USGC Gulfstream Program 700_GS_509_12 The Dow Chemical Company Page 1 of 94 Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL Scope 1.1 This procedure covers the general safety requirements for the setup and operation of equipment and instrumentation necessary to perform a pneumatic test on newly constructed, completely isolated piping systems in close proximity to operating systems – no connection to process or utility systems in Construction OSBL Areas. Vessels, process equipment, instruments and relief devices are not included in the scope of the Pneumatic Test. This Procedure follows under the Gulfstream EH&S variance. 1.2 This procedure is to be used in conjunction with G4D-6422-01 [Guidelines for the Application of Pneumatic Testing], G4S-6422-01 [Class D – Sensitive Leak Test – Gas and Bubble Method], G4S-6422-02 [Class DH – Pneumatic Testing – Greater Than 1 Bar (15 PSIG)], G4Q-6422-02 [Pneumatic Testing – Safe Work Procedure Checklist]. NOTE: Contractor specific practices must be evaluated for agreement with Dow Pneumatic Testing practices and where differences are identified, agreement between the contractor and Dow Engineering practices must be established. This procedure must be attached and completed as part of the contractor’s specific requirements and documentation for the overall pneumatic testing process. L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental DOW CONFIDENTIAL – Do not share without permission

Upload: tranlien

Post on 17-Mar-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 1 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL

Scope 1.1 This procedure covers the general safety requirements for the setup and operation of equipment and instrumentation necessary to perform a pneumatic test on newly constructed, completely isolated piping systems in close proximity to operating systems – no connection to process or utility systems in Construction OSBL Areas. Vessels, process equipment, instruments and relief devices are not included in the scope of the Pneumatic Test.

This Procedure follows under the Gulfstream EH&S variance.1.2 This procedure is to be used in conjunction with G4D-6422-01 [Guidelines for

the Application of Pneumatic Testing], G4S-6422-01 [Class D – Sensitive Leak Test – Gas and Bubble Method], G4S-6422-02 [Class DH – Pneumatic Testing – Greater Than 1 Bar (15 PSIG)], G4Q-6422-02 [Pneumatic Testing – Safe Work Procedure Checklist].NOTE: Contractor specific practices must be evaluated for agreement with Dow Pneumatic Testing practices and where differences are identified, agreement between the contractor and Dow Engineering practices must be established.

This procedure must be attached and completed as part of the contractor’s specific requirements and documentation for the overall pneumatic testing process.

L&EOs covered by this procedure

This procedure is used for the following LEO tasks:

Opening vent and drains Line breaks on analyzers & instruments (e.g. blowing leads) Removing/replacing of caps, plugs, blind flanges, and pressure gauges, Removing/replacing safety valves. Removing/replacing small bore piping or tubing Changing gaskets Connecting Hydro Testing equipment to piping systems Slip blind installation/removal

Categories and attributes

Categories

Critical Emergency Operating Other

Attributes

Routine Non-routine

Equipment Status The status of equipment covered under this LEO procedure is:

In Service Cleared Isolated New & Isolated

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 2: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 2 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Additional Hazard Analysis

Based on a review of section 4.2 of the Global L&EO Standard, the additional Hazard Analysis is NOT required for this procedure. No combustible, flammable, toxic, water reactive or unstable materials have being contained or will be introduced into the piping system that is being Pneumatically tested – new construction, new piping systems.

Hazards and precautions

The table below lists job hazards and the precautions that should be taken when using this procedure. For specific chemical hazards and the precautions needed to prevent exposure, refer to the Material Safety Data Sheets (MSDS) for the chemicals involved.

Hazards and precautions

Abrasions Back Strain Burns (>60C/140F)

Chemical Exposure

Cuts Driving Dust Electrical (>50V) Environmental Ergonomics Falls (>=6 ft) Fire Flammable (L3) Fumes Lighting Low Oxygen Noise (>85db) Pinch Points Pressure (>30

psig) Radioactive (L4)

Rotating Equip Slip Hazard Stairs Temperature Thermal Stress Toxic Weather Excessive force Long duration

task Repetition Heavy lifting Bending torso

Twisting torso Environmental Arms extended Arms out of neutral

Hands/ Wrist out of neutral

Vibrations Other

Hazard Precaution

Chemicals Involved: High Pressure Air, Nitrogen or other Gas as specified.

Requirements on what PPE and when it must be used (by task and/or chemical) can be found in the PPE section below.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 3: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 3 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Hazards and precautions (continued)

The table below lists job hazards and the precautions that should be taken when using this procedure. For specific chemical hazards and the precautions needed to prevent exposure, refer to the Material Safety Data Sheets (MSDS) for the chemicals involved.

Hazard Precaution

Personnel not involved in the LEO

Clear the area of non-essential personnel. Area where the pneumatic testing is to be performed must be cleared of non-essential personnel to the test stand safe distance calculated from the system being tested. The safe distance must be specified by the group performing the pneumatic testing.Use “RED BARRICADE and TAGS” to prevent non-essential personnel from entering.Test Stand Safe Distance must be clearly established for Pneumatic Testing.Reference: G4D-6422-01 for guidance.

Flammables If working in proximity to equipment / lines containing combustible or flammable chemicals or within the 35 FT effected area of a flammable area, monitor area with LEL meter for potential flammables present, surrounding work area.

Radioactive Sources If applicable, close and isolate radiation device per IOES standard and local agency requirements. Follow proper procedure for isolating radiation source and confirming it is isolated.

Environmental Considerations If required, use containers, absorbent materials and spill containment, provide instructions for properly disposal of removed insulation, drained material and washing.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 4: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 4 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Hazards and precautions (continued)

The table below lists job hazards and the precautions that should be taken when using this procedure. For specific chemical hazards and the precautions needed to prevent exposure, refer to the Material Safety Data Sheets (MSDS) for the chemicals involved.

Hazard Precaution

Emergency Response Procedure

Locate and test the nearest safety showers Ensure a clear escape path is kept open as well as identify alternate access/egress routes. Use the buddy system or two way radio communication to contact Immediate Response personnel or emergency personnel.

Inadvertent Pressure Release De-pressure equipment by slowly opening specifically identified vents and drains. Break flanges away from the body. Do not stand in the line of fire.

Line Of Fire Ensure that no part of the body is positioned in the line of fire while executing the required tasks.Examples: Inspecting flanges for leaks while the line is pressurized, approaching flanges while the line is being pressurized or under pressure, etc.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 5: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 5 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Hazards and precautions (continued)

The table below lists job hazards and the precautions that should be taken when using this procedure. For specific chemical hazards and the precautions needed to prevent exposure, refer to the Material Safety Data Sheets (MSDS) for the chemicals involved.

Hazard Precaution

Energy Sources Equipment / Piping System must not be connected to any process or utility systems. The Pneumatic Testing Crew Foreman and the Dow Safe Work Permit Writer must verify that the system is not connected to any Dow process or utility systems.Ensure that all the energy sources are effectively controlled or isolated for the duration of the L&EO. Verify that systems that are being Pneumatically Tested are isolated from systems that could have construction personnel exposed to the high pressure of the test.If the equipment / piping system being tested is connected to other new systems that are under construction (i.e., branch connections, etc) and that are not part of the system being tested, the equipment / piping system must be isolated following a LOTO process in order of preference:– The contractor specific LOTO process that meets Dow

requirements. – If contractor does not have a LOTO process, the Gulfstream

Construction LOTO Process (F0278 Tagout Authorization Form, F0281 Danger – Do Not Operate Tag, F0279 Tagout Index, etc.) must be followed for new piping systems

– When specifically requested, the Dow Red Tag Master must be followed.

