REPÚBLICA DEMOCRÁTICA DE TIMOR-LESTE
COUNCIL FOR ADMINISTRATION OF THE
INFRASTRUCTURE FUND
MINISTRY OF PLANNING AND STRATEGIC INVESTMENT
MAJOR PROJECTS SECRETARIAT
SECOND QUARTER REPORT 2015
INFRASTRUCTURE FUND
July 2015
Dili
i | P a g e
PREFACE
It is my pleasure to present the Infrastructure Fund’s Second Quarter Report for the Fiscal
Year 2015. It was prepared based on the progress achieved in each individual projects that
reported by the relevant line ministries and/or agencies. The covers the milestones on the
course of implementation of IF programs/project activities undertaken during this reporting
period. The data and information presented in this report has the objective of providing
reliable, meaningful and useful information to the CAFI, National Parliament and other
concerned parties. It highlights key activities undertaken during the second quarter and
presents the most relevant results achieved for each Program and the status of individual
projects.
The Government has made significant efforts to manage, monitor and administer the
implementation of the IF projects in an appropriate and sustainable manner in order to follow
the objective of the Infrastructure Development Program and to improve the infrastructure,
reduce poverty and contribute to the country's economic development.
The Government also recognizes that there are still major challenges ahead to achieve the
desired overall objective. We hope the report provides useful information on the status of
implementation for the second quarter of the 2015 Infrastructure Fund projects.
Council for Administration of Infrastructure Fund
Kay Rala Xanana Gusmão
President
ii | P a g e
ABBREVIATIONS AND ACRONYMS
ADN/NDA National Agency for Development
ADB Asian Development Bank
AMP Asphalt Mixing Plant
BoQ Bill of Quantity
CAFI Council for Administration of Infrastructure Fund
CPV Commitment Payment Voucher
CFP Civil Service Commission
CNE Comissão Nacional de Eleição
CPAR Corrective & Preventative Action Request
DSDMP Dili Sanitation and Drainage Master Plan
EdTL Electricidade de Timor Leste
EOI Expression of Interest
EXIM Export-Import
GoTL Government of Timor-Leste
IF Infrastructure Fund
IFC International Finance Corporation
JICA Japan International Cooperation Agency
MAF Ministry of Agriculture and Fishery
MoF Ministry of Finance
MoJ Ministry of Justice
MoH Ministry of Health
MPSI Ministry of Planning and Strategic Investment
MPS Major Projects Secretariat
MPW/MoP Ministry of Public Works
MPWTC/MoPTC Ministry of Public Works, Transport and Communication
NDE/DNME National Directorate for Environment
NPC/CNA National Procurement Commission
O&M Operation and Maintenance
PISC Project Implementation and Supervision Consultants
PO Purchase Order
PPP Public-Private Partnership
PR Payment Request
RNUP Road Network Upgrading Project
RNUSP Road Network Upgrading Sector Project
RP Resettlement Plan
SGP Secretariat for Grand Projects
WB World Bank
iii | P a g e
FIRST QUARTER REPORT 2015
INFRASTRUCTURE FUND
CONTENTS
1 INTRODUCTION ....................................................................................................................................... 1
2 GENERAL MANAGEMENT OF THE FUND .................................................................................................. 2
3 PROGRAM REPORT .................................................................................................................................. 4
3.1 BUDGET ALLOCATIONS AND DISBURSEMENTS FOR 2011 TO 2014 AND 2015 ............................................................. 5
4 AGRICULTURE AND FISHERIES ................................................................................................................. 9
4.1 REHABILITATION OF RAIBERE IRRIGATION SYSTEM ................................................................................................ 10
4.2 REHABILITATION OF OEBABA IRRIGATION SYSTEM- PHASE I ................................................................................. 10
4.3 DETAILED DESIGN, CONSTRUCTION AND SUPERVISION OF KARAU-ULUN IRRIGATION SCHEME ...................................... 11
4.4 DETAILED DESIGN AND STUDIES FOR IRRIGATION PROJECT PROPOSALS .................................................................... 12
4.5 CONSTRUCTION AND SUPERVISION OF THE LARISULA IRRIGATION SCHEME................................................................ 13
4.6 CONSTRUCTION AND SUPERVISION OF RAIBERE IRRIGATION SECOND PHASE .............................................................. 14
4.7 CONSTRUCTION AND SUPERVISION OF OEBABA IRRIGATION SECOND PHASE .............................................................. 15
4.8 CONSTRUCTION AND SUPERVISION OF CARAULUN IRRIGATION SECOND PHASE .......................................................... 15
4.9 OTHER IF FUNDING PROJECTS ......................................................................................................................... 16
5 WATER AND SANITATION ...................................................................................................................... 18
5.1 PHASE II OF DILI SANITATION AND DRAINAGE MASTER PLAN (DSDMP) ................................................................ 18
5.2 DILI WATER SUPPLY SYSTEM WITH PPP MODALITY ............................................................................................. 19
5.3 DRAINAGE CLEANING AND REHABILITATION ........................................................................................................ 20
5.4 DILI WATER DISTRIBUTION NETWORK ............................................................................................................... 22
5.5 WATER SUPPLY IN 10 DISTRICT ........................................................................................................................ 22
6 URBAN AND RURAL DEVELOPMENT PROGRAM..................................................................................... 23
6.1 NATIONWIDE SPATIAL PLANNING ..................................................................................................................... 23
iv | P a g e
6.2 LIDAR SURVEY AND SPATIAL MAPPING ............................................................................................................. 24
6.3 DILI URBAN PLANNING ................................................................................................................................... 25
7 ELECTRICITY ........................................................................................................................................... 26
7.1 CONSTRUCTION OF TRANSMISSION LINES OF 150 KV ........................................................................................... 26
7.2 CONSTRUCTION OF 20KV DISTRIBUTION LINES ................................................................................................... 27
7.3 SUB-STATIONS .............................................................................................................................................. 28
7.4 COMORO POWER STATION ............................................................................................................................. 29
7.5 20KV OVERHEAD LINE CONNECTING 150/20KV DILI SUB-STATION WITH 20KV FEEDERS .......................................... 29
7.6 20KV OVERHEAD LINE CONNECTING 150/20KV MALIANA SUBSTATION WITH THE EXISTING 20KV NETWORK IN THE AREA 29
7.7 20KV OVERHEAD LINE CONNECTING TO THE NEW 150/20KV SUAI SUB-STATION WITH 20KV NETWORKS .................... 30
7.8 FUEL SUPPLY LINE FROM HERA LOADING DOCK TO HERA POWER PLANT ................................................................... 30
7.9 HERA POWER STATION ................................................................................................................................... 30
7.10 BETANO POWER STATION .......................................................................................................................... 31
7.11 MEDIUM AND LOW VOLTAGE DISTRIBUTION LINES ......................................................................................... 31
8 ROADS ................................................................................................................................................... 33
8.1 GENERAL ..................................................................................................................................................... 33
8.2 PROJECT STATUS ........................................................................................................................................... 35
8.2.1 Rehabilitation of Baguia – Uatucarbau Road ................................................................................. 35
8.2.2 Rehabilitation of Baguia – Laga Road (6.6 km) .............................................................................. 36
8.2.3 Cassa – Wemassa Road (18 km) ..................................................................................................... 36
8.2.4 Rehabilitation of Ermera – Atsabe Road (15 km)............................................................................ 37
8.2.5 Rehabilitation of Ermera – Hatolia Road (7 km) ............................................................................. 38
8.2.6 Rehabilitation of Maubara – Loes Road (4.35 km) ......................................................................... 39
8.2.7 Rehabilitation of Los Palos – Tutuala Road (10.6 km) .................................................................... 39
8.2.8 Rehabilitation of Los Palos – Iliomar Road (13.6 km) ..................................................................... 39
8.2.9 Rehabilitation of Weleu-Tilomar Road (14 km) .............................................................................. 40
v | P a g e
8.2.10 Rehabilitation of Atauro Vila – Beloi – Macadade / Biqueli Roads ............................................ 41
8.2.11 Rehabilitation of Maubisse-Turiscai Road (20.5 km) ................................................................. 41
8.2.12 Rehabilitation of Ossu-Viqueque Road....................................................................................... 42
8.2.13 Reconstruction of Dili Urban Roads............................................................................................ 42
8.2.14 Rehabilitation of Alto Barique to Natarbora Road ..................................................................... 43
8.2.15 Pothole Repair Nationwide ........................................................................................................ 44
8.2.16 Flood Control .............................................................................................................................. 45
8.2.17 Rehabilitation of Aituto - Same Road ......................................................................................... 46
8.2.18 Rehabilitation of Urban Roads in Same ..................................................................................... 46
8.2.19 Rehabilitation of Luro - Buihomau Road .................................................................................... 46
8.2.20 Rehabilitation of Miabuti Edemumo, Sapatula (Edemumo - Iralere Roads) district in Uatulari
Viqueque 47
8.2.21 Rehabilitation of Aituto - Ainaro Roads (in Book 6: Dare - Ainaro) ............................................ 47
8.2.22 The Construction of Ainaro Villa - Sarai Road (Alternative Road to Jakarta II) .......................... 48
8.2.23 Rehabilitation of Dili Urban Roads Phase II ................................................................................ 48
8.2.24 New Road Projects ..................................................................................................................... 52
9 BRIDGES ................................................................................................................................................ 54
9.1 GENERAL ..................................................................................................................................................... 54
9.2 PROJECT STATUS ........................................................................................................................................... 55
9.2.1 Completed Bridge Projects .............................................................................................................. 55
9.3 ON-GOING BRIDGE PROJECTS .......................................................................................................................... 55
9.3.1 Construction of Dilor Bridge ............................................................................................................ 55
9.3.2 Taroman Bridge .............................................................................................................................. 56
9.3.3 Construction of Comoro I Bridge ..................................................................................................... 57
9.3.4 New Lauala Bridges in Gleno .......................................................................................................... 58
9.3.5 Rehabilitation of New Bridges ........................................................................................................ 58
vi | P a g e
10 PORTS AND AIRPORTS ........................................................................................................................... 59
10.1 PORTS .................................................................................................................................................... 59
10.1.1 Excavation, Dredging, and Rehabilitation of Dili Port ................................................................ 59
10.1.2 Construction and Supervision of Regional Ports Development (Atauro and Carabela) ............. 60
10.1.3 Transaction, Construction and Supervision Port of Tibar (PPP) ................................................. 60
10.1.4 Rehabilitation and Supervision of Com Port ............................................................................... 61
10.1.5 Excavation, Dredging, and Rehabilitation of Hera Naval Port ................................................... 61
10.2 AIRPORTS ................................................................................................................................................ 62
10.2.1 DESIGN CONSTRUCTION AND SUPERVISION OF SUAI AIRPROT ................................................. 63
10.2.2 DESIGN CONSTRUCTION AND SUPERVISION OF DILI AIRPROT .................................................. 65
11 INFORMATICS ........................................................................................................................................ 66
11.1 MINISTRY TRANSPORT AND COMMUNICATION ............................................................................................... 66
11.2 NATIONAL CONNECTIVITY........................................................................................................................... 67
11.3 SATELLITE INTERNET CONNECTIVITY UPGRADE ................................................................................................ 67
11.4 EXTENSION OF PCN II AND NETWORK FIBER OPTIC ......................................................................................... 68
12 PUBLIC BUILDINGS ................................................................................................................................. 69
12.1 PROJECT STATUS ...................................................................................................................................... 70
12.1.1 National Commission for Elections New (CNE) Office ................................................................ 70
12.1.2 National Parliament Building ..................................................................................................... 71
12.1.3 Construction of Residence for the First President of the National Parliament ........................... 71
12.1.4 Civil Service Commission Office Building (CFP) ........................................................................... 71
12.1.5 Public Administration Office ....................................................................................................... 71
12.1.6 New Construction of INAP Office Building .................................................................................. 71
12.1.7 Design, Construction and Supervision of CAC Office .................................................................. 72
12.1.8 Construction of Criminal Investigation Office ............................................................................ 73
12.1.9 Construction of Tribunal Office (STJ, TSAFC, CSM) ..................................................................... 74
vii | P a g e
12.1.10 New Ministry of Justice Office Building ...................................................................................... 74
12.1.11 Construction of Commercial Bank Office Building in Dili ............................................................ 75
12.1.12 Construction of National Development Bank in Dili ................................................................... 76
12.1.13 Construction of Commercial Bank Office Building in Dili ............................................................ 76
12.1.14 Construction of Manleuana Market Phase IV ............................................................................ 76
12.1.15 Construction of Taibesi Commercial Centre ............................................................................... 77
12.1.16 Ministry of Social Solidarity Office ............................................................................................. 77
12.1.17 Construction of Institute for Management of Heavy Equipment Office and Warehouse .......... 78
12.1.18 New Resident of First President of National Parliament ............................................................ 78
12.1.19 Design, Construction and Supervision of New MAF Office Building ........................................... 79
12.1.20 Detail Design for Residence of Official and Office of the President of Republic ......................... 79
12.1.21 Construction of the New MCIE New Office Building ................................................................... 79
12.1.22 Construction of New Markets in Ainaro, Maliana, Loes and Manaturo .................................... 79
12.1.23 Construction of Rest Place in Loes .............................................................................................. 80
12.1.24 Construction and Supervision of Laboratory in Tibar ................................................................. 80
12.1.25 Construction Youth Center ......................................................................................................... 80
13 EDUCATION ........................................................................................................................................... 81
13.1 CONSTRUCTION OF NEW POLO REFERENCE SCHOOLS ...................................................................................... 82
13.2 CONSTRUCTION OF POLYTECHNICS ............................................................................................................... 85
13.3 NEW NATIONAL UNIVERSITY COMPLEX ......................................................................................................... 86
14 HEALTH .................................................................................................................................................. 88
14.1 CONSTRUCTION OF BAUCAU REFERRAL HOSPITAL ........................................................................................... 88
14.2 CONSTRUCTION OF PEDIATRIC BUILDING AT GUIDO VALDERES NATIONAL HOSPITAL .............................................. 89
15 MILLENNIUM DEVELOPMENT GOALS PROGRAM ................................................................................... 91
15.1 GENERAL ................................................................................................................................................ 91
15.2 PROJECT PROGRESS .................................................................................................................................. 92
viii | P a g e
15.3 DISBURSEMENT FOR HOUSING AND FACILITY.................................................................................................. 93
15.4 HOUSING DEVELOPMENT ........................................................................................................................... 93
15.5 FACILITY DEVELOPMENT............................................................................................................................. 94
16 SECURITY AND DEFENCE ........................................................................................................................ 95
16.1 EIGHT DISTRICT HEAD QUARTERS OF PNTL ................................................................................................... 95
16.2 ELEVEN SQUADRONS OF PNTL .................................................................................................................... 96
16.3 FIVE BAIROS OF PNTL ............................................................................................................................... 97
16.4 CONSTRUCTION OF HEAD QUARTER OF PNTL DILI .......................................................................................... 98
16.5 MARITIME POLICE OFFICE BUILDING ............................................................................................................ 98
16.6 HERA BARRACKS....................................................................................................................................... 99
16.7 MILITARY POLICE OFFICE ........................................................................................................................... 99
16.8 CONSTRUCTION OF F-FDTL POSTS ............................................................................................................ 100
16.8.1 F-FDTL Posts in Tiliomar and Tunubibi ..................................................................................... 100
16.8.2 F-FDTL Post in Atauro ............................................................................................................... 101
16.9 CONSTRUCTION OF F-FDTL HEAD QUARTER COMMAND TRAINING CENTRE IN METINARO ................................... 102
16.10 CONSTRUCTION OF NATIONAL DEFENCE INSTITUTION OFFICE BUILDING ............................................................ 102
17 SOCIAL SOLIDARITY ............................................................................................................................. 104
17.1 CONSTRUCTION OF PRESIDENT NICOLAU LOBATO’S MONUMENT ..................................................................... 104
18 TASI MANE .......................................................................................................................................... 106
18.1 BETANO PETROCHEMICAL FACILITIES – DETAILED GEOTECHNICAL AND MARINE SURVEYS ..................................... 107
18.2 DESIGN, CONSTRUCTION AND SUPERVISION OF THE SUAI–BETANO-BEACO HIGHWAY ROADS ............................... 107
18.3 DESIGN, CONSTRUCTION AND SUPERVISION OF SUAI SUPPLY BASE ................................................................... 108
18.4 DETAILED SURVEY FOR LOCAL DEVELOPMENT OF INFRASTRUCTURE OF SOUTHERN COAST IN BEACO ....................... 110
18.5 CONCEPT AND SUPERVISION FOR DEVELOPMENT OF INFRASTRUCTURE – BEAÇO ................................................. 112
18.6 WATER SUPPLY IN DATO RUA TO TOLU....................................................................................................... 112
18.7 URBAN PLANNING IN SUAI ....................................................................................................................... 113
ix | P a g e
19 DESIGN AND SUPERVISION OF NEW PROJECTS .................................................................................... 114
19.1 GENERAL ............................................................................................................................................ 114
19.2 PROJECT STATUS ................................................................................................................................ 114
19.2.1 Detailed Design of Ministry of Commerce, Industry and Environment New Office Building .... 114
19.2.2 Detailed Design of MCIA Training Centre ................................................................................. 114
19.2.3 Detailed Design of New Market of Ainaro Phase I, Maliana and Manatuto Phase II .............. 116
19.2.4 Detailed Design for Ministry of Agriculture and Fisheries New Office Building ....................... 116
19.2.5 Detailed Design for Terminal and Market Loes ........................................................................ 117
19.2.6 DED for Institute for Management of Heavy Equipment Office and Warehouse .................... 117
19.2.7 Detailed Design for Construction of Fishing Port at Metinaro ................................................. 117
19.2.8 Master Plan and Detailed Design for Ecological Protection and Improvement of Tasitolu ..... 118
20 TRANSPORT PROGRAM ....................................................................................................................... 119
20.1 GENERAL .............................................................................................................................................. 119
21 TOURISM SECTOR PROGRAM .............................................................................................................. 119
22 FINANCE SYSTEM AND INFRASTRUCTURE SUPPORT PROGRAM .......................................................... 122
22.1 INFORMATICS SYSTEM.............................................................................................................................. 123
22.1.1 IT Design of New Ministry of Finance Building ......................................................................... 123
22.1.2 ASYCUDA WORLD ..................................................................................................................... 124
22.1.3 SIGTAS ...................................................................................................................................... 124
22.1.4 Free Balance ............................................................................................................................. 124
22.1.5 Interior Design for MoF New Building ...................................................................................... 125
22.1.6 Housing Accommodation for Integrated Border Post Officers in Batugade ............................ 126
22.1.7 Construction of Integrated Border Post in Oesilo and Tunubibi ............................................... 126
22.1.8 Design, Construction and Supervision of Custom and Revenue New Building ......................... 127
23 YOUTH AND SPORT PROGRAM ............................................................................................................ 128
23.1 PROJECT STATUS ..................................................................................................................................... 128
x | P a g e
23.1.1 Design, Construction and Supervision of National Outdoor Sports Stadium ........................... 128
23.1.2 Multi-Function Indoor Sports Facility ....................................................................................... 128
23.1.3 Construction of 4 Football Stadia (Baucau Maliana, Manufahi and Ermera) .......................... 129
24 PUBLIC PRIVATE PARTNERSHIP ............................................................................................................. 132
24.1 TIBAR BAY PORT .................................................................................................................................... 133
24.2 INSTITUTO SUPERIOR OF AILEU .................................................................................................................. 134
24.3 DILI WATER SUPPLY SYSTEM..................................................................................................................... 134
24.4 DIAGNOSTIC SERVICES IN THE HEALTH SECTOR ............................................................................................. 135
24.5 PETROLEUM HOUSE ................................................................................................................................ 135
24.6 ELECTRICITY SECTOR PPP PROJECTS ........................................................................................................... 135
25 LOAN FUNDED PROJECTS ..................................................................................................................... 137
25.1 ADB LOAN: ROAD NETWORK UPGRADING PROJECT-ADB LOAN NOS.2857-TIM AND 2858-TIM (SF) ................ 137
25.1.1 Road rehabilitation and maintenance ..................................................................................... 139
25.1.2 Roads under detailed design .................................................................................................... 141
25.2 ROAD NETWORK UPGRADING SECTOR PROJECT (RNUSP) - ADB LOAN NOS. 3020-TIM AND 3021-TIM ............ 141
25.2.1 Road rehabilitation and maintenance ..................................................................................... 141
25.3 ROADS UNDER DETAILED DESIGN ................................................................................................................ 143
25.4 JICA LOAN: NATIONAL ROAD NO.1 UPGRADING PROJECT-DILI-BAUCAU .......................................................... 143
25.5 ROAD CLIMATE RESILIENCE PROJECT- (WB LOANS) – IDA CREDIT 5303-TL AND IBRD LOAN 8290-TL ................ 144
25.4.1 Lot 1: Halilaran to Laulara Road Section (10 kms) ................................................................... 146
25.4.2 Lot 2: Laulara to Solerema Road Section (22.6 kms) ................................................................ 146
25.4.3 Lot 3: Solerema to Bandudatu Road Section cost (30 kms) ...................................................... 146
25.4.4 Lots 4 (25kms): Bandudatu to Aituto Road Sections ................................................................ 147
25.4.4 Lots 5 (23kms): Aituto to Ainaro Road Sections ....................................................................... 148
25.4.5 Roads under detailed design .................................................................................................... 148
25.6 SAFEGUARDS COMPLIANCE ....................................................................................................................... 148
xi | P a g e
25.6.1 Resettlement Plan .................................................................................................................... 148
25.6.2 Environmental Compliance ...................................................................................................... 149
26 PROJECT PROPOSALS FOR 2016 FINANCING ........................................................................................ 150
26.1 RECEIPT OF PROJECT BRIEFS ..................................................................................................................... 150
26.2 REVIEW OF PROJECT BRIEFS ...................................................................................................................... 150
26.3 CANCELATION OF NEW PROJECT FOR FISCAL YEAR OF 2016 ............................................................................ 151
27 CAFI MEETING ..................................................................................................................................... 152
28 DATABASE & IT UNIT ........................................................................................................................... 153
29 CHALLENGES ........................................................................................................................................ 154
ANNEX 1. MINUTES OF CAFI MEETINGS, END- 2015 ...................................................................................... 156
ANNEX 2. FREE BALANCE REPORT - END- 2015 ............................................................................................. 157
1 | P a g e
1 INTRODUCTION
The Infrastructure Fund (IF) was set up by Law No. 1/2011 on 14 February, 2011 approving
the State Budget (OGE) for 2011. The subsidiary Decree-Law No. 8/2011 of 16 March, 2011
defines the primary objective of establishing the IF, which is to finance the implementation of
sets of infrastructures that require massive investment in multi-year infrastructure projects that
meets the needs of Timor-Leste. It is a financial instrument that enables the financial resources
for capital investment in infrastructure projects requiring multi-year contracts to be ring-
fenced and therefore not restricted or lost to the point of jeopardizing project implementation.
