it asset reassignment / moves david levine information technology ikon network center
TRANSCRIPT
IT Asset Reassignment / Moves
David LevineInformation TechnologyIKON Network Center
2
Background – Current Process & Facts
Over 7900 major assets were due back to Compaq Financial between October 2002 and July 2003, of the 7900 assets over 3000 were never located or returned.
Until late 2002 a company wide physical inventory of IT assets had never been conducted.
Current National Help Desk (NHD) IT Asset Relocation web form, introduced in 2002 is being utilized less than 27% of the time.
Current NHD Move Employee web form does not track IKON Bar Code asset ids, Employee IDs (EID) or asset serial numbers.
The NHD desk currently tracks 12,000+ add, move or change tickets and 3,700+ hardware repair tickets annually.
Beginning January 2004 a significant amount of Dell equipment will be due to Dell Financial Services.
3
Project Definition
Problem Statement:
The process of tracking IKON's personal computing assets, which includes laptops, desktops and servers, does not allow us to accurately locate these assets when they need to be returned to the lessor. During the last three rounds of lease returns IKON was unable to locate 3,000 assets representing a write-off amount of $1.2mm. Without improving processes in this area IKON will perpetually write-off residual lease amounts for assets that IKON may actually be in possession of but can not locate. Over a 48 month period we estimate this expense, which has a direct impact on OI, will reach $3.5mm. This estimate is based on prior history and a review of future lease renewals.
4
Project Definition, Cont’d
Project Definition:
Implement controls that allow IKON to capture or validate location information as assets are touched by IT. Assets are physically touched by a member of IT as people are moved between offices or as assets are reassigned due to employee turn over. In addition to IT physical touching the assets this process can be augmented by performing data collection at the Help Desk. As users call into the Help Desk for assistance we have an opportunity to validate asset information with minimal effort. It is expected that the new controls will be in place within four months of starting this project.
5
Project Definition, Cont’d
Project Benefits:This project will not fully eliminate the write-off amounts but is expected to address 70% of them. This represents $2.45mm over the next 48 months. The $2.45mm can be easily measured and will be visible as an improvement to OI.
15% of the write-off amounts can be corrected through serialization issues with the lessors. (This will be a separate project, not part of this charter.) The remaining 15% is reserved for loss due to theft, etc.
6
Project Definition, Cont’d
Financial Benefits: Net Project Benefits: Year 1 = $575,000 and Year 2 = $650,000
Project Metric “Y”: Big Y = Asset Tracking 2nd Level Y = Asset Control 3rd Level Y = Asset Moves & Reassignment
Defect Definition: Each leased IT asset that is not found and returned to the
lessor leads to a write-off expense. The success of this project can be quantified by measuring the reduction in the raw number of units not returned.
Leveragability: Possible reduction in the number of physical IT inventories.
(Soft dollar benefit only through staff prioritization)
7
Additional Financial Information
Total Value of equipment on lease with Dell and IBM through 1-01-06 = $28,805,294.88
Monthly lease payments to Dell & IBM = $861,683.90 Total Laptops & Desktops Due = 15,386 Total Servers Due = 341 90% (14,163 items) of the equipment is due between 5-1-04
and 12-31-05 (20 Month Period) Average items due per month (14163/20) = 708 Average monthly lease cost per item = $61 Average monthly exposure for equipment returned outside of 5
days within the 20 month period (708x61) = $43,188 or $518,256.00 a year
8
Project Team
Champion – Tracey Rothenberger Process Owner – Mac McGraw Black Belt – David Levine Financial Analyst – Carol Uhlig Team Members:
Process Personnel – Rick Faber Process Personnel – Chris Fauth Process Personnel – Danny Goode Process Personnel (GHD) – Bob Burchell
Master Black Belt – Dan Douglas
9
Other Contributing Factors
Other factors contributing to low lease returns Stolen Equipment Equipment damaged beyond repair
10
Other Contributing Factors Cont’d
Serial numbers not matching lease schedules Technical issues with the bar code system Inconsistent use of the bar code system
Other General Lease Return Issues resulting in higher processing costs IKON owned equipment was shipped to the lease-end processing
company Equipment on leases with other lessors was shipped to the lease-end
processing company Equipment was miss-shipped to the lease end processing company
12
CT Flow Down
Critical to Satisfaction (CTS)
IT Asset Disposition within 5 days of the lease termination date.