If necessary, the “700_GS_509_02 List of Temporary Blinds for Pressure Test” or form G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist must be filled out documenting the specifications and location of all split blinds utilized for isolation of the system.

Continue on next page.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 6: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 6 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Hazards and precautions (continued)

The table below lists job hazards and the precautions that should be taken when using this procedure. For specific chemical hazards and the precautions needed to prevent exposure, refer to the Material Safety Data Sheets (MSDS) for the chemicals involved.

Hazard Precaution

Energy Sources(Continue)

The isolation of energy sources will be verified by the Pneumatic Testing Crew Foreman and documented on the form “700_GS_ 509_03 F75201 Pressure Test Report”.NOTE: If the system is connected to any Dow process or utility system, the system must be under the control of a Dow Operational Group, the Dow IOES (RTM system)and Return To Operation (RTO) processes must be followed and implemented by Dow Trained and Approved Operations Personnel.

Energy Sources – Pneumatic Testing

Warning: Pneumatic Testing should be used as the last alternative. Carefully planned, approved and supervised procedures must be followed. EMTL DE-G4D-6422-01 must be followed. Pressure testing conducted utilizing pneumatic testing must be approved by Dow Engineering and the Dow Construction Manager. Test Stand Safe Distance must be clearly established for Pneumatic Testing.Reference: G4D-6422-01 for guidance.

Improperly calibrated testing equipment or insufficient personnel training

All pneumatic testing equipment; pressure gages, relief valves, regulators, etc, must be calibrated and certified prior to be used on any pneumatic testing.Personnel performing pneumatic testing must be trained on the specific requirements.

If any physical contact or exposure occurs, report and seek medical treatment immediately!

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 7: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 7 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

PPE Requirements on what PPE and when it must be used (by task and/or chemical) can be found in the reference table below.The following PPE must be worn:

LEO Task Chemicals/Agents Involved

Required PPE and when it can be relaxed

Opening vent and drains High Pressure Air Hard Hat, Face Shield, Safety Glasses, High Visibility vest/shirt, Leather Gloves, Long Sleeves, Hearing Protection – may require double hearing protection based on noise level, Safety Steel Toe Shoes. Single Hearing Protection required at ≥ 85 db up to 105 db. Double Hearing Protection required at ≥105db. Face Shield and Double hearing protection can be relaxed once the system is de-pressured and the person is outside <105db limits.

L&EO activity (installing slip blinds, correcting leaks on the system being tested, etc.)

High Pressure Air See above!

Uncontrolled de-compression of the system being pneumatically tested.

High Pressure Air, Uncontrolled Energy Release

Follow procedures and communication while performing test.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 8: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 8 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Tools and equipment

The tools and equipment listed below are needed to do this job. Box End Wrench Bung Wrench Channel Locks Come Along Dial Indicator Fall Protection Flange Separator Hammer Laser Alignment Pry Bar Radios Rope Screw Driver Stands Supplied Air Bottles Torque Wrench O2/LEL meter Barricade Tape &

Tags Other:

Tools and/or Equipment Use (if explanation is needed)

Barricade ribbon/tape and warning signs Used to warn others of potential hazards and to maintain a safe zone away from the hazard.

O2/LEL Meter If required, to ensure safe atmosphere.

Hazard Monitoring

The table below lists required monitoring to do this LEO job.

Type of monitoring Limits Where and When

Oxygen % (in the working atmosphere)

>19.5% to <23.0% If performing LEO in areas that could be within close proximity of an Oxygen deficient atmosphere.

LEL % 0% in case the test occurs in areas within a flammable area.

If performing LEO in areas that contains flammable chemicals.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 9: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 9 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Identification of LEO Locations

The methods used for identification of line break locations are specified below:

This procedure will be used by non-operations personnel (e.g., construction, maintenance, etc).Acceptable options for identification of line break locations: o The Pneumatic Testing Crew Foreman (a trained construction representative) will be

responsible to physically indentify in the field the exact location of every break at the time that each break is initiated, then document as such in “700_GS_ 509_03 F75201 Pressure Test Report” and on the LEO Safe Work Permit.NOTE: This is only acceptable in the Construction Site ISBL.

o Use the L&EO identification tags/labels. The L&EO identification tags must have the same information as the L&EO Identification tag on the example on Attachment No.1 (i.e., Yellow Tag) at the end of this procedure. Each tag/label is unique and non-perishable. Each L&EO Identification Tag (i.e., Yellow Tag) hung in the field to identify a L&EO must be numbered and listed on the LEO (Break-Bleed-Vent) Tag Location List. A copy of the LEO (Break-Bleed-Vent) Tag Location List can be found on Attachment No.2 at the end of this procedure or in the Gulfstream Safety Manual under the 52_GS_3320 Line and Equipment Opening Standard.

In case of multiple works being done in the same area, the numbering system used shall ensure that each tag being used to identify the location of the L&EO are clearly associated with the specific job.

If the contractor has a unique identification number for every pneumatic/ hydrostatic test to be performed on a specific project, their unique numbering system could be utilized to identify the specific L&EO identification tags.Example: For Hydrostatic Test on a line in PDH

Numbering System for L&EO Identification Tags (i.e., Yellow Tags):Hydrostatic Test Number: HP0535-04-WO-01

HP0535-1 for L&EO ID Tag #1HP0535-2 for L&EO ID Tag #2And continue, Etc.

If the contractor does not have a unique identification number for every hydrostatic test.A specific numbering convention has been developed to meet this objective:Example: For Hydrostatic Test on a line in PDH

Numbering System for L&EO Identification Tags (i.e., Yellow Tags):Project-P&ID Number-Line Number-L&EO ID NumberPDH-P&ID Number-Line Number-1 for L&EO ID Tag #1PDH-P&ID Number-Line Number-2 for L&EO ID Tag #2And continue, Etc.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

This number must be unique to this specific hydro

Page 10: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 10 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Before you begin Before beginning this procedure :

1. Review this entire procedure and become familiar with the requirements.

2. Verify that conditions (e.g., extreme environmental conditions, physical/chemical conditions, PPEs, risks associated with the activities) have not changed since the L&EO procedure was written. In case of changes, the work must be stopped and:

o The work being reassessed to document new hazards and precautionso If applicable, a new Hazard Analysis must be completedo As appropriate, the procedure updated.

Ensure an emergency procedure which includes provisions for decontamination of personnel, if necessary, is available prior to the LEO.

3. Ensure there is a plan, if necessary, to collect and dispose material from the system in compliance with environmental regulations.

