jeevan nagar co-operative housing society ltdjeevannagar.com/pdf/circular final draft...
TRANSCRIPT
Jeevan Nagar Co-operative Housing Society Ltd.(REG.NO.BOM/HSG/812 OF 1964)
BLOCK NO.C-1/4, MITHAGAR ROAD,MULUND (E),MUMBAI 81. Ph. 25637463
Date: 11.06.2009
To,
All the members
Subject: Proposed Re-development of Land & Property of Jeevan Nagar CHS ltd.
It is nearly four months since the special general body meeting held on 01/02/2009,
gave its unanimous mandate to the managing committee to proceed ahead with the Re-
development scheme. Since then, the managing committee is continuously making
efforts to overcome the hurdles which were time consuming and required lot of detailed
work for the process of Re-development scheme. The managing committee is pleased
to give here below the steps taken so far in implementation of the scheme.
LETTER OF INTENT:-
Pursuant to the decision taken by the special general body meeting held on 1st Feb.
2009 to appoint M/s. Matoshree Infrastructure Pvt. Ltd. as the Developers for our Re-
development project, a letter of intent dated. 03/02/2009 was issued to them. The
Developers have given their confirmation vide their letter dated 05/02/2009.
OPTION FORMS:-
The option forms for the selection of a new flat area desired, from six categories was
distributed to the members. All the members have diligently responded within the
stipulated time. A few members had made some suggestions/request. Having regard to
these suggestions the Managing Committee had discussions with the Developers. We
are pleased to inform the members that most of the suggestions are being incorporated
in the layout and building plans by the Developers. The Developers have agreed to add
two more categories of flats of 600 sq. ft. (2 BHK) and 800 sq. ft. (3BHK) in their plans
for choice of members. Any member who desires to opt for 600 sq. ft. (2BHK) OR 800
sq. ft. (3BHK) flat, should submit his/her revised option in prescribed option form
available in the office, and return it duly completed to the society office not latter than
21 st June 2009, within office time i.e. 10 AM to 06.00 PM and Sunday 11.00 AM to 01.00
PM from.
This will be final opportunity for selection of new flat area. The members who do not want to revise there options submitted earlier are not required to submit any option for now since their earlier option stands.
1
CONVERSION OF BIG FLATS INTO TWO FLATS :-
Some of the members had requested to examine the feasibility of their entitled area to
be converted into TWO FLATS. We have requested the Developers to make this
feasible for the existing members only. Any member can divide his/her entitled area into TWO FLATS subject to the following conditions.
1) That if the total area of two flats exceeds the entitled area the concerned member
shall have to pay for the additional carpet area at the rate of Rs.8000/- per sq. ft.
of carpet area.
2) The 50% (half) of the total additional projection area of two flats (like flower beds)
will be charged at the rate of Rs.8000/- per sq. ft. for the additional projection
area.
3) The additional cost of one no. kitchen including plumbing, electrical fittings and
additional main door and miscellaneous items will be Rs.1,75,000/- on fixed
basis.
4) The cost of stamp duty, adjudication, and registration and out of pocket expenses
for the second agreement for the additional flat will be borne by the concerned
member.
5) The member concerned shall not be entitled to additional membership. That is
TWO FLATS would remain in the name of the same member by holding the
same share certificate.
6) The members who want to revise their option for TWO FLATS are requested to
submit an application within stipulated time which will be displayed on the notice
board.
OPTION ABOUT SOCIETY’S OFFICE PREMISES:-
The Managing Committee has decided to opt for an entitled area of 540 sq. ft. for the
existing office area of 360 Sq.Fts. This would be in addition to the office premises to be
provided free of charge by the Developers. The Managing Committee shall endeavor to
make the best use of 540 sq. ft. + office area (free of charge). in the best interest of the
members. (after approval from General Body)
ALLOTMENT OF NEW FLATS :-
Having regard to methods of allotment of flats as given in the bye-law no.76 (a) the
Managing Committee has in its meeting held on 16.03.2009 unanimously decided to
recommended the method of seniority of existing members based on the members
register maintained by the society. Accordingly new flats will be allotted in the proposed
2
towers on the basis of the dates of admission of the members. The list of seniority as
per the record of the society will be notified on the notice board and also will be kept in
the Society office for perusal and information of the members in due course..
The detailed scheme of the allotment procedure/rules will be placed before the General
Body for its approval.
TAXATION :-
The members have been raising queries about capital gains vis-à-vis taxation. The
taxation aspect varies from individual to individual depending upon income, sources of
income and standard deductions allowed under Income Tax rules. The Managing
Committee has decided to arrange for a workshop on taxation matter. The date, time
and place for workshop for taxation will be intimated to the members sufficiently in
advance.
Resignation of Mr. Abhijit A. Sawant (C-1/9) from the Sub-committee:
Mr. Abhijit A. Sawant has resigned as a member of the sub-committee on 16/03/2009
and the Managing Committee has accepted his resignation at its meeting held on
25/05/2009.
The Managing Committee has appointed Mr. Sanjay Nawani (B-7/8) (Associate
Members) as a member of the sub committee in place of Mr. Abhijit A. Sawant at its
meeting held on 06/06/2009, Shri. Sanjay Nawani is a qualified Civil Engineer (B.E.)
and also has successfully completed course of construction management programming.
APPOINTMENT OF PROFFESSIONALS:-
The special general body in its meeting held on 1st Feb.2009 had unanimously
authorized the managing committee to appoint professionals i.e. Advocates, Architects,
Tax Consultant for the proposed Re-development and fix their remunerations in the best
interest of the members, in terms of the resolution no.5. Initially, the Managing
Committee received four proposals/quotations each for Advocates and Architects. The
Managing Committee made a fresh attempt to adhere to procedure and called for the
proposals/ quotations giving the scope of work and stipulating the final date of
submission to the following Advocates and Architects.
3
ARCHITECTS ADVOCATESM/s. Niwate & Asso.. M/s. Seelan & Associates.
Ar. Shri Vijay Turbadkar . Shri Rajeshwar M. Deshmukh.
M/s. Popat Narkhede & Asso. Shri Ajit Karandikar.
M/s. Sapre & Associates. Smt. Rekha Pendharkar & Asso.
M/s. Architectural Associates Miss. Komal Kandhaarkar
Ar. Shri Datta V.Damle
M/s. Harish Gawankar & Asso.
The Managing Committee received sealed quotations within the stipulated final date
from four Architects i.e. Sapre & Asso., M/s. Architectural Asso., Shri Datta V. Damle
and Harish Gawankar & Asso, and from four Advocates i.e. M/s. Seelan & Asso., M/s.
Karandikar & Vaidya Asso., Smt. Rekha Pendarkar & Asso. and M/s. Komal
Kandhaarkar.
The Managing Committee handed over all the quotations to the Sub- committee (Re-
dev.) for evaluation and ranking. The Sub-committee (Re-dev.) analyzed all the
quotations and had personal discussions with all the four Architects and four Advocates.
The Sub-committee (Re-dev.) submitted the detailed report dated 23rd May 2009 to the
Managing Committee giving evaluation and ranking to all the above four Architects and
four Advocates.
The Managing Committee in its meeting held on 25th May 2009 unanimously approved
the report dated 23rd May 2009 submitted by the Sub- committee (Re-dev.). The
Managing Committee selected the professionals who ranked no.1 as Architects and
no.1 as Advocate which are as follows.
ARCHITECTS:- M/s. Architectural Associates- Estd.1942
Name of the Associates.
1) Ar. Anand Pandit. (B.Arch),
2) Ar. Devendu Sawant (B.Arch.),
3) Ar. Dushyant Desai (B.Arch),
4) Ar. Abhijit Sawant (B.Arch)
It is a partnership firm and Shri A.M.Pandit is the Sr. Architect of M/s. Architectural
Associates, which is having four Architects as partners, three Architects are full time
employees, and in addition, two site Architects and two supervisors. M/s.
4
Architectural Associates has given a list of 29 projects of different types along with
their quotations. It is observed that they have carried out Re-dev. Projects for
housing societies also. They have quoted their fees at 1% of the cost of construction
negotiated to not exceeding Rs.90,00,000/- including fees for structural, electrical,
plumbing and sanitary consultancies. They have assumed the cost of projects at Rs.
100 crores. They have also given their schedule of payments to be made at different
stages. In addition, they have insisted to have site office for them so that they can
keep constant supervision during the progress of work. They agreed to co-ordinate
with Ms. Komal Kandhaarkar, Adv. for preparation of Re-dev. Agreement, Power of
Attorney, Tri-partite agreements and other documents. The Managing Committee
found that M/s. Architectural Associates have adequate professional experience to
supervise the Re-dev. Project of our society. The Managing Committee also
observed that their fees include structural, electrical, plumbing and sanitary
consultancies. Therefore the entire package at 1% of construction cost not
exceeding Rs.90,00,000/- will be more beneficial to the society, and will be in the
best interest of all the members of the society. Looking to their experience, their
perceptions and their suggestions during our personal discussions as well as the
quantum of fees, the Managing Committee came to the unanimous decision that
M/s. Architectural associates are very much suitable for our Re-development
Project.
Advocate/Solicitor:-
Miss Komal Kandhaarkar- Advocate & Solicitor
Name of the firm -“The Law House”
Qualifications- LL.B, LL.M, Solicitor (England & Wales)
Name of the Associates- Advocate V.S.Khurana.
Advocate Miss. Komal Kandhaarkar explained that she has specialization in property
matters and she is currently working as Legal Advisor for housing societies. She
said that necessary approval could be obtained from the Dy. Registrar for utilization
of sinking fund by following proper procedure under Maharashtra Co.op. Societies
Act 1960. In case of any disputes between society and developers or between
members and the society or between any third party and the society, she will handle
all such matters and will charge separately depending upon merits of each case.
She suggested obtaining a declaration and Indemnity Bond in favour of the society
from the members who have raised housing loans against their flats. She is of the
opinion that the society’s representatives can participate in the joint meetings to be
held with the Advocates of the Developers. She has quoted her total fees Rs.3.25
lakhs. She has clarified that it is necessary to have the opinion and comments from
the Architects on all the plans and important drawings before finalizations of the Re-
5
dev. Agreement. She has clarified that she will be available to the society for
consultations/discussions and even for important meetings of the general body. The
managing committee came to the unanimous decision that Advocate Miss. Komal
Khandaarkar is capable, knowledgeable and most efficient amongst all the four
Advocates. She has also handled arbitration cases and is found suitable as
Advocate for our Re-development Project.
PAYMENT OF PROFFESSIONAL FEES:
Thus, it is to be noted that we have to pay professional fees about Rs. One Core
(including relevant taxes) within a period of four to five years. The Managing
Committee has studied the financial condition of the society and we are glad to
mention that society can pay the professional fees as per schedule given by them
without putting additional financial burden on members; in the event of our Society
having to pay any litigation fee or such other expenses in future, we will have to raise
additional fund.
PLANNING OF BUILDINGS:-The developers M/s. Matoshree Infrastructure Pvt. Ltd. have shown PowerPoint
presentation to the managing committee members about re development of our
society. The managing committee along with subcommittee attended the
presentation on 2nd June 2009. The developer along with their architect explained us
their concept and vision about our re-development. The developer has also
incorporated our major suggestions in new planning.
It is to be noted that a draft building layout plan for your suggestion is displayed in
societies office from Dt:11/06/2009 and final building plan, lay out plan with detailing
and incorporating all amenities and municipal submission plan with detail FSI & area
calculation will be put up to the members in AGM. / Sp. GM for approval.
The developer has submitted the building layout plan comprising of three wings
containing four flats of different typologies.
The managing committee has requested the appointed architects M/s. Architectural
Associates to give overall comments to that effect.
The members are requested to go through the plans displayed in the office.
6
Development Agreement & other related documents:
The development agreement, power of attorney and other related legal documents
are expected soon from the M/s. Matoshree Infrastructure Pvt. Ltd. which will be
checked and approved by our appointed professionals. All the draft documents will
be available for the members for giving their final comments (by giving sufficient
time) before placing them before the General Body for its approval.
The office bearers of the society will be available for the discussion/queries in the above matter from 12/06/2009 from to 21/06/2009 08.30 PM to 09.30 PM on working days and 11.00 AM to 01.00 PM on Sundays.
Your co-operation will be highly appreciated.
Hon. Secretary
Annexure:a) Comparative statement of advocates/solicitor.
b) Comparative statement of architects.
7