Critical toQuality (CTQ)
Critical toDelivery (CTD)
Critical to Cost(CTC)
All lease itemsreturned or
accounted for
Accurate leaseschedules
No "miss-ships"
No serial numberissues
Accurate Bar Code(Asset Tracking)
Database
All data "cleaned"to DOD level 3Specifications
Replacementasset at the end
user prior toremoval of the "off
lease" asset
Final dispositionrecorded in theasset tracking
database
Timely employeenotification
Accurate leaseschedules
Timely equipmentreplacement
Accurate shippingand receiving
reports
Equipmentreturned On-Time
No damagedequipment
No "miss-ships"
No special operations/rework to account for
assets (i.e.. Census of allassets that have beenconducted in the past
13
Performance Standards
Y= IT Asset disposition within 0 - 5 days of lease end Tolerance Range is 0-5 days after lease end date and 30
days prior to lease end date. Any asset returned after 5 days triggers additional rental
charges to be billed to IKON Any asset returned more than 30 days prior to lease
termination results in an overlap of lease payments. The internal tolerance and acceptable customer range in this
case is equal. The total number of assets returned as a percentage will
also be measured.
14
End State Disposition Process Time
Disposition Process should take no longer then 31 Days 1 Day to locate equipment 17 Days to order and replace equipment
2 Request to Approve 10 Days from Order to Receive 5 Days from Receive to Install
6 Days to ship equipment to 3rd Party lease-end processor 2 Days required for 3rd Party lease-end process 5 Days to ship equipment to Dell via non-dedicated freightCalculation is based on fixed data
Locate EquipmentReplace
Equipment
Ship to 3rd PartyLease-endProcessor
Lease EndProcessing
Ship to DellDell Receives
Equipment
1 Day 17 Days 6 Days 2 Days 5 Days 0-5 Days
15
Current Process Capability for Returning Equipment On-time
3002001000-100-200
USLLSL
Process Capability Analysis for Days Late
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
Ppk
Z.LSL
Z.USL
Z.Bench
Cpm
Cpk
Z.LSL
Z.USL
Z.Bench
StDev (Overall)
StDev (Within)
Sample N
Mean
LSL
Target
USL
973741.45
730809.07
242932.37
999999.85
999999.84
0.00
973462.25
673318.25
300144.00
-0.21
0.70
-0.62
-1.94
*
-1.70
5.79
-5.11
-5.12
61.2451
7.3691
4861
37.6818
-5.0000
*
0.0000
Exp. "Overall" PerformanceExp. "Within" PerformanceObserved PerformanceOverall Capability
Potential (Within) Capability
Process Data
Within
Overall
USL = 0 DaysLSL = -5 DaysZ Bench = -1.94Mean = 37.7 DaysDPMO = 973,741
Based on the Compaq Lease Return Data
16
High Level Process Map
Lease EquipmentPrepare and
Deploy EquipmentEquipment In Use Replacement
StrategyDisposition
Cycle time = 24 - 36 Months
Track Asset
17
Process Map Order to Deploy
RIPP checks forexisting inventory
RIPP assigns oneticket to CISP andone to Break-Fix
Request forHardware\
Software is madevia GHD
GHD creates 1 ParentRemedy ticket and 2
Child tickts and assignsthem to appropriate RIPP
RIPP obtainsapproval from
Reg. IT managers,MP DFO and Reg.
DFO
RIPP obtainsapproval from
Reg. IT managers,MP DFO and Reg.
DFO
RIPP assigns oneticket to Break-Fix
for deployment
Equipment isdeployed and
tickets are closed
CISP obtainsrequired approvals
CISP placesorder(s) and
updates all tickets
Product isrecieved at IKONat config centersand is scanned
Packing Slip isfaxed to CISP
CISP ticket isClosed
Equipment isdeployed to end
user
Break-Fix ticket isclosed
No
Yes
Request to Ordermin = 0 Daysmax = 105 DaysAverage = 15.8 Days
Order to Deliverymin = 3 Daysmax = 36 DaysAverage = 8.6 Days
Deliver to Installmin = 1 Daysmax = 55 DaysAverage = 20.9 Days
Request to Installmin = 4 Daysmax = 196 DaysAverage = 45 Days
18
Request to Install Process Capability
-20 0 20 40 60 80 100 120 140
LSL USL
Process Capability Analysis for R to I
USL
Target
LSL
Mean
Sample N
StDev (Within)
StDev (Ov erall)
Z.Bench
Z.USL
Z.LSL
Cpk
Cpm
Z.Bench
Z.USL
Z.LSL
Ppk
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
PPM < LSL
PPM > USL
PPM Total
17.0000
*
0.0000
45.4167
48
18.5416
23.0251
-1.59
-1.53
2.45
-0.51
*
-1.38
-1.23
1.97
-0.41
0.00
895833.33
895833.33
7153.72
937311.80
944465.52
24277.18
891428.31
915705.49
Process Data
Potential (Within) Capability
Ov erall Capability Observ ed Perf ormance Exp. "Within" Perf ormance Exp. "Ov erall" Perf ormance
Within
Overall
USL = 17 DaysLSL = 0 DaysZ Bench = -1.38Mean = 45.4 DaysDPMO = 915,705
19
Delivery to Install Process Capability
6040200-20
USLLSL
Process Capability Analysis for Delivery to
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
PPM Total
PPM > USL
PPM < LSL
Ppk
Z.LSL
Z.USL
Z.Bench
Cpm
Cpk
Z.LSL
Z.USL
Z.Bench
StDev (Ov erall)
StDev (Within)
Sample N
Mean
LSL
Target
USL
936886.20
850796.26
86089.94
947493.93
904450.10
43043.82
895833.33
895833.33
0.00
-0.35
1.37
-1.04
-1.53
*
-0.44
1.72
-1.31
-1.62
15.3667
12.2227
48
20.9792
0.0000
*
5.0000
Exp. "Ov erall" Perf ormanceExp. "Within" Perf ormanceObserv ed Perf ormanceOv erall Capability
Potential (Within) Capability
Process Data
Within
Overall
USL = 5 DaysLSL = 0 DaysZ Bench = -1.62Mean = 20.9 DaysDPMO = 936,886
20
High Level Touch Point Map
EmployeeTermination\Resignation
Process
Employee MoveProcess
Equipment isscanned into
Asset Databseand deployed to
User
Equipment lost\Stolen
Process
WarrantyReplacement
Process
Physical InventoryProcess
Has equip. benn lostor stolen?
Has the item beenreplaced under
warranty?
Has the employeeresigned or been
terminated?
Is there a physicalinventory taking
place?
Is the employeemoving locations?
DispositionOffice is closed orsold?
Office Move\Sale\Closing Process
No No No No No
No
Yes Yes Yes Yes Yes
Yes
Asset Informationverified\Updated
when a call isplaced to the GHD
Call Placed to GHD?
Yes
NoLANDesk Scan
Asset is updated in this process
Asset is updated some of the time in this process
Asset is never updated in this process
Process does not exist
LANDeskHardware\
Software Inventory
No
Yes
21
Touch Point Inputs & Outputs
Physical InventoryProcess
Employee MoveProcess
Office Move\Sale\Closing Process
LANDeskHardware\
Software Inventory
Inputs Outputs
Equipmentlease Assumption andAssignment FormsBuyout QuotesUpdated Asset InformatonUpdated Asset Database
EquipmentUpdated Asset InformationUpdated Asset Database
Updated Asset InformationUpdated Asset DatabaseInventory
Asset Information inLANDesk Software Inventory Hardware Inventory
EquipmentLANDesk ClientLANDesk Servers
EquipmentNew OwnersContractInventory ListsHR Forms
EquipmentHelp Desk TicketsHep Desk FormsIT EmployeeHR Forms
EquipmentBar Code LabelsBar Code ScannerEmployee ListLocation ListInventory DataIT Employee
ITFinanceEnd User
Customers
ITHREnd User
ITFinanceEnd UserLegal
ITEnd User
Equipment lost\Stolen
Process
WarrantyReplacement
Process
Asset Informationverified\Updated
when a call isplaced to the GHD
Inputs Outputs
EquipmentEmployeeHelp DeskHR Forms
Verified\Updated AssetInformationVerified Updated AssetDatabase
EquipmentCall into Help DeskEmployee
Defective EquipmentHelp Desk TicketVendor Service CallEmployeePC Technician
New EquipmentNew Serial Number (sometimes)Updated Asset InformationUpdated Asset Database
Police ReportLease Buyout QuotePurchase OrderUpdated Asset ListUpdated Asset DatabaseIKON Incident ReportCheck InventoryHelp Desk Tickets
Customers
SecurityITFinanceEnd User
ITFinanceEnd User
ITEnd User
No Connection to Asset DatabaseThis process does not exist today
EmployeeTermination\Resignation
Process
Updated AssetInformationUpdated Asset Database
NoticeHelp Desk TicketsHelp Desk FormsEquipmentEmployees ManagerHR Forms
ITHREnd User
8/19/20030307-01-001 David Levine
IKON SixSigma
IssueC = ControllableS = SOPN = Noise
Asset is updated in this process
Asset is updated some of the time in this process
Asset is never updated in this process
Process does not exist
Employee NewHire Process
Updated AssetInformationUpdated Asset Database
NoticeHelp Desk TicketsHelp Desk FormsEquipmentEmployees ManagerHR Forms
ITHREnd User
22
Process Map for Inventories
Does item have anIKON Bar Code
Label?
Scan the itemIs the item in
the Database?Is all of the
information correct?
Update theinformation
Add item and allrelevant
informationAdd the label
Did the itemScan correctly?
Replace Bar CodeLabel and send
the old BC numberto Foster
Yes
No
Yes Yes Yes
No No No
Physical Inventorywith Bar Code
Scaner
C EquipmentC Bar Code Labels
C Device with label
C EquipmentC Bar Code Scanner
C Equipment ListC Bar Code ScannerC Bar Code Lables
C New Bar Code Label
C Old Bar Code #
C Updated Asset Information C Updated Asset Information
C Updated User\equipment Information
C Updated User\equipment Information
Go to next asset
10 sec.
20 sec.
30 sec. 5 min. 3 min.
Cycle Time = 20 sec. - 5.5 min.
Key C - Controllable N - Noise S - SOP
Issue
23
Process Map for Disposition
72 Min. - 35 Days
LocateEquipment
Equip.Found
KeepEquipment
ReplaceEquipment
Ship to 3rd PartyShip to lessor\lessor recieves
equipment
Buy OutEquipment
Is Equip.Returnable
No
Yes
Yes
No
No
Yes
C Lease Schedules C Equipment ListC Asset DatabaseC Other Asset RecordsC Vendor Information
C Lease ScheduleS Buyout RequestS Purchase OrderC Serial or Asset Number(s)
S RequestS Help Desk TicketS Existing Equipment
-or-S Purchase OrderS New Equipment
C Equipment to ReturnC Packing SlipC Packing MaterialsC Shipping Labels
Old Equip.Packing Slip
Shipping Report
Invoice
FoundEquipment
EquipmentList
Rework
C Equipment to ReturnC Packing SlipC Packing MaterialsC Shipping Labels
ReconciliationReport
List of equipmentto be returned
Lease scheduleclosed
Key C - Controllable N - Noise S - SOP
Issue
30 Min. - 1 Year +
2 Days for adedicated truck
5 Days for anon-dedicated
truck
Lease EndProcessing
C Equipment
Old Equip.Packing Slip
4 Days - 196 Days 1- 5 Days
24
Lease End Processing Map
Recieve Equipment New Equipment Preperation
Unbox EquipmentRecieve
Equipment intosystem
Fix Issue
Is there a Problemwith reciept?
2 Min. 5 Min.
30 Min.
Cycle Time = 7 min - 47 min
Prep to Ship
Cycle Time = 52 min - 5 Days
Total Cycle Time = 72 min - 35 Days
No
Yes
Is EquipmentDamaged?
Setup EquipmentRun inventory
program & uploadresults to server
Wipe Hard Drive
2 Min. 20 Min.
30 Min.
PasswordIssue?
No
Yes
Resolve Issue
20 Min.PhotographEquipment & Send
Photograph toIKON
10 Min.
Yes
No
Manual Inventory
Boot Issue?
Send Unit toRepair
Does Unit Boot to C:Prompt?
Is repair cost>= FMV?
Repair Equipment
Dispose ofEquipment
5 Min. - 5 Days
No
NoYes
Yes
Swap hard drivewith a known good
hard drive
No
Yes
Clean Equipment
Send to BulkStorage until truck
is ordered
Sort equipmentonto lease pallet
per lease due date
Ship equipment inSystem
Cycle Time = 13 min - 30 Days
7 Minutes
1 Min.1 Min.30 Days
Pack according tolessor quidelines
Send to Lessor
3 Min.
Times are averagesbased on 1 person and1 piece of equipment
Potential Issue
Spreadsheet EntryBox
1 Min.
20 Min.
Does equip. needother repair?
Yes
No
25
Data Collection Plan
Data Description Collection Type Type Collection Plan Status
Days + or - the lease end date that equipment is received by the lessor
On-Going Continuous – Time in Days Setup standard reports with Dell Complete
Return Status On-Going Discrete- Classification Setup standard internal reports Not Started
Returned
Bought-out - Missing
Bought-out – Stolen
Bought-out – Damaged
Bought-out - Retained
Cycle time from request to order One -Time Historical Continuous - Time in Days Systematic Random (every 40th ticket from the last 6 Months)
Complete
Cycle time from order to delivery One -Time Historical Continuous - Time in Days Systematic Random (every 40th ticket from the last 6 Months)
Complete
Cycle time from delivery to installation One -Time Historical Continuous - Time in Days Systematic Random (every 40th ticket from the last 6 Months)
Complete
Cycle time while at 3rd Party Lease End Processor
One -Time Historical Continuous - Time in Days Systematic Random (every 40th ticket from the last 6 Months)
Complete
26
Data Collection Plan Continued
Data Description Collection Type Type Collection PlanStatus
Number or Desktops, Laptops and Servers on lease with Dell and their Lease End Dates.
One -Time Historical Discrete – Count and Month All Dell Lease Schedules up to 1/1/2006 Complete
Number or Desktops, Laptops and Servers on lease with IBM and their Lease End Dates.
One -Time Historical Discrete – Count and Month All IBM Lease Schedules up to 6/30/05 Complete
Number of Moves, Add Changes One -Time Historical Discrete – Count GHD Report for the last the past quarter with annual estimates
Complete
Final Disposition Report for Compaq Lease Schedules
One -Time Historical Discrete – Returned\Not Returned Request Report from CFS-HPFS WIP
Final Disposition Report for Compaq Lease Schedules
One -Time Historical Continuous – Days early or late Request Report from CFS-HPFS Complete
Cycle time from 3rd Party Lease End Processor to Lessor
One -Time Historical Continuous - Time in Days Request data from Dendrite Complete
Cycle time from IKON to 3rd Party Lease End Processor
One -Time Historical Continuous - Time in Days Request from Regional IT managers Complete
27
Project DMAIC Checklist/Status
Problem Statement:
Black Belt: David Levine CTS’s: _______________________________________________________
Project Champion: Tracey Rothenberger Defects to be Reduced: Units not returned to lessor on time or at all
Deployment Champion: Andrew Twadelle Beginning DPMO/Sigma Level: 973741.45
Master Black Belt: Dan Douglas Final DPMO/Sigma Level: ________________________________________
Six Sigma Project DMAIC Checklist
Project : IT Asset Reassignment / Moves
Define Measure Analyze Improve Control
Completion Date: Completion Date: Completion Date: Completion Date:
Discover Variable Relationships
Establish Current Performance
Establish Performance Objective
ID Alternative Solutions
Determine “Best Fit” Solution
Establish Process Tolerances
Update FMEA
Develop Pilot Plan
Pilot “Best Fit” Solution
Validate Improved Performance
Conduct Cost/Benefit Analysis
Complete Improve Phase Project Review
Redefine Process Capability
Develop Control Plan
Develop Mitigation Plan
Implement Process Controls
Develop Monitoring Plan
Implement Process Control Plan
Obtain Financial Validation
Completion Date:
Define Project Scope
Initiate Team (Kick-off)
ID Process Customers
ID Process CTS’s
ID Process Metrics (Y’s)
Complete SIPOC Map
Complete Define PhaseProject Review
Receive Approval to Move to theMeasure Phase
Receive Approval to Move to theControl Phase
Confirm Baseline Capability
Identify Sources of Variation
Complete Detailed Process Map
Complete C&E Diagram & Matrix
Complete FMEA
Perform Data Collection for Analysis
Screen Potential Causes
Conduct Graphical Analysis-
Conduct Hypothesis Testing
Complete Root Cause Analysis
Receive Approval to Move to theAnalyze Phase
Develop Data Collection & Sampling Plan
Identify Potential X’s
Validate Measurement System
Collect Data on Y’s
Perform Capability Analysis
Voice of Process/Benchmark
Define Performance Objectives
Complete Measure Phase Project Review
Receive Approval to Move to theAnalyze Phase
Receive Approval to Close the Project
Complete Control Phase Project Review
Obtain Financial Analyst Sign Off
Obtain MBB Sign Off
Obtain Project Champion Sign Off
Obtain Steering Committee Sign OffComplete Analyze Phase Project Review
Leverage Project within Organization
August 19,2003