This report summarises general progress made and financial status of the IF programs and
projects during the reporting period enabling CAFI to remain informed, to facilitate decision–
making processes and help ensure that the IF meets its objectives in an effective manner. The
“Matrixes for Implementation and Coordination of the Strategic Development Plans” issued
by line Ministries also presents status report of most IF projects. Information presented in
these reports may overlap in terms of project status.
2 | P a g e
2 GENERAL MANAGEMENT OF THE FUND
To ensure effective implementation of the projects, the Government established the Council
for Administration of the Infrastructure Fund (CAFI), as the executive body with authority
over the decision making process for all matters related to Infrastructure Fund projects and to
provide policy guidance to the executing agencies or line ministries.
Originally, CAFI was comprised of a Chairperson and three permanent Members as follows:
The Prime Minister, Chairperson
The Minister of Finance, Member
The Minister of Public Works, Member
The Minister Transport and Communications, Member
Upon the remodeling of the V Constitutional Government made in February 2015, Council of
Ministry Meeting in March 27, 2015 decided and approved to restructure the chairman and its
permanent members and also basis on the second alteration decree law No. 12/2011 dated 23
March with decree law No. 10/2015 dated 3 June, as follows:
The Prime Minister Planning and Strategic Investment, Chairperson
The Minister of Finance, Member
The Minister of Public Works, Transport and Communications, Member
Other Ministers and State Secretary are requested to attend the CAFI meetings when the
agenda of the meeting is relevant to the responsibilities and activities of their ministries. The
Major Projects Secretariat (MPS) was established to perform the functions as specified in the
workflow process of Infrastructure Fund, as well as providing technical and secretariat support
for the CAFI with close coordination with National Development Agency (A.D.N) and
National Procurement Commission (C.N.A). In particular, the roles of MPS in addition to
facilitating CAFI meetings are to carry out the preliminary evaluation of all major project
proposals and provide recommendations on project viability as well as financing options to
CAFI and execution of payments based on the recommendation from A.D.N, that include
raising CPVs, POs and PRs. Staffing of the Major Projects Secretariat is based on the annual
Business Plans for MPS.
Field inspection of projects funded from the IF is carried out by the National Development
Agency (ADN) which is assigned responsibility for ensuring that projects are implemented
according to approved specifications. Accordingly, ADN raises recommendations on the
payment of invoices prior to submission to MPS for final review and presentation to Treasury
for settlement. ADN is also responsible for reviewing Design and Studies, Drawings and Bills
of Quantities (BoQ) and for final review of tender documents before submission to the
National Procurement Commission (NPC) which executes the procurement process for works
contractors and service providers. The Line Ministries and Agencies, being owners of the
projects, are responsible for identifying projects, presenting project briefs to CAFI,
preparation of project documents for tendering, signing contract agreements, issuing notices to
3 | P a g e
proceed, monitoring the day-to-day implementation and management of the projects,
approving project progress and/or final reports and raising certifications for payments.
The National Procurement Commission (NPC) handles the procurement of contractors and
supervision consultants for the implementation of projects in the IF portfolio.
4 | P a g e
3 PROGRAM REPORT
The Infrastructure Fund is the Government vehicle for financing carefully, transparently and
efficiently investments in major public infrastructure projects requiring multi-year contracts
exceeding a value of $1 million. Such investments are essential to a well-functioning
economy, will reduce capacity constraints and will assist in facilitating a more productive
economy, stimulate domestic market integration and promote economic growth in the medium
to long term future.
Infrastructure development has two stages, each with multiple sub-stages. The First stage
encompasses definition and location of the project, planning, design/studies/feasibility/impact
studies and the physical construction. The Second stage refers to the management and
oversight of the infrastructure, including operation, maintenance and collection of user fees, if
any. The role of the IF is confined to the first of the above two stages.
Currently the Infrastructure Fund covers 22 Development Programs:
1. Agriculture and Fisheries Program
2. Water and Sanitation Program
3. Urban and Rural Development Program
4. Electricity Program
5. Roads Program
6. Bridges Program
7. Airports Program
8. Ports Program
9. Informatics Program
10. Public Buildings Program
11. Education Program
12. Health Program
13. Millennium Development Goals Program
14. Security and Defence Program
15. Social Solidarity Program
16. Tasi Mane Program
17. Design and Supervision of New IF Projects
18. Program Purchase of New Ship
19. Program for Tourism
20. Finance System and Infrastructure Support Program
21. Program for Youth and Sports
22. External Loans
Following a brief review of progress prior to the reporting period, accomplishments and issues
during the first quarter of 2015 are detailed hereunder.
5 | P a g e
3.1 BUDGET ALLOCATIONS AND DISBURSEMENTS FOR 2011 TO 2014 AND
2015
In 2011, a total of US$599.3 million was allocated for disbursement in 2011. Of this
total, US$474.4 million was successfully disbursed representing 79.2 % of the total budget.
In the following fiscal year, the Government allocated US$800.3 million to the Fund,
including US$43.1 million outsourced from external loans. By adding the 2011 leftover
budget of US$124.9 million, the total budget of 2012 was adjusted to US$925.1 million. Of
this, US$50 million was subsequently re-allocated to the Consolidated Fund of Timor-Leste
(CFTL) through budget rectification which reduced the available 2012 budget to US$875.1
million. In terms of execution, as of December 2012, US$372.4 million dollars or 43% of the
IF budget was disbursed (Free Balance Report, December 2012) leaving an estimated US$
502.7 million to be carried forward to 2013.
As for the 2013 fiscal year, the Government approved an allocation of US$ 604.4 million for
Infrastructure Fund programs inclusive of US$ 43.6 million of external loans. This comprised
the balance of US$ 444.4 million as estimated at budget preparation to be carried over to
the2013 budget plus new additional appropriation of US$ 160.0 million (including a small
provision for design and supervision of new projects). The actual final amount undisbursed in
2012, following settlement of payments and audit report publication, amounted to US$ 499.0
million which, with the additional appropriation gave total available funds in 2013 of US$
659.1 million.
As for the 2014 fiscal year, the government allocated a total budget of US$368.6 million
including US$ 31 million sourced from external loans. At the end of 2014 fiscal year, the total
amount disbursed was US$ 330 million or 90% of the allocated fund including loan or 96% of
the budget excluding loan. No rollover on IF but rollover occurred US$ 11 million on External
Loan-Funded Projects.
For Fiscal Year 2015, the approved allocated a total budget was amounted to US$ 367.301
million including US$ 70 million sourced from external loans. The allocation budget was
rectified to US$ 317.301 million as $50 millions were transferred to ZEEMS Program in
during the budget rectification made in the late March 2015. By 30 June 2015, the total
amount disbursed was amounted to US$ 44.093 million from total budget including loan or
14% execution rate. The disbursement of IF budget excluding loan alone, was amounted to
US$ 36.601 millions or 15% execution rate.
6 | P a g e
Table 3.1 Summary of Budget Allocations and Expenditures as of 31 March 2015
No. Projects
2015
Approval
Budget
2015
Revised
Budget
Disbursement
as of 30 June
2015
Rate of
Execution
$'000 $'000 $'000 %
Total for Programs (Include Loans) 367,301.10 317,301.32 44,093.7 14
Total for Programs (Exclude Loans) 297,301.10 247,301.32 36,501.00 15
1 Program for Agriculture and Fishery 7,235.66 11,702.89 4,137.77 0.00
2 Program for Water and Sanitation 5,598.44 3,598.44 167.72 0.00
3 Program for Urban and Rural
Development 9,594.88 7,194.88 4,025.35 0.00
4 Program for Public Buildings 13,713.20 8,712.99 102.00 0.00
5 Program for Education 7,961.99 5,894.75 968.01 2.65
6 Program for Electricity 57,128.40 47,128.40 13,242.00 0.00
7 Program for Informatics 1,400.00 1,400.00 0.00 0.00
8 Program for Millennium Development
Goals 8,500.00 5,000.00 0.00 0.00
9 Program for Health 3,996.00 4,380.00 522.00 0.00
10 Program for Security and Defense 11,045.55 10,601.31 577.83 0.06
11 Program for Social Solidarity 0.00 0.00 0.00 0.00
12 Program for Tasi Mane 35,080.77 35,080.77 0.00 0.00
13 Program for Airports 19,000.00 14,000.00 3.471.42 0.00
14 Preparation of Design and Supervision
of New Projects Program 8,189.43 7,189.43 199.00 0.00
15 Program for Roads 54,800.03 50,010.03 5,440.00 3.99
16 Program for Bridges 11,317.00 6,107.00 1,172.48 0.00
17 Program for Ports 7,854.56 3,855.00 249.43 0.00
18 Program for Tourism 1,000.00 3,560.24 0.00 0.00
19 Program for Finance System and
Infrastructure Support 19,135.20 19,135.20 1,074.00 2.70
20 Program for Youth and Sports 2,750.00 2,750.00 0.00 0.00
21 Program for Transport 12,000.00 0.00 0.00 0.00
22 External Loan-Funded Projects 70,0000.00 70,0000.00 7,592.7 11.00
Table 3.1 shows the performance of each program based on Free Balance record as of 30 June
2015. It can be seen that disbursements have occurred in 17 programs including external loan
payments, while the remaining 7 programmes has no execution made up to the end of this
quarter.
A graphical representation of the above matrix is shown in Figure 3.1 to easily grasp the trend
of allocation budget and disbursement of IF funds as of 30 June 2015.
Figure 3.1 – Graphical Representation showing budget allocation and Performance of Each
Program in 2015
7 | P a g e
Various factors contributing to the low execution rate, including, the government remodelling
in the early 2015, where the progress (physical and payment) was delayed due to restructuring
the relevant agencies in the IF project management.
As for physical progress, there were projects constrained by a number of factors, namely:
Late approval of the budget for the year and the processing time in the Freebalance
system. The system was closed due to restructure and 2015 rectification.
The procurement process was slow down due to inadequate budget allocation, Audit
Court Endorsement and wait budget rectification.
Inadequate pre-construction works planning and scheduling including right of way
and/or property acquisition processes and mobilisation of equipment and construction
materials.
Inadequate method for the selection of appropriate location of projects and its
accessibility.
Insufficient budget allocation as a result of miscalculated Bill of Quantities and/or
oversight in the design of the structures, and/or due to other critical factors.
-
10.000,00
20.000,00
30.000,00
40.000,00
50.000,00
60.000,00
70.000,00
80.000,00
Pro
gram
fo
r A
gric
ult
ure
…
Pro
gram
fo
r W
ater
an
d …
Pro
gram
fo
r U
rban
an
d …
Pro
gram
fo
r P
ub
lic B
uild
ings
Pro
gram
fo
r Ed
uca
tio
n
Pro
gram
fo
r El
ectr
icit
y
Pro
gram
fo
r In
form
atic
s
Pro
gram
fo
r M
illen
niu
m …
Pro
gram
fo
r H
ealt
h
Pro
gram
fo
r Se
curi
ty a
nd
…
Pro
gram
fo
r So
cial
So
lidar
ity
Pro
gram
fo
r Ta
si M
ane
Pro
gram
fo
r A
irp
ort
s
Pre
par
atio
n o
f D
esig
n a
nd
…
Pro
gram
fo
r R
oad
s
Pro
gram
fo
r B
rid
ges
Pro
gram
fo
r Po
rts
Pro
gram
fo
r To
uri
sm
Pro
gram
fo
r Yo
uth
an
d …
Pro
gram
fo
r Tr
ansp
ort
Exte
rnal
Lo
an-F
un
de
d …
Revised Allocation Budget Rate of Execution - 30 June 2015
8 | P a g e
Lack of experienced and committed technical staff as well as skilled labourers to
perform the work and services according to the specifications and technical
requirements.
Inadequate works supervision and management by supervision engineers and project
managers. Equally important is to ensure that monitoring work must always be
performed by capable engineers to ensure that the materials and works carried out are
in accordance with the specifications stipulated in the contract and design standards.
Implementation of legal regime requiring Contract endorsement by the Audit Court
prior to implementation.
In some locations, heavy rain hampers project execution progress particularly during
this quarter report.
These challenges that bear the risks of unsatisfactory performance, low quality of works and
delay in the completion schedule have been critically evaluated by the CAFI and resolutions
passed to address and improve the situation. These have included opportunities for companies
to revise the contract completion dates for projects, subject to the following conditions:
Failure of the companies to complete the project as per new timeline will result to their
suspension from participation in any procurement process held by the GoTL by one to
two years.
The company must improve their management system and increase the construction
workforce to accelerate work progress;
Improved supervision and progress monitoring by Technical Teams formed from ADN,
MPW and Project Owners.
The above requires assurances that project owners employ suitably qualified staff and
consultants for project preparation and supervision until and unless internal capacity is
available to ensure that projects can be implemented satisfactorily in accordance with
technical specifications and other contractual conditions. Similar enhancement of human
resource capability is also required of the private sectors contractors and supervision engineers
to raise the quality of project delivery.
9 | P a g e
4 AGRICULTURE AND FISHERIES
Agriculture is a strategic sector for future economic growth with some 63% of households in
Timor-Leste being engaged in this sector. Public investment in the rehabilitation and
expansion of existing irrigation schemes are regarded by the Ministry of Agriculture and
Fisheries (MAP) as a key component for resuscitation of the sector and achieve targets of self-
sufficiency in staple food crops, principally rice and maize. 2015 budget allocation and
payments made in 2015 are presented in Table 4.1.
Table 4.1.: 2015 budget allocation and disbursement status
Projects
Original
Budget
Allocation
2015
('$000)
Revised
Budget
Allocatio
n 2015
('$000)
Expenditure
as of the 30
June 2015
($000)
Balance
2015
Budget
($000)
Remarks
Construction and supervision of the
Raibere irrigation scheme
151 151 - 151 Retention will
pay in 2015
Construction and supervision of the
Oebaba irrigation scheme
850 850 850 Retention will
pay in 2015
Construction and supervision of the
Caraulun irrigation Scheme
- - - - Retention will
pay in 2015
Construction and supervision of the
Larisula irrigation scheme
1,750 1,750 50.00
1,700.0
In progres
Studies for Detailed Design and
construction of irrigation
500 500 84.30 415.70
In progres
Construction and supervision of the
irrigation Raibere Scheme phase II
1,485 1,485 817.47 667.53
In progres
Construction and supervision of the
Oebaba irrigation Scheme phase II
1,500 5,967 3,186 2,781
In progres
Construction and supervision of the
Carau-ulun irrigation Scheme phase II
1,000 1,000 - 1,000
In progres
Concept and Design, Construction and
Supervision of Fishing Port, Metinaro
- - - - Study and design
progressing
Construction and supervision of
irrigation Maukola
- - - - Need TOR for
DED
Construction and supervision of
irrigation Beikala
- - - - Need TOR for
DED
Construction of Irrigation Buluto - - - - Funded by JICA
Construction and supervision of
irrigation Galata
- - - - Need TOR for
DED
Construction and supervision of
irrigation Dardau
- - - - Need TOR for
DED
Total 7,236 11,703 4,138 7,565
Source: MPS and Free Balance, 31 June 2015
On the establishment of the Infrastructure Fund, a number of projects were proposed. While
some projects were already completed, others are still on-going, namely:
Construction and Supervision of the Raibere Irrigation Scheme.
Construction and Supervision of the Oebaba Irrigation Scheme
10 | P a g e
Construction and Supervision of the Caraulun Irrigation Scheme
Construction and Supervision of the Larisula Irrigation Scheme
Construction and Supervision of the Raibere Irrigation Scheme Phase II.
Construction and Supervision of the Oebaba Irrigation Scheme Phase II.
Construction and Supervision of the Caraulun Irrigation Scheme Phase II
Detailed Design of Rehabilitation of Ten Irrigation Schemes and 15 Dam locations
Further development of the Raibere, Oebaba and Caraulun Irrigation Phase II, CAFI meeting
dated 22 August 2014 approved renewal of contracts to the current contractors of Raibere,
Oebaba and Caraulun Irrigation Scheme to carry out second phase of the project. CAFI also
approved payment for revised design of the rehabilitation of Raibere, Oebaba and Caraulun
Irrigation Phase II by PT Fajar Nusantara recommended by MAF at US$ 385,856.43.
Table 4.2: Rehabilitation of Raibere Irrigation Scheme Project
PROJECT SUMMARY
Company Name PT Brantas Abipraya
(Persero) Tbk
Cipta Wahana
Nusantara Unip. Lda
Contract Signing Date 3-May-2013 30-Apr-2013
Commencement Date 27-Jun-2013
Original Completion Date 10-Nov-2014
Audit Court Endorsement Date 25-Jun-2013 20-Jun-2013
Issue Notice to Proceed Date 27-Jun-2013 27-Jun-2013
Actual Completion Date 27-Oct-2014 27-Oct-2014
Original Contract Value 2,163,478.26 807,012.00
Contract Amendment
Final Contract Value 2,163,478.26 807,012.00
Physical progress till quarter end % 100 100
Payment Schedules
2013 IF payments ($) 194,713.04 248,187.00
2014 IF payments ($) 1,752,417.39 502,719.00
2015 IF payments ($) - -
Total paid 1,947,130.43 750,906.00
Balance to be paid 216,347.83 56,106.00
Source: MPS and Free Balance, 30 June 2015
4.1 REHABILITATION OF RAIBERE IRRIGATION SYSTEM
Raibere Irrigation System is located in Hatu’udo, Ainaro with the total beneficial area of 225
hectares. The rehabilitation of this irrigation scheme started in June 2013 and has reached
100% completion of its physical progress in October 2014. The project is in the defect liability
period that will end by this year. US$ 0.151 million was allocated for 2015 to cover the
expected retention payment. The defect liability period (DLP) will complete in October 2015.
Detail of contract presented in table 4.2.
4.2 REHABILITATION OF OEBABA IRRIGATION SYSTEM- PHASE I
The Oebaba irrigation scheme covers two sucos, Raimea and Mape at Zumulai Sub-district,
Covalima District. The total potential beneficial area is approximately 2200 Ha but only about
11 | P a g e
523 Ha is utilized for growing rice. The preparation of Detailed Engineering Design and
Supervision of construction were undertaken by PT Cipta Wahana Nusantara, while the first
phase of construction works was implemented by KSC Construction Co., Ltd from South
Korea.
Flushing and Regulating Canopy Gates at Right side
Weir of Oebaba Downstream Right side Area
The rehabilitation of Oebaba irrigation scheme was commenced in June 2013 and physical
works 100% completed in October 2014 with the 90% of total contract price was paid to the
company. The phase I of the project is in the DLP and expected to be ended by this year.
CAFI approved allocated US$ 0.85 million for 2015. Detail of contract are summarised in
table 4.3.