4. Safe Work Permits for Pneumatic Testing will be issued per crew, per line for every working Shift/Day.

For Pneumatic Testing work extending beyond one working shift (12 hrs), the work scope associated with the specific pneumatic test must be evaluated to determine if the extension on time is justifiable, allowing the safe completion of the job scope: Could the testing be completed within the maximum 16 hours duration of a

Safe Work Permit? Does the same Pneumatic Testing Crew is willing to stay and complete the

testing? Does the Dow Construction Manager or designee approve the extension of the

safe work permit to 16 hours to complete the specific work scope?

If the pneumatic test will exceed the 12 hours, and the conditions above cannot be met, or exceeding the 16 hours, the on-coming shift and safe work permit issuer must be at work earlier and proceed to obtain a new safe work permit (i.e., complete field inspection, review job status, etc) and prepare to conduct a shift relief in the field with the off-going shift personnel (hot shift relief). Otherwise the specific piping system being pneumatically tested must be placed in a safe condition (de-pressured, pneumatic pump shut-off) and the job must be turned over to an on-coming work shift personnel. A new safe work permit will be issued for the new work shift.

NOTE: Under no circumstances should the line be left pressurized unattended.Example: Foreman shall maintain supervision while line is pressurized.System must be de-pressure when leaving area after hours.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 11: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 11 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Before you begin(continued)

To minimize the time required to issue the safe work permit, it is recommended that the pneumatic test crew (i.e., contractor) has the line prepared and ready to comply with the safe work permit requirements: The Pneumatic Testing Crew Foreman must verify that the Equipment/Piping

System is not connected to any Dow process or utility systems. Ensure that all the energy sources are effectively controlled or isolated for the

duration of the L&EO. Verify that systems that are being Pneumatically Tested are isolated from systems that could have construction personnel exposed to the high pressure of the test.

If the equipment / piping system being tested is connected to other new systems that are under construction (i.e., branch connections, etc) and that are not part of the system being tested, the equipment / piping system must be isolated following a LOTO process in order of preference:– The contractor specific LOTO process that meets Dow requirements.– If contractor does not have a LOTO process, the Gulfstream Construction

LOTO Process (F0278 Tagout Authorization Form, F0281 Danger – Do Not Operate Tag, F0279 Tagout Index, etc.) must be followed for new piping systems.

– When specifically requested, the Dow Red Tag Master System must be followed.

If necessary, “700_GS_509_02 List of Temporary Blinds for Pressure Test” or form G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist must be filled out documenting the specifications and location of all split blinds utilized for isolation of the system.

The isolation of energy sources verification will be documented by the Pneumatic Testing Crew Foreman on the form “700_GS_ 509_03 F75201 Pressure Test Report”.NOTE: If the system is connected to any Dow process or utility system, the system must be under the control of a Dow Operational Group, the Dow IOES (RTM system)and Return To Operation (RTO) processes must be followed and implemented by Dow Trained and Approved Operations Personnel.

The L&EO breaks must be identified as per the requirements of this procedure [i.e., The L&EO identification tags (Yellow Tagged) and listed in the LEO (Break-Bleed-Vent) Tag Location List].o LEO: Vent and drain valves must be identified as per the requirements of this

procedure [i.e., The L&EO identification tags (Yellow Tagged) and listed in the LEO (Break-Bleed-Vent) Tag Location List].

o LEO: The location where the testing equipment is to be connected to the Equipment/Piping System to be tested must be identified as per the requirements of this procedure [i.e., The L&EO identification tags (Yellow Tagged) and listed in the LEO (Break-Bleed-Vent) Tag Location List].

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 12: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 12 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Before you begin (continued)

o The testing equipment (i.e., Pneumatic pressure source and relief device, hoses, gauges, etc) must be connected to the Equipment / Piping System being prepared for pneumatic testing with a double block and bleeds with check valves (prevent back flow into utility systems and allow to de-pressure the system to connect and disconnect the testing equipment).

o LEO: If additional fill hoses are required to expedite the filling of the Equipment/Piping System, the lines used to fill the system (fill hoses), if connected through locations other than the test rig, must be connected with double block and bleeds with check valves (prevent back flow into utility systems and allow to de-pressure system to connect and disconnect test medium) to the fill valve(s) of the system being tested. The location where the fill lines are to be connected to the line to be tested must be identified as per the requirements of this procedure [i.e., The L&EO identification tags (Yellow Tagged) and listed in the LEO (Break-Bleed-Vent) Tag Location List].

NOTE: Do not commence filling of the system until the safe work permit has been issued.

Red barricades and barricade tags must be installed, preventing personnel not involved in the LEO entering test area as per the guidance of this procedure as per G4D-6422-01.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 13: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 13 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Safe Operating Limits

The Safe Operating Limits must be documented on the “700_GS_509_03 F75201 Pressure Test Report” or a similar form with the same information.

Otherwise the specific Pneumatic Testing safe operating limits must be documented below as applicable. If not applicable, the line must be filled as “N/A”.

Safe Operating Parameter Limit Value Units

Testing Fluid To BE Used Approved by QC Mgr & Dow Construction Mgr or Designee

Ref: G8S-4001-60

Test Media/Metal Minimum Testing Temperature

DEG C ( DEG F)

Test Media/Metal Maximum Testing Temperature

DEG C ( DEG F)

Ambient Temperature Minimum Temperature

DEG C ( DEG F)

Minimum Testing Pressure PSIG (Bars)

Maximum Testing Pressure PSIG (Bars)

Pneumatic Testing Rig Relief Valve Setting

PSIG (Bars)

Holding Time (Test Duration)

Minutes

System Component to be Tested Lowest MAWP

PSIG (Bars)

System Component to be Tested Lowest Brittle Fracture Temperature Limit

DEG C (DEG F)

Test Safe Distance(i.e., Barricading & Tagging)

Feet

Pressure Ramping Rate or Stages:See Table 1. Pneumatic Test Procedure (attached).

De-Pressure Rate or Stages:See Table 1. Pneumatic Test Procedure (attached).

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 14: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 14 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Consequences of deviation

This section lists any consequences of deviation from the procedure steps or safe operating limits.

Type of Deviation Consequences and How to Avoid

Inadvertent pressure release during pneumatic testing.

Personal injury (i.e., Eye injury, etc), Equipment damage.De-pressure equipment by slowly opening specifically identified vents and drains. Break flanges away from the body. Do not stand in the line of fire.

Personnel not involved in the LEO, entering test area.

Personal injury (i.e., Eye injury, etc).Clear the area of non-essential personnel. Area where the pneumatic testing is to be performed must be cleared of non-essential personnel to a distance equal to the Test Stand Safe Distance. Use “RED BARRICADE and TAGS” to prevent non-essential personnel from entering. Test Stand Safe Distance must be clearly established for Pneumatic Testing. Reference: G4D-6422-01 for guidance.

Performing improper LEO tasks:o line break on the wrong line or

equipment o opening line or equipment with

hazardous materials when not properly isolated, de-pressured and/or cleaned to acceptable levels

o Improper operation of valves on “In Service” line or equipment.

Possible chemical exposure or uncontrolled release of material. How to Avoid - Perform LEO activities in a cautious, controlled manner. Monitor for signs of material present. Return equipment to a safe position/state, if material is detected. Proper ID of LEO location Follow checklist/procedure Conduct thorough hazard analysis,

follow procedures.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 15: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 15 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Consequences of deviation(continued)

This section lists any consequences of deviation from the procedure steps or safe operating limits.

Type of Deviation Consequences and How to Avoid

Failure to wear required PPE Removal or relaxing of PPE prematurelyCorrect PPE not identified

Possible personal injury.How to Avoid – Always use all the required PPE; do not remove or relax PPE if not specifically indicated by this procedure.Follow specified PPE hazards and task.

Inadequate Hazard Monitoring If applicable, possible chemical exposure, oxygen deficient atmosphere or fire/explosion from adjacent systems.How to Avoid – If applicable, maintain hazard monitoring within the scope of work being performed, if needed, and take the necessary precautions to prevent exposure to the hazards identified.

Checking for leaks in inaccessible areas; i.e. scaffolds, ladders, platforms, etc.

Possible fall, personal injury.Follow elevated work standard, practices and procedures.Provide adequate access to work areas.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 16: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 16 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

IOES Control Method Exclusive Control

Master Red Tag System Individual Red Tag System In Construction Areas; For Construction Outside Battery Limits (OSBL):o Equipment / Piping System must not be connected to any process or utility

systems. The Pneumatic Testing Crew Foreman and the Dow Safe Work Permit Writer must verify that the line is not connected to any process or utility systems.

o If the equipment / piping system being tested is connected to other new systems that are under construction (i.e., branch connections, etc) and that are not part of the system being tested, the equipment / piping system must be isolated following a LOTO process in order of preference:– The contractor specific LOTO process that meets Dow requirements.– If contractor does not have a LOTO process, the Gulfstream Construction

LOTO Process (F0278 Tagout Authorization Form, F0281 Danger – Do Not Operate Tag, F0279 Tagout Index, etc.) must be followed for new piping systems.

– When specifically requested, the Dow Red Tag Master System must be followed.

NOTE: If the system is connected to any Dow process or utility system, the system must be under the control of a Dow Operational Group, the Dow IOES (RTM system)and Return To Operation (RTO) processes must be followed and implemented by Dow Trained and Approved Operations Personnel.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 17: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 17 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Summary of IOE Methods for One-Plus

List below the method(s) for One-Plus. The method of One-Plus should be listed as a note in the RTMS (if used) for each Isolation of Energy.

Lock Secure handle Disconnect air line

Design Remove fuse Disconnect leads Inaccessible Remove valve handle Round handled valve Slip Blind per Spec Other: Contractor Specific Do Not Operate Tags

List below the energy sources to be isolated and describe the hazards associated with them.

Energy Source Energy Description Hazard of Energy Source

Electrical <120 V >120 V

Electrocution, Electric Shock, Burns

Chemical Release Health or Fire Hazard:

Pressure Gas: <30 psig >30 psig

Liquid: <100psig

>100psig

Personal Injuryhigh pressure air, potential mechanical system failure under pressure.

Mechanical Pinch Points Suspended Load Spring(s) Rotating Equip Other – de-

pressure

fracture, abrasion, caught between

Other

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 18: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 18 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

1 3 Ensure that the Pneumatic Crew Forman has been trained on the following processes and procedures:

G4D-6422-01-DES Guidelines for the Application of Pneumatic Testing.pdf

G4S-6422-01-DES Class D Sensitive Leak Test – Gas & Bubble Method.pdf

G4S-6422-02-DES Pneumatic Testing Greater Than 15 PSIG.pdf

G8S-8005-09-DES Line Blank Specification.pdf

G4Q-6422-02-DES Pneumatic Testing Safe Work Procedure Checklist.pdf

G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist

700_GS_250 50050 Piping Pressure Testing.docx

700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

700_GS_250.50050_02 Piping Pressure Testing Attachment 02.docx

700_GS_250.50050_03 Piping Pressure Testing Attachment 03.docx

700_GS_250.50050_04 Piping Pressure Testing Attachment 04.docx

700_GS_509_00 Hydrotest Legend.pdf

700_GS_509_01 F75101 Aboveground Pipe Inspection Record.pdf

700_GS_509_02 List of Temporary Blinds for Pressure Test.pdf

700_GS_509_03 F75201 Pressure Test Report.pdf

700_GS_509_04 F75602 Pipe Restoration Report.pdf

700_GS_509_05 F75601 Pipe Cleaning And Verification Checklist.pdf

700_GS_509_06 F75102 Visual Inspection of Flanges, Gaskets and Bolting.pdf

700_GS_509_07 F78001 Coatings Inspection Record.pdf

700_GS_509_08 F02407 Punch List _Construction.pdf

4 6 Confirm that the equipment / piping system to be Pneumatically Tested in a construction OSBL area is completely isolated from any process and utility system. The Pneumatic Testing Crew Foreman and the Dow Safe Work Permit Writer must verify that the system is not connected to any Dow process or utility systems.

7 9 Verify that the high pressure Pneumatic Testing is not applied to a non metallic Equipment / Piping Systems as per G4S-6422-02.Verify that vessels, process equipment, instruments and relief devices are not included in the scope of the Pneumatic Test.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 19: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 19 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

10 11 12 Verify or determine that the Pneumatic Test Pressure has been determined as per G4D-6422-01, Section 4.2 and documented on form “700_GS_509_03 F75201 Pressure Test Report” under “Test Conditions” or on the Safe Operating Limit session of this procedure.

13 14 15 Verify that the Brittle Fracture Failure Pressure (maximum pressure that could cause a hoop stress equivalent to 6000 psi) has been determined per G4D-6422-01, Section 4.3.

16 17 18 Verify the Pneumatic Test Pressure determined in step 4 is less than the Brittle Fracture Failure Pressure determine step 5.

NOTE: If Pneumatic Test Pressure is higher than Brittle Fracture Failure Pressure, consult a piping stress specialist.

19 20 21 Verify that the Metal Temperature Limitations have been established in accordance with G4D-6422-01, Section 4.4 and 700_GS_250 50050 Piping Pressure Testing, Section 3.7. Non-impact tested carbon steel piping (i.e., ASTM A 53, ASTM A 106,

etc.). Temperature of piping must be considered and above 4 Deg C (40 Deg F). Cast Iron and semi-steel piping and fittings are especially susceptible to fracture also. Piping systems must be properly supported and anchored.

Non-ferrous and Stainless Steel pipe or tubing shall not be colder than the minimum design temperature specified on the Common Product Pipe Speciation plus 16.7 Deg C (30 Deg F).

Carbon Steel Pipe shall not be colder than 15.5 Deg C (60 Deg F) unless the calculated Pneumatic Test Pressure is lower than the calculated Brittle Fracture Failure Pressure on step 5 above.

If the calculated Pneumatic Test Pressure is less than or equal to the calculated Brittle Fracture Failure Pressure, the test may be conducted at temperatures not colder than -12.2 Deg C (10 Deg F).

22 23 24 Verify that the Stored Energy Potential has been calculated and recommendations followed, in accordance with G4D-6422-01, Section 5.

25 26 27 Verify that the Minimum Safe Distance has been determined per G4D-6422-01, Section 6.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 20: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 20 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

28 29 30 Before conducting the pneumatic test, verify that all parties involved (i.e., Dow Construction, contractor, inspector, EH&S safety representative and personnel performing the test, may be involved) meet to address and review a safe work procedure. The procedure must include the elements of G4D-6422-01, Section 7.2: – Visual Inspections– Pre-test procedures– Minimum Distance to be roped off and evacuated– Influence & impact on adjacent plants– Location of test (i.e., grassroots, existing plant)– Conducting test off hours or weekends to reduce the work activity in test

areas.– Weather conditions and impact on test.– Training and indoctrination of personnel on hazards involved.– Completion of Pneumatic Testing Safe Work Procedure Checklist,

G4Q-6422-01.

31 32 33 When piping cannot be isolated from equipment for pneumatic testing, as per G4D-6422-01, Section 7.4, the following must be verified:– Piping system pressure does not exceed manufacturer’s test pressure or

pressure limits imposed by the position and condition of the equipment.– The equipment does not contain internals or materials that may be damaged

by testing.– No rotating equipment may be included in any piping system leak test.– The increase in stored energy potential due to the added volume.

34 35 36 Any deviation from compliance with G4D-6422-01 must undergo a safety evaluation as per G4D-6422-01, Section 7.4.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 21: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 21 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

37 38 39 Proper installation of vent and drain connections needs to be carefully considered. Suggested configurations:- G4G-6414-01, “Pressure Test Drain Valve - Threaded Plug Outlet”- G4G-6414-02, “Pressure Test Vent Valve - Blind Flanged Outlet”- G4G-6414-03, “Pressure Test Drain Valve – Blind Flanged Outlet”- G4G-6414-05, “Pressure Test Drain or Vent Valve Tapped Flange Connection”- G4G-6414-21, “Pressure Test Drain Valve for Systems Subject to Vibration -

Threaded Plug Outlet”- G4G-6414-22, “Pressure Test Vent Valve for Systems Subject to Vibration - Blind

Flanged Outlet”- G4G-6414-23, “Pressure Test Drain Valve for Systems Subject to Vibration - Blind

Flanged Outlet”

40 41 42 Test connection components, i.e., weldolets, sockolets, etc., shall comply with the components specified in the Global Common Product Pipe Specification governing the piping system. Use of threaded components, where not included in the Global Common Product Pipe Specification, is not permitted.

43 44 45 Blind flanges must be in accordance with pipe specifications or as specified in G8S-8005-09.

46 47 48 A set of marked-up P&IDs may be used to identify the boundaries of separate systems or piping to be tested, location of isolation blanks, valve positions, double block and bleed valve arrangements, location of pressure injection points, location of pressure gauges and other instrumentation to validate the test.

49 50 51 List of isolation blinds and location may be documented on “700_GS_509_02 List of Temporary Blinds for Pressure Test” or form G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist.

52 53 54 The leak test detection solution must comply with the requirements established G4D-6422-01, Section 8.3.- Stainless Steel, Nickel, Chromium Alloys: Leak detection fluid must be Sulfur and

Halogen (chloride) content of less than 10 PPM of each.- Polyethylene or structural parts; Fluid shall not promote environmental stress

cracking. Compressed air temperature should be to a maximum of 150 Deg C (300 deg F) to avoid possible auto ignition of lubricating oils.

- For Oxygen systems: Must meet MIL-L-25567D.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 22: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 22 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

55 56 57 As an interim test, may use sonic leak detector to listen for leaks. Follow procedures G4S-6426-01 and G8S-5033-03.The sonic testing equipment must be capable of detecting frequencies between 30 KHz and 50 KHz.

58 59 60 A Safe Work Procedure Checklist (G4Q-6422-02) shall be written and approved prior to beginning of a Class DH Pneumatic Test. The procedure should cover the following minimum requirements:a. Pretest visual inspection. The system to be tested shall be reviewed to ensure

that the complete system can be de-pressurized at completion of the test.b. Areas to be rope-off and minimum distance to be maintained, according to

local site standards, government regulations or Table 1 in EMETL G4D-6422-01.

c. Time schedule.d. Indoctrination of personnel on hazards involved.e. Form G4Q-6422-02, Pneumatic Testing Safe Work Procedure Checklist mus

be completed and signed.

61 62 63 Pneumatic test shall be made with air, nitrogen or other approved gases.– Nitrogen is the preferred test fluid at pressures above 100 PSIG (6.9 Bar).– Air shall not be used to test new piping at pressures above 300 PSIG (20

Bar).– Air shall not be used to test un-cleaned pipe at any pressure unless cleaned

and verify free of combustible.

64 65 66 Air compressor shall be equipped with discharge filters for removal of water, oil and foreign matter. Maximum discharge temperature shall be 150 Deg C (300 Deg F).

67 68 69 Verify that a line schedule is available with Common Product Specification, Material of Construction, Size, Insulation Specification, Required Test Pressure, and other piping specifications.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 23: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 23 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

70 71 72 Perform a thorough visual inspection for defects such as:- improper materials of construction, - poor gaskets installation- loose joints- Verify all bolts are tight.- Unless noted otherwise, gaskets per pipe specifications shall be used.- All other mechanical joints shall be examined.- Piping surface shall be clean and free of oil, grease, paint, weld slag or other

contamination.- Weld joints shall not be painted or covered before testing.

NOTE: Inspections performed on parts of the equipment/ piping system that has been pre-fabricated and pre-painted prior to field installation will be inspected only in the areas fabricated in the field (i.e., weld joints, flanges, etc.). Pre-fabricated parts shall have documented certified shop or mil test and must be received with the parts and available prior to field installation.

73 74 75 Joints shall not be insulated or covered in any manner for this test.

76 77 78 Piping systems connected to equipment shall be isolated from the equipment by means of a line blind, prior to cleaning and testing. If a valve is connected to the equipment, the blind shall be between the valve and the equipment, with the valve in the open position. Where piping cannot be isolated from equipment for testing, or it is

desirable to include equipment in leak testing, the equipment may be included in the test provided:– The piping system Test Pressure does not exceed either manufacturer’s

test pressure or a pressure limit imposed by the position and condition of the equipment.

– The equipment does not contain any internals or materials that may be damaged by testing.

– No rotating equipment may be included in any piping system leak test.– The increase in stored energy potential due to the added

volume of the equipment being tested is considered on the overall stored energy potential calculation for the system.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 24: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 24 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

79 80 81 Valves shall be left open during the testing. If a valve is located at the end of a line, a blind flange or plug shall be installed. Where a valve cannot be tested in the open position, consider:– Blank the upstream side of the valve.– Remove the valve and install a blind flange.– Remove the valve and install a flanged test spool where continuity of the

line is required for purpose of the test.

82 83 84 Test blinds shall be installed between existing piping and new piping to prevent introducing cleaning and testing medium into existing lines, or pressurizing the existing system.– Test blinds shall be capable of withstanding the test pressure as per

Common Piping Product Specification (CPPS) or Engineering Specification G8S-8005-09.

Note: This condition should not be encounter within the construction environment.

NOTE: If the system is connected to any Dow process or utility system, the system must be under the control of a Dow Operational Group, the Dow IOES (RTM system) and Return To Operation (RTO) processes must be followed and implemented by Dow Trained and Approved Operations Personnel.

85 86 87 All contractor fabricated appliances for testing of pipe lines - such as test stands, test blinds, blind flanges, etc - shall be designed and fabricated in accordance with governing Codes and Standards, such as ASME B31.3, ASME B16.5, ASME B16.47, ASME B16.48,  etc. This includes use of proper materials, as well as assembly, welding, post treatment, and inspection requirements.

88 89 90 Leak tests shall include as much instrument process piping as possible. Where an instrument process line contains more than one block valve, all valves shall be open except the one nearest the instrument.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 25: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 25 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

91 92 93 If cleaning has a negative effect on control valves, pressure reducing valves, level controllers, level switches, orifice plates, turbine meters, massflow meters, vortex meters and other instruments or fittings, then remove these items only if designated by the Owner. These items shall be removed from the lines before cleaning and reinstalled before testing. All such items shall be cleaned separately after removal.

94 95 96 Where control valves are closed, the line shall not be tested until the valve has been opened by the Owner. The line bore orifice spacers and gaskets or spare rings furnished with meter runs shall be installed prior to cleaning and remain in place during testing.

97 98 99 If any instruments and similar special equipment cannot withstand the required test pressure, they shall be removed only if designated by the Owner. Direct operated or self-contained regulators and float actuated devices shall be removed, or blocked and vented.

100 101102 Safety valves and rupture discs installed for fit-up shall be removed during the test and reinstalled only after successfully completing the test. Some inline equipment and valves, such as transflow or three-way valves, may not be able to be tested. The line shall then be tested with temporary spool in place

103 104105 Check available drawings for any specific installation or operating instruction pertaining to expansion joints. Test pressure shall not exceed the maximum allowable specified test pressure of the expansion joint.

– Expansion joints having tie-rods shall be tested as part of the piping system unless otherwise specified. The tie-rod nuts must be hand tight, with no slack under the outside nuts.

– Expansion joints not having tie-rods may be removed or isolated from the test.

106 107108 Insulation will not be allowed on systems under test except on those parts which have had a documented certified shop or mil test.

109 110111 Spring support travel stops shall not be removed until all testing has been completed.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 26: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 26 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

112 113114 Prior to administration of the test visually observe the piping system to assure it is properly prepared.

115 116117 Care should be exercised to check and confirm that there are no sections of the piping system where gas can be trapped downstream of check valves, or sections isolated by other valves, such that the piping cannot be safely vented after testing.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 27: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 27 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

Administration of Test

118 119120 All tests shall be witnessed and accepted by the Owner or Owner designee.

121 122123 Special precautions shall be taken if testing is to be performed in the open air, with regard to weather such as wind or rain or other influences which may affect the accuracy of the test results.

124 125126 Verify that form “700_GS_509_01 F75101 Aboveground Pipe Inspection Record.pdf” has been completed.

127 128129 If applicable, verify that form “700_GS_509_06 F75102 Visual Inspection of Flanges, Gaskets and Bolting.pdf” has been completed.

130 131132 If applicable, verify that form “700_GS_509_07 F78001 Coatings Inspection Record.pdf” has been completed.

133 134135 If applicable, verify that form “700_GS_509_05 F75601 Pipe Cleaning And Verification Checklist.pdf” has been completed.

136 137138 Clear the area of non-essential personnel. Area where the Pneumatic testing is to be performed must be cleared of non-essential personnel to the “Test Stand Safe Distance” from the system being tested. The safe distance must be specified by the group performing the Pneumatic testing.“Test Stand Safe Distance” must be clearly established for Pneumatic Testing.Use “RED BARRICADE and TAGS” to prevent non-essential personnel from entering.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 28: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 28 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

139 140141 Ensure that all the energy sources are effectively controlled or isolated for the duration of the L&EO. Verify that systems that are being Pneumatically Tested are isolated from systems that could have construction personnel exposed to the high pressure of the test.If the equipment / piping system being tested is connected to other new systems that are under construction (i.e., branch connections, etc) and that are not part of the system being tested, the equipment / piping system must be isolated following a LOTO process in order of preference:– The contractor specific LOTO process that meets Dow

requirements. – If contractor does not have a LOTO process, the Gulfstream

Construction LOTO Process (F0278 Tagout Authorization Form, F0281 Danger – Do Not Operate Tag, F0279 Tagout Index, etc.) must be followed for new piping systems.

– When specifically requested, the Dow Red Tag Master System must be followed.

If necessary, the “700_GS_509_02 List of Temporary Blinds for Pressure Test” or form G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist must be filled out documenting the specifications and location of all split blinds utilized for isolation of the system.The isolation of energy sources will be verified by the Pneumatic Testing Crew Foreman and documented on the form “700_GS_ 509_03 F75201 Pressure Test Report”.

NOTE: If the system is connected to any Dow process or utility system, the system must be under the control of a Dow Operational Group, the Dow IOES (RTM system)and Return To Operation (RTO) processes must be followed and implemented by Dow Trained and Approved Operations Personnel.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 29: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 29 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

142 143144 The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every break (i.e., flanges that will be opened for the insertion of a slip blind for isolation or disconnected and blind flanged or capped) at the time that each break is initiated. The Pneumatic Testing Crew Forman’s name will be listed in the SWP under the LEO section as the person identifying each LEO in the field.NOTE: This is only acceptable in the Construction Site ISBL.The LOTO tag of the slip blinds and blind flanges for isolation of the system will also identify the location of the LEO’s in the field.An alternative is the use of L&EO identification tags/labels (i.e., Yellow Tagged) and listed on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

145 146147 Any flange or tubing open to remove instrument or equipment (i.e., flow meter, pressure device, permanent system pressure relief devices, etc) from the system for the purpose of Pneumatic Testing must be physically identified in the field by the Pneumatic Testing Crew Foreman (a trained construction representative) at the time that each break is initiated.An alternative is the use of a L&EO identification tag/label (i.e., Yellow Tagged) and listed on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

148 149150 The Pneumatic Testing Crew Foreman must clearly identify the Pneumatic Testing vent and drain valves for the specific test. Document as completed on form “700_GS_509_01 F75101 Aboveground Pipe Inspection Record.pdf”.An alternative is the use of a L&EO identification tag/label (i.e., Yellow Tagged) to identify the Drain and Vent valves and list them on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

151 152153 Never leave the pneumatic pressure source unattended.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 30: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 30 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

154 155156 Face shields must be worn while personnel are inside the red barricaded area, when test pressure is applied, while checking for leaks and when the system is being de-pressured.

157 158159 A properly sized and calibrated safety valve or relief valve shall be used at the pressure source to protect systems under test. Such a device shall have a set pressure equal to the test pressure plus 50 PSIG (3.4 BAR) or 110% of the test pressure, whichever is less.Document completion of this step on form “700_GS_509_03 F75201 Pressure Test Report.pdf”.

160 161162 Document or verify that all of Pneumatic Test Data / “Safe Operating Limits” have been documented on form “700_GS_509_03 F75201 Pressure Test Report.pdf”.An alternative is to document the Pneumatic Test Data / “Safe Operating Limits” on the Safe Operating Limits section of this procedure for the system being tested.

163 164165 Test Equipment – Inspect test rig to ensure hose and fittings are in good condition.

166 167168 Pressure gauges shall be of a suitable scale capacity for the Test Pressure, having a dial at least 115 mm (4-1/2”) in diameter. The Test Pressure should be approximately 60% of full scale. The maximum pressure capacity shall not exceed three times the particular Test Pressure. Gauges will have established traceable identities and shall be accurate to within 1% of full scale. There shall be a minimum of two pressure gauges for each test.

– Pressure gauges used for testing shall be calibrated at least every six months. Calibration shall be traceable to individual gauges for verification. Records of calibration shall be made available upon request.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 31: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 31 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

169 170171 Two gauges are required to be mounted on the system being tested with no isolation possible on either gauge from the system under test.The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every LEO (i.e., connection of the pressure gauges) at the time that each break is initiated. An alternative is the use of a L&EO identification tag/label (i.e., Yellow Tagged) to identify the LEO and list them on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

172 173174 Connect the pressure source and test rig to the piping system being tested utilizing a Double Block and Bleed with backflow prevention.NOTE: When connecting to the Equipment /Piping System to be tested, always use fittings of rating strong enough to withstand the test pressure. Provide a relief valve on the test rig to protect the connecting fitting in case the pump discharge is isolated from the system being tested with the pump in operation. The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every LEO (i.e., fitting connections to the system being tested) at the time that each break is initiated. An alternative is the use of a L&EO identification tag/label (i.e., Yellow Tagged) to identify the LEO and list them on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

175 176177 Verify that the test media / fluid has been approved and documented on form “700_GS_509_03 F75201 Pressure Test Report.pdf”. The Pneumatic Testing Crew Foreman and the QC inspector must have signed the form under the “Test Conditions” section.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 32: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 32 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

178 179180 If the test media is different than air, connect, purge and fill the system to be tested with approved testing gas.NOTE: If the testing media is not air, ensure that the locations where the system is being purged are barricaded preventing personnel from being exposed to the asphyxiating hazard of the testing media. NOTE: The lines used to fill the system (fill hoses), if connected through locations other than the test rig, must be connected with double block and bleeds with check valves (prevent back flow into utility systems and allow de-pressure system to connect and disconnect test medium) to the fill valve(s) of the system being tested.The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every LEO (i.e., connections of fill lines to the system being tested) at the time that each break is initiated. NOTE: Identify break points with L&EO identification tags/labels (i.e., Yellow Tagged) and list on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

181 182183 Purge or drain possible water pockets from the system (flow of water from low points in the system).NOTE: If the testing media is not air, ensure that the locations where the system is being purged are barricaded preventing personnel from being exposed to the asphyxiating hazard of the testing media. The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every LEO (i.e., connections of fill lines to the system being tested) at the time that each break is initiated. NOTE: Identify break points with L&EO identification tags/labels (i.e., Yellow Tagged) and list on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 33: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 33 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

184 185186 If the test media is different than air, disconnect filling lines and other fittings that are not designed to withstand the pneumatic test pressure.The Pneumatic Testing Crew Foreman (a trained construction representative) will be responsible to physically indentify in the field the exact location of every LEO (i.e., disconnecting the filling lines and other fittings) at the time that each break is initiated. NOTE: Identify break points with L&EO identification tags/labels (i.e., Yellow Tagged) and list on the LEO (Break – Bleed – Vent) Location List.NOTE: This is a LEO step.

Pre – Test of System at Pressure Not To Exceed 15 PSIG (I Bar)

187 188189 Screw the air regulator supplying the driving force for the pump all the way out before opening the air valve (shut off valve) on the pneumatic test pump.

190 191192 If test medium is different than air, open the test medium supply valve to the pneumatic test pump.

193 194195 Open the isolation valve from the test rig into the system being tested.

196 197198 Turn air regulator screw to reach 5 PSIG (0.3 Bar) to perform the first leakage check.Hold pressure for 15 minutes before applying bubble test solution.The first leakage check shall be made at 0.3 BAR (5 psig) MAXIMUM. Any detectable leaks shall be eliminated before proceeding. The leakage pre-test must be repeated at higher pressure not to exceed 1 BAR (15 psig).NOTE: Regulator may be preset to desired pressure by operating against a closed discharge valve and observing the gauge on the test rig.NOTE: Priming and/or painting is permitted as long as the pre-test in not considered a “Sensitive Leak Test”.NOTE: Application of bubble foaming solution to the joints is not mandatory.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 34: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 34 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

199 200201 Examine the gauges to ensure no leakage exists that may create a pressure drop.NOTE: If a leakage is detected, stop pressurizing the system and correct the leakage.NOTE: Ensure personnel correcting any leaks are utilizing the correct PPE.

202 203204 Variations of pressure and volume due to temperature changes will be taken into account in determining whether the pressure during test is satisfactory, at the end of the test. All attempts shall be made to stabilize the temperature of the test, prior to starting the test.

205 206207 Over tightening of a valve in an effort to make it hold may be cause for rejection of the valve by the Owner.

208 209210 Turn regulator screw to continue pressurizing the system until the desired level (pre-test pressure) of 15 PSIG (1 Bar) has been obtained. Shutdown the pump by backing the air regulator screw (pump driving force) on the pump all the way out.

211 212213 Close the air valve (shut off valve) supplying the driving force for the test pump.

214 215216 Close the air (test medium) supply valve to the test rig.

217 218219 Close the isolation valve from the pump into the Equipment/Piping System being tested.

220 221222 Open the bleed valve upstream of the isolation valve from the pneumatic pressure source into the Equipment/Piping System being tested to de-pressure connection. NOTE: This is a LEO step

223 224225 Check the system for leaks and correct as necessary.

226 227228 System must hold pre-test pressure of 15 PSIG (1 Bar) for a time specified on the testing document.

Continued on next pageL&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 35: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 35 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

Pressure Test

229 230231 Close the bleed valve on the double block and bleed of the test rig. Open the test media (pressure source) supply valve. Open the isolation valve from the regulator into the Equipment/Piping System being tested. Open the air valve (shut off valve) supplying the driving force for the test pump.

232 233234 Follow attached Table 1 to perform the pneumatic test of the system.Turn regulator screw to continue pressurizing the system until the desired level (test pressure) has been obtained.

235 236237 Interim testing for leaks may be done using a sonic leak detector. The testing shall continue in increments until the final test

pressure is reached and held for 30 minutes minimum without evidence of any leakage.

238 239240 Variations of pressure and volume due to temperature changes will be taken into account in determining whether pressure during test is satisfactory. All attempts shall be made to stabilize the temperature of the test, prior to starting the test.

241 242243 Once the pressure is stable, shutdown the pump by backing the air regulator screw (pump driving force) on the pump all the way out, close the air valve (shut off valve) supplying the driving force for the test pump. Close the air (test medium) supply valve to the test rig. Close the isolation valve from the pump into the Equipment/Piping System being tested. Open the bleed valve upstream of the isolation valve from the pneumatic pressure source into the Equipment/Piping System being tested to de-pressure connection.

244 245246 Once test conditions are met and system passes the pressure test, de-pressure piping and equipment being tested.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 36: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 36 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Line/Equipment Preparation and Opening Procedure(continued)

Use the procedure below to prepare a new construction piping system (no chemicals have being introduced into the system) to be isolated for Pneumatic Testing. If not applicable fill as “N/A”.Note: These steps must be followed in order and initialed as performed.

Step Action Initials & Date

247 248249 Return the system that was Pneumatically Tested to “Construction Complete Status”. Reconcile isolation tags / LOTO process and listing. Remove split blinds Remove plugs and caps Remove the Pneumatic Test equipment. Re-install equipment and instrumentation that were removed for

testing. New gaskets shall be used when reinstalling flanged equipment. Do not re-use gaskets.

Vents and drains shall be capped, plugged or blanked after completion of test according to pipe specifications or job instructions.

All valves shall be placed in the open or closed position as determined by the system owner.

Reconcile the L&EO identification tags/labels (i.e., Yellow Tags) with the LEO (Break – Bleed – Vent) Location List.

NOTE: We recognize that the L&EO breaks have not been leak tested after returning the system to “Construction Complete Status”, but the tags must be reconciled at this time. The system will undergo a detailed Return To Operation (RTO) leak testing as part of the commissioning process.

250 251252 Complete form “700_GS_509_04 F75602 Pipe Restoration Report.pdf”.

253 254255 Complete the Pneumatic Test documentation.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 37: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 37 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Table 1. Pneumatic Test Procedure

Preliminary Test Step 1

Primary TestStep 2

Primary TestStep 3

Primary TestStep 4 (Final)

Raise pressure to 25 PSIG (172 kPag) or to 25% of primary test pressure, whichever is lower.

Gradually increase the pressure to 50% of the primary test pressure. Do this in steps of approx. 20% of the primary test pressure, holding at each step for 2 to 3 minutes for piping to equalize strains.

Increase pressure in increments of 10% of the primary test pressure until primary test pressure is reached. At each increment, close test gas inlet valve at test manifold and observe test gage for 5 minutes.

Maintain primary test pressure for 30 minutes.

Disconnect supply. Hold pressure for 10 Minutes.

Hold for 10 minutes at 50% of the primary test pressure mark. Observe gage for loss of pressure (visual) inspection of the system is not required.

If pressure loss is noted, release pressure and do necessary repair. Repeat preliminary test.

See acceptance standard, Paragraph 5.6.2 of G4S-6422-02 Apply commercially available

bubble foaming solution to all joints under examination including valve stems and packing glands.

Flanges joints (except wafer valves and similar) may be taped and punch with a small hole so leakage can be observed at the hole.

Hold piping at specified test pressure for specified time.

Check for leaks. If pressure loss exceeds 10%,

blowdown to preliminary test pressure and check for leaks.

Proceed to next increment if pressure loss is not detected.

See acceptance standard, Paragraph 5.6.2 of G4S-6422-02Blowdown system to 80% of primary test pressure for final leak testing. Apply commercially available

bubble foaming solution to all joints not previously tested. When no leakage is observed the piping is acceptable.

If leaks are found, release pressure and do necessary repair. Repeat preliminary test. If no leaks are found, proceed with primary test. Step 2.

If no appreciable loss of pressure is detected (in the judgment of the inspector) after 10 minutes, proceed with Step 3.

Proceed with Step 4. End of test.

Return to Step 75 on the procedure.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 38: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 38 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Related Documents List related and supporting documents here, if applicable.

1. G4D-6422-01-DES Guidelines for the Application of Pneumatic Testing.pdf

2. G4S-6422-01-DES Class D Sensitive Leak Test – Gas & Bubble Method.pdf

3. G4S-6422-02-DES Pneumatic Testing Greater Than 15 PSIG.pdf

4. G8S-8005-09-DES Line Blank Specification.pdf

5. G4Q-6422-02-DES Pneumatic Testing Safe Work Procedure Checklist.pdf

6. G4Q-6409-01 – Pressure Leak Testing Valve and Equipment Isolation Checklist

7. 700_GS_250 50050 Piping Pressure Testing.docx

8. 700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

9. 700_GS_250.50050_02 Piping Pressure Testing Attachment 02.docx

10. 700_GS_250.50050_03 Piping Pressure Testing Attachment 03.docx

11. 700_GS_250.50050_04 Piping Pressure Testing Attachment 04.docx

12. 700_GS_509_00 Hydrotest Legend.pdf

13. 700_GS_509_01 F75101 Aboveground Pipe Inspection Record.pdf

14. 700_GS_509_02 List of Temporary Blinds for Pressure Test.pdf

15. 700_GS_509_03 F75201 Pressure Test Report.pdf

16. 700_GS_509_04 F75602 Pipe Restoration Report.pdf

17. 700_GS_509_05 F75601 Pipe Cleaning And Verification Checklist.pdf

18. 700_GS_509_06 F75102 Visual Inspection of Flanges, Gaskets and Bolting.pdf

19. 700_GS_509_07 F78001 Coatings Inspection Record.pdf

20. 700_GS_509_08 F02407 Punch List _Construction.pdf

Signature This procedure checklist was completed by:

____________________________________ ____________________(Name/Names) (Date)

Document and Records Management

This procedure will be filed in the Gulfstream SharePoint.File this completed procedure in seven day SWP document retention box.

Continued on next page

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 39: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 39 of 50

Pneumatic Testing New Equipment / Piping Systems in Construction Areas Away from Operating Systems Procedure at Greater Than 15 PSIG - ISBL, Continued

Validation This procedure was validated as the best known way to do this job by: Les Toler / Leen Jongman 03/30/2015(Name/Job Title) (Date)

Approver The last revision of this procedure was approved by:

Cody Beasley / Luis Colon 03/30/2015 (Name/Job Title) (Date)

Review History The following information lists at least the last two reviews to this document, and all reviews that were done in the last 12 months.

Date Reviewed By Comments

03/30/15 Luis Colon / Les Toler /Cody Beasley / Leen Jongman

Reviewed with no changes.

Revision History The following information documents at least the last 3 changes to this document, with all the changes listed for the last 6 months.

Date Revised By Changes

03/30/15 Luis Colon / Les Toler /Cody Beasley / Leen Jongman

Place the Pneumaticc Test Procedure (EMTL G4S-6421-04) into LEO Template Format.

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 40: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 40 of 50

Appendix 1 – LEO Connection Tag

Connection Tag available through E-Mart, Item #12306

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 41: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 41 of 50

Appendix 2 – LEO (Break-Bleed-Vent) Tag Location ListJob Description or Job No.:______________________________________________

Tag # Tagged By

Tagged Date

Location Reconciled Date

LEO IDInitial

Walk-Thru

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

Page 42: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 42 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 43: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 43 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 44: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 44 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 45: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 45 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 46: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 46 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 47: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 47 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 48: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 48 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 49: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 49 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form

Page 50: (Insert Department Name) LEO Operating Proceduresgulfshe.com/gshe_doc_ctr/Master_Safety_Manual0184/700_GS... · Web view700_GS_250.50050_01 Piping Pressure Testing Attachment 01.docx

USGC Gulfstream Program 700_GS_509_12The Dow Chemical Company Page 50 of 50

L&EO Hydro Test Procedure This is a controlled document. No un-authorized modifications. Health, Safety, and Environmental

DOW CONFIDENTIAL – Do not share without permission

See Hydrostatic – Pneumatic Test Reports Forms for Original Form