance among three temperatures i.e. temperature at outlet of top cyclone, kiln inlet hood and burning zone. For example, the burning zone temperature may be high while other two temperature are low.

(2) When the heating up time is too short, sudden increase in temperature will cause excessive thermal stress inside refractory, thus damaging it.

(3) When there is rapid rise in temperature during short time, the newly lined refractory (without coating), particularly the refractory in burning zone will be damaged due to thermal shock, thus leading to unstable operation condition of burning section.

(4) Others •

Page 4: Kiln Heat-up, Optimun Kiln Operation

ONODA ENGINEERING CO., LTD.

3. HEAT DISTRIBUTION DURING HEATING UP

Even if the total heating up time is optimum, the improper speed of raising the temperature will give rise to troubles mentioned at 2(2) and 2(3) above.

The bending strength of refractory decreases with increase in temperature. If the difference in temperature rise between loaded face and inside of refractory is large (i.e. rapid rate of raising the temperature), the thermal stress in refractory will increase. If this thermal stress at a particular temperature, exceeds the bending strength of refractory at that temperature, then refractory will be damaged.

(According to laboratory tests conducted by Asahi Glass Co., Ltd., Japan for basic refractory bricks, if half of the thermal stress

developed at particular temperature exceeds the bending strength at that temperature, the inside of refractory is damaged.)

Considering the above, the rate of raising the temperature at least up

to about 800°C should be kept as slow as possible (actually it is decided by stable burning condition achieved at minimum fuel feed

rate corresponding to burner design). In our opinion, the rate of raising the temperature up to about 800°C during heating up can be

kept as 80--i 00°C per hour. Above 800°C, the rate of raising the

temperature is determined by dividing 1,500-800 = 700°C temperature by remaining heating up time.

For example,

Normal temperature to 800°C : 9Q°C/hour, heating up time 8.5 hours 800 to 1,500°C : 700/(15-8.5)=110°C/hour, heating up time 6.5 hours

Page 5: Kiln Heat-up, Optimun Kiln Operation

Instructions for Optimization of Kiln and Cooler Operation Doc. No : UT - KLCL - 01 Date : 7 Jan. 1998

1. Purpose of this document

UBE invited Mr. Kimura and Mr. Ujikawa ( Chichibu Onoda Cement Co., ) to CHC site from 15 — 25 Dec.1997 in order to check and optimize the kiln and cooler operation.

During their stay, Mr. Kimura explained much important and useful] matter for kiln and cooler operation, and also prepared reports. The purpose of this document is to record Mr. Kimura's various explanation during meetings ( which were written and explained on white board ) to keep as technical document in CHG.

2. Contents

Explanation by Mr. Kimura ( Chichibu ()noda) about kiln cooler operation

No. 1 : on 16 Dec.'97 at 9 . 30 — 12:00

No. 2 : on 18 Dec.'97 at 10 00 — 11:45

No. 3 : on 19 Dec.'97 at 14:00 — 15:00

No. 4 : on 22 Dec.'97 at 14: 45 — 16: 30

No. 5 : on 25 Dec.'97 at 14'00 ,,, 16:30

(Explained with above mentioned report "Report concerning damaged grate plates, 25 Dec.'97")

3. Reference documents

Refer to the following documents which were submitted to CHC together with this document.

0.) Report concerning damaged grate plates ( 25 Dec.'97 by Mr. Kimura, Mr.Ujikawa )

(Z Modification proposal during kiln shut-down from 21 Dec.'97 to beginning of Jan. '98

( UBE letter ; A/N - 234 on 24 Dec. '97 )

- New grate narrowing

- Installation of kiln burning zone thermometer at the side of kiln hood

- 2 sets of new inspection hole for cooler inside

- Change of location for grate thermometers

- Installation of guide vane for cooler 1st chamber cooling air

(a) Reference training text

(Prepared by Mr. Kimura for a training text book of cement plant in Taiwan )

t)C\wu&O.,A (1 4 47

tit

Page 6: Kiln Heat-up, Optimun Kiln Operation

Explanation of Kiln, Cooler Operation by Mr. Kimura on16 Dec.'97 No. 1 : Present operating condition

on 16 Dec. '97 at 9:30 — 12: 00

I. Status of the meeting

- To explain the present operating condition

- To explain some important matter for kiln Operation

2. Kiln torque and kiln speed

Kiln torque Kiln power (kW) Kiln speed (rpm)

Kiln power (kW)

Kiln speed (rpm)

Kiln torque shoidd be observed to monitor the kiln burning condition.

3. Problem of the present kiln operation condition

The most problem of the present kiln operation is that the kiln burner flame is " too short ". In this case, the following problem occur.

(1) Kiln brick trouble around 7m-12m from kiln discharge end

© Clinker telrnperature at the kiln discharge becomes high, then it causes the grate damage.

OO The quality of clinker becomes worse

- Free Ca0 increase (1/41 c

- Voltnetric weight (V.W) of clinker increase AAL

Page 7: Kiln Heat-up, Optimun Kiln Operation

Kiln length (m) Om 7m (Kiln out let)

freSerit" C ond 111'011 0 CHC

(VI -t- ern )

Max. tem retoch,o- e ■ Temp.

1420°C

1250°C

mi- v€

3

• Burning time is short Free CaO increase

Maximum temprature high Volmetric weight (V.W) of clinker is high.

The present operating condition of CFIC kiln is "the short flame condition of kiln burner" and "the high max;mum temperature".

(Show in line in above graph)

In this case, free CaO is high and the volmetric weight ( V.W. ) of clinker is high The brick problem ( about 7m) is caused by the short fl.nie condition.

4. Operat ng condition of yesterday (15 Dec.'97 )

Due to the leakage at the pulverized coal transport piping, kiln fuel was changed to 100% heavy oil conbustion.

The kiln torque was high after changing to 100% heavy oil, then red river was not observed in cooler.

15 Dec Kiln power Kiln speed Kiln burning zone 12nip.

Kiln torque Red river

14 : 00 221 kW 2.44 rpm 1459 "C 221/2.44 = 90 NO

15 :00 231 kW 2.51 rpm 1491°C 231/2.51 = 92 NO

Page 8: Kiln Heat-up, Optimun Kiln Operation

Tool-et IS In _til 15 cir€q•

f5; 00 on /590

r N4

7 7/"'\

/

\_ %I/ r ftd---- 1-z 00 on i C. -t)

Buthing zone

Temp.

1500°C

1450

1400

ec.

Kiln tol que Vs temperature of kiln burning zone

Kiln torque 80

90

100 ( kiln power/ kiln rpm )

6. Calculation of liquid phase of clinker

at 1340°C 6.1 Fe 203 + MgO R20 = 6.1X 3.16 + 0.87 + 0.47 = 20.6%

at 1400°C 2.95 Ae 203 2.2Fe2 O 3 + MgO 1- R 20 = 2.95 x 5.34 +2.2 x 3.16 +0.87 -4-0.47

= 24.1 %

at 1450°C 3.0 A(. 203 + 2.25 Fe203 + MgO + R20 = 3.0 x 5.34 + 2.25 x 3.16 + 0.87 +0.47 7 24.47 %

Normally, 24_5% of liquid phase id desirable figure.

,Sh ort an ,,,e

CooQer

° 4thie

jh Co.se of S‘/tort fame, di'iiker teinrerafore

is 191A 1 akic( &Ae ic'ttiki'o( rAase ineveAcec,

T4E/i, cooffria r( _.,_ r

efi-Ec I. o i- Cx irl ker becomes

wors- e. pier lore , v-a-te olan-,75 eas,1/

occukv-s,

Page 9: Kiln Heat-up, Optimun Kiln Operation

'7. Heat Flux 5

Heat flux means quantity of heat trasfer,

171- ;ek incide L "Pi A 4-f CoGr6in

V = calorific value of Fuel ( kcal/kg )

m = amount of fuel ( kg/sec )

Heat flux Ilfr , V x m (kcal / sec.m 2 )

ixTcxD

0 In case that the length of coatingt is around 15m — 16m, Free - Ca0 is high, or Free - Ca0 fluctuate ( high, low, high, low ).

In this occasion, kiln operation becomes quite difficult. The present kiln operation is in such conditions caused by short flame.

Free— CAO -OtAc -Evcs -tes,

© About 22 —,25m of coating length ( ) is desirahble for this size of kiln.

© The coating length can be observed by kiln shell temperature scanner.

8. Important factors of kiln operation

Et) Following factors are very important for kiln operation,

- Volmetric weight ( V.W ) of clinker

Page 10: Kiln Heat-up, Optimun Kiln Operation

- Free-CaO

- kiln power ( kW) and torque

- TBZ ( temperature of kiln burning zone )

- Length of kiln coating

6

the prfseht rocitiur,

(2) Especially, the monitoring of kiln burning zone temp. ( TBZ) is quite important. 7

In the most of ONODA cement factories, the temperature of discharged clinker from the kiln end is monitored. Then, such modification is recommended.

(;3) Average temperature of discharged clinker at kiln end in ONODA factories is 1350°C.

9. Brown color clinker

The reason of" Brown color clinker /1 is low MgO content in clinker.

( MgO content is 0.74% in CHC clinker. )

Mr. Kimura experienced " Brown color clinker" in a cement factory in China.

Finally, this factory decided to feed dolomite ( as adding MgO) in raw material.

Ae203 Fe20, MgO SO3 A p n /p,a -2.,3, . ‘...2%-, 3

C3S : Ordinary clinker 0.83 0.53 1.04 0.08 1.57

Brown clinker 0.97 0.72 1.08 0.15 1.35

C 2 S : Ordinary clinker 1.71 0.92 0.47 0.89 1.85

Brown clinker 2.14 1.2S 1.75 1.24 1.71

GAF : Ordinary clinker 24.81 15.45 4.94 0.07

Brown clinker 31.82 5.07 0.54 0.00

The color of cement is effected by C4AF.

Cement color is indicated " b value " in Japan

High

(Brown r)

b value

low

(blue)

1.0

20

3.0

MgO.

Page 11: Kiln Heat-up, Optimun Kiln Operation

In case of low MgO content in clinker, Fe-2.03 goes to C 3 S and C2 S, and Fe2O3 in C4AF becomes low.

If MgO content increase by 0.1%, b value degrease 0.5%. ( Cement color becomes blue. )

10. Actual method for change of kiln operation

Or Following procedures shall be done,

- Change of the length of kiln burner flame ( from short flame to long flame )

- Change of fuel combustion ratio of SC / kiln ( Increase of kiln burner fuel )

Howere, a high temperature position of kiln shell ( 440°C) is observed at 7.6m from discharge end. Therefore, change of operation should be done very carefully.

© The fuel combustion ratio of SC/ kiln is decided by a de-carbonation ratio of raw meal ( at the inlet of kiln ) and free - CaO content in clinker.

The target value is ;

De-carbonation ratio of raw meal = more than 90%

Free-CaO in clinker= less than 0.8 vo

The present. de-carbonation ratio is reported about 85%, but sometimes it decrease to 70-75%.

© In case of the consideration of fuel ratio of SC / kiln and De-carbonation ratio of raw meal , not only the . SC fuel, but also the tertiary air temp. shall be taken into account.

Total heat value of SC = SC (fuel) + ( tertiary air temp. x tertiary air volume x Cp ( specific heat air ) )

In case of low temperature of tertiary air, fuel amount increases.

OD Relation between the vonietric weight ( V.W ) of clinker and tertiary air temperature

V.W of clinker increase -4 Tertiary air temp. decrease

V.W of clinker decrease Tertiary air temp. increase

Page 12: Kiln Heat-up, Optimun Kiln Operation

8 11. Cooler width control and operation

Reference of cooler width control

CHC China 1 China 2 Japan 1

Clinker Production

( t/d )

4,000 4,300 4,100 4,000

Kiln D 4.55 4 4.64) 4.64) 4.24

Brick thickiless(T)

0.2 0.2 0.2 0.2

Non width ! control e I (m)

2,7

2.7/4.15-0.65

2.4

2.4/4.2 = 0.57

2.4

2.4/4.2 = 0.57

2.1

0.55 e ti D

(0 The cooler width control in ONODA plant is done by blind grate, not by castable like CIIC.

(.4 In case of width control by castable, cooling air leakage occurs between the clinker bed and the castable (r41,1- t 0 nett- r--,9.e•)

[A.r1

Ctoier Co4er- w 04 Cory( r-4 04: Non vtid-til Coerti-oY

,6/ = Q. s- O. 6 (3) Control of cooler

The following matters are important factors for cooler operation.

- Setting of suitable thickness of clinker bed, and keep this thickness

- Control of red hot area of clinker

In orderix) know the thickness of clinker bed, the following method is recommendable.

In order to look inside of cooler of 1st — 4th chamber, installation of additional inspection hole is recommended .

Page 13: Kiln Heat-up, Optimun Kiln Operation

/ / r

Air ct;r

-

/j7 / / T.

Cas-ta e

Cooler Narrowin

ithn4

In ONODA's plant, narrowing is made by blind grate.

In case of narrowing by castable ( as present CHC cooler ), air goes through between the castable and clinket bed.

Confirmation of the clinker bed thickness

71

'',,I —,--,—...

/

h.-

, --,

In order to check the clinker bed thickness, it is recommended to install the marking brick.

i / ,

0,8m

0.6p,

Page 14: Kiln Heat-up, Optimun Kiln Operation

dinkr iro9rstribt"tior, of

Coo -re r tr, °meter --

riird e

(11) Cooler efficiency

(J) Cooler efficiency vs Thickness of clinker bed

/ 0

Cooler

Efficiency

0.6 0.8 clinker bed thickness (m)

- In case that the thickness of clinker bed is too thick, the secondary sintering occurs on the surface of clinker bed.

- The target of clinker bed thickness is about 600mm.

(.5) Heat consumption vs tertiary air temp.

Heat Consumption Kcal / kg.c1

To goo Ro O

Tertiary air temp. ( °C )

(0) Monitoring of grate plate temperature

Cnventional cooler : Normal 55% — 60%

In case of good width control 60% — 65%

Mulden type cooler = 70% — 75%

Page 15: Kiln Heat-up, Optimun Kiln Operation

W rnit 'clottArY■ t vies'o

150

100

50

0 3/1 211

kl:c17 (VA ( ti n'Acr cri

"111 ClA 1

( 141113C$ )

nuoutri: 7>ip of

'1300 700

44 1000 1500 1100

loll

311211 31170 9/11511 1011111 1111 2113

3/170 9111511 10/110 111121 61

c-rp,1) 1 )1/ >1,11.Aig10 43t41- rri

1290 '190

opo 9( , 1,

800 7011

3/120

hvi i) 1 1) 1 c. i i' rok-e7.

3 11'0 0 9111511

11:1) S 1, 1

,311711 9111511

10)1111 11112111

1011 III 111'21(1

9'1;/ IM

1 1 - Ca O

YERR:14MALVIA

9200 4100 4000 3900 3800 3700 3600

31121

.11.21a c.1;m1<c)-- vi':041A(t(i.b. I

I. 30 31120 31170 911150 10 /Mil 11/1 21 El

3/1 711 911150 101110 ,11 1 12111 .

• fwe i rctaddi 50 48 46 44 42 40 31120

Mff111;1. 1 1 1 1 ,7. //eat ColiS0 .1 tr) 800 kr6/ 780

10.111H 11/12111

10)1111 1 .1,2111

4i

10

35

311711 911 15 11 1011111 , 11 12111

760 - 1 ' 740

720 • - vs

700 311 20 311711 911 1 511

11P)

, / &S- _- ___

31170 911150 10/110 11112111

2. 20

2. 15

2. 10

2. 05 Rte'

2. 00 3/1 20

3. 00 2.80 2. 60 2.40 2. 20 mr,-'

2.00 31120

2. 00 1. 80 I. 60 I. 40 I. 20 1.00 —

31120 311 711 9/11511

3 . 10

2 0 210 2 0 2(40

311 211

1 10

1 110

' 1 00 0

Liu 3 1 1211

2

1111,11alff ter-T;0-17 CO,/1 Titl(t)

3117H

31170 911150 ; 1011121 11)12111

writ Df

---- I

311711 9111511 -f 10/110 1111 210

1111 I )17:.KIR C aS teavi

51170 9111517 1011 1.11 1111210

1 , ,

1111 /->TiFf10,111; 1. 1 1 1 fq. Ur111 o fj i

I 11 * - „_------

911150 1011111 111121H

0 — 311 20 321711 9111511 1011 1 H 11 1 12111

O. 5

1. 5

Page 16: Kiln Heat-up, Optimun Kiln Operation

7,11 A IV CAS

Ock

v'c Irvin I- )1/9 V S

1750

1700

1 650

1000

• ' e.,„

Id:1550 - JZt

1500

1450

1400 50 60 70 Bo oo 100 I o

I- )1, 9 / )1:, IfThlia()

Page 17: Kiln Heat-up, Optimun Kiln Operation

144 %IN MT- ELI

b 3 ,1 /3:7'

2.8 3

Te-'4-c‘ 1 h CtINc, <F,Ax3).1 ,ri>

c

FAit).1

f,0 1 2,S 2 I 2,3,:;:

8,2

s-?

g st 2A-54 12,28

t re * fit tztild

-Z<B - / . 2 27-.. t

z. -o6 [z-S-5 28,8 j2-143 cp()

2- 2 j2 -2.1 [3 - 12

I 2 . / J22.0 c>,4 , _4) 2.

7 , 2 ; 2-° 7 P.

2.7 .18,o ;Z-2.1--- 2

3..io

;..1111, 4 f 111 iS,. / ); 1 IS gL", (1 I S (.-; 13 th ((CA)

3d

13,3/214_

fLLA [I IS) 7 d /1 c'uft 118d

4/1. 1 12 ASTilviiqff,. 6/4

i' 3 AsiK 470/.7

28d

7 P( 8 ?,- fc

Ak -1-1"7 1 _6/ 2y ,3 z/D .

Ash 1 2, S-../,/)'0, 27_ 0 <4,,8 / 8,0/. 2 y,

(4

49 7 17 1 5-

,5.1 7 0L(17.( -0

•!,20is3/0_, 17 G is; 2 5 R — P 2 1_11_, t!i[!,

Lot I S03 igloss ‘/(1. :`; 2,( 1.7 ,C 1-4 7 2 _ v_3

gE Tif ,, B") --ivDTT-,i.fgc

sl I • _tif:f.i - 41):f vans -01-1<1441 .

-V14. .........

14 1711— 1 IR .42 kt;',i> \ zL(Ep. -FtAzo

s/13- 8 9J- 172 *T

17t< To04 1 5 ;-;t<

2:1‹ th?,1 /1' ( /Ei t1 ftI1 Sfi I (S1', 11 13 I ' S03 R20 . kci

-S-7.12 FYI 71,--fit 1\1 3.-24_0 2/ 2- 2 - q.8

-

2- 1, 2

Et-E4-vir ( G 13 )

/LI ;U: 3 d 7 d wIi /1:1

S72 z2. 2. 7 1-

3 A- Y'./ 7.s-A 0 . 6 2: 7, 3/1 . 7

As77).,1(" . 0'4-b

28d .(W. 20 °c ASTM

oft tl ; 36 5/6 160 44f 0 1/4 ti Ch , ;“'0 47TO

0 .:±.6 <MS 0

‘11 . 3-18 F ,:??

22741 z 71( SZI H-Lij ._E 6=1-11 )

'SIR, fit (MT' ifi1 a 471 x III '

0_ 0 10 2- 2

1 if] S-36 ;)-1 0. 0 332- 2 ;Fl 47 AST1, ,z1 374

13 '')‹ 42 AS7JA $7o 0

... \

14

/H

4f7

6 27

R,111 J62 7 3-82 1

rii'..tat SW1 7, I M t4g0 S03 • Ca0 I, W

408 2.63 Z. / o,?q, t),43[ c (,20 2_01, ,c1. 62 . 1s c.24i 0,e/ 2 (,17

48o7 V3,.? 2,4 f ,4 0 2,1B 0..22 o.s4 r).,8 f,( I

40,0 2-67 2_ ,,j o , 4-r jo, if 2,r2 o 6,-(-3

2 a . 6 6 0 2.c o 133 o, S Z o,

SOR 01; S03 2 7 , 2

o, 0 3 D o 2 3 2 0

( 9 7 11 • FT -

ft H )

0 2 0

3 2 . 2

2 _ 2

a ,0

Page 18: Kiln Heat-up, Optimun Kiln Operation

TEST CFI VITICATE E Clinker

Dale

Supplied lo

Sampling Dale

Vessel

v- ^ tr-9ec - A ve vole

: Clinker

Requirements max. max.

CHINFON HAIPHUNG CEMENT CORP. TRANGKENI I - MINHDUC - 1111, )/NIGUYEN -11A1PlIONG - VIETNAM

TEL: (84.31) 875 ) FAX (84.31) 875 478

—441, ❑ Poi Hand Cement

Conlract,l40.

Type .

Qu Inlay

Lot Ito. i

CHEMICAL COMPOSITION & MINF,LAL CONS'ITIVENT

M a X.

Los on ignition (W' )

In s~lilhl¢~IZ~si~luc (%)

SiO z I y';',

Al z03 (`;"(), 13&:*.y. 81; X. ((70

MgO (rg,) SO3 (VC') K2 0 Nai9 C;f0)' Total alkalies (as Na 2 0) ' Fro Ca()I

C3 5 I (:)c(:)) e2S

C3 A (To) C4 A (%)

Results* 0.47

22.06 5.32 3.36

64.97 0.74

0.38 0.63 0.19 0.61 0.76

55.21 21.60 8.41

. 10.22

mar. .

111 a X.

l i

PITYSICAI., PROPERTIES

Con tires 1tC strenglli

3(tiys

7days I .

28days

Setting tiMe: (Vicat lest)

set Final set

Soul' lness: (Le Chatelicr)

Fineness:

Sieve 0.08 nun

• Plaine

*Tet TCVN

(N/n), ,

) min.

(min)

(min) max.

(`ro) max.

(%)

(cin'j); I min.

Oft lion Clung - SI Hung

Chief - ()wilily Mgt Sec.

Page 19: Kiln Heat-up, Optimun Kiln Operation

Explanation of Kiln, Cooler Operation by Mr. Kimur No 2 : Change of kiln speed and burner position, Kiln passage time

on 18 Dec.'97 at 10:00 11:45

1. Status c f the meeting

After checking of the present operating conditions, the following matters are proposed.

- Change of kiln speed

- Change of burnner position ( for long flame )

- Consideration of passage time of raw material in the kiln

2. Present operating condition

•CO The present kiln speed 2.60 rpm at 260 t/h Kiln feed rate is too fast.

According to the attached graph, the target of material filling rate in the kiln shall be 6%, then the target of kiln speed is 2.34 rpm at 260 t/h kiln feed.

Kiln

torque

kiln burning zone

Temp. ( TI;Z )

Passage time

in kiln

Kiln speed

17 Dec. 75 1550°C 22 min 2.60 rpm

5 Dec. 85 1450°C 27 min 2.60 rpm

In case that the material filling ratio in the kiln Is changed, the condition of falling down clinker on the cooler is also changed.

3. Importantfactors for kiln operation

Factors

The present condition of CHC

(-0 Kiln torque Low

W Temperature of burning zone ( TBZ ) High

.r) End of kiln coating 15m ( short ) 2 ,, 1, ,....,

(4 ) Material passage time in the kiln 22 min. ( short ) ...-s. - I.:, %.." ■■•• ,

V Volmen ic weight of kiln

©

High

Free - Ca0 High

(-7) Temp. Of kiln inlet end Low

V Temp. of tertiary air OK

Page 20: Kiln Heat-up, Optimun Kiln Operation

- 0A -feed zoo 270 2-2 9 230 .240 2 SO _aeo 270 280 E_-`71,3

f.-)00 T +A1.3 icrrdtwfioil,

raw wts.r.ot,/ / t- cAin,4e-

3 00 > 600 •

in.5icke r-Q,lorcutvvi

1%.t,t froAi 0 tA. 49

kt 0 rn bet w e.e ,n Fateal feed tune om ty,

2 (

Yir)6° ;. 1 6

147 207

2. c) — 22

185 3 0

/. 77

2 16

2_, cg — 2.6

1. 20

1.54-

/.62 7 a

a. 6

(. 6

1 .4

Page 21: Kiln Heat-up, Optimun Kiln Operation

4. Operation data on 17 Dec.'97

Sift

Kiln speed

( rpm )

Kiln

torque

TBZ

( Kiln burning zone)

Kiln

passage time

1st : 2.60 75 1435 — 1576 25 min.

2nd 2.60 73 1400 — 1597 25 min.

3rd 2.55 80 1407 — 1598 28 min.

5. Raw material passage time in kiln

Kiln passage time Kiln condition

Less than 25 min. Kiln condition becomes unstable.

30 min, Kiln condition is stable, and clinker quality is good.

More than 40 min. Kiln condition becomes dusty. Red river occurs.

(t) The red river of CHC occurs in the condition of the passage time of less than'25 min, and high temperature of clinker discharged from kiln.

The red river of CHC is not the case of long passage time of more than 40 min.

The target of the passage time is 28 min — 3 0 min.

6. Target of kiln speed, kiln torque and the burning zone temperature ( TBZ )

Target of kiln torque 80 — 90

Target of TBZ 1400 — 1500 °C

Target of kiln speed is 2.50 rpm as a first step.

Present kiln speed 2.60 x 60 = 156 rph

First target 2.50 x 60 = 150 rph

17

Page 22: Kiln Heat-up, Optimun Kiln Operation

Kiln length 15m 20m

Tc nip.

142.0°C

1250°C

Theorei ic ally, final target is 2.34 rpm x 60 = 140 rph

/8.

7. Kiln burner position and adjustment of burner flame

A / Present- cbnd4isot PrRseht et,pet (0,Feco

cAcie / /b(aveh)

Under the area of 1420°C

is a cooling zone.

The current operating condition is show in " " line, and it means high burning zone temperature and short burning time ( short flame ).

© The operating condition shown in " " line is desirable, and the current condition should be changed to " " line .

After change of operation

Condition

B < A Free - CaO is high.

Volmetric weight of clinker is low .

Then, kiln fuel shall be increased from 42% to 43%.

B = A Free CaO is low

Volmetric weight of clinker is low

Then,this condition is OK

A,B is each area above 1420°C ( A is current condition, B is the condition after change of kiln flame. )

(i) Length of kiln cooling zone

Desirable length of kiln cooling zone = ( 1.5 ) x D = 4.15 — 6.2m

D = kiln inside brick dia. ( m )

The present cooling zone length seems to bey about 2m only.

Page 23: Kiln Heat-up, Optimun Kiln Operation

Karl feed ( t/h )

C4 material temp.

Burning zone temp. ( TBZ ) •

IM=111/11•11111■

V When the bUrner position is changed, operating condition should be monitored for minimum 4 hours until situation changes. ( Due to large heat capacity of kiln )

8. Raw material passage time in the kiln

T= K x L T = Passage time min. )

DxNx0 K : constant value

L : Kiln length ( 76 m )

D = Kiln inside bri&k dia. 4.15 in )

N = Kiln speed ( rpm )

0 = Kiln inclination ( 4/ 100 )

The theoretical value of K is 0.142.

In CHC kiln, T is measured as 22 min by trend chart graph.

K is caliculated by using T = 22, then K is 0.13.

)te kr 110 "Xo

Method of determination T by trend chart geduce -Peel to -6A

-Soy. 5 ^- 10 m in.

Actual passage tinn e Time

Lictec.ot fr, ate r itd tethrev.0-6- 01-e,

-tto cool be vsed or cd,ove

/et hoot

Page 24: Kiln Heat-up, Optimun Kiln Operation

Explanation_of Kiln,Cooler OperationbyMr,Kimura No. 3 : Condilion_after 100mm insert_of kiln burn=

_on Mice. '97 al 14:00 — 15:00

1. Status of meeting

(1) Kiln burner was inserted into kiln by 100rum on 18 Dec. at 14 : 30.

The burner position before insert was just the kiln end at hot condition. After insert

of burner, the burner front end is 100mm inside of kiln in hot condition.

2. Condition after inserting kiln burner ( 100m n

The condition after inserting burner is the case B < A. ( Refer to the explanation of 18

Dec.'97)

That is, Free - Ca0 is high and Volumetric weight of clinker is low.

3. Analysints by the concept of Heat Flux ( refer to explanation on 16 Dec.'97 )

Hf = 7200 kcal/kg / 3600 x 7400 kg/h = 73.7 kcal/m2

x D x-e

D = 4.15 m (;kiln inside brick dia. )

e = 15 in ( Coating length )

Le rie A ,e Coating length was changed from 15m to 16m. Hf ( at = 16m ) = 75.7 x 15 = 71.0 kcal/m 2

If Hf is kept constant, fuel shall be increased as follow.

7400 x 75.7 = 7890 kg/h

71.0

7890 - 7400 = 490 = 0.5 ton coal/h

Z2

Page 25: Kiln Heat-up, Optimun Kiln Operation

23 Therefore, fuel of kiln and SC ( calciner) shall be changed as follow.

Kiln fuel 7.4 -1- 0.5 = 7.9 t/h

SC ( calciner ) 10.5 - 0.5 = 10.0 t/h

4. Kiln Coating monitored by kiln shell temp. Scanner

When the butter position is changed or burner flame shape is changed, the most import

check points are above mentioned coating end position ( coating length ) and the

position or coating ring .

5. Fluctuation of ELM in the kiln feed raw mul

If H.NI fluctuates as 2.15 ± 0.04, kiln operator can not control the operation.

In case ,of fluctuation as 2.15 ± 0.02 which has continued from yesterday, it is very

difficult to keep good operation.

In the worst case, it may cause the melting of kiln brick.

(Ii) Kiln heat load of cross section heat load is calculated of follow.

Heat load = 7,200 kcal/kg x 7,400 kg/h 3.9 x 10 6 kcal/m2 h

7C / 4 x D 2 t 1 3,0)

D = kiln inside brick dia = 4.15m

The average figure of kiln heat load in Japanese cement fectories is 5.0 — 5.2 x 10 6 kcal/m2 h.

The, figure. of CHC is lower than the average of kiln in Japan, thus even if ELM

flactotes, there is not concern about melting of kiln brick.

But, low heat load cause high Free-CaO in general. Thus, the heat load is

recommended to be increased more. If the kiln fuel is increased from 7,400 kcal/h to

7,900 kcal/h, the kiln heat load is increased from 3.9 x 10 6 to 4.2 x 106 kcal/m2 h.

Page 26: Kiln Heat-up, Optimun Kiln Operation

711100•IMII■

21- The kiln heat load about 4.2 x 106 kcal/111 2h is recommended to keep Free-CaO in a

target range.

(E)) In Tsukumi plant, the target value of ITN; deviation ( clinker basis ) is ± 0.02.

0 The kiln heat load is depended on burnability of raw material.

In case of low burnability material, kiln heat load should be higher.

(4) Whtn R. 1W mill is stopped, kiln dust collected by EP ( high HM dust ) should be

stored in kiln dust bin.

After Raw mill start, the kiln dust is gradually discharged, and is mixed to raw meal.

(After finish of this day's meeting, it is confirmed that kiln dust is stored in the kiln

dust bin from 2 months ago. Operator forgot this action only on 18 Dec. )

6. The next action for operation

If the lbllowing conditions are fulfilled,

> 2.17

Kiln torque > 70

Kiln burning zone temp. < 1550 ° C

( TBZ )

Change fuel by the step of 0.1t/h at avery 30 minutes.

7. Mater* filling ratio in kiln

For rough visual checking method is described in Cement Data Book. ( It is attached to

this report. )

8. When S.M is decreased, the burnability of raw meal becomes good. ( It becomes easy

burning. )

9. Kiln heat load vs Free-CaO the normal relation is as follows.

Free

CaO

4.2

Kiln heat load

5.0 x 106 kcal/m2 h

Page 27: Kiln Heat-up, Optimun Kiln Operation

2 5- 10. Action of operation on 19 Dec.'97.

After finish of above explanation, kiln condition is as follows.

Kiln torque = 140kW/ 2.51rpm = 56 ( very low )

TBZ = 1600° C ( very high )

Therefore, the damper of kiln primary air +An ( 24FN5 ) is reduced in order to make

burner flame longer.

Before

action

16 : 15

19 Dec.

16 : 49

19 Dec.

Kiln prim. Air

fan damper

26.8 °A 18.1 % 14.6 % Keep

continuously

Pressure of circulation

flow of kiln burner

1150mm H2 O 1050mm H2 O 950mm H2 O

Afer above action, kiln power was going high.

11. Operating condition on 20 Dec.'97

After the action on 19 Dec. ( making kiln burner flame longer ), kiln condition became

stable and the following points were observed.

(I) Free CaO keeps less than 0.8 %.

Kiln torque became high

13e1bre Action Action for

long flame

19 Dec 16:00

After Action

19 Dec

10 :00 12 :00 14 :00

19 Dec.

22 :00

20 Dec.

2:00 6:00 10 :00 14 :00

Free-CEO

( % )

1.69 0.86 0.38 0.49 0.86 0.47

Kilit Torque

' 61 60 62 79 77 75 77 74

( Refer to attached " TY'end after action. )

Page 28: Kiln Heat-up, Optimun Kiln Operation

(,3.) Grate plates of 2nd row in 1st chamber was heated to red color before action.

( was observed from inspection window under grate. )

Hoverer, after above action was taken, rcd color heat was disapeared.

It meanS that the clinker temperature at kiln discharge end was rather decreased.

(4) The color of red river ( which is observed from the tertiary duct on 4th chamber of

cooler ) became dark.

According to the identification sample (color vs temperature), the color of red river

was changed from " light orange red : about 950 ° C " to "orange red = about 850°C).

Page 29: Kiln Heat-up, Optimun Kiln Operation

a CdFt, D/Yi trem t)71 2r/Dec '9'1

u/4-

.,_----7 -------,_ / . .

- __ x . ,.________L , - - , - _

------ __---

1------7.-- -

/ . 3 36

/, 5 (j(

1 , 30 1.16

8.0 0

,

,

,

''"

„.„ 7E,o0 20,0a 22,00 .2,00 2.0D bo o 10,00 1.1)0

?t/I' -1- 1 e bc.o-(1) -6- 1011-0 11t}:: 111 ai .1.-30 .

,00,77,,„

1.00 oz —4

0.6

1 ..-..,--.• c 1 I I

I 1 I — z/lr----"---'NN `-1 I 1 I - • •

I ,,,,.----7 qr -........ I

"1", I r '

I '4

1

i

- ' N o------- \ i----1, vi

/ , . , N . / 1 ' ------- i

/ i 1 /

0 0 0

r-r 1.1 lv

TDRaUC - 73

/7 0

/ : \

Page 30: Kiln Heat-up, Optimun Kiln Operation

-1 ,

IS 1,1_ A

.41 II A the • a • f

Mar q-f-tet- acil oii ( aVet-O,e e_v try hown

?/0(0c)

H. 870 0It/02Q

'870 2.80 ( °c) 27D 260 -

1,4,01.9_13u7_(g,

X Teernr x /1111111111Mil/MMMINIMPAIMIIMMMIAMIIIIMIAMINNIII

,./ 1 \

-

i \ /

i I x i I

i 1 1 I X i 0 ' I

, / j 1 f?, /411111111111/

,.. 11111111111111/4111111

..i — i

1 1 i i I - — -

I - ..

1 ' 1 I i i 1I I S 1 :

A 1

" 1 ■.. al I A\ I /i ---,•■ I , \

mi12 ONIMIIIMMIIII NIMMUMMMINNIIMMINE=11111■

In11111111111111•1211111 W/1101111111111211111111111111111=11

111111111111111111 ILVAIIIIIIIIM1111111111MMIUM111

. 6 to Fri is/pec

••

o.6

1 2 4 ,0 23 0

1660 (°c)

1620

ILO

(v/\-Pf4) 30 78

E3

KILW 77?

7 .70 kA

2..16

ienrir

00u1 670

br -L37-

1E:A-0 ■ -40 5-3D

I- D

lo b=i-

Pre.mAre 'fi gs cj,47/ked, fro/71 /8-Dmout. 9±-0

441- c,losect ro-/X6X. •

t.

10 14- 15 22 2

2}6ec rvec. 2,_ I S

Mt, n! Vri "Te

Page 31: Kiln Heat-up, Optimun Kiln Operation

19. Der Otehofun

schen C'fensch issen. Die Ausmauerung on 1Ther-gangsz Lien ist kompliziert, arbeitsaufwendi und verlam t Spe7dalforinsteine. Eine besonders

F)rmgebung, die mehrfach angetroffen wind, ist lie Ve -engung der Auslaufzone des Drelic.fens ; dies (Wart z •t teil .veisen Ktahlung des Klinkers in, Olen und zu; schnellen Abnutzung des Ofenfutters ,n die-sem At schnitt_

Sowohl praktische Erfahrungen als auch theorctische Cfherlegungen ftihren zur Erkenntnis, dad der Dreh-ofen ohne Einschniirungen bz-w. Erweiterungen die derzeit g , instigste Ofenform darstellt. Die Dreiirohre der mr dernen WarrnetauscherOfen weisea hereits durchwe.gs einheitliche Querschnitte auf. Schtechte Erfahrungen mit Drehofen verschiedener Quer-schnitte veranla3ten die Zementindustrie der Sowjet-union, rur noch Olen mit einheitlichem Durchmesser zu bauen,.

19.1.1. Of.mfdlIungcgraci

Die Ma:erialftilleng ina Drehofen bildet einen Kreis-abschni t des Ofnquerschnittes. Das Flachenv rhalt-nis diesel Kreisabschnittes zum gesainten Ofenquer-schnitt 'a Prozent ausgedriickt wird als OfehfUllungs-grad f bezeichnet (siehe Fig. 193.).

Ofenfrillungsgrade schwanken in den Grenze i von etwa 5— UnebbAngig vora Ofenclurchnies er ist der Fulliulgsgrail hit- die verschiedenen Wertz des Zentriwinkels rc wie

19. The rotary kiln

highly labor consuming, job, requiring specially shaped refractory bricks. A kiln shell shaping which is particularly disadvantageous, Is the narrowing of the kiln's discharge end; this results in partial cooling of the clinker in the kiln and in a rapid wear of the refractory in this section. I

Practical experience as well as theoretical delibera-tions lead to the observation that rotary kilns without constrictions or enlargements represent currently the most useful kiln construction. The ;hells of modern preheater kilns already sh'c)w uniformity throughout the cross-sections. Unfavorable experience with rotary kilns of different cross-sections, prompted the cement industry of the SOviet Unio). to build rotary kilns with an invariable diameter exclusively.

19.1.1. Degree of kiln

The feed forms a segment of the rotary 1- iln's cross-: ection. The area ratio of this segment to the area of the kiln's cross-section expressed in percent is called the kiln's degree or percent of filling f, (see Fig. 19.3.).

Fig 19.3. Scheinatische Darstellung des OfenInflungsgra- des

Fig 19.3. Schematic of the de g ree of kiln filling

Kiln filling degrees fluctuate within the limits of about 5-17 go. Independent from Ulf- kiln's diameter, the percent of filling for the different values of the centric angle a is as follows;

Zq

Zentrk\a inkel Centric angle cc

r -tfenfrillungsgrad 0/0 010 of kiln filling

11C ' 15.65 o/o 105 ' 13.75 (lib 100 ' 12.10 0/0 95' 10.70 0/0 90' 9.09 0/0

7.75 0/o BO' 6.52 oio 75' 5.40 0/0 70' 4.50 nio

Der Einflu3 des Dfenhillungsgrades auf den Derch-satz des Drehofen; ist in Fig. 19.4. dargestellt. Drei Kurven reprasentieren FCillungsgrzele von 7, 1‘' und 13 Vo, wit den dazugeharigen Durchsatzen in t, h (dr Drehofen rift Durchmessern von 2 his 3.5 m.

Tile influence of the degree (.1 filling to the rotary kiln's capacity is shown in Fig. 19.1. Three curves represent filling degrees of 7, 10, and 13 0/o, with the corresponding capacities in t/h for rotary kilns with di imeter from 2 to 3.5 m.

19.1.2_ 0'?;ineigun;

Es gibt k eitie allgemein giiitige Regal fur (lie richtige Neigung von Dreil5fen. Neigungen von Drehofen lie-

/P./.2. Kiln slope

No generally valid rule exists for the proper slope of rotary kilns. Rotary kilns shpv slopes from 2 to 6 0/o.

384

Page 32: Kiln Heat-up, Optimun Kiln Operation

Drehoienneigung and Ofenifinungsvad Rotary kiln slope ver as .11n load

Ofenneigung No Kiln slope No

4.5 ',la 4.0 0/o 3.5 No 3.0 wo 2.5 No

Entsprechender Ofentullungsgrail an Corresponding kiln load 0/

9 a/o 10 0/s II Vo 12 No 13 0/

19.1. Ausfri nrungsformen uas Drehofens

.1

19.1. Types of rotary kAns

11'6 -

11 0"

10'0'

Fig 19.4. OfeuRillung.tgrail end Drehofendurchsatz

Fig. 19 4. Degree of filling versus rotary kiln capacity

.7. In

sid

e k

iln

d

ia

me

ter

10 Drenolendurchsotx

20 30 35 lin

60 120 Rotary kiln capacil y

1150 210 Win

gen zwi ir- hea 2 und 6 Vo. Meistens triff:, man jr loch Ofen mit Neigungen von etwa 2-4 Wo znr Hod? )rita-ln an. Eirsprunglich hatten Drehofen qn56ere 1‘fei-g , ingen lei niedrigen Umdrehungszahlon von -,tv a 05-0.75 LUrnin. Geringere OfennuiguLrg erk dert e i ne ho'wre Drehzahl ; dies hat den Vo;teil, dad das Ofenmaterial besser gemischt und eLrem intensi-veren Warmeaustausch ausgesetzt wird. Nlan erreicht auch mit geringerer Neigung hohere )(en-hillungs grade. Aus praktischer Erfahrung resuliert, daft den folgenden Ofenneigungen im prakti; :hen Ofenbetri!b optimal erreichhare Ofenhillungs; rade entsprechen; siehe Tabelle 19.1.

Tabelle 19.1.

Most kiln slopes are between 2 and 4 olo to the hori-zontal. Originally, rotary kilns had higher slopes with lower revolutions ranging (rola 0.5 to 0.75 rpm. Lower kiln slopes require higher numbers of revolutions; this has the benefit of better mixing of the kiln feed, together with a more intensive heat exchange. Lower slopes also permit higher degrees of kiln filling or of kiln load. Practical experie'r, :e resulting from kiln operation shows that the following kiln slopes yield the corresponding average kiln loads; see table 19.1.

Table 19.1.

:kndererseits wird behauptet, dab der Clenfrillv ngs-grad vorn Verhaltnis der Lange (L) zum 1,?nrc:hrn sser (D) des ()fens abhangt. NaBdrehofen mit 'einem './D-Verhaltr is von 40 und darriber weisen Fullungst•rade his zu 11 0/o auf [1761 dedenfalls bestim nt die lei-gong des Drehofens in erster Linie den ngs-g[ad, wobei ein steigendes L/D-Verhaltnis den Fril-lungsg -ad noch erhohen kann.

fm praktischen Ofenbetrieb soil ein Frillungsgrar' von 1:1 °A) nicht uberschritten werden, da 1rohere ['CIL tungsgrade den Warmelibergang versddr chtern.

On the other hand, it is said that the kiln load depends on the length (L) to diameter (D) ratio of the kiln. Wet process rotary kilns with an LID-ratio of 40 and more, show kiln loads of tip to 17 % 0761. In any case it is the rotary kiln's slo'pe which determines the kiln's load in the first place; in addition to this Is an increasing L/D - ratio a factor, v-hich can contribute to the kiln's higher load!

In practical kiln operation the kiln load should not exceed 13 ,/o, since higher kiln loads impair the heat transfer.

385

Page 33: Kiln Heat-up, Optimun Kiln Operation

EN')lac ation of Kiln, Cooler Operation by Mr. Kimura No.4 : Modification plaA during Kiln stoppage

on 22 Dec. '97 at 14:45 — 16 :30

1. Status of this meeting

cooler was stopped on 21 Dec. at 20:00 by falling down of 2 pieces of nose

ring of kiln discharge end.

0 In this meeting, proposal of next cooler narrowing and necessary modification plans

were explained to CHC.

2. New narrowing idea of cooler

Tis narrowin4 plan comes from much experiences of ONODA.

3. Installation of kiln burning zone pyro meter ( 24T72 ) at the side of kiln firing hood

4. New installation of 2 inspection holes at cooler

5. Relocation of grate plate thermometers to check the clinker bed conditions properly.

6. Guide vanes for cooler 1st chamber cooling air duct

These modification items are officially proposed by UBE's letter. ( Ref. No. A/N-234

dated 2.4 Dec.'97 )

3l

Page 34: Kiln Heat-up, Optimun Kiln Operation

Explanation of Kiln, Cooler Operation by Mr. KitniAVok

No.5 : Summary of Instructions from 16 Dec. And

Instruction for Next Kiln, Cooler Operation on 25 Dee. '97 at 14: 00 — 16 - 30

1. Status cf this meeting

CO Mr. Kimura and Mr. Ujikawa prepared a report " Report Concerning damaged grate

plates, dated on 25 Dec.'97 " and submitted it to CHC.

In this meeting, Mr.Kimura explained this report, and summarized the optimization

of kiln and cooler operation.

And also, important items for next kiln operation was explained to CHC.

2. Page 4/12 of the report " Trend after action '

(.0 When Mr. Kimura came to CHC site, and checked operating condition, the kiln

passage time was short ( 22 min. ) and Frce-Ca0 was high. ( It fluctuated rapidly. )

The damper of kiln primary air fan was cb)sed from 26.8 % to 14.6 %, and tried to

make the kiln burner flame longer on 19 Dec. at 16:50.

(0) After this Ac tion was taken, kiln torque kept high, and Free —Ca0 was decreased.

This change of condition are obsered in the graph of " Trend after action " in page 4/12 of the report.

32

Kiln

torque

70

19 Dec.

16 : 50

I )ate and time

Page 35: Kiln Heat-up, Optimun Kiln Operation

33

Free

CaO

19 Dec. Date and time

16 : 50

3. Kiln material filling ratio

S = 1.667 x T x M. x R = 7.2 %

AxLN9

T = Kiln passage time ( 28 min. )

M = Clinker production 3900/24 = 162.5 t/h

R = Average material in On R + 1.0 - 1. 055

R 1 = Material at kiln inlet

R j = 1 55 t/t x (1- 14)c ) 1- 1.0 t/t cl' x c 1.11 (q) c = Decarbonation ratio = 80% )

100 100

A = Kiln cross section area = 7" x ( 4.55 - 0.4) 2 = 13.52 m2

4

L = Kiln. length = 76m

G = Average bulk density = 0.9 + 1.27 = 1.085 Um'

2

In case of the calculation at the most recomn endable kiln passage time : T = 28 min the

filling ratio S = 7.2 %.

In case of the passage time T ( before the kiln burner shape adjustment )

S= 7,2 x 21 = 5.4 %. ( lt is too low. )

28

The target value of kiln passage time should be 28 min. — 30 min.

After fie action for the kiln burner long flame on 19 Dec.'97, the passage time is about

32 min ( 13y• the time difference of trend chart of kiln inlet temperature and burning

zone to trip.

Page 36: Kiln Heat-up, Optimun Kiln Operation

it; e n' ; . Tresa atfity aci-1 an C aver-eV evtrYil- hours)

OMMOMO MOMIMMOMMOMM maims=iii

IMMONIMMOMPIPErb' • IMMII

.. - IMPININOMEMIN MOW MO 1111111111413111111111111111MIMMO

111111WZO=.3011•110115IMMEMIr....1•11MO -c. MI

11111111111M11111=1111141•1 wis

II k VA T .,,,,............ .. .... IMIIIII MIMI . - ---+"---. '-c- \--- /---1-----

\AI

----": 1-'-----1 it '

I

/ I N ' I . I / I I

\D II I \ I •

• *---`-' , -

-.',-

670

(vA-FfA ) 80

7 $3

KILN '72

iiK RUE

. i<n_03ugue-i- z 04s -E- -1- TO the /0o/non

QS chaiisect froir►l /8-041 “" a$. ikr)

ed from, 2‘,kre •

- -

I i I ■

) ' i 1 1 x I i

/1

. i u N. mum • m EN • i rd No m NI m INP rammorminommEmmilimmmi

) z 11111101111MINMENNIMILINIM immiumminiamm .iuriaim mmur.

YAIIIIIIIIWAIIIIIIIINIMIIMIIIIIIIMERIINIINIIINRIININEIFAMIIIIIII 1111111•11111111Mmw

I : 1 , ' I 0 • 1 . ammulswalmm e

ammommoimonsi mmum ., .,_ - , /1 , ,. 6 mil airrommempras.- --gmlimomailmomminfflommilmuziiiimiNk 1111111111111MIU111111 MI ‘ 1 IILWAIIIIIIIMNI i4 two

I 11■111M111•111.1.111111 cl) IIIMIIIII IIIIIIIIIIMMESIMINVAIS , MaillIMMINNIMMINE ME

6 10 -

1S/PeC

IS 22 z 6 10 t , -

iv DeC

I 22. - ID 14- IS 22 2 6 10 1 ± 2,0/

ec .zV /Dec

Pressure % , 1 1.--A A N..,-1._ 3-L,, -. ! _ ,,. _ L_ — ().__,._, . t.

Cc) WO H 87o

0 2.80 (°c) 2.71) ~cn fn.& Q ,3 - •

Ter x 2. X

230

1 660 ( ° o) 1 6 q-0 1620 1600

E,c) Abu

15/1-0

U:./(7) 1.24- d— I .3

LA 1.3 3

X X 1.3

- 1.2

41 M

KILN -r1.7

c'f) Coal rtc

Page 37: Kiln Heat-up, Optimun Kiln Operation

In casc of the present low heat load ( about 3,9 x 10 6 kcal/m2 h ), clinker quality ( Free-

Ca0 ) is not stable

C5 C/c2on(,

1 -S ki,Qr 4.4 Imo/ iS

(/.50 °G, Coal ir9 occuir'S

“12 1- 0 /4C ckoo( MC o(utrt.

inKet h000t iS qs-O °c

iC OnRif tAiS cU-e4.

4. Kiln heat load, Coating length and kiln inlet hood temperature

Kiln heat load

( kcal/ in2 h)

Coating length

( m )

Temperature of kiln

inlet hood ( °C )

4.2x 106 17 — 18 .950

5.0 x 106 22 1050

5.5 x 106 25 1150

Around 4.2 4.7 x 10 6 kcal/m2 h is a recommendable range of kiln heat load for CHC

kiln.

5. Kiln bi.irning 'zone temperature and kiln power

( Page 4/6 of the report " Report concerning daliaged grate plates" )

73X ( kArtitil

20rie teiT )

1c16*t livv"vw%

In case that 113Z increase and kiln power decrease ( as above mentioned trend ), it

means that the liquid phase of clinker is increasing. This case is a very dangerous

situation for ttrate plates, because it is easy to be damaged by incerased liquid phase,

In such case, operator must open the damper of cooler 1st chamber fan more for

preventing grate damage.

35

Page 38: Kiln Heat-up, Optimun Kiln Operation

If the damper can not be opened more, kiln buring zone temperature should be

decreased.

Operator must consider such cases as emergency case, i.e. grate plates might be easily

damaged.

For decreasing kiln buring zone temperature following action shall be taken

- Decrease of kiln fuel

- Open of kiln primary air fan damper to make flame longer

6. Difference of clinker bed thickness between 1st and 2nd stage grate ( Page 5/6 of the

report " Report concerning damaged grate plates " )

The present difference of the pressure between 4th chamber and 5th chamber ( 1st

stage and 2nd stage of grate ) is 150 — 200mm H 2 O ( = 15 — 20mbar )

It seems that the thickness of 2nd stage grate is much thinner than 1st stage grate.

In this case, red river can easily flush from 1st stage to 2nd stage of grate, then grate damage occurs.

The thiekticsS of clinker bed of 2nd stage grate should be same as 1st stage, or thicker than 2nd stage.

This is a very important matter for cooler operation.

The suitable pressure difference of 4th chamber and 5th chamber can be considered as about 70mm 14,0 ( = 7mbar ). However, the situation of clinker bed should be well obsertkd.

7. Kiln torque vs kiln burning zone temperature.

( The graph in page 2/12 of " Report concerning damaged grate plates" )

The operation target is kiln torque 75 and burning zone temperature 1500 — 1550 °C.

8. Red river in case of too long burning time

Red river occur at the following 2 cases

- Too high temperature of kiln burning zone ( it is the case of CHC )

- Too long burning time

3t

Page 39: Kiln Heat-up, Optimun Kiln Operation

Temp.

1450°C

1250°C

37

KjIii length (m)

The largeo(eause smaller A lite size ( large size clinker) :

The smallo(cause larger A lite size ( Dusty clinker ) then, red river easily occurs. ( But,

this case of red river is not CI-IC case. ) ; 4. 2

9. Countermeasure for the damage of castable at SC ( Swirl calciner) of RSP

In case of the tertiary air volume F I is less than F2, castable damage easily occurs.

Therefore, it is important to make tertiary air flow Fl and F2 equal flow rate. ( It can be

achie'ed by installing pressure gauge and making both pressure equal. )

Ak'fi2v4A,

0.3D (A 0

F2

11 if F1< F 2

roo----t- of- cas fade

ctamleot,

Page 40: Kiln Heat-up, Optimun Kiln Operation

C07.1 C'R - — - I

flfl

• • 2 o--DeC

'SYSTEM : i:UNC MENU 20/1)EG/1997 11:33

- 2 --, 24314 2 4 I 8 24:01

I -52,,;.! 5

- -

=3,4

- , — _

-!-!! A!'

-J3 2'''''')2 !CCj3::

221 2'001 ,.:4;; col 2-713"14 7

r'S). 5, 22132 25EQ!..61

1570 kt;+ • ! CT' 0 M i I

=LEL ::.11-41:77' cr°

22CA1l 1

2 244 ;:S73 1-- 422.93 P-C-1-*=L

OIL T"■K

- 14C-.'

24TF 1H-. 1.!, 21.2,, 4 . 4 -

"P'37 F.T/37: 1

PECK

2.1.;.'2,2 -6-5- 11^

r I id.

CC!■ •■17-49... 1 JUD 2'

• I &RO...° ■

C 4 .

I CS

-1 7

! COOL 171-! ! IL KL/1-1!

0C3 10- ! a

a 0

PP•cl-EAsTER

I 24,KL1 I I\..

54

7

1::: .1.3 .i !. . 1 1 r- !P- ...s!. ! 1:7 .-. /U 1: r— - E. - _ie./ r----- ■

- . ■ : 71 12:2.2 C :!4.21!-..:- = . ..).; . :is,. .r,

6:_...- _I .,.. 1..! ,._... i . .:(_ :-, I R CA-. .... .. A rt. c! C --lk

141_1 .1 .12 i -..' :!ITT.777 4 7 . - 7.; .:, 7-77, -,._.-4.!.a.

41. ... .:.:: .' "

1 ..1E2S 14162 ! :a 2‹.: 24767 30, '''' • :s 1 7. ! . .._

71:

26S-31

Page 41: Kiln Heat-up, Optimun Kiln Operation

2

SYSTEM HEAVY LIGET L FUNC MENU 20/DEC/1997 11:31

- - r ! -KILN - 7̀:.T V = u.nTr'.P _ D7:1? _ 7-"__. L. - . / 05 1 ,.;;L— - - ,-,,,- ■ , ,,-, .

113/ 430 TAG- NAME 1 KIND i VALUE 1 UNIT 1 MINIMUM j MAXIMUM I

TEMP Dv C CS--CY .-. OLITLE 7

! 3 1 KL1; AC1'; END GAS TF!.'P. D'.1 I 4 12:;41F1 KILN N T--.7--11) I \if-,' r D ' 77 PV 15 1 .:i C,ii,,1 T3 R. !

260,51 -L/h A

8311' r: 946I .

'713° CC)' On I

:;-

2 I KU N BURNING ZONE TEMP. Dtii

1520 : iC„ 1 9/Z))

F' i KT_ ■ N sPEED Dv 2.531rpm 18 1FLANL T:--- 74J-'. H'2,.',::;111 1 P, 6,50 I-stf, ------/3c,.=, •74,'" 3. - 1 '7'm

543 I 2,:rd-1 !c,

--------------- ----------

•-•• ,••■•■•

''..

,

,

1

. • .,-..t.,,

. . ' ' i M410.1 Y r • • ,

' r

,s, Syr' V 41•4 1,.. '‘..1 : sAt.../ .‘" 4 \ •It.t ,.... ,.‘ 1./..,,,,,I .1 ji .\i'l: ‘k71'--'-"-‘„ I

.. rtt

,mi i-rp7.97,4,$,T1,41 ,.... 4 4,7' ,4rirer:77. t 7.A.77A '±.2:*:'.7. 7 ` 'f'-' ' : *31'.; '.: '' ''.1"' 47/ '';‘?•±I.15.' 1 \ •Ali cif,. 0,,,..46 Al.‘e;,n ifiP1 Ir. 4,: 4 '4., ..et -,,,1„,ii ii3OkA, ,t 94141° "l kl illAii -ri‘PiklAi f . I.I.

..' I I Tt P n. '

I

, -7 ,,- , . 't f 4 r • all t 7...1 :7 l. d ' . ,1

(1) ----..." ..N., A • . -. , ..3: ,,,,,. "An' ••• -•••••• L'It . r f Vt44 ILA ll .4 ,1,11? 'ILI 4 :4' 1 I . a •

I I • , I it

•,--t-c_t !I ! ", fr.m,f:...... --, :t , ....‘s I ' V .,,' - .75 -,P WYN. If mei ' •.

0. 00 I 91 I

'.) .•,)0 1 500

I% "1

. .

OLY: •

INTERVAL= OM .303

REF TREND

• 1 303 (0 POINT) 114- I I 3

20D1 1 1-127M30S

Page 42: Kiln Heat-up, Optimun Kiln Operation

>031'3 >03-C! >11133-C' >!:33-C!

1 CN317: C31.*.F.J 1 i 61Fi 7..C.T7 1

>Or:HZ)

114:1›t:H 1 M117'2 Y3-100 1,.) 1

• •

1 W1_1.1. 1e1E3-13 )..7.01ZT a?gt:',".+1 ki7L.67 v:. p

r. . ■_4; /.7-t!

IC3aL

1l,NNt, 7'•\•N},-4 •Ns L3111.

I

../C,Z111.

66 41)(1 11. aDqu

81

it.

1 7.-p.-1771.1

I.:9-ff:

7. 116 .1; 7 - 1.Z. 9 1 1.0

I

t-,

MO .C!

S-i!N3i7Z l

•■•,-,!. 170, 7 1 169 oo: (!-, 1SZ.... 1.1.:!3v6 1=11°0 10

77 L7

2-017?

2:3177.1

I_ 1 /

'1r 0 Sr

-.)0 1 61.11.7' C 1 VT..1 1.

N11.4';6 691_ 1;11!_9 7?)..!: N1Mv 61

0338:1

1 f 1 0E . . 7/.1. 7Fr

1n14717':

6 119C- r_!!--_,-,...7!

7 •-•

1, 1 6

1-415- 1-11;v1

! ;1

It! ;71 1 17, 1: ft -

czN,z VIN ZLN,,,,t: I

4toti

d -

DS9 169

: •:!!,

Sr

\!^, !pc: E1T±UOJO •O

• • pc 8-1411,_

6t1_1111 t 17 11 1.1 1 -P- 1811

a1.1.1-_, 10). 1-=. _

15-'0-115 1 - - - - - -

z -

Q Z