Table 4.3: Detail of Rehabilitation Oebaba Irrigation Project
PROJECT SUMMARY
Company Name Ksc Construction Co. Ltd
(Korea)
Cipta Wahana
Nusantara Unip. Lda
Contract Signing Date 3-Mar-2013 30-Apr-2013
Commencement Date 27-Jun-2013
Original Completion Date 10-Mar-2015
Audit Court Endorsement Date 25-Jun-2013 20-Jun-2013
Issue Notice to Proceed Date 10-Jul-2013 27-Jun-2013
Actual Completion Date 20-Oct-14
Original Contract Value 6,503,269.40
Contract Amendment
Final Contract Value 6,503,269.40 -
Physical progress till quarter end % 100
Payment Schedules
2013 IF payments ($) 2,001,958.78
2014 IF payments ($) 3,850,983.68
2015 IF payments ($) - 0
Total paid 5,852,942.46 0
Balance to be paid 650,326.94 -
Source: MPS and Free Balance, 30 June 2015
4.3 DETAILED DESIGN, CONSTRUCTION AND SUPERVISION OF KARAU-ULUN
IRRIGATION SCHEME
The Karau-Ulun Irrigation Scheme is located in Betano, Manufahi District with the potential
irrigated area of 1,303 ha. Studies and preparation of Detailed Engineering Design were
carried out by SNC Lavalin Consultant in 2012. The same company has supervised the
12 | P a g e
construction works that was awarded to Romante Pty. Ltd. on 3 May 2013. The rehabilitation
of Caraulun irrigation scheme has commenced in July 2013. The project in the DLP and
retention payment will be released by this year but no budget allocation for 2015. The
additional budget for these payments has proposed by MAF to CAFI. Details contract and
payment are shown in table 4.4.
Table 4.4.: Construction and Supervision Carau-ulun Irrigation Project
PROJECT SUMMARY
Company Name Romante Pty Ltd PT SNC Lavalin Consultant
Contract Signing Date 3-May-2013 Mar-2013
Commencement Date Jul-13
Original Completion Date Jul-13
Audit Court Endorsement Date 1-Jul-2013
Issue Notice to Proceed Date Jul-13
Actual Completion Date 25-Sep-2014 25-Sep-2014
Original Contract Value 2,163,948.02 219,967.00
Contract Amendment
Final Contract Value 2,163,948.02 219,967.00
Physical progress till quarter end % 100 100
Payment Schedules
2013 IF payments ($) 779,186.21 60,976.07
2014 IF payments ($) 1,168,367.01 158,990.93
2015 IF payments ($) 0 0
Total paid 1,947,553.22 219,967.00
Balance to be paid 216,394.80 -
Source: Free balance report, 30 June 2015
4.4 DETAILED DESIGN AND STUDIES FOR IRRIGATION PROJECT PROPOSALS
Timor-Leste receives enough rainfall in the wet season to grow crops, but has little capacity to
store and manage water supplies throughout the dry season to support food production. Better
water management is a high priority for Timor-Leste, which relies heavily on food imports as
it struggles to grow sufficient product for its people. The MAF has proposed funding through
the IF funds to carry out the technical studies of 34 potential sites for new or rehabilitation of
existing irrigation schemes. CAFI approved the amount of US$1 million in 2012 for the
feasibility study of smaller existing schemes. The contract was awarded to PT SNC Lavalin –
TPS and signed on 25 August 2013 for the feasibility study of 10 irrigation schemes, potential
dam sites in 15 river basins that include the actual studies and survey works. Following, notice
to proceed issued on 27 Aug 2013 and 10% payment was made to company.
When the services reached 15%, MAF found that the company did not provide the services
required, therefore MAF then cancelled the contract and concurred by CAFI on 16 June 2014.
The National Procurement Commission performed the negotiation with the second bidder as
per approval of CAFI on 9 October 2014. NPC completed contract negotiation with second
bidder on 16 January 2015 with total contract amount of US$ 0.887 million. The contract for
remain scope of works signed by MAF and Consultant Salu Corporation Unipesoal Lda joint
venture with PT. Inacon Luhur Pertiwi and Sinotech Engineering Consultant Ltd on January
13 | P a g e
20, 2015 and intend to be completed within 9 months . To finalise project studies and design,
CAFI has approved US$ 0.5 million for 2015. Total disbursement in this reporting was ten
percent (10%) of the contract amount.
4.5 CONSTRUCTION AND SUPERVISION OF THE LARISULA IRRIGATION
SCHEME
The principal objective of this project is to provide better irrigation facilities and protect the
387 hectares of paddy fields from destructive flooding during periods of torrential rain. As of
end-2014, procurement of contractors for the construction and supervision of Larisula
Irrigation Project were carried out. The design for the project has been completed in 2011,
prior to tender in 2014, CAFI meeting dated 22 August 2014 has approved payment revised
design of the Larisula and Tono irrigation scheme recommended by MAF at US$ 0.129
million. Payment for revised design at US$ 0.128 million paid in November 2014. The
contract for Samhan Construction Co., Ltd. in Joint Venture with Samhee Construction Co.
Ltd. has been endorsed by Audit Court late October 2014, while supervision works was
awarded to Salu Coporation Unipessoal Lda in joint venture with Sinotect Engineering
Consultant Ltd and PT Inacon Luhur.
The allocation budget for 2015 is US$ 1.75 million, while the project is in the stage of
mobilization and preliminary works and total disbursement in this reporting period only
US$0.05 million. Project details are shown in the table 4.6.
Table 4.6: Construction and Supervision Larisula Raibere Irrigation Scheme Project
PROJECT SUMMARY
Status Construction and supervision works is progressing
Company Name
Samhan Construction Co.
Ltd. in JV with Samhee
Construction Co. Ltd.
Salu Coporation Unipessoal Lda in
JV with Sinotect Engineering
Consultant Ltd and PT Inacon Luhur
Contract Signing Date 3-October-2014 21-October-2014
Commencement Date
Original Completion Date
Contract duration 540 days 18 months
Audit Court Endorsement Date October 2014
Issue Notice to Proceed Date
Actual Completion Date
Original Contract Value 5,952,980.05 626,201.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 5,952,980.05 626,201.00
Physical progress till quarter end % 12.60 12.60
Payment Schedules
2014 IF payments ($) 1,190,596.01 0
2015 IF payments ($) 0 49,992.70
Total paid 1,190,596.01 49,992.70
Balance to be paid 4,762,384.04 576,208.30
Source: Free balance report, 30 June 2015
14 | P a g e
4.6 CONSTRUCTION AND SUPERVISION OF RAIBERE IRRIGATION SECOND
PHASE
The second phase of the Rehabilitation of the Raibere irrigation scheme which covers the
scope of works that were not included in the previous contract (phase I)Therefore, CAFI
meeting dated 22 August 2014 approved renewal contract of PT BRANTAS ABIPRAYA
(Persero) Tbk to continued phase II of the projects. NPC then finalised the procurement
process and contract signed on 20 of January 2015 with total contract prices of US$ 1.3
million, and intended to be completed for 365 days.
The scope of second phase consists of: preparatory works, 70 m retaining wall to protect
sediment trap, 100 m retaining wall left downstream two sites, structure works, and canal
works. For the execution of the second phase CAFI has approved and allocated US$ 1.5
million for 2015. While, for the consultant supervision MAF has recommended PT Fajar
Nusantara who has revised design for second to supervise rehabilitation of the Raibere,
Oebaba and Caraulun irrigation second phase to CAFI.
CAFI meeting held on 13 April 2015 approved the proposal from MAF to appoint PT. Fajar
Nusantara to be the consultant supervision for the third project, which need the verification
from ADN prior to the issuance of contract by NPC that will be sgined by MAF. MAF
informed that 71.26% has been completed. Contract detailed as shown in table 4.7.
Table 4.7.: Rehabilitation of Raibere Irrigation Scheme Second Phase Project
PROJECT SUMMARY
Status Construction and supervision works is progressing
Company Name PT Brantas Abipraya
(Persero) Tbk PT Fajar Nusantara
Contract Signing Date 20-Jan-2015
Commencement Date
Original Completion Date 365 days
Audit Court Endorsement Date N/A
Issue Notice to Proceed Date
Actual Completion date
Original Contract Value 1,274,702.52
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 1,274,702.52 -
Physical progress till quarter end % 71.26 0
Payment Schedules
2014 IF payments ($)
2015 IF payments ($) 817,467.15 0
Total paid 817,467.15 -
Balance to be paid 457,235.37 -
Source: Free balance report, 30 June 2015
15 | P a g e
4.7 CONSTRUCTION AND SUPERVISION OF OEBABA IRRIGATION SECOND
PHASE
The phase II of the Rehabilitation of the Oebaba irrigation scheme covers the scope of works
that were not included in the previous contract (Phase I). Therefore, CAFI meeting dated 22
August 2014 approved renewal contract of KSC CONSTRUCTION CO., LTD (KOREA) to
continued phase II of the projects. On 11 November 2014, the Council of Ministers approved
KSC CONSTRUCTION CO., LTD (KOREA) to pursue construction of the second phase of
Obaba Irrigation which uses better technology ensuring the security of canals and its
suitability. NPC has finalised the procurement process and contract for second phase early
February 2015. NPC submitted contract documents to Audit Court in February 2015 for ver
preliminary review and endorsement. However the endorsement was suspended due to budget
shortage in the budget book 6 2015, which required further mitigation in the CAFI meeting.
In respond to the Audit Court queried, CAFI meeting on 13 and 24 April 2015 approved
additional budget US$ 4,467,235. The approved additional budget was transferred from
Water and Sanitation’s program US$ 1 million, Urban and Rural Development’s program US$
2.4 million, Education’s program US$ 1,067,232.60 and MDG US$ 1.5 million to
Construction and Supervision of Oebaba Irrigation scheme second phase. The revised
allocated budget for 2015 was US$ 1.5 million and increased to 5.967 million. As result, Audit
Court provided their endorsement on 28 April 2015.
The contract amount for second phase was
set to US$ 5,775,218.24, as per contract
US$ 5,179,696.42 to be paid in 2015, and
remain will release in 2016. The physical
progress is 62% completed and expected
to be completed in third quarter
report.Details of contract is summarised in
the table 4.8.
Concrete Canal & Bridge Structure of Main Canal at Left and
Rigth side
4.8 CONSTRUCTION AND SUPERVISION OF CARAULUN IRRIGATION SECOND
PHASE
The continuation from the previous development of the Rehabilitation of the Caraulun
irrigation scheme, the phase II is proposed to cover the scope of works that did not included in
the phase I contract. The CAFI meeting dated 22 August 2014 approved renewal contract of
ROMANTE PTY LTD to continued phase II of the projects. NPC then finalised the
procurement process and contract signed on 20 of January 2015 with total contract prices of
US$ 3.1 million.
The scope of work for the second phase consists of: preparatory works, 70 m retaining wall to
protect sediment trap, concrete block on stilling basing, and 300 m retaining wall to left
downstream, 300 m retaining wall at Caraulun River, structure works, and canal works. For
the execution of the second phase CAFI has approved and allocated US$ 1 million for 2015.
16 | P a g e
The physical progress has been reached 63% in the field but no disbursement in this quarter
report due payment still under verification of the project owner, details of contract as shown in
the table 4.9.
4.9 OTHER IF FUNDING PROJECTS
Detailed Design for New Construction of Fishing Port in Suco Duyung, Metinaro Sub
District, Dili District. The tender for Study and Detailed Engineering Design was
completed and the contract has been signed by the company (Consulmar – Projectistas
e Consultores, Lda Portugal and Engipro, Timor Leste Joint Venture) and MoAF on 9
July 2014 in the amount of US$ 273,270.7. The amount US$ 109,308.28 from this
contract has been paid to the company in November 2014. The studies and designs are
progressing and MoAF is preparing additional terms of reference for Market and
Socio-economic Studies to be part of the contract. The contractor has completed the
inception report, master plan and concept design. As there is limitation of data, the
Detailed Engineering Design and restructuring Government the Consultant is
improving detail engineering design which plan to be present to New Minister. The
study and design are expected to be completed in the fiscal year of 2015. While there
has been a shortage of budget for this project contract under budget code 8090501,
MAF inform to utilise other budget of MAF project to be cover remain balance of
payment.
Detailed Design and Studies for the Construction of New Office Building for the
Ministry of Agriculture and Fisheries
As of end-2014, the Detailed Engineering Design and Bid Documents for the
Construction of Ministry of Agriculture and Fisheries Building had been completed by
PT BITA ERNACO Consultant from Indonesia and US$ 495,300 of the contract
amount has paid to the company. MAF are planning to carry out construction tender
this year.
17 | P a g e
Table 4.8.: Rehabilitation of Oebaba Irrigation Scheme Second Phase Project
PROJECT SUMMARY
Status Construction and supervision works is progressing
Company Name Ksc Construction Co. Ltd (Korea) PT Fajar Nusantara
Contract Signing Date 12 February 2015
Commencement Date
Original Completion Date 12 February 2016
Audit Court Endorsement Date 28 April 2015
Issue Notice to Proceed Date
Actual Completion date
Original Contract Value 5,755,218.24
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 5,755,218.24 -
Physical progress till quarter end % 62 0
Payment Schedules
2014 IF payments ($)
2015 IF payments ($) 3,185,794.41 0
Total paid 3,185,794.41 -
Balance to be paid 2,569,423.83 -
Source: Free balance report, 30 June 2015
Table 4.9.: Rehabilitation of Caraulun Irrigation Scheme Second Phase Project
PROJECT SUMMARY
Status Construction and supervision works is progressing
Company Name Romante Pty Ltd PT Fajar Nusantara
Contract Signing Date 20 January 2015
Commencement Date
Original Completion Date 20 January 2016
Audit Court Endorsement Date N/A
Issue Notice to Proceed Date
Actual Completion date
Original Contract Value 3,078,105.66
Contract Amendment
a. Amendment 1 (Cost / Duration)
Final Contract Value 3,078,105.66 -
Physical progress till quarter end % 63 0
Payment Schedules
2014 IF payments ($) - -
2015 IF payments ($) - -
Total paid - -
Balance to be paid 3,078,105.66 -
Source: Free balance report, 30 June 2015
18 | P a g e
5 WATER AND SANITATION
Total allocated fund for water and sanitation program in 2015 was orinally amounted to US$
5.598 Million. However, during the rectification made in Macrh 2015, the allocated budget
was reduced to US$ 3.598 million, which was allocated into sub-programs as shown table 5.1
below:
Table 5.1: Summary of Budget Execution for Water and Sanitation
Project
2015
Budget
$'000
2015 Revised
Budget $'000
Disbursement,
30 June 2015
$'000
Balance
$'000
Construction/Rehabilitation and Supervision of
Drainage-Master Plan of Dili Drainage and Sanitation
1,715
1,215 0 1,215
Water Supply in 10 Districts 1,500 500 0 500
PPP of Dili water supply 250 250 0 250
Study, Design, and Construction of Dili water
Distribution zone 2-9 and Suai
470 470 0 470
Dili Drainage Rehabilitation 1,163 500 0 500
Construction of Dili Drainage (L-CF) 500 663 168 495
Total 5,598 3,598 168 3,430
Source: MPS and Free Balance, 30 June 2015
Status of each subprogram is narrated as follows:
5.1 PHASE II OF DILI SANITATION AND DRAINAGE MASTER PLAN (DSDMP)
Initial works for Phase 2 is being undertaken by Agua de Portugal (AdP) as selected by MPW
and approved by Prime Minister on December 23, 2013. Amount of contract is US$ 2,383,800
which covers Detail Engineering Design of selected drainage system, a pilot project on
sanitation improvement scheme, training and capacity building of National Directorate of
Basic Sanitation Services (DNSSB), and ground data collection via LiDAR.
The DNSSB proposed to additional scope of works which is not included in the previous
scope of the Dili drainage contract with the consultant of AdP. The additional scope of study
area covered bridges along Kuluhun River (5 bridges), drainage channel interceptor at hill
side, and main drainage canal at Dili airport. The cost additional works is USD 483,750 which
has been reviewed and approved by ADN. The proposal has presented to CAFI meeting on 13
April 2015 and approved. The amendment contract is under preparation of the project owner.
The AdP contract expected to be completed this year. To finalise design and study as well as
some construction works, government has allocated US$ 1.72 million for 2015. Due to
inadequate budget of the other infrastructure fund program, consequently US$ 0.5 million of
this budget line was transferred and remain US$ 1,215 million. Details of the contract are
shown in the table 5.2.
19 | P a g e
Table 5.2: Phase II of Dili Sanitation and Drainage Master Plan Project
PROJECT SUMMARY
Status Study and Design is progressing
Project Name Construction/Rehabilitation and Supervision of Drainage-Master Plan
of Dili Drainage and Sanitation
Company Name AdP Timor Leste
Contract Signing Date 7-Mar-14
Commencement Date 24-Mar-14
Original Completion Date 24 September 2014
Audit Court Endorsement Date
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 2,384.800
Contract Amendment 0.00
a. Amendment 1 (Cost/Duration) Payment structure
b. Amendment 2 (Cost/Duration) Duration up to January 31, 2015
Final Contract Value 2,384.800
Physical progress till quarter end % 75%
Payment Schedules
2014 IF Payments ($) 1,788,600
2015 IF Payments ($) -
Total Paid 1,788,600
Balance to be Paid 596,.200
Source: Free balance report, 30 June 2015
5.2 DILI WATER SUPPLY SYSTEM WITH PPP MODALITY
The allocated budget of 2015 for Dili Water Supply System was US$ 0.25 million. The project
is on-going with the feasibility study is being carried out by EGIS international consultant
with joint venture with EGIS Indonesia and Lelo Engineering consultant (local). The total
contract was roughly $0.5 million and study will conclude in 2015. The result of the study
will present to CAFI for finance option and execute through PPP modality or not.
Table 5.3: Dili Drainage Cleaning and Rehabilitation Project as per CAFI Decision on Nov 13-14,
2013
Company
Project = Dili
Drainage
(EGOSTO)
Contract
Value
($000)
Disbursement
up to end
2014 ($000)
Budget
2015
($000)
Disbursement
up to end
June 2015
($000)
Total
payment
of this
project
($000)
Payment
progress
Caileba
Unip Lda
Emergency
Installation of Box
Culvert Along
Caicoli, Villa Verde
180,470.87 165,527.11
663,000
1,462.89
166,990.
00
91.72%
Dhalelan
Unip Lda
Emergency
Construction of
New Drainages
Along Osindo Area
in Hudi Laran
222,890.78 210,863.05 0
210,863.
05
94.60%
Lesi Unip
Lda
Cleaning and
Clearing of Canals
and Drainage
76,892.86 76,892.86 0 76,892.8
6 100.00%
20 | P a g e
Sediments in the
Area of Bairo-Pite,
Perunas, Aimutin,
Fatuhada, Kampung
Alor, Lanud and
Pantain Kelapa
Lomolo
Unip Lda
Emergency
Cleanning, Clearing
of Enclosed Drain
Along Dili
64,319.23 64,319.23 17,700.62
17,700.6
2
100.00%
Liberta
Unip Lda
Re-instala Kanu
Distribusaun no
Retikulasaun -
Bundaran-Mercado
lama, Audian-
Kuluhun, ho Husi
381,000.82 306,000
-
306,000.
00
80.31%
Table 5:4 Dili Drainage Cleaning and Rehabilitation Project per CAFI decision on October 24, 2014
Tifoho
Unip Lda
Rehabilitation of
Main Roads Laong
Colmera Liceu Area
to Install New Box
Culvert
1801764.64
1,485,547.09
148,554.71
1,485,54
7.09
100%
Tres
Irmao
Unip Lda
Cleaning of
Sediments in
Enclosed
drainAlong Dili
Central
46,044.00 46.004.60 0
46.004.6
0
100%
Total 2,773,383.2
0 2,309,149.34 663,000 167,718.22
2,328,31
2.85 83.26%
Source: MPS Analysis, 30 June 2015
5.3 DRAINAGE CLEANING AND REHABILITATION
The table 5.3 presents the summary of contract between the Ministry of Public Works and
companies engaged in drainage rehabilitation.
The allocated budget for all the drainage cleaning and rehabilitation in Dili in 2015 was US$
1,163 million but CAFI meeting dated 13 and 24 April 2015 approved to transferred US$ 0.5
to agriculture and fisheiry program to cover payment for rehabilitation Oebaba irrigation
scheme phase II. A Co-Finance for construction of Dili drainage is US$ 0.5 million to pay
remain contracts and new contracts. Contract details for each project are summarized in
Tables.5.4.
21 | P a g e
Table 5.4: Various Contract for Rehabilitation and Drainage Cleanning Project
PROJECT SUMMARY
Project Name
Rehabilitation of Main
Roads Laong Colmera
Liceu Area to Install
New Box Culvert
Emergency
Installation of Box
Culvert Along
Caicoli, VillaVerde
Emergency
Construction of New
Drainages Along
Osindo Area in Hudi
Laran
Company Name Tifoho Unipessoal Lda Caileba Unipessoal
Lda
Dhalelan Unipessoal
Lda
Contract Signing Date 5-Feb-14 5-Feb-13 5-Feb-13
Commencement Date 3-Dec-13 3-Dec-13 3-Dec-13
Original Completion Date 31-Aug-14 31-May-14 8-Mar-14
Audit Court Endorsement Date NA
Issue notice to Proceed Date
Actual Completion Date 31-Dec-14 31-May-14
Original Contract Value 1,801,764.64 180,470.87 222890.78
Contract Amendment
a. Amendment 1 (Cost/Duration)
b. Amendment 2 (Cost/Duration)
Final Contract Value 1,801,764.64 180,470.87 222,890.78
Physical progress till quarter end % 100% 92% 95%
Payment Schedules
2014 IF Payments ($) 1,485,600.00 163,901.68 210,863.05
2015 IF Payments ($) 148,554.71 1,625.43 -
Total Paid 1,634,154.71 165,527.11 210,863.05
Balance 167,609.93 14,943.76 12,027.73
Notes: US$ 167,609.93 under contract for Rehabilitation of Main Roads Laong Colmera Liceu Area to Install New Box
Culvert is for un-claimed item
Project Name Emergency Cleanning, Clearing of
Enclosed Drain Along Dili (Kampung
Alor, Lanud and Pantai Kelapa)
Re-installation Distribution Pipe –
Bundaran to Mercado lama, Audian –
Kuluhun and Ailele Hun Paulus to Largo
Company Name Lomolo Unipesoal Lda Liberta, Unip. Lda
Contract Signing Date 5 February 2014 27/5/2014
Commencement Date 5 December 2013 28/5/2014
Original Completion Date 31 August 2014 100 days after commencement date
Audit Court Endorsement Date
Issue notice to Proceed Date 28/5/2014
Actual Completion Date 27/10/2014 27/10/2014
Original Contract Value 64,319.23 381,823.00
Contract Amendment 19,667.35
a. Amendment 1 (Cost/Duration) 19,667.35 / Oct 28 2014 – Jan, 31 2015
b. Amendment 2 (Cost/Duration) 19,667.35/ March 24, 2015 – June 30,
2015
Final Contract Value 83,986.58 381,823.00
Physical progress till quarter end % 100% 80%
Payment Schedules
2014 IF Payments ($) 57,889.31 306,000.00
2015 IF Payments ($) 17,346.61 0
Total Paid 75,235.92 306,000.00
Balance 8,750.66 75,823.00
Source: MPS Analysis, 30 June 2015
22 | P a g e
All the above drainage cleaning and rehabilitation have been completed last year and this year
and the payment expected is for the retention.
5.4 DILI WATER DISTRIBUTION NETWORK
The TOR for Dili water distribution Zone 2 to 9 was forwarded to A.D.N. in 2013 for review
with no update received as to date. An emergency work for water distribution network
rehabilitation in Dili was approved by CAFI as the system was damaged due to road drainage
construction. The information about the water distribution network rehabilitation in Dili is
shown in table 5.8. For the study and detail design of Zone 2 to 9, CAFI has approved allocate
US$ 0.47 million in 2015.
5.5 WATER SUPPLY IN 10 DISTRICT
To provide better drinking water for the people in the district, Government has planned to
develop existing water supply facility in 10 districts. To carry out study and design, CAFI has
approved and allocated US$ 1.5 million for 2015. Further, US$ 0.5 million rectified in late
March 2015 and CAFI meeting on 13 April 2015 approved to trasfered US$ 0.5 million to
agriculture and fisheries program. The National Directorate for Water Services is preparing
TOR for relevant study and design.
23 | P a g e
6 URBAN AND RURAL DEVELOPMENT PROGRAM
In achieving the goals of Strategic Development Plan (SDP), urban and rural developments
based on integrated and comprehensive spatial planning is essential. This program is to
finance the necessary studies which commenced in 2010 with the Spatial Plan for the Southern
Region comprising the Districts of Covalima and Viqueque and southern part of Manufahi.
The study was completed in 2011.
Similar spatial plan for the Highland Region and the Northern Region are at TOR preparation,
Spatial Plan for National Wide and LiDER Survey & Spatial mapping are implementation
process. The project Owner proposed LiDER and Spatial Mapping Second Phase in the
extraordinary CAFI meeting on 9 June 2015 in Oequsse and currently under preparation of
TOR by project owner. The disbursement at end of June 2015 was 56%. CAFI meeting 24
April 2015 approved virement of US$ 2 million from LiDER Survey & Spatial mapping to the
construction of supervision of Oebaba irrigation phase II. Detail is presented at table 6.1
Table 6.1: Budget and Status of Execution as of 30 June 2015
No. Name of Project
Final Budget
Approval
2015 ($)
Revised Budget
2015 ($) Execution ($) %
1 Spatial Plan for National Wide 610,000.00 610,000.00 0.00 0
2 Spatial Plan for High land zone 500,000.00 300,000.00 0.00 0
3 Spatial Plan for North zone 500,000.00 300,000.00 0.00 0
4 LiDER and Spatial Mapping 7,985,000.00 5,985,000.00 4,025,350.00 67
Total 9,595,000.00 7,195.000.00 4,025,350.00 55
Suource: Free Balance report dated 30 June 2015 and MPS record.
6.1 NATIONWIDE SPATIAL PLANNING
The project is comprised of the following: 1) National Spatial Plan (NSP), 2) Spatial Planning
Legislation (SPL), and 3) Housing and Settlement Legislation (HSL).
The NSP component includes recommendations on national spatial planning policy and
directives for all development sectors in terms of spatial usage. Its objective is to address land
use issues or land use conflict resolution guidelines in the implementation of the national scale
development programs or for implementation of specific major projects.
The SPL component is intended to draft spatial planning policies and regulations on which to
base and provide direction in the implementation and control of spatial planning in Timor
Leste.
The HSL component is to provide housing and settlements regulations, and provision on
which to base and provide direction in the implementation and control of housing and
settlements in Timor Leste.
24 | P a g e
The Project is being carried out by Intersismet SA in Joint Venture with Quarternaria Portugal
in the amount of US $1.22 million. The project was scheduled to be completed end of
September 2014 but due to none completion of works, Ministry of Public Works approved
extended contract to December 2014. Further, MoPW again extended contract from 31
December 2014 to 31 March 2015. To finalize the project, CAFI approved allocated US$
0.61 million in 2015.
No significant physical works achived in the end of June 2015 and no disbursement made by
the company. As learned from the project owner that the consultant did not show good
commitment on the implementation of this project. The third time extension is under
reviewing process by NPC. Detail of contract shown in the table 6.2:
Table 6.2: Nationwide Urban Planning Studies Project
PROJECT SUMMARY In the implementation stage
Company Intersismet SA joint venture with Quarternaria Portugal
Date of Contract 12 of March 2014
Contract Duration 6 Months
Notice to Proceed 31 March 2014
Completion Date 31September 2014
Revise Completion Date no.1 31December 2014
Revise Completion Date no.2 31March 2015
Revise Completion Date no.3 -
Contract Value ($) 1,219,755.75
Present physical completion status 40%
Payment Schedule
2014 IF Payments ($) 585,482.76
2015 IF Payments ($) 0.00
Total to be paid ($) 585,482.76
Balance to be paid ($) 634,272.99
Source: MPS Analysis and Free balance 30 of June 2015
6.2 LIDAR SURVEY AND SPATIAL MAPPING
The primary objective of LiDAR Mapping is to obtain an accurate geographic and spatial data
for Timor-Leste using LiDAR technology. As of end-2014, the accomplishments are as
follows: Aerial Photo Data acquisition at 100% covering the entire Timor Leste; LiDAR and
air photo survey at 100%; LiDAR and photo data processing at 72%, and; ground survey at
100%. Details of contract and payment shows in table 6.3.
As Capacity Building is part of the TOR, the Consultant conducted the first training in
Bandung, Indonesia on 24 of November to 5 of December 2014 in collaboration with Institut
Teknologi Bandung, Karvak Consultant and Timor Leste Government. The objective of the
training program is to sustain the use of LiDAR Technology. Six agencies of the Timor Leste
Government participated in the program, these include: Ministry of Public Works, Ministry of
Justice, Ministry of Agriculture, Institute of Petroleum and Geology, Agency of National
Development and Major Project Secretariat.
The second training that planned held on mid of February 2015 at ITB Bandung was changed
25 | P a g e
to 11 of April to 29 of April 2015. The third training in the management and policy decision
maker that involved superior level of each relevant ministry was conducted on 29 of June to 3
of July 2015 in Bali, Indonesia. To cover balance of this contract US$ 7.985 million for 2015
but CAFI meeting 13 April 2015 approved transfer US$ 2 million to agriculture and fishery
program and revised budget was US$ 5.985 million for 2015. The contract details are shown
in the table 6.4.
Table 6.3: LiDAR Survey and Mapping Project
PROJECT SUMMARY Implementation Process
Company PT Karvak Nusa Geomatika
Date of Contract 29-05-2014
Contract Duration (year) 1
Notice to Proceed 16 July 2014
Completion Date 16 July 2015
Contract Value ($) 12,985,000.00
Present physical completion status 92.43%
Payment Schedule
2014 IF Payments ($) 7,661,150.00
2015 IF Payments ($) 4,025,350.00
Total to be paid ($) 11,686,500.00
Balance to be paid ($) 1,298,500.00
Source: MPS Analysis and Free balance 30 of June 2015
6.3 DILI URBAN PLANNING
Another major study being done is the preparation of the Dili Urban Plan. This covers Dili
urban areas including Tibar and Hera with an aggregate area of 178.62 km2. Based on 2010
census and household survey conducted, the area has a total population of 223,793. It is being
funded by Japanese International Cooperation Agency (JICA) and no budget from the IF was
involved. The project owner is the National Directorate for Housing and Urban Planning,
Ministry of Public Works, Transport and Communication. Dili Urban Plan project still
progressing under the supervision of the MPWTC and JICA.
26 | P a g e
7 ELECTRICITY
The original aim of the program was to provide reliable electricity generation, transmission
and distribution throughout Timor-Leste by 2014. The program involves the installation of two
new power plants at Hera and Betano and erection of a 150KV nationwide power line grid
plus 20KV distribution lines, 9 substations, medium and low voltage of house connection, and
illumination of street light. The two power stations are operational and most of the power
distribution lines and sub-stations are now operational. Details are presented below:
Hera and Betano Power Generation Plants 100% completed
Medium Voltage Transmission Lines - 99.09% completed
Substations – 98.68% completed
Hera Power Station Fuel Tanks - 100% completed
20 KV lines - 98.95% completed
Betano Power Stations, Fuel Tanks - 100% completed
Contracts for the overall program amount to $844 million. Of the budget in 2011 of
$448.7million $428.845 million or 95.5% was disbursed. The budget allocation of $282
million for 2012 plus the balance of $20 million carried over from 2011 made available $ 302
million for 2012, of which $283 million or 94% had been disbursed by end-December 2012.
The 2013 budget for electricity was US$123.67 million which comprised new appropriation in
the amount of US$113.7 million plus the balance of US$ 10 million carried over from 2012.
The original budget allocation for 2014 was US$ 56.350 million including US$ 40.323 million
transferred from the 2013 balance. This amount was then increased from US$ 82.123 million
to US$ 138.123 million. The execution rate as of 31 of December 2014 was US$ 133.791
million or 97%.
The original allocation budget for the electricity program in 2015 was amounted to US$
57.128 million and the budget was reduced to US$ 47.128 million or decreased US$ 10
million during the budget rectification in March 2015. As per 30th
of June 2015, the total
disbursements have reached US$ 13.242 million or 28% of total allocation budget. The
execution rate per second quarter was expected to be 40%, however a few invoice that have
certified by the project owner was failing to fulfill a legal requirement which delay the
payment process. The total allocated budget as shown in Table 7.1.
7.1 CONSTRUCTION OF TRANSMISSION LINES OF 150 KV
All transmission line networks are completed including power grid ring in the section between
Maliana to Suai. The Operational Acceptance Certificates were signed by EDTL and
Consultant for previous work done on June 2014, when section Maliana to Suai completed
EDTL and Consultant signed Operational Acceptance Certificates on 19 November 2014.
Installation of networks have been supplied with power, tested and issued with completion
certificate on 19 May 2014, the power grid has energized and operation consisted of 9
27 | P a g e
substations and 12 sections of 150 KV transmission lines. Shown in Table 7.2 is the progress
of works.
Table 7.1: Summary of Financial Status of Electricity Program
Description
Balance
2014
Original
Budget
Revised
Budget
Post
Review
Disbur-
sement % Obligation
Commit
ment Balance
'$000 '$000 '$000 '$000 '$000 '$000 '$000 '$000
Rehabilitation and Distribution
Medium Voltage
-98 15,000 10,000 14,902 1,158 12 259 189 8,394
Rehabilitation and Distribution Low
Voltage
10,206 14,000 10,000 14,000 1,889 19 90 348 7,673
Distribution and Transmission Line
of Betano and Hera Power Plan
Generators
2 17,608 17,608 27,814 10,195 58 3,594 3,820
Maintenance of LMV Line in
District and Sub District
- 1,000 1,000 1,002 1,000
Work preparation operation and
Maintenance of Betano Electricity
- - - - -
Rehabilitation and Modification
electricity distribuition line control
system
- 820 820 820 820
Rehabilitation and Modification
electricity distribuition line control
system
7 - - - -
Installation of Street Lighting in Dili 1 750 750 751 750
Contruction of Comoro power plant
residence
- - - - -
Contruction of Comoro power plant
residence
20 7,500 6,500 7,520 6,500
Masterplan of Submarine 20 KV
from Dili to Ata'uro of 5 KM
underground cable in Dili
1 150 150 151 150
Design preparation of 57 residences
and offices in Sub District
- - - - -
Design preparation of 12 residences
and offices in the District
- - - - -
Maintenance of 11 substation - 150 150 150 150
Maintenace of Distribution line - 150 150 150 150
Total 10,138 57,128 47,128 67,266 13,242 28 3,943 735 29,407
Source: Free Balance per 30th June 2015
Line Traps are installed and provisory tests were conducted against each substation from
National Dispatch Centre, however the contractor performed functional test but did not make
any quality control test.
7.2 CONSTRUCTION OF 20KV DISTRIBUTION LINES
The construction of 20kV distribution lines is complete. The contractor, however, made a
request to the project owner for the possibility of extending the distribution line from Lugasa
through Uatolari, Uatocarabau and Iliomar. As to date, there is no information as to the
distance and number of poles required for such work. As EDTL still assess distribution line for
this section. Table 7.3 indicates the individual section of works achieved as of end May 2014.
28 | P a g e
Table: 7.2. Project Name: Construction of 150 KV Transmission Lines Linhas de
Transmissão 150
KV
Performancia do Trabalho
Observação
Secção Excavação
Fundação
em Betão
Armado
Torres
Erguidas
Condu
ctores Total Km
Costa Norte
Hera - Dili 30 30 30 30 30 9.891 Duplo circuto está em
operacional
Hera – Manatuto 91 91 91 91 91 40.902 Duplo circuto está em
operacional
Manatuto-Baucau 132 132 132 132 132 52.33 Único circuto está em
operacional
Baucau-Lospalos 141.5 141.5 141.5 141.5 141.5 63.499 Único circuto está em
operacional
Dili-Liquica 86.5 86.5 86.5 86.5 86.5 38.818 Único circuto está em
operacional
Sub total 481 481 481 481 481 205.44 Concluido100%
Este/Oeste
Baucau-Viqueque 107 107 107 107 107 43.125 Único circuto está em
operacional
Liquica-Maliana 108.5 108.5 108.5 108.5 108.50 44.921 Único circuto está em
operacional
Maliana-Suai 129 129 129 129 129 58.183 Único circuto está a concluir
operacional
Sub total 344.5 344.5 344.5 344.5 344.5 146.229 Progresso fisico 100%
Costa Sul
Suai-Cassa 95 95 95 95 95 38.555 Único circuto está a concluir
operacional
Cassa-Betano 57 57 57 57 57 25.408 Único circuto está em
operacional
Betano-Viqueque 198 198 198 198 198 84.475 Único circuto está em
operacional
Viqueque-Lospalos 231.5 231.5 231.5 231.5 231.5 103.439 Único circuto está em
operacional
Sub total 581.5 581.5 581.5 581.5 581.5 251.877 Progresso fisico 100%
Total 1407 1407 1407 1407 1407 603.546 Progresso fisico 100%
Percentage 100% 100.0% 100% 100% 100.00%
Source: ELC Bonifica Report, 31 May 2015
7.3 SUB-STATIONS
All nine sub-stations were completed by end-2012 and connected to the power grid. Furniture
and facilities for guard house are completed. However, maintenance works, rectification of
some civil and electrical components including fire-fighting, alarm systems in most of
substations needs to be completed.
29 | P a g e
Table 7.3.: Installation of 20 KV Distribution Lines
Secção Comprimento
(Km)
Numero de Poles Estado
Requerido Erguidas
Dili (Becora-Seloi) 32 762 762 Energized since 13 January 2012
Seloi-Gleno 22 440 440 Energized since 24 January 2012
Seloi-Aileu 6 128 128 Energized since 24 January 2012
Betano-Same 26.20 420 420 Energized since 16 de November, 2012
Viqueque - Lugasa 30 600 600 Energized since 16 de November, 2012
Cassa-Ainaro 23.60 427 427 Energized since desde 23 de
Novembro, 2012
Total 139.8 2,777 2,777 Energized 100%
Uatulari-Uatucarbau-
Iliomar 44
Foi requisitado para extenção mas não
se sabe qual e o seu comprimento e
poles
Total 139.8 2822 2,482 Progresso fisico 98.41% Segundo
trimestre o relatorio de Maio 2014
Source: Bonifica Report for February 2015
7.4 COMORO POWER STATION
The 24 MW Comoro Power Station became fully operational in December 2012. Local
operators were trained by CSI in January, June and July 2013 and, following completion of
testing, official acceptance of the plant by EDTL took place on August 29, 2013.
Additional works such as road rehabilitation, fuel station rehabilitation, painting of the
existing fuel tanks and supply of office furniture have yet to commence. The contractor for the
civil works has submitted a proposal to EDTL for operation and maintenance of the plant for a
two-year period, which is important, sustain the system operation and ensure the reliability. .
7.5 20KV OVERHEAD LINE CONNECTING 150/20KV DILI SUB-STATION WITH
20KV FEEDERS
The contractor has completed the works based on the conditions of contract which involved
the operation and supply of power to six feeders of Comoro Power Plant. All the six feeders
have been energized and are in full operation. Changes in the scope of works for feeders 2 & 6
and feeders 4 & 5 resulted in adjustment in the contract value to US$2,308,318.18 and all
payment has been made to the company.
7.6 20KV OVERHEAD LINE CONNECTING 150/20KV MALIANA SUBSTATION
WITH THE EXISTING 20KV NETWORK IN THE AREA
The SOSO Electrical Unipessoal Lda has installed overhead lines to Maliana Town, Bobonaro,
Ritabou, Kailaco, Batugade, and Mandoki under Variation Order No.1 in the amount of US$
30 | P a g e
353,256.04 in addition to the contract value of US$ 1,743,351.04. The 4.1 km line extension
was connected to feeder Lima Maumali-Mandoki that will improve the system in Bobonaro
District. All circuits between those areas have been energized, the final acceptance has been
issued and the contract has been concluded and all payment has been made to the company.
7.7 20KV OVERHEAD LINE CONNECTING TO THE NEW 150/20KV SUAI SUB-
STATION WITH 20KV NETWORKS
This section of the line has been completed which became operational since 18 September
2013, the contract value for this work was US$ 242,000.00 and all payment has been made to
the company.
7.8 FUEL SUPPLY LINE FROM HERA LOADING DOCK TO HERA POWER PLANT
The project will enable fuel for Hera Power Station to be supplied from tankers moored in
Hera Bay adjacent to the storage tanks of Hera Power Plant, eliminating the need for road
transport of fuel from Tibar. The contract for the project included supply and installation of 6
inch-diameter pipes, supply and installation of fuel pump system, and construction of safety
fence around the site. The system has been tested, approved and is currently in full operation.
Additional work under Change Order Nos.1 and 2 has been approved to provide: DN 200 gate
valve, automatic shutdown valve, fire protection system, filters and flow meters. This raised
the total contract value to US$ 494,000.00.
Timor Gap turned over the installation works to the project owner on 9 of May 2013 with the
operation of first vessel loaded with 3,000 metric tons of diesel fuel during its inauguration.
The acceptance certificate of the system was issued on 16 May 2013.
7.9 HERA POWER STATION
Hera Power Plant commenced its commercial operation on 01 December 2011 using all seven
installed generator sets and with the full provision on fuel tanks. Despite the higher operating
cost of the power plant when using the High Speed Diesel Fuel, the choice of technology
installed (generator) is robust so that in the future, other more affordable fuel such as gas and
heavy fuel oil (HFO) can be considred to reduce the operating cost.Additional proposed
structures to be provided at the site include: Training Center for mechanics and operators,
administration Building, and Residential Facilities.
In order to ensure the successful operation of the power plant by means of supying the power
to each grid, the functional test was conducted on 30th
November 2013. However, the
unexpected shut down occurred during the testing, which indicated that there was a problem in
the main transformer of the switchyard and misinteprepration of the procedures and
transmitted signal by the operator.
31 | P a g e
7.10 BETANO POWER STATION
Betano Power Plant has been in operation since its inauguration on 20 August 2013 and on
24th
October 2013, the certificate of completion for the plant was issued. The complete
structures and works consit of major mechanical, electrical, civil works, pipeline from fuel
treatment house to fuel tanks, storage tanks and fire-fighting facilities. Betano Power Plant has
started operation works keeping one engine running 24 hours per day since November 2014
up to date, the project owner (EDTL) started supply a fuel to keep the power plant operation.
Puri Akraya Engineering Ltd will operate and maintain Betano Power Plant, as an extension
(supplemental agreement) to their contract (ref: contract RDTL 12003387 signed 3 April
2012) for operation and maintenance of the Hera Power Plant. This supplemental agreement
for Betano Power Plant operation has duration of three (3) years ending on 30 April 2017.
Some of the major issues but not limited to those identified by the Supervision Consultant
have to be addressed as part of the contractual obligation by EPC Contractor are as follows: a)
commissioning process has not been completed, b) the plant is not officially handed over to
the owner, c) repair of mechanical, electrical and civil works made known to the contractor are
not yet accomplished, d) transmission of signals between Power Plant Switchyard and
National Dispatching Centre has not been completed, e) metering system which monitor the
energy generation and dispatched has not been installed, f) replacement of the Black Start
Generator has not been done, g) supply of required spare parts has not been completed, h)
contractual tools for maintenance of the plant has not been provided, i) weigh bridge retesting
and commissioning after it was flooded by rain water has not been done yet, j) guard house
No. 2 that was flooded by water from leaking pipe has not been adjusted and, k) cleaning the
site within the property limit from garbage, levelling and lawn has not been done yet.
The above mentioned issues have been raised from the previous year, however, there is no
action being taken by contractor to address the finding that Consultant Company raised in
their monthly report. It is recommended that the project owner should not release payment
certificate until the contractor comply with its performance obligation.
7.11 MEDIUM AND LOW VOLTAGE DISTRIBUTION LINES
The installation of medium and low voltage distribution lines are implemented in three
packages by 267 national and international contractors. Emergency works are implemented by
55 contractors as the first package; the second package is the extension and rehabilitation of
distribution lines, public illumination, and transformers which are implemented by 52
contractors and; the third package is comprised of line extensions for medium voltage (MV),
low voltage (LV) and house connections as implemented by 160 contractors.
This project started in 2009 and has so far benefited 48 sub districts. As reported by the Office
of EDTL, 17 Subdistricts (Dilor, Soibada, Natarbora, Turiscai, Fatuberliu, Alas, Bazartete,
Hatulia, Hatubuilico, Balibo, Fatululik, Fohorem, Fatumean, Atauro, Nitibe, Pasabe, Oesilo,
and Pante Makasar) have no access yet with electricity. EDTL intends that by 2013 and 2014,
32 | P a g e
all sub-districts in the entire country will be served by the electrification program of the
government.
From 2012 the implementation of the installation of medium and low voltage distribution lines
was managed by Management and Implementation Committee of National Electricity
Program known as CGI-PEN (Comição e Gestao Implementação - Programa Electrificaço
Nacional) as per decree law 40/2012, 5 September. The objective of establishment CGI-PEN
is to provide feasible electirty power for 24 hours to the entire country. The CGI-PEN also
undertakes procurmanet, supervising and certifying the payment before submitting to ADN for
next process.
As of to date 389 projects have been awarded to both national and international contractors
with contract value 865,092,290.36, some of project have been completed and other still
progressing. In 2015, some of projects have been announced to be implementing in this year
and 2016.
Further, CAFI through its meeting on 9 June 2015 in Oecusse has decided and approved
payment for the new installation medium and low voltage, and house connection could be paid
under IF, the decision made due to insufficient budget allocation for Oecusse region. MPS
have processed the payment for delivering equipment and installation services of electrical
installation and metering for Public School and Health Centre Building that conducted in
Baucau, Bobonaro, Ermera and Lautem District which approved by CAFI.
33 | P a g e
8 ROADS
8.1 GENERAL
The road network was generally in poor condition with many roads requiring extensive repair
or re-building1 when the IF was set up on 2011. As a result many parts of the country were
regularly isolated by roads and bridges that were permanently or frequently temporarily
impassable because of flooding, washout or landslides. The strategy set out in the SDP for
investment in the road network is based on a three-tier hierarchy of investment: National,
District and Rural / Urban roads. The road network is similarly structured with roads classified
as National, Regional2 and Rural/Urban.
The road development strategy is designed to support this program and will provide good
transport connectivity between activity centres and establish all-weather roads to connect
presently isolated areas and improve access between rural areas and the main cities of the
country. This provision existence of reliable, well maintained roads is essential to economic
growth, social cohesion and national security; hence the government’s assignment of a high
priority to road investment and justification for a high allocation of funds to road projects in
the Infrastructure Fund budget. The annual allocations to date have been: 18% in 2011, 13%
in 2012, 15.7% in 2013, 17.3% in 2014 and 18.43% in 2015 of the total I F budget.
The original allocation budget for 2015 was US$ 54.8 million and it was reduced to US$ 44.8
million during the budget rectification in late March 2015 where total of US$ 10 million was
transferred to ZEEMS. Hence, as per CAFI decision dated 24 April 2015 it was approved
virement of US$ 5.21 million from bridges program thus the budget was revised to US$ 50.01
million. The revised allocation budget for loan co-finance projects was reducing from US$ 26
million to US$ 18.5 million. The disbursement made by end of June 2015 was US$ 5.44
million as some of payment still under process of verification of ADN and raising PO by NPC
and PR to treasury.
Apart from the above progress, there are still a number of challenges faced during the project
cycle period. Some ongoing projects encounter difficulties to finalise the work within the
planned timeframe, some contracts have been extended several times, and a number of new
projects have been implemented late due to delay in project preparation. Several road projects
have been generally slow and oftentimes with low quality of work. In many instances, there
seemed to be lack of discipline on the part of contractors and supervision is oftentimes
inadequate or ineffective. Many works started before the issuance of “Notice to Proceed”
1 80% of National roads, over 90% of District roads and almost 100% of Rural roads were reported to be in poor
condition as of 2011 (various sources).
2 Previous referred to as District roads
34 | P a g e
and/or without enough preparation while other contractors even proceed with the works before
their contracts are signed. The representative of project owner was recommended to strength
project monitoring system on the ongoing contracts in order to improve execution rate. The
summary of 2015 budget allocation for road projects and its disbursements are described in
Table 8.1.
Table 8.1.: Summary 2015 allocation budget for road projects and its disbursements
Projecto
Orçamento 2015 $'000
1. Comentários
Original
Revição após
Retificação,
Virement e
Transferência
Interna
Despesas
até 30
Junho
2015
Saldo
Total 54,800 50,010 5,440 44,570 11% executed
Reabilitação Estrada Zumalai Beco-Suai (Fase II) 1,000 300 300 Need finalise bid doc.
and tender
Reabilitação de Estradas Díli - Aileu (Laulara-Solerema) 1,000 1,000 1,000 Previous contract
completed.
Reabilitação e construção de estradas urbanas Fase II 5000 5000 5000 38 Contracts will charge
to this budget
Reabilitação de Estradas Lepo - Zumalai 20 km 500 500 500 Previous contract
completed.
Construção de Estradas e Esgotos, Posto Integrado
Batugade-Mota Ain
500 500 500 Need finalise bid doc.
and tender
Reabilitação de Estradas Assalaitula -Ossu - Viqueque 982 982 916 66 2 contracts will charge
to this budget
Reabilitação de Estradas Ermera-Atsabe 15 km 0.00 0.00 0.00 0.00 In progress 90%
completed
Reabilitação de Estradas Ermera-Hatolia 12 km 0.00 0.00 0.00 0.00 In progress 53%
completed
Reabilitação de Estradas Tilomar-Weleu 14 km 0.00 0.00 0.00 0.00 Slow progress, contract
extended
Reabilitação de Estradas Baguia-Laga 6.6 km 0.00 0.00 0.00 0.00 Previous contract on 21
Feb 2014
Reabilitação de Estradas Baguia-Watucarbau 12 km 600 600 269 331 100% completed and
remain retention
Reabilitação de Estradas Maubise-Turiskai, 10 km 220 220 220 In progress 30%
completed
Reabilitação de estradas Maubisse-Bubur Laran-Turiskai
Vila (Pacote II)
1,630 1,630 1,630 No allocation budget
Reabilitação de Estradas Lospalos -Tutuala 10.5 950 950 950 In progress, 52%
completed
Reabilitação de Estradas Lospalos-Ilomar 13.6 Km 370 370 370 In progress, 35%
completed
Reabilitação de Estradas Atauro Villa - Beloi - Biqueli 500 500 500 In progress, 71%
completed
Reabilitação de estrada Aituto-Same 1,200 1,200 1,200 In progress, 28.2%
completed
Reabilitação de Estradas Maubarra-Loes (Karimbala) Fase I
4 km
0.00 0.00 0.00 0.00 Completed.
Rehabilitasaun Estrada Karimbala Fase II 9 km 500 500 500 Need finalise bid doc.
and tender
Reabilitação de estrada Cruzamento Alto Barique-Natarbora
25.5 Km
881 881 881 In progress 86.37%
completed
Reabilitação de estrada Luro-Buhuimau 750 750 750 In progress 68.71%
completed
Reabilitação de estrada Dare-Ainaro 131 131 131 Previous contract
completed.
Reabilitação de estrada Edmumu-Spatula in Uatulari/Irabere 109 109 109 In progress 45%
completed
Rehabilitação de estradas Lospalos-Lore 350 350 350 Need finalise bid doc.
and tender
Reabilitação de estradas urbanas em Same 2,000 2,000 2,000 In progress 60%
35 | P a g e
completed
Construção e supervisão para o desemvolvimento de
Estradas Dili-Liquica e Tibar Ermera (L-CF)
7,000 7,000 1,509 5,491 2 contracts charged to
this budget code
Construção e supervisão para o desemvolvimento de
Estradas Dili-Manatuto- Baucau (L-CF)
4,000 2,500 1,500 Price evaluation for
Dili-Manatuto and ITB
for Manatuto - Baucau
Desenho Manatuto - Natarbora, Supervisão e outros custos
associados (L-CF)
6,000 4,000 1,244 2,756 2 contracts charged to
this budget code
Construção e Supervisão de Estradas de Quatro Vias Tasi
Tolu-Porto Tibar (L-CF)
2,000 1,000 1,000 Preliminary design is
progressing
Reabilitação de estradas nacionais (Potholes Repair) 500 500 500 In progress, 64%
completed
Reabilitação de estrada Zumalai-Suai 0.00 0.00 0.00 0.00 No allocation budget
Normalização e proteção da Ribeira de Hera 700 700 700 In progress 29%
completed
Reabilitação de estrada no recinto de Cristo Rei 500 2500 500 Need finalise bid doc.
and tender
Controlo de cheias 758 758 758 6 contracts charge to
this Budget
Reabilitação de estrada Bobonaro-Suai 486 486 486 Need finalise bid doc.
and tender
Reabilitação de estradas distritais de Wiuka - Quelikai 500 500 500 Same as above
Rabilitação de estradas Dili-Manleuana-Solerema-Aileu 15
km
750 750 750 Same as above
Construção ou rehabilitação de Estradas Metinaro-Laclo-
Manatuto
500 250 250 Same as above
Construcao de estrada alternativa Jakarta II 700 700 700 2 contracts charged to
this budget code
Reabilitação de Estradas Viqueque- Uatulari 500 300 300 Need finalise bid doc.
and tender
Reabilitação de estradas distritais de Baucau - Laga
incluindo preparação de desenho em seções determinadas
para elevar nivel da estrada
0.00 0.00 0.00 0.00 No allocation budget
Reabilitação no Construcao de Estradas Maliana-Cailaco-
Hatolia
500 250 250 Need finalise bid doc.
and tender
Reabilitação de Estradas Venilale-Fatulia-Waimuri 200 200 200 Same as above
Construção e Supervisão de Estrada Dili-Ainaro (Lot 3, Lot
4 & Lot 5 -LB)
7,000 5,000 5,000 In progress, Lot 3, 4,
and 5 contract
Preparação Estudo e Desenho Detalhado das Estradas 2,000 1,000 1,000 Need finalise bid doc.
and tender
Aquisicao de Bens Imoveis projectos do FI 1,500 6,710 6,710 Resettlement issue to be
finalized
Construção Estrada Ainaro - Momolau - Bobonaro 0.00 0.00 0.00 0.00 No allocation budget
Sources: MPS record and Free Balance Report dated 30 June 2015
8.2 PROJECT STATUS
8.2.1 Rehabilitation of Baguia – Uatucarbau Road
The Baguia-Uatucarabau Road Project which commenced in early 2012 was 12 km long
linking Baguia Sub-district, Baucau and Uatucarabau Sub-district, Viqueque. This contract has
been extended several times since the contractor failed to finalize the work within the planned
time frame. The project has been 100% completed in March 2015 and under defect liability
period (DLP) now. The actual work completed after verification of A.D.N. is only for US$
2,489,630.78 from US$ 3.1 million total contract amount and US$ 610,369.22 is for
unclaimed items. Details of contract and its disbursement are presented in Table 8.2.
36 | P a g e
Table 8.2: Road Rehabilitation Baguia-Uatucarbau 12 KM Project Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Baguia Uatucarbau 12 Km180 m
Empresa: Real Construction Lda Renardet
Data do Contracto: 17 Janeiro 2012
Data de Conclusão Inicial: 31 Janeiro 2013
Valor Contrato Inicial (US$): 3.100.000,00
Data de Conclusão revisto 1: 1. 31 Outubro 2015
Valor contrato revisto 1 (US$): 3.100.000,00
Data de Conclusão actual March 2015
Progresso Fisico actual (procento): 100%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 268.085,90
Pagamento FI 2014 (US$): 1.952.873,99
Pagamento FI 2015 (US$): 268.670,89
Total Pago (US$): 2.489.630,78
Balanço do Contrato (US$): 610.369,22
8.2.2 Rehabilitation of Baguia – Laga Road (6.6 km)
This project has suffered significant delays due to a number of issues which include changing
of BoQ based on As-staked drawings, poor quality of work as reported by ADN, and the
financial difficulties encountered by the firm. It has been concluded that the works cannot be
completed as scheduled. In addition to that, the Ministry of Public Works terminated the
contract with the company based on the resolution of CAFI during the meeting held on 21
February 2014. US$ 300,068.98 of total contract prices of US$ 1.5 million was paid to the
company. For the incomplete scope of works, the project owner will reassess and make
necessary correction on the engineering design before processing tender.
8.2.3 Cassa – Wemassa Road (18 km)
The project was divided into four (4) contract packages. Contract Packages 1, 2 and 3 were
awarded to three (3) different contractors, construction of Package 4 (km 10.5 – 14.0) has not
yet been awarded to any contractor. The physical works for the three contracts including the
final inspection for the defects and liability period have been completed. However there is still
issue on package implemented by EDS Company, therefore the final payment for this contract
has not been paid. The project owner informed that company still not finalise defect list
identified. Overall status of Casa – Wemassa Road is reflected in Table 8.3.
Table 8.3: Rehabilitation of Cassa-Wemassa Road Project Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Cassa wemassa 1,2,3 contracs
Empresa: Star Suai Lda, Naroman and EDS Renardet
Data do Contracto: 22 Março 2010
Data de Conclusão Inicial: 8 de Janeiro 2014
Valor Contrato Inicial (US$): 2.256.508,15
Data de Conclusão revisto 1: 2. 30 de Novembro 2014
37 | P a g e
Valor contrato revisto 1 (US$): 2.256.508,15
Progresso Fisico actual:
Procento 100%
Pagamentos / Estado Financeira
Pagamento FI 2011 (US$): 849.423,91
Pagamento FI 2012 (US$): 617.000,00
Pagamento FI 2013 (US$): 412.000,00
Pagamento FI 2014 (US$): 156.201,17
Pagamento FI 2015 (US$):
Total Pago (US$): 2.034.715,42
Balanço do Contrato (US$): 221.792,73
8.2.4 Rehabilitation of Ermera – Atsabe Road (15 km)
The rehabilitation of this section of road was awarded to Gunung Kijang Lda with the
commencement set on 7 December 2010 and completion by 31 January, 2012. However, the
completion date has been extended two times, the first extension was up to 31 October 2013
and second one until 8 April 2014. Despite of these extensions, the project still running behind
the schedule, delays as per reports are due to weather condition, which should have been
factored into the work scheduling and lack of technical capacity to manage, plan and
implement the work. On the other hand, MOP has also approved the reduction of length from
15 km to 10 including the completion date based on MOP’s evaluation of As-staked drawings.
The project is progressing but no allocation budget for 2015. The project owner informed the
project has been 100% completed and claim from the contractor under verification. MPS will
present to CAFI upon receive request or payment from the project owner. Contract details are
summarised in Table 8.4.
Table 8.4: Rehabilitation of Ermera-Atsabe Road Project (15KM)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Ermera Atsabe 15 Km
Empresa: Gunung Kijang Unipessoal Lda Renardet
Data do Contracto: 7 de Dezembro 2010
Data de Conclusão Inicial: 31 de Janeiro 2012
Valor Contrato Inicial (US$): 3.181.888,00
Data de Conclusão revisto 1: 1. 31 de Outubro 2013
Data de Conclusão revisto 2: 2. 30 Agosto 2015
Valor contrato revisto 1 (US$): 3.181.888,00
Progresso Fisico actual:
Procento 100%
Pagamentos / Estado Financeira
Pagamento FI 2011 (US$): 390.309,70
Pagamento FI 2012 (US$): 970.326,65
Pagamento FI 2013 (US$): 573.978,56
Pagamento FI 2014 (US$): 764.640,91
Pagamento FI 2015 (US$):
Total Pago (US$): 2.699.255,81
Balanço do Contrato (US$): 482.632,19
38 | P a g e
8.2.5 Rehabilitation of Ermera – Hatolia Road (7 km)
The rehabilitation of this road section was awarded to Suai Indah LTD. Beginning of the
project was September 22, 2011 with duration of 840 calendar days or until 31 December
2013. The work involves the construction of a macadamized road with two lanes of 4.5 meters
width and 1.5 meter shoulder each side, as well as cross lateral flow and slope protection
works. This project has suffered significant delays with the completion date revised two times,
the first revision date is up to 30 April 2014, and second is up to 30 August 2015. However,
the actual physical progress reported was only 53.48%. On the other hand, the total length of
roads has been reduced from 12 km to 7 km based on the As-staked drawings approved by
MOP. The project still yet 100% complete but no allocation budget for 2015.
The project owner informed that the actual physical progress is about 69.69% but no
allocation budget for 2015. MPS will present to CAFI upon receive request or payment from
the project owner.
MPS received an issue to CAFI from DGCS-MPWTC on 24 June 2015 with regards to
variation order No. 3 with no additional cost. The variation order No. 3 proposed was to
complying with the 8 meter wide for national road requirement with none cost increase to
original contract because just realignment some line items in the original bill of quantity.
Variation order was verified and approved in the technical level on 17 April 2015. MPS will
review and present this issue to the next CAFI meeting for decision. Contract details are
summarised in Table 8.5.
Table 8.5: Rehabilitation of Ermera-Hatolia Road Project (12KM)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Ermera Hatolia 12 Km
Empresa: Suai Indah Unipessoal Lda Renardet
Data do Contracto: 11 July 2011
Data inicio de Obra 22 de Setembro 2011
Data de Conclusão Inicial: 31 de Dezembro 2013
Valor Contrato Inicial (US$): 2.050.000,00
Data de Conclusão revisto 1: 3. 8 de Janeiro 2014
Data de Conclusão revisto 2: 4. 30 Agosto 2015
Valor contrato revisto 1 (US$): 2.050.000,00
Progresso Fisico actual:
Procento 69,69%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 599.035,66
Pagamento FI 2014 (US$): 387.731,62
Pagamento FI 2015 (US$):
Total Pago (US$): 986.767,28
Balanço do Contrato (US$): 1.063.232,72
39 | P a g e
8.2.6 Rehabilitation of Maubara – Loes Road (4.35 km)
The original scope of work involved the construction of a 6.0 m pavement with 1.0 m shoulder
plus lateral and cross drainage and slope protection structures for the full 13 km stretch. The
rehabilitation work was awarded to Jonize Construction Tinolina Pty. LTD. (JV) and started on
19 November, 2010 with target completion by first quarter of 2012. However, despite the
rescheduling of works and time extension to October, 2012, changes in prices and quantities
constrained the completion of the 13 km road to satisfactory standard. The Supervision
Consultant and MPW recommended reduction in length of section to be completed to preserve
works quality. As a result the works were re-defined with only 4.35 km in length to be
completed under the present contract and the remaining 8.65 km to be tendered under a
separate contract.
The new scope of works for the rehabilitation of Maubara Loes Road Phase I (4 Km)
contracted to Jonize Construction JV Tinolina with final contract price of US$ 4,772,650 was
completed in December 2013. The final payment to the company was US$ 4,722,214.91. US$
0.5 million was allocated for upgrading Maubara to Karimbala phase II (9 Km) section. The
NDRBFC-MPWTC still preparing and verify design and bids document before tender.
8.2.7 Rehabilitation of Los Palos – Tutuala Road (10.6 km)
The contract was awarded to Miguel Group Ltd. The works commenced on 27 October 2011
with the contract duration of 840 calendar days or until 12 February 2014. Scope of
rehabilitation involves Double Bituminous Surface Treatment (DBST) pavement, 5.4 meters
wide, 10.6 km long, 0.60 meter shoulder width to each side, outlet side structures and
transversal slope protection. In addition, there is application of Bio-engineering to protect
erosion at several sections of the roads. This project has been delayed due to modification of
unit prices.
The original contract value was US $2.76 million to cover a total length of 10.5 km. However,
based on As-staked plan prepared by the contractor as requested by MPW, it necessitates
adjustment in the original unit price for some items. This adjustment resulted to the reduction
of road length to be rehabilitated from 10.6 km to 4 km. Renegotiation has been conducted
resulting in significant delays. Finally, on 16 June 2014, CAFI approved the continuation of
the work with the same contract value to cover the rehabilitation of 4 km. After negotiation
with the contractor, the final contract prices increased to $3,695,729.13, the construction work
is about 95% was reported. No disbursement in this reporting period as the claim still under
verification of the project owner Details of the project are presented in Table 8.6.
8.2.8 Rehabilitation of Los Palos – Iliomar Road (13.6 km)
The rehabilitation of Lospalos - Iliomar Road was awarded to Kiar Maek LDA with the
contract period of 840 calendar days. The project commenced on 22 September 2011 for
completion until 08 January 2014. Due to some issues such as lack of experienced field staff
and capacity to implement the project, significant delays had been encountered in its
implementation. The extension of the contract has been approved up to 30 April 2014. Due to
40 | P a g e
site condition, CAFI meeting held on 22 August 2014 approved extend contract until 30
August 2015. The actual physical progress as reported by project owner is about 42% due to
weather condition and other site issues. During Detail of the project is presented in Table 8.7.
8.2.9 Rehabilitation of Weleu-Tilomar Road (14 km)
The contract for this project was awarded to Marabia Lda, with the works starting on 6
January 2011 and for completion within 300 calendar days. This project has been extended
several times due to slow progress of works and completion date is now 20 August 2015.
While, the scope of work has been reduced from 14 km to 8.30 km as a result of As-staked
drawings requested and approved by MOP. The cumulative physical progress reaches up to
date about 64.34% only. No disbursements made by end this second quarter report as the claim
still under verification of the project owner. Details of the contract are presented in Table 8.8.
Table 8.6: Rehabilitation of Lospalos - Tutuala Road Project (10.6 Km)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Lospalos Tutuala 10.5 Km
Empresa: Miguel Group Unipessoal Lda Renardet
Data do Contracto: 27 de Oetubro 2011
Data de Conclusão Inicial: 12 de Fevereiro 2014
Valor Contrato Inicial (US$): 2.760.000,00
Data de Conclusão revisto 1: 5. 31 de Dezembro 2014
Valor contrato revisto 1 (US$): 3.695.729,13
Progresso Fisico actual:
Procento 95%
Pagamentos / Estado Financeira
Pagamento FI 2012 (US$): 689.786,79
Pagamento FI 2013 (US$): 152.447,26
Pagamento FI 2014 (US$): 877.803,89
Pagamento FI 2015 (US$):
Total Pago (US$): 1.720.037,93
Balanço do Contrato (US$): 1.975.691,20
Table 8.7: Rehabilitation of Lospalos - Iliomar Road Project (13.6 Km)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Lospalos Iliomar 13.6 Km
Empresa: Maek Kiar Unipessoal Lda Renardet
Data do Contracto: 19 de Julho 2011
Data de Conclusão Inicial: 22 de Setembro 2014
Valor Contrato Inicial (US$): 3.680.000,00
Data de Conclusão revisto 1: 6. 31 de Dezembro 2014
Valor contrato revisto 1 (US$): 3.680.729,13
Progresso Fisico actual:
Procento 42%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 192.427,20
Pagamento FI 2014 (US$): 963.792,00
Pagamento FI 2015 (US$):
Total Pago (US$): 1.156.219,2
Balanço do Contrato (US$): 2.523.780,80
41 | P a g e
8.2.10 Rehabilitation of Atauro Vila – Beloi – Macadade / Biqueli Roads
The rehabilitation for Atauro Vila to Beloi Section (9 km) for first phase was contracted to
Hidayat Unip Lda with total amount of US$1,464,788.74 on 19 July, 2011 and completed in
February 2012. All payment has been made to company. CAFI meeting dated 22 August 2014
approved rehabilitation of Atauro Vila – Maumeta – Beloi – Biqueli Roads (Sta. 0+000 –
12+372) second phase through single source with total contract amount of US$3,830,011 to
Hidayat Unip Lda.
The project owner that the project has been achieved 85% completed and it expected to be
completed by end of 2015. No disbursements made by end this reporting report as claim still
under review of the project owner. Details of the contract are presented in Table 8.9.
Table 8.8: Rehabilitation of Weleu - Tilomar Road Project (14 Km)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Weleu Tilomar 14 Km
Empresa: Marabia Unipessoal Lda Renardet
Data do Contracto: 6 de Janeiro 2011
Data de Conclusão Inicial: 1 de Novembro 2011
Valor Contrato Inicial (US$): 4.257.112,70
Data de Conclusão revisto 1: 7. 24 de Agosto 2013
Data de Conclusão revisto 2: 8. 20 de Agosto 2015
Valor contrato revisto 2 (US$): 4.257.112,70
Progresso Fisico actual:
Procento 64.43%
Pagamentos / Estado Financeira
Pagamento FI 2011 (US$): 1.043.684,67
Pagamento FI 2012 (US$): 367.477,19
Pagamento FI 2013 (US$): 0.00
Pagamento FI 2014 (US$): 394.336,58
Pagamento FI 2015 (US$): 0.00
Total Pago (US$): 1.805.498,44
Balanço do Contrato (US$): 2.451.614,26
8.2.11 Rehabilitation of Maubisse-Turiscai Road (20.5 km)
The project was divided into 2 phases executed by Montana Diak Unipessoal Lda. The first
phase which commenced on 22 September 2011 has a total length of 10 km. to be completed
within 840 calendar days while the second phase covers the remaining 10.5 km which started
on 1 November 2013. The physical reported as reported by project owner was 78%. However,
none disbursement made in this reporting period as the claims still under verification of the
project owner. Details of the both projects are presented in Table 8.10.
42 | P a g e
Table 8.9: Rehabilitation of Atauro Vila – Maumeta – Beloi – Biqueli Phase II Project
Estado do projecto Completo Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada
Atauro Vila – Beloi –
Macadade/Biqueli 9 Km
Reabilitação de Estrada
Atauro Vila – Maumeta -
Beloi - Biqueli 12.372 Km
Empresa: Hidayat Unipessoal Lda Hidayat Unipessoal Lda Renardet
Data do Contracto: 19 de Julho2011 28 de Agosto 2014
Data inicio de obra 19 de Julho2011 28 de Agosto 2014
Data de Conclusão Inicial: 31 de Dezemmbro 2013 28 de Agosto 2015
Valor Contrato Inicial (US$): 1.464.788,74 4.830.011,46
Valor contrato revisto (US$): 1.464.788,74 4.830.011,46
Progresso Fisico actual:
Procento 100% 85%
Pagamentos / Estado Financeira
Pagamento FI 2011 (US$): 293.000,00
Pagamento FI 2012 (US$): 8050948,31
Pagamento FI 2013 (US$): 365.840.43
Pagamento FI 2014 (US$): 0,00 3,109,730.45
Pagamento FI 2015 (US$): 0,00
Total Pago (US$): 1.464.788,74 3,109,730.45
Balanço do Contrato (US$): 0,00 1.720.281,02
8.2.12 Rehabilitation of Ossu-Viqueque Road
The project was divided into 2 phases with 3 different contracts. The first phase has only one
contract which was awarded to Uhucae in Joint Venture with Modena. It commenced on 8
November 2011 and completed in December 2012. The second phase is the rehabilitation of
the other two road sections, namely: Assalaitula – Ossu and Ossu – Viqueque. CAFI
approved the second phase in June 2013 and works contract for the first section was awarded
to Uhacae and that for the second section was awarded to Modena Lda.
US$ 0.916 million was disbursed from US$ 0.982 million in this reporting period. Both of the
contracts are progressing. The contractor for Emergency Road Rehabilitation Package II from
Ossu - Viqueque District requested time extension from 15 July 2015 to 31 December 2015.
The requested time extension was verified by NDRBFC and approved by Minister of PWTC
on 18 June 2015. MPS will present requested time extension to the next CAFI meeting for
approval before amend its contract. Details of both contracts are presented in Table 8.11.
8.2.13 Reconstruction of Dili Urban Roads
Reconstruction of Dili Urban Roads as supervised by DRBFC / ADN was implemented by
Consorcio Nacional Timorense Ltd with the final contract value of US$ 29,823,091.27. The
actual works completed after verification of A.D.N. is only for US$ 28,981,709.25. The defect
liability period completed, and final payment of 10% retention has been released in 2014 and
this contract is closed.
43 | P a g e
Table 8.10: Rehabilitation of Maubisse-Turiskai Project (20KM)
Estado do projecto Em Implementação Físico
Estado Físico Construtor
Nome do Projecto: Reabilitação de Estrada
Maubesse-Turiskai 10 Km
Reabilitação de Estrada Maubesse- Bubur
Laran Dalan ba Turiskai (Pacote I)
Empresa: Montana Diak Unip Lda Montana Diak Unipessoal Lda
Data do Contracto: 19 de Julho 2011 31 de Outubro 2013
Data Inicio da Obra 22 de Setembro 2012 1 de novembro 2013
Data de Conclusão Inicial: 31 de Dezembro 2013 31 de Outubro 2014
Valor Contrato Inicial (US$): 2.208.000,00 3.875.082,95
Data de Conclusão revisto 1: 9. 8 de Janeiro 2014 31 de Dezembro 2015
Data de Conclusão revisto 2: 10. 30 de Março 2015
Valor contrato revisto 2 (US$): 2.208.000,00 3.875.082,95
Progresso Fisico actual:
Procento 100% 78%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 1.207.964,43
Pagamento FI 2014 (US$): 725.009,81 1.402.846,39
Pagamento FI 2015 (US$): 0,00
Total Pago (US$): 1.932.974,24 1.402.846,39
Balanço do Contrato (US$): 275.025,77 2.472.236,56
8.2.14 Rehabilitation of Alto Barique to Natarbora Road
This road project was awarded to Consorcio Five Amizade Lda in the amount of
US$3,657,720.96. The contract has been signed on 31 July 2012 with the completion date of
3 May 2013. As reported by ADN, the project was only 86.38% completed with slow progress
of work attributed to bad weather condition. An extension of contract until 31 December 2014
has been agreed. None disbursement in this reporting period as the contractor still rectified
defect indentified by project owner. Details of contract and payment status are presented in
Table 8.12.
Table 8.11: Rehabilitation of Ossu - Viqueque Road Project
Estado do projecto Em Implementação Físico
Estado Físico Construtor
Nome do Projecto: Reabilitação de estrada Assalaitula -Ossu Reabilitação de estrada Ossu-Viqueque
Empresa: Uhacae Unip Lda ModenaUnipessoal Lda
Data do Contracto: 25 de Junho 2013 25 de Junho 2013
Data inicio da Obra 1 de Julho 2013 1 de Julho 2013
Data de Conclusão Inicial: 15 de Julho 2015 15 de Julho 2015
Valor Contrato Inicial (US$): 3,447,900,00 4.003.115,00
Data de Conclusão revisto 1: 11.
Valor contrato revisto 2 (US$): 3,447,900,00 4.003.115,00
Progresso Fisico actual:
Procento 69.4% 63%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 403.200,00 542.880,5
Pagamento FI 2014 (US$): 967.684,06 679.221,52
Pagamento FI 2015 (US$): 374.171,53 541.842,33
Total Pago (US$): 1.745.055,59 1.763.944,36
Balanço do Contrato (US$): 1.702.844,42 2.239.170,64
44 | P a g e
Table 8.12: Rehabilitation of Alto Barique-Natarbora Road Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitação de Estrada Alto Barique Natarbora
Empresa: Consorcio Five Amizade (CFA) Lda.
Data do Contracto: 31 de Julho 2012
Data de Conclusão Inicial: 3 Maio 2013
Valor Contrato Inicial (US$): 3.251.536,00
Data de Conclusão revisto 1: 3. 30 de Dezembro 2014
Valor contrato revisto 1 (US$): 3.251.536,00
Progresso Fisico actual:
Procento 86,38%
Pagamentos / Estado Financeira
Pagamento FI 2012 (US$): 376.448,71
Pagamento FI 2013 (US$): 1.399.802,82
Pagamento FI 2014 (US$): 1.067.166,92
Pagamento FI 2015 (US$):
Total Pago (US$): 2.843.418,45
Balanço do Contrato (US$): 814.302,51
8.2.15 Pothole Repair Nationwide
This project was awarded to Estrada Boot Lda in January 2012 with the scheduled completion
set as 31 August 2013. The physical progress recorded up to date only 71%. While the project
is nationwide in scope, the current works are focused along Dili - Manatuto - Baucau –
Venilale Road. A total of US$ 5,089,848.65 million has been disbursed comprising15%
advanced payment and the amount of US$ 3,192,000 through Letter of Credit. The physical
progress as reported by project owner is 76%. However, no disbursement was made in this
reporting period as MPS are processing payment for some amount of US$ 0.47 from claims 11
to 13 received in November 2015 as per requested of the Ministry of Public works, Transport
and Communication letter dated 8 June 2015. Project details are described in Table 8.13.
Table 8.13: Potholes Repair Nationwide Road Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: National Road Pothole repair in Country Wide
Empresa: Estrada Boot Diak DRBFC/A D N
Data do Contracto: 30 de Janeiro 2012
Data inicio da Obra 30 de Janeiro 2012
Data de Conclusão Inicial: 31 de Augoto 2012
Valor Contrato Inicial (US$): 9.936.885,20
Data de Conclusão revisto 1: 30 de Outubro 2012
Data de Conclusão revisto 2: 31 de Dezembro 2012
Data de Conclusão revisto 3: 25 de Fevereiro 2015
Valor contrato revisto 1 (US$): 9.936.885,20
Progresso Fisico actual:
Procento 76%
Pagamentos / Estado Financeira
45 | P a g e
Procento Adiantamento 15%
Valor Adiantamento (US$): 1.490.532,78
Recuperação de adiantamento (US$): 1.490.532,78
Balanço Adiantamento (US$): 0,00
Pagamento atraves Letter of Credit (US$): 3.192.000,00
Recuperação de LC (US$): 1.094.602,72
Balanço recuperação LC (US$): 2.097.397,29
Pagamento FI 2012 (US$): 1.060.902,64
Pagamento FI 2013 (US$): 1.512.539,06
Pagamento FI 2014 (US$): 917.993,93
Pagamento FI 2015 (US$): 0,00
Total Pago (US$): 8.173.968,41
Balanço do Contrato (US$): 1.762.916,80
Source: MPS analysis and Free Balance report 30 June 2015
8.2.16 Flood Control
From the implementation of ten (10) contracts for flood control works with total contact
amount of US$ US$18,842,633.37 approved by CAFI in 2014 which four (4) completed in
2014. Further, six (6) are continue it construction works in 2015 while one (1) has been
substantial completed and remain are in progress. Provided below are other details for such
flood control structures and the recently approved emergency works protection work at Seisal
River on 22 August 2014 with an approved budget ofUS$4,000,000.00 is still in contractual
process. Further details of contract are presented in Table 8.14.
Table 8.14: Flood Control Program Components Project
Program Estradas e Projecto Empreza Valor
Contrato
Original
('$000)
Despesas Annual
('$000)
Despesas
Total
('$000)
Balanco
do
Contrato
('$000)
Atè fin do
2014
Atè 30-
06-2015
Controlo de cheias 12.709,04 7172.95 214,71 7387,66 5.321,39
Reabilitição Emergencia muro de
proteção na Ribeira Laleia, Distrito
Manatuto
Mejori Unip Lda 1.336,95 1.128,20 1.128,20 208,75
Reabilitição Emergencia muro de
proteção e Barreira na Ribeira Terminal
Becora, Distrito Dili
Jonize Unip Lda 2.151,81 1.932,38 214,71 2.147,09 4,72
Reabilitição Emergencia muro de
proteção ao longo a Ribeira Becora,
Distrito Dili
Carya Timor Leste
Unip Lda
943,71 754,29 754,29 189,42
Emergency works KUHA River
Protection, Suco Caraubalo, Viqueque
Villa, Viqueque
SANA Unipessoal
Lda
1.131,88 1.007,30 1.007,30 124,58
Construction of Gabion Retaining Wall
at Carau Ulun River, Manufahi District
Concorsio
Nacional Manufahi
Lda
1.828,70 720,77 720,77 1.107,93
Construction of Gabion Retaining Wall
at Ayasa River, Manufahi District
Concorsio
Nacional Manufahi
Lda
3.668,71 711,81 711,81 2.956,90
New Construction of Retaining Wall at
Comoro River, Beduku, Dili
Hunter Const. Unip
Lda
1.647,28 918,21 918,21 729,07
Source: Book 6 2015
46 | P a g e
8.2.17 Rehabilitation of Aituto - Same Road
The contract for rehabilitation of Aituto - Same Road was awarded to Tinolina and King
Construction Unipessoal Lda as approved by the Council of Ministers (CoM) dated 7 October
2013. The 24 km of road rehabilitation works commenced on 25 October 2013 under the
contract for US$23,676,115.33 to be completed by 24 October 2015. The rehabilitation works
is progressing but none claim yet submit to MPS for payment. The rehabilitation works are
reported was 48%, while claim from the contractor are under verification of the project owner.
The details are shown in Table 8.15.
Table 8.15: Rehabilitation Aitutu - Same Road Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitacao de estrada Aituto-Same DRBFC / ADN
Empresa: Tinolina Unip Lda JV King Construction Unip Lda Regional Engineer Same
Data do Contracto: 25 de Outubro 2013
Datainicio d Obra 25 de Outubro 2013
Data de Conclusão Inicial: 24 de Outubro 2015
Valor Contrato Inicial (US$): 23.676.115,33
Data de Conclusão revisto 1: 4.
Valor contrato revisto 1 (US$): 23.676.115,33
Progresso Fisico actual:
Procento 48%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 2.587.838,92
Pagamento FI 2014 (US$): 3.088.008,71
Pagamento FI 2015 (US$):
Total Pago (US$): 5.675.847,63
Balanço do Contrato (US$): 18.000.267,70
.
8.2.18 Rehabilitation of Urban Roads in Same
The rehabilitation of urban roads in Same was awarded to Tinolina and King Construction
Unip Lda, the same contractor for Aituto-Same Road. The works commenced on 25 October
2013 upon approval by the Council of Ministers on 7 October 2013. The total contract value
for this project is $16,250,633.14 to cover rehabilitation of 28.86 km road in Same town,
District of Manufahi. The scope of the work involves asphalting of six-meter carriageway,
provision of one-meter shoulder on each side of the alignment, culverts crossing, gabion, as
well as slope protections works. The rehabilitation works is progressing, the contractor
progress report shows that the actual physical progress is 89.78% completed. The contractor is
preparing their claims to the project owner for approval. The details about the project are
shown in Table 8.16.
8.2.19 Rehabilitation of Luro - Buihomau Road
Luro - Buihomau Road Road is part of the district road that connects sub-district of Luro to
the national road linking Baucau and Lautem. This rehabilitation project was awarded to
47 | P a g e
Consorcio ASCEM with a contract amount of US$ 4.95 million. The works commenced on 1
October 2012 and planned completion date was 31 July 2013. Due to some difficulties
including the lack of technical capacity of the contractor to manage activities in the project
site, the contract has been extended two times with the last extension up to 31 July 2014.
ADN and DRBFC reported that the physical progress is about 93%, rehabilitation work still
progressing. A claim from Consorcio ASCEM joint panther was received on 20 March 2015 to
hold next progress payment of the rehabilitation of Luro – Buihomau Roads. The issue were
presented in the CAFI meeting 13 April 2015, CAFI instructed MoPWTC to solve payment
problem between local company and their partner from Indonesia before submission of next
payment to A.D.N. Further, NDRBFC informed that issue has been solved by both company,
the rehabilitation works expected to be completed in 2015. No disbursement in this reporting
report as the claim still under verification of the project owner. The details are shown in Table
8.17.
Table 8.16: Rehabilitation of Urban Road in Same Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitacao de estradas em Same Vila DRBFC / ADN
Empresa: Tinolina Unip Lda JV King Construction Unip Lda Regional Engineer Same
Data do Contracto: 25 de Outubro 2013
Datainicio d Obra 25 de Outubro 2013
Data de Conclusão Inicial: 24 de Outubro 2015
Valor Contrato Inicial (US$): 16.250.633,14
Data de Conclusão revisto 1: 5.
Valor contrato revisto 1 (US$): 16.250.633,14
Progresso Fisico actual:
Procento 89.78%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 3.410.396,33
Pagamento FI 2014 (US$): 5.568.988,31
Pagamento FI 2015 (US$):
Total Pago (US$): 8.979.384,63
Balanço do Contrato (US$): 7.271.248,51
8.2.20 Rehabilitation of Miabuti Edemumo, Sapatula (Edemumo - Iralere Roads) district in
Uatulari Viqueque
The project is part of the emergency roads rehabilitation projects approved by CAFI in June
2013. The rehabilitation works is progressing but none claim yet submit to MPS for payment.
Detail of contract and its disbursement status are presented in table 8.18.
8.2.21 Rehabilitation of Aituto - Ainaro Roads (in Book 6: Dare - Ainaro)
A contract made on 19 August 2013 for rehabilitation of Aituto to Ainaro Road is part of an
emergency rehabilitation work relative to the road blockage caused by heavy rainfall in the
area was completed in July 2014 and all payment was made to the company. Further, the
48 | P a g e
project locations now cover by RCRP - Upgrading and Maintenance of Dili-Ainaro Road LOT
5: Aituto-Ainaro (World Bank Loan financing).
Table 8.17: Rehabilitation of Luro – Buihomau Road Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Reabilitacao de estradas Luro - Buihomau
Empresa: Consorcio ASCEM Renardet
Data do Contracto: 1 de Outubro 2012
Data inicio d Obra
Data de Conclusão Inicial: 3 de Maio 2013
Valor Contrato Inicial (US$): 4.950.000,00
Data de Conclusão revisto 1: 6. 30 de Abril 2014
Data de Conclusão revisto 2: 7. 31 de Janeiro 2015
Valor contrato revisto 1 (US$): 4.950.000,00
Progresso Fisico actual:
Procento 93%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 831.687,42
Pagamento FI 2014 (US$): 2.229.438,83
Pagamento FI 2015 (US$):
Total Pago (US$): 3.061.126,25
Balanço do Contrato (US$): 1.888.873,75
8.2.22 The Construction of Ainaro Villa - Sarai Road (Alternative Road to Jakarta II)
Construction of alternative road to Jakarta II is part of the emergency project approved by
CAFI on 17 June 2013. The purpose of this project is to ensure improved access to Jakarta II
by linking roads that connect Ainaro Vila to Serai which runs parallel to the Ainaro - Cassa
Road. Contract was awarded to Jonize Construction Lda in joint venture with Ramelau Ainaro
Lda in the amount of US$4.2 million. The work commenced on 1 July 2013 and the target
completion date was 1 July 2014. Based on ADN and DRBFC reported both contract are
progressing and contractor still prepare their claim for next payment. Details are presented in
Table 8.19.
8.2.23 Rehabilitation of Dili Urban Roads Phase II
In response to the CPLP summit in July 2014, the Government of Timor Leste through the
Ministry of Public Works awarded 17 contracts to the Timorese companies to rehabilitate the
urban roads in Dili with the total contract value of $60,006,092.28. A total of $16,433,500.29
is paid in 2014 and the balance of $43,572,591.99 will be paid in 2015 and the following year.
It is expected that all 17 contracts will be concluded in 2015. Details of each contract are
highlighted in the Table 8.20.
49 | P a g e
Table 8.18: Project Name: Rehabilitation of Miabuti Edemumi, Spatula Roads
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Rehabilitation of Miabuti Edmumo, Sapatula Road /reabilitacao de estradas
distritais de Uatulari Viqueque District
Empresa: Karakuta Unipessoal Lda Renardet
Data do Contracto: 25 de Junho 2013
Data inicio d Obra 1 de Julho 2013
Data de Conclusão Inicial: 1 de Maio 2014
Valor Contrato Inicial (US$): 1.639.085,75
Data de Conclusão revisto 1: 8. 31 de Maio 2015
Data de Conclusão revisto 2: 9.
Valor contrato revisto 1 (US$): 1.639.085,75
Progresso Fisico actual:
Procento 45.2%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 397.855,29
Pagamento FI 2014 (US$): 268.924,80
Pagamento FI 2015 (US$):
Total Pago (US$): 666.780,08
Balanço do Contrato (US$): 972.305,67
Table 8.19: Emergency Construction of Ainaro Vila - Sarai Road Project (8.23 Km)
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Emergency Construction of New
Roads 8.23 Kms Ainaro Vila-Sarai
Ainaro District
Construction of Two New Bridges
on the Ainaro Vila-Sarai roads
(Alternative Jakarta II)
Regional Engineer of
Same, NDRBFC
Empresa: Jonize Construction Unip Lda JV
with Ramelau Ainaro, Co Lda.
Jonize Cont. Unip Lda JV with
Ramelau Ainaro, Co Lda.
Data do Contracto: 25 de Junho 2013 25 de Junho 2013
Data inicio d Obra 1 de Julho 2013 1 de Julho 2013
Data de Conclusão Inicial: 1 de Julho 2014 1 de Julho 2014
Valor Contrato Inicial (US$): 4.223.004,05 3.596.249,07
Data de Conclusão revisto 1: 10. 1 de Julho 2016 1 de Julho 2016
Data de Conclusão revisto 2: 11.
Valor contrato revisto 1 (US$): 4.223.004,05 3.596.249,07
Progresso Fisico actual:
Procento 55% 8%
Pagamentos / Estado Financeira
Pagamento FI 2013 (US$): 1.931.836,68
Pagamento FI 2014 (US$): 254.163,47 477.714,86
Pagamento FI 2015 (US$):
Total Pago (US$): 2.186.000,15 477.714,86
Balanço do Contrato (US$): 2.037.003.90 3.118.534,21
50 | P a g e
Table 8.20: Dili Urban Roads Project No. Name of Project Company Contract
Value (US$)
Physical
Progress
Total Paid up
to 2014 (US$)
Total
Paid in
2015
(US$)
Balance of
Contract
(US$)
1 Dili Roads and Drainage Rehabilitation,
Roads Section: Tigar Fuel Lecidere (Palacio
Presidente - Bidau Santana)
Monatana
Diak Unip
Lda
4,088,451.43 76% 2,534,136.89 1,554,314.54
2 Dili Roads &d Drainage Rehabilitation,
Roads Section: Jct Metiaut Hera-Cristo Rei
Carya Timor
Leste
3,858,598.28 47% 624764.56 3,233,833.72
3 Dili Roads and Drainage Rehabilitation,
Roads Section: Bidau Bridge-Jct Metiaut
Hera
Arquiris
Unip Lda
3756121.74 36% 767468.43 2,988,653.31
4 Dili Roads and Drainage Rehabilitation,
Roads Section: Ponte Halilaran - Aituri
Laran
Miracle Unip
Lda
2,733,358.41 53% 257,419.55 2,475,938.86
5 Dili Roads and Drainage Rehabilitation,
Roads Section: Palacio Presidente-Jct
Pantai Kelapa, Manadarin-Farol
Meteor Unip
Lda
4,319,153.77 6% 217,836.57 4,101,317.2
6 Dili Roads and Drainage Rehabilitation,
Roads Section: Palacio Governo -
Procuradoria da Republica
Jonize
Construction
Unip Lda
3,749,042.43 29% 642,846.71 3,106,195.72
7 Dili Roads and Drainage Rehabilitation,
Roads Section: Maufelo Bridge-Koramil
Becora
Mejori Unip
Lda
3,064,813.39 50% 921,518.45 2,143,294.94
8 Dili Roads and Drainage Rehabilitation,
Roads Section: Koramil Becora-Terminal
Becora
Nananiu
Unip Lda
2,763,327.67 38% 640,346.22 2,122,981.45
9 Dili Roads and Drainage Rehabilitation,
Roads Section: Bidau Kuluhun-Maufelo
Bridge
Tasi
Naroman
Unip Lda
2,889,099.11 39% 615,530.24 2,27,3568.87
10 Dili Roads and Drainage Rehabilitation,
Roads Section: Palacio Presidente-
Bairopite-Cacaulidun-Tugu Pramuka
Santana Diak
Unip Lda
4,266,265.70 60% 1,129,742.09 3,136,523.61
11 Dili Roads and Drainage Rehabilitation,
Roads Section: Cina Rate-Becora
Marabia
Unip Lda
3,863,286.35 34% 359,466.14 3,503,820.21
12 Dili Roads and Drainage Rehabilitation,
Roads Section: Cruzamento Bemori-Largo
Lecidere
Rai Naroman
Unip Lda
2,757,409.45 46% 1,110,580.58 1,646,828.87
13 Dili Roads and Drainage Rehabilitation,
Roads Section: Rotunda-Mercado Lama-
Ponte Kuluhun
Suai Indah
Lda
3,656,954.47 60% 1,826,829.64 1,830,124.83
14 Dili Roads and Drainage Rehabilitation,
Roads Section: Bidau-ANZ-Palacio
Governo
Aspalink
Unip Lda
3,490,502.92 42% 790,005.31 2,700,497.61
15 Dili Roads and Drainage Rehabilitation,
Roads Section: Becora Bridge-Hera Jct
Fitun Diak
Unip Lda
4,388,058.13 63% 2,298,608.07 2,089,450.06
16 Dili Roads and Drainage Rehabilitation,
Roads Section: Leader-Elemloi
Hedge Const
Unip Lda
1,935,713.42 61% 483,165.51 1,452,547.91
17 Dili Roads and Drainage Rehabilitation,
Roads Section:Halilaran - Matadoro - Ponte
Obrigado Barak
Monte
Veado Lda
4,425,935.61 60% 1,213,235.334 3,212,700.28
Total 60,006,092.28 16,433,500.29 43,572,591.99
Following, The Ministry of Public Works, Transport and Communication presented another
list of emergency road rehabilitation to the CAFI meeting dated 24 April 2015. The Minister
informed that project was related to the visit of CPLP, celebrations in Aileu, etc with total 21
projects at estimated budget of US$ 55,593,327.13. The list of project has been approved in
previous CAFI meeting in 2014 but it does not include in the minutes, therefore, CAFI
instructed MPS to elaborate these emergency projects in the minutes of meeting on 24 April
2015. Details of each contract are highlighted in the Table 8.21.
51 | P a g e
Table 8.21: 2015 Dili Urban Roads Project Phase II
No. Name of Project Company Budget
(US$)
Physical
Progres
s
Remarks
1 Dili Roads and Drainage Rehabilitation Embassy
Portugal, Aitarak Laran Roads
Super Jaya Unip.
Lda
1,517,202.13 40% Project verified by A.D.N.
2 Dili Roads and Drainage Rehabilitation Palacio
Presidente - Finanças - Tasi Ibun
Hidayat Unip.
Lda
4,054,769.23 20% Project verified by A.D.N.
3
Dili Roads and Drainage Rehabilitation
Cruzamento Aitarak Laran Mesid An'ur KBRI
Helmi
Construction
Unip. Lda
3,701,758.11 50% Project verified by A.D.N.
4 Dili Roads and Drainage Rehabilitation Fomento
I to Timor Block Junction
Lizy Unip. Lda 1,723,410.62 10% Project verified by A.D.N.
5 Dili Roads and Drainage Rehabilitation Timor
Block Junction to SD Fomento
Aban Loron
Futuru Unip. Lda
3,163,388.61 72% Project verified by A.D.N.
6 Dili Roads and Drainage Rehabilitation SD
Fomento - Uma Roofing
King Const.
Unip. Lda
3,425,598.15 80% Project verified by A.D.N.
7 Dili Roads and Drainage Rehabilitation Timor
Block Junnction to Elemloi Jct
Funan Buras
Unip. Lda
1,488,028.63 60% Project verified by A.D.N.
8 Dili Roads and Drainage Rehabilitation Elemloi
Jct Hudilaran
Tinolina Unip.
Lda
4,803,143.5 10% Project verified by A.D.N.
9 Dili Roads and Drainage Rehabilitation
Hudilaran - Bairo Pite
Pereira Limitada
Unip. Lda
4,687,374.86 30% Project verified by A.D.N.
10
Dili Roads and Drainage Rehabilitation Ocean
view (Arbiru Hotel) Comoro river downstream
Comoro Bridge (North of Bridges)
G and S
Unipessoal Lda
4,733,745.44 8% Project verified by A.D.N.
11 Dili Roads and Drainage Rehabilitation
downstream Comoro bridge area roads
Nautetu Unip.
Lda
2,664,763.11 15% Project verified by A.D.N.
12
Dili Roads and Drainage Rehabilitation Timor
Block east Comoro river and intersection of
future bridge 3 west Comoro
Sangus Unip.
Lda
4,163,849.09 5% Project verified by A.D.N.
13 Roads and Drainage Rehabilitation Auto Timor -
Bebonuk
Hidayat
Unipessoal Lda
2,567,424.86 10% Project verified by A.D.N.
14
Construction of Jct Lacloho-Duyung roads 2,32,7969.13 42% CAFI dated 14 Nov 2014
approved but it does not
write in the minutes.
A.D.N. still verify this
project
15 Rehabilitation Lapangan Sepak Bola Aileu 184,647.42 63% Project verified by A.D.N.
16 Rehabilitation of Sloi Tocoluli roads Aileu 218,231.77 25% Project verified by A.D.N.
17 Rehabilitation Bacamp roads Aileu Town 417,602.26 31% Project verified by A.D.N.
18
Rehabilitation Lapangan Cararas Hoven II Unip.
Lda
CAFI dated 14 Nov 2014
approved but it does not
write in the minutes.
A.D.N. still verify this
project
19 Dili Roads and Drainage Rehabilitation Liceu to
Colmera
Quatro Colegas
Unip. Lda
1,272,987.42 Project verified by A.D.N.
20 Dili Roads and Drainage Rehabilitation Catedral
- Campo Demokrasia
Tifoho Const.
Unip. Lda
4,676,932.15 Project verified by A.D.N.
21 Dili Roads and Drainage Rehabilitation Jct
Campo Democrasia Jct ponte Bidau Masau
Shabryca Const.
Unip. Lda
3,800,500.64 Project verified by A.D.N.
Total 55,593,327.13
Source: National Directorate of Roads, Bridge and Flood Control, MoPWTC, 24 April 2015
In addition to the above projects in the table 8.21 contract has been made for 17 companies
after all relevant project documents from NDRBFC-MPWTC verified and approved by
A.D.N. Details of each project summarized in the table 8.22.
52 | P a g e
Table 8.22: Contract Data for 17 Urban Roads Project Phase II
No. Name of Project Company Date of
Contract
Contract
Duration
(days)
Contract Value
(US$)
Physical
Progress Remarks
1 Dili Roads and Drainage Rehabilitation
SD Fomento - Uma Roofing
King Const.
Unip. Lda
8 June
2015
365 3,225,598.15 80% Project in
progress
2 Dili Roads and Drainage Rehabilitation
Timor Block Junnction to Elemloi Jct
Funan Buras
Unip. Lda
8 June
2015
365 1,239,284.63 60% Project in
progress
3 Dili Roads and Drainage Rehabilitation
Timor Block Junction to SD Fomento
Aban Loron
Future Unip.
Lda
8 June
2015
365 2,963,388.61 72% Project in
progress
4 Dili Roads and Drainage Rehabilitation
Fomento I to Timor Block Junction
Lizy Unip. Lda 8 June
2015
365 1,523,410.62 10% Project in
progress
5 Dili Roads and Drainage Rehabilitation
Elemloi Jct Hudilaran
Tinolina Unip.
Lda
8 June
2015
365 4,603,143.50 10% Project in
progress
6 Dili Roads and Drainage Rehabilitation
Hudilaran - Bairo Pite
Pereira
Limitada Unip.
Lda
8 June
2015
365 4,223,035.47 30% Project in
progress
7 Construction of Jct Lacloho-Duyung
road
S.K.K.B Unip
Lda
12 June
2015
210 2,287,003.33 42% Project in
progress
8 Dili Roads and Drainage Rehabilitation
Catedral - Campo Demokrasia
Tifoho Const.
Unip. Lda
22 June
2015
575 4,579,932.15 Project in
progress
9 Dili Roads and Drainage Rehabilitation
Jct Campo Democrasia Jct ponte Bidau
Masau
Shabryca
Construction
Unip. Lda
22 June
2015
575 3,700,500.64 Project in
progress
10 Dili Roads and Drainage Rehabilitation
Timor Block east Comoro river and
intersection of future bridge 3 west
Comoro
Sangus I Unip.
Lda
22 June
2015
365 3,752,597.99 5% Project in
progress
11 Dili Roads and Drainage Rehabilitation
Liceu to Colmera
Quatro Colegas
Unip. Lda
22 June
2015
140 1,122,987.42 Project in
progress
12 Dili Roads and Drainage Rehabilitation
downstream Comoro bridge area roads
Nautetu I, II
Unip. Lda
22 June
2015
300 2,377,535.18 15% Project in
progress
13 Dili Roads and Drainage Rehabilitation
Ocean view (Arbiru Hotel) Comoro
river downstream Comoro Bridge
(North of Bridges)
G and S
Unipessoal Lda
22 June
2015
365 4,290,731.32 0% Project in
progress
14 Dili Roads and Drainage Rehabilitation
Embassy Portugal, Aitarak Laran Roads
Super Jaya
Unip. Lda
22 June
2015
365 1,357,264.81 40% Project in
progress
15 Dili Roads and Drainage Rehabilitation
Cruzamento Aitarak Laran Mesid An'ur
KBRI
Helmi
Construction
Unip. Lda
22 June
2015
365 3,501,758.11 50% Project in
progress
16 Dili Roads and Drainage Rehabilitation
Palacio Presidente - Financas - Tasi
Ibun
Hidayat Unip.
Lda
22 June
2015
3,854,769.23 20% Project in
progress
17 Roads and Drainage Rehabilitation
Auto Timor - Bebonuk
Hidayat Unip.
Lda
22 June
2015
2,417,424.86 10% Project in
progress
Total 51,020,366.02
Source: National Directorate of Roads, Bridge and Flood Control, MoPWTC, 17 and 26 June 2015
8.2.24 New Road Projects
A number of new road projects were approved budget allocation for each project and it will
implement in 2015. The National Directorate of Bridge and Flood Control of the Ministry of
Transport Communication and Public Works will prepare bid documents for these projects.
The allocation budget was increased from US$ 9.6 million to US$ 12.3 million due to
rectification of allocated budget late March 2015 and virement as per CAFI decision dated 24
April 2015The details of each project as shown in table 8.23.
53 | P a g e
Table: 8.23 Summary Budget Allocations for New Roads
No Projecto Orçamento 2015 ($000) Commentarios
Original Revição
Total 9.567 12.277
1 Rehabilitação Estrada Zumalai Beco-Suai
(Fase II)
1.000 300 Need finalise bid documents
and tender
2 Rehabilitação de Estradas Lepo - Zumalai 20
km
500 500 Need finalise bid documents
and tender
3 Construção de Estradas e Esgotos, Posto
Integrado Batugade-Mota Ain
500 500 Previous contract completed
and retention paid
4 Rehabilitação Estrada Karimbala Fase II 9
km
500 500 Need finalise bid documents
and tender
5 Rehabilitação de estrada Dare-Ainaro 131 131 Previous contract completed
and retention paid
6 Rehabilitação de estrada Bobonaro-Suai 486 486 Need finalise bid documents
and tender
7 Rehabilitação de estradas distritais de Wiuka
- Quelikai
500 500 Same as above
8 Rehabilitação de estradas Dili-Manleuana-
Solerema-Aileu 15 km
750 750 Same as above
9 Construção ou rehabilitação de Estradas
Metinaro-Laclo-Manatuto
500 250 Same as above
10 Rehabilitação de Estradas Viqueque- Uatulari
- Watukarbau
500 200 Same as above
11 Reabilitação no Construcao de Estradas
Maliana-Cailaco-Hatolia
500 250 Same as above
12 Rehabilitação de Estradas Venilale-Fatulia-
Waimuri
200 200 Same as above
13 Preparação Estudo e Desenho Detalhado das
Estradas
2.000 1.000 Same as above
14 Aquisicao de Bens Imoveis projectos do FI 1.500 6.710 Same as above
Source: Book 6, 2016
54 | P a g e
9 BRIDGES
9.1 GENERAL
Reliable bridges are crucial for ensuring reliable access to markets, education and health
services and for sustaining security and social stability. These are fundamental requirements
for economic and social development as recognised by the Government in the Strategic
Development Plan 2011 - 2030. Therefore construction of new bridges, rehabilitation of
deteriorated bridges and widening of narrow bridges where justified by high traffic are high
priority projects in the allocation of funds from the Infrastructure Fund. Since the
establishment of this fund, there were 13 completed bridges funded through the IF, four of
which are multi-span structures with an average length of 120 meters and the rest are bridges
of less than 50 meters length. Summary of 2015 budget allocation for bridges and its
disbursement as of end-June 2015 are shown in Table 9.1.
Table 9.1: Summary of 2015 Budget Allocation Status of Disbursement
Projectos
Orçamento
Original
2015 $'000
Orçamento
2015 - após
Virement e
Transferência
Interna$'000
Despesas
ate 30
Junho
2015
$'000
Saldo
Orçament
o $'000 Commentarios
Total 11,317 6,107 11,72.48 4,934.52
Construção de Ponte Dilor 180 m 323 323 323 90% complete
Construção de Ponte Taroman 60 m 245 245 245 Retention will pay in 2015
Construção de Ponte Baer 120 m 316 316 316 5% retention will pay in
2015
Construção ponte de Bidau-Santa Ana 800 200 200 Design process
Reabilitação de pontes 220 220 186.48 Paid retention of Comoro I
Construção Ponte Comoro II 77 77 77 100% completed
Construção Ponte Comoro I 986 986 986.00 Retention paid in May
2015
Construção ponte Lawana, Ermera 1,000 500 500 Construction in progress
Construção ponte Ritabou 500 200 200 Design process
Construcao ponte de travesia de piões de
Raikotu a Maloa
500 200 200 Need bid documents
Construção ponte Mota Masin em Suai 850 350 350 Need bid documents
Construção de Oprit ou normalization da
Ribeira no Ponte Irabere
500 200 200 Need bid documents
Construção Ponte Comoro III 500 0 0
Construção ponte mota ulun Comoro, Dili 500 502 502 Design process
Preparação Estudo e Desenho Detalhado
dos Pontes
1,000 500 500 Need bid documents
Construção do Arco aos Pontes Comoro
I/II (Arch Bridge)
3,000 1,288 1,288 Need bid documents
Sources: IF Book 6 and MPS record
As per above table number of new bridges projects have been planned to implement last but
still cannot implemented due several issues such as incomplete design, tender took longer
process, and insufficient data to complete the design. Therefore, theses new bridge projects
has been shifted to this year, and the budget were allocated accordingly. CAFI meeting 24
April 2015 approved to transfer US$ 5.21 million from US$ 11.317 million allocation budget
55 | P a g e
to Roads Program to cover loan resettlement payment proposed by Project Management Unit
(PMU). The disbursement up to end of June 2015 only US$ 1.173 million due to number of
existing contract are in the retention stage
9.2 PROJECT STATUS
9.2.1 Completed Bridge Projects
Since the establishment of the Infrastructure Fund, a number of bridges have been completed.
These are the long span Daudere Bridge in Lautem district, Belulik Bridge in Ainaro district,
and Comoro II and I in Dili district. The completed small bridges that have been constructed
or rehabilitated are: Aiasa Bridge, Loes Bridges and Mola Bridge Details of the completed
bridge projects and retention paid are summarised in Table 9.2.
Table 9.2: Summary of the completed Bridge Projects
Programa de Pontes Companhia
Valor
Contrato
('$000)
Progress
o Físico
Progresso
Financeira Despesas ('$000) Ate Total
Despesas
('$000) Sal
do
('$
00
0)
Ob
serv
ação
% % Fin do
2014
30 Jun
2015
Total 37.079,10 35.642,86 1.172,48 36.815,33 13,77
Construção de Ponte
Daudere 120 m
Carya Timor
Leste 4.616,48 100 99,.98 4.615,75 4.615,75 Concluido
Construção de Ponte
Belulik 180 m
Posco Plant Eng.
Co. Ltd JV East
Sunrise TL
Construction
5.602,00 100 100
5.602,10 5.602,10 Concluido
Construção de Ponte
Bukoli 15 m
Perola de Timor
Unip Lda 405,.00 100 100
405,00 405,00 Concluido
Construção de Ponte
Lebaloa Bazartete 15 m
Betbor Unip
Lda. 786,65 100 100
786,65 786,65 Concluido
Construção de Ponte Jct
Laclubar para Manehat
40 m
Risah Unip Lda
859,77 100 100
857,77 857,77 Concluido
Construção Ponte
Comoro I
CNT JV WiKa 11.724,77 100
100 10.552,29 1.172,48 11,724.77
Concluido Construção Ponte
Comoro II
CNT JV WiKa 8.758,09 100
99,85 8.744,94 8.744,94
Concluido Rehabilitação ponte
Loes
Istaka Karya 1.523,29 100
83,59 1.723,29 1.723,29
Concluido Rehabilitação ponte
Aiasa
Jonize Co. JV
PT. Multi Arch 2.803,05 100 100
2.803,05 2.803,05 Concluido
Sources: IF Book 6 and MPS record
9.3 ON-GOING BRIDGE PROJECTS
9.3.1 Construction of Dilor Bridge
Dilor Bridge is located in the sub-district of Dilor, Viqueque that connects the south coast
network from Natarbora to Viqueque Road. The 180 meter long bridge plays an important role
in ensuring access to the agricultural areas in the south of Manatuto and Viqueque districts.
The contract was awarded to PT Daya Mulia Turangga JV Precision Corporation Unip Lda on
31 May 2011 to be completed in 365 calendar days in the amount of US$3.2 million.
56 | P a g e
This project has suffered significant delays due to deferred delivery of construction materials
to the site caused by bad weather, while the contractor failed to submit documents for piling
works to the supervision engineer on time. As reported by DRBFC and ADN, the physical
progress was 93% as of end of June 2014. As the reported by DRBFC and ADN that
contractor still fixing defect identified and finalise no completion item. Details of contract and
its payment status are summarised in Table 9.3.
Table 9.3: Construction of Dilor Bridge Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Construção de Ponte Dilor 180 m
Empresa: PT Daya Mulya Turangga Bonifica S.P.A
Data do Contracto: 31 Maio 2011
Data de Conclusão Inicial: 31 Maio 2012
Valor Contrato Inicial (US$): 3.251.536,00
Data de Conclusão revisto 1: 12. 31 Outubro 2015
Valor contrato revisto 1 (US$): 3.251.536,00
Progresso Fisico actual:
Procento 100%
Pagamentos / Estado Financeira
Pagamento FI 2011 (US$): 219.761,26
Pagamento FI 2012 (US$): 179.508,29
Pagamento FI 2013 (US$): 1.819.285,09
Pagamento FI 2014 (US$):
Pagamento FI 2015 (US$):
Total Pago (US$): 2.218.554,64
Balanço do Contrato (US$): 1.032.981,36
9.3.2 Taroman Bridge
Taroman Bridge is a steel truss with 60-meter span located in Covalima district. The contract
for its construction was awarded to ENSUL Esphera Engenharia SA on 10 November 2011 in
the amount of US$2.4 million and was due for completion by December 2012. However, the
contractor failed to complete the works as scheduled due to financial difficulties, poor access
to the project site, and weather condition. CAFI’s agreed in its meeting held on 21 February
2014 to a contract extension up to 31 July 2014. Considering site status on 22 August 2014
CAFI approved to extend the contract up to 31 October 2015. As reported by ADN and
DRBFC, the physical work has completed and handed over to the Government in early
December 2014. No disbursement in this reporting period as claim from contractor still under
verification of the project owner Details of contract and status of project are summarised in
Table 9.4.
57 | P a g e
Table 9.4: Construction of Taroman Bridge Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Construção de Ponte Taroman 60 m
Empresa: Ensul Esphera Engenaria Bonifica S.P.A
Data do Contracto: 10 November 2011
Data de Conclusão Inicial:
Valor Contrato Inicial (US$): 2.445.005,05
Data de Conclusão revisto 1: 13. 31 Outubro 2015
Valor contrato revisto 1 (US$): 2.445.005,05
Progresso Fisico actual:
Procento 100%
Pagamentos / Estado Financeira
Procento Adiantamento 20%
Valor Adiantamento (US$): 489.011,19
Recuperação de adiantamento (US$): 489.011,19
Balanço Adiantamento (US$): 0,00
Pagamento FI 2011 (US$): 0,00
Pagamento FI 2012 (US$): 118.554,34
Pagamento FI 2013 (US$): 534.782,19
Pagamento FI 2014 (US$): 748.067.96
Pagamento FI 2015 (US$): 0,00
Total Pago (US$): 1.890.405.68
Balanço do Contrato (US$): 554.600.27
9.3.3 Construction of Comoro I Bridge
Replacement of Comoro I Bridge commenced on 28 May 2013 and was completed by end-
May 2014 was carried out by Consorcio Nacional Timorense (CNT) in Joint Venture with
Wijaya Karya (Wika).This bridge carries the eastbound carriageways of the major
thoroughfare linking Dili with the Nicolao Lobato International Airport. The contract has
amended to accommodate the pedestrian way at both sides of the bridges which is increased
the contract value to $11,724,769.46. The retention payment has been released in May 2015
and the project is closed. Details of contract and payment status are presented in Table 9.5.
Table 9.5: Construction of Comoro Bridge Project
Estado do projecto Em Implementação Físico Desenho e Supervisão
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Construção de Ponte Comoro I
Empresa: CNT JV WiKa DNEPCC
Data do Contracto: 14 Agosto 2013
Data de Conclusão Inicial: 14 Maio 2014
Valor Contrato Inicial (US$): 9.845.885,04
Data de Conclusão revisto 1: 14.
Valor contrato emenda 1 (US$): 1.878.884,42
Valor contrato revisto 1 (US$): 11.724.769,46
Progresso Fisico actual:
Procento 100%
Pagamentos / Estado Financeira
Procento Adiantamento 20%
58 | P a g e
Valor Adiantamento (US$): 1.969.177,01
Recuperação de adiantamento (US$): 1.969.177,01
Balanço Adiantamento (US$): 0,00
Pagamento FI 2013 (US$): 261.900,54
Pagamento FI 2014 (US$): 8.321.214,86
Pagamento FI 2015 (US$): 1,172,476.93
Total Pago (US$): 11.724.769,34
Balanço do Contrato (US$): 0,12
Sources: Free Balance 30 June 2015
9.3.4 New Lauala Bridges in Gleno
CAFI meeting dated 22 August 2014 has approved award contract for Construction of new
Lauala Bridge on the road between Gleno - Gleno, Ermera District to Mejori Unipessoal Lda
in Joint Venture with Seisura Unipessoal Lda at US$ 1,718,404 based on the cost estimated
evaluated by National Development. The contract was signed on29 September 2014 and
intended to be completed within 540 calendar days. The allocation budget for 2015 is for $ 1
million but CAFI meeting 24 April 2015 approved to transfer US$ 0.5 million to roads
program. As reported by NDRBFC that the construction works has commenced but none
claim received at this reporting period.
9.3.5 Rehabilitation of New Bridges
To provide better connection, accessibility and safe travel, The NDRBFC has identified
number existing and new bridges which planned to be implementing last year and shifted to
this year. Total allocation budget has approved for these new project are US$ 9.15 million. List
of new bridges summarised in Table 9.6.
Table 9.6: Summary of 2015 Budget Allocation Status for New Bridges
No. Naran Projecto
Orçamento 2015 ('$000)
Observações Original Orçamento 2015
- após Virement
Total 8.150 3.440
1 Construção ponte de Bidau-Santa Ana 800 200 1. Precisa prepar e sumissão
documentos concurso
2 Construção ponte Ritabou 500 200 Idem
3 Construcao ponte de travesia de piões de
Raikotu a Maloa
500 200 Idem
4 Construção ponte Mota Masin em Suai 850 200 Idem
5 Construção de Oprit ou normalization da
Ribeira no Ponte Irabere
500 200 Idem
6 Construção Ponte Comoro III 500 200 Idem
7 Construção ponte mota ulun Comoro, Dili 500 200 Idem
8 Preparação Estudo e Desenho Detalhado dos
Pontes
1.000 500 Idem
9 Construção do Arco aos Pontes Comoro I/II
(Arch Bridge)
3.000 1.288 Idem
Sources: Free Balance and MPS Record as of 30 June 2015
59 | P a g e
10 PORTS AND AIRPORTS
10.1 PORTS
Development of ports is very important to support economic growth of Timor Leste and to
respond to the growth of local industry and export-import activities that require fast and
reliable freight service. Short term programs for IF shall focus on the following projects:
Development Suai Port
Necessary rehabilitation of Dili Port.
Upgrade of port facilities for regional ports in Com, Atauro, Oecussi and Vemase
Construction of the new Tibar Bay Port, to start by 2015
Necessary rehabilitation of Hera Port.
As per government plan, the Suai Port will be combined with the Supply-Based Port under the
Tasi Mane Development Program. Total budget allocated for port projects in 2015 was US$
7.855 million. The budget was rectified to US$ 3.855 which is US$ 4 million was transfer out
from IF to ZEEMS. Overall disbursement in this reporting period was 6%. Details allocation
budget and disbursement status is summarized in table 10.1.
Table 10.1: Summary of Budge allocation and Disbursements status as of 31 March 2015
Project
Original Budget
Allocation 2015
('$000)
Revised
Budget 2015
('$000)
Expenditure
as of 30 June
2015 ('$000)
Balance
2015
('$000)
Excavation (Dredging) and Rehabilitation of Dili
Port
1,500 500 500
Construction and Supervision of Atauro Port
development
500 250 250
Transaction , construction and supervision Port
of Tibar (PPP )
4,605 2,105 2,105
Rehabilitation and Supervision of Com Port 500 250 250
Excavation ( Dredging ) and Rehabilitation of
Hera Port, Dili
750 750 249 500
Construction and Supervision of Vemase Port - - -
Total 7,855 3,855 249 3,505
Sources: Book 6 rectification, June 30, 2015
Details budget allocation of port program and of port sub-programs as of 30 June 2015 are
presented as follows:
10.1.1 Excavation, Dredging, and Rehabilitation of Dili Port
The budget line under this project is utilized to finance rehabilitation and excavation works of
the Dili Port. In the fiscal year of 2014, the government engaged “Ramkaby-Tasibala II Lda”
for the excavation and dredging at Dili port with the contract amount of US$ 3,746,722. The
dredging and excavation works were completed in 2014 and all payment has been made to the
60 | P a g e
company. Further rehabilitation of Dili Port may be required and therefore the government
allocated US$ 1.5 million in 2015 and it was revised to US$ 0.5 million.
10.1.2 Construction and Supervision of Regional Ports Development (Atauro and
Carabela)
The budget allocation for Regional Ports Development which include study and concept
design of the existing ports is only cover for Atauro and Com. As required by the Project
Owner, TOR has to be improved with the corresponding adjustment in budget prior to its
resubmission to ADN and NPC.
In 2014, CAFI meeting 22 August 2014 decided and approved to use allocation budget for
Com and Atauro Ports to pay the construction of dry port of Cargo (container) terminal in
Tasitolu as an extension of Dili Port and balance to be release in 2015, with the details shown
in table 10.2. For the study and design of Atauro and Carabela, US$ 0.5 million was allocated
in 2015 as the project in the preparation of TOR the allocation budget was rectified US$ 0.25
million in March 2015.
10.1.3 Transaction, Construction and Supervision Port of Tibar (PPP)
The budget line under this project is utilized to finance the Tibar Bay Container Port
Development, which has been prepared under PPP modality. The status of the project in under
evaluation of the four shortlisted companies and the evaluation is being finalise based on
comments and inputs from bidder. It expected issuance of final bidding documents will carry
out in the next quarter report. For the design and build of project US$ 4.605 was allocated in
2015 that is expected to cover the initial cost of the project which may include the transaction
cost and cost for detail engineering design. As the project still in the procurement stage the
allocation budget was rectified to US$ 2.105 million in March 2015.
Table 10.2: Construction of Dry Port of Cargo (Container) Terminal in Tasitolu Project
PROJECT SUMMARY Under defect liability period
Company Name W.T.J. Contractor Unipessoal Lda Design & Supervised by A.D.N.
Contract Signing Date 2 September 2013
Commencement Date 6 September 2013
Original Completion Date 30 January 2014
Amendment No. 1 Completion Date 31 December 2014
Amendment No. 2 Completion Date
Audit Court Endorsement Date NA
Issue Notice to Proceed Date
Actual Completion Date 20 November 2014
Original Contract Value 2,335,537.27
Contract Amendment
a. Amendment 1 (Cost / Duration) 0.00
b. Amendment 2 (Cost / Duration) 1,003,875.08
Final Contract Value 3,339,412.35
Physical progress till quarter end % 100
Payment Schedules
Pre IF Payments ($) 2,101,983.54
61 | P a g e
2011 – 2013 IF payments ($) 0.00
2014 IF payments ($) 903,487.57
2015 IF payments ($) 0.00
Total to be paid ($) 3,005,471.11
Balance to be paid ($) 333,941.24
Source: MPS and Free Balance, 30 June 2015
10.1.4 Rehabilitation and Supervision of Com Port
The budget allocation for rehabilitation and supervision of Com Port which include study and
concept design, detailed engineering design and rehabilitation works of the existing Com port.
The Project Owner is assessing the existing facilities before prepare TOR study and design
work. The allocation budget for the project in 2015 was US$ 0.5 million, as the project in the
preparation of TOR the allocation budget was rectified US$ 0.25 million in March 2015.
10.1.5 Excavation, Dredging, and Rehabilitation of Hera Naval Port
There are two projects being implemented by Carya Timor Leste, PTY. One is Dredging and
Excavation of Hera Naval Port Project with a physical progress of 100% as of end-2014.
Futher development of the projects, US$ 0.75 million was allocated in 2015. Details are
shown in table 10.3.
Table 10.3: Excavation, Dredging, and Rehabilitation of Hera Naval Port Project
PROJECT SUMMARY
Status Under defect liability period
Company Name Carya Timor Leste Unipessoal Lda Design & Supervised by A.D.N.
Contract Signing Date 2 January 2012
Commencement Date 2 January 2012
Original Completion Date 28 October 2012
Amendment No. 1 Completion Date 30 April 2013
Amendment No. 2 Completion Date 31 December 2014
Audit Court Endorsement Date NA
Issue Notice to Proceed Date
Actual Completion Date 25 Aug 2014
Original Contract Value 4,934,749.98
Contract Amendment
a. Amendment 1 (Cost / Duration) 0.00
b. Amendment 2 (Cost / Duration) 0.00
Final Contract Value 4,934,749.98
Physical progress till quarter end % 100
Payment Schedules
2013 IF payments ($) 3,230,846.98
2014 IF payments ($) 939,751.37
2015 IF payments ($) 0.00
Total to be paid ($) 4,170,598.35
Balance to be paid ($) 764,151.63
Source: MPS and Free Balance, 30 June 2015
62 | P a g e
The second project is the Urgent Rehabilitation of Armor Rock in Naval Base Hera which has
reached a physical progress of 89% with the details provided in the table 10.4:
Table 10.4: Rehabilitation of Armor Rock in Naval Base Hera Project
PROJECT SUMMARY
Status Under defect liability period
Company Name Carya Timor Leste Unipessoal Lda Design & Supervised by A.D.N.
Contract Signing Date 1 Aug 2013
Commencement Date 1 Aug 2013
Original Completion Date 31 Aug 2014
Amendment No. 1 Completion Date 31 December 2014
Amendment No. 2 Completion Date 31 May 215
Amendment No. 3 Completion Date 15 July 2015
Audit Court Endorsement Date NA
Issue Notice to Proceed Date
Actual Completion Date 25 Aug 2014
Original Contract Value 4,934,749.98
Contract Amendment
a. Amendment 1 (Cost / Duration) 0.00
b. Amendment 2 (Cost / Duration) 0.00
c. Amendment 3 (Cost / Duration) -289,821.13
Final Contract Value 4,137,830.41
Physical progress till quarter end % 94.91
Payment Schedules
2014 IF payments ($) 3,532,785.41
2015 IF payments ($) 249,433.97
Total to be paid ($) 3,782,219.38
Balance to be paid ($) 355,611.03
Source: MPS and Free Balance, 30 June 2015
10.2 AIRPORTS
The Government of Timor Leste has a vision to improve and develop existing airport i.e. Dili,
Suai, Baucau, Maliana and Viqueque as clearly identified in the SDP southern coast
infrastructure development, the government has commenced the in upgrading of Suai Airport
where, construction has started in 2014. The Dili airport development on the other hand has
undergone various studies on the economic, financial feasibilities as well as technical, social,
and environment impact assessment in order to provide a better air transport facility in
supporting the transport of goods and services and in enhancing and supporting the tourism
development in the country.
By taking the result of the previous studies conducted by IFC, the government of Timor Leste
needs to go further stage of the Dili Airport development, which is detail study and
engineering design. Budget allocation for airport program in 2015 is US$ 19 million and
rectified to US$ 14,000 in addition to restructure of the VI Government these are provided in
table 10.1.
63 | P a g e
Table 10.1: Summary Budget Allocated for Airport Program
Project
Original
Budget
Allocation
2015
('$000)
Rectification
Budget
Allocation
2015 ('$000)
Disbursement
as of 30 June
2015 ('$000)
Balance
2015
('$000)
Remarks
Design, Construction and
supervision for Southern Coast
infrastructure development of
Suai Airport rehabilitation
13,000 13,000 3,471.42 9,528.58 Construction
and Supervision
in progress
Rehabilitation of runway,
construction of Dili Airport
5,000 500 500
Design, construction and
supervision for the
Development of Dili Airport
1,000 500 500
Design, construction and
supervision for the
Development of Maliana
Airport
Design and study for the
Infrastructure Development of
Southern Coast - Viqueque
Airport
Design, construction and
supervision for the
Development of Baucau Airport
Total 19,000 14,000 3,471.42 10,528.58
Source: MPS and Free Balance, 30 June 2014
Following are the status of individual projects of the Airport Program:
10.2.1 DESIGN CONSTRUCTION AND SUPERVISION OF SUAI AIRPROT
The overall objective of the project is to improve aviation services for easy access of the
population to Suai as well as the transport needs by in the mineral and agricultural sectors. The
preliminary design, detailed engineering design and bid documents were completed on 31 July
2012 by Jurutera Perunding Zaaba Sdn Bhd (JPZ). The design documents were reviewed by
Katahira and Engineers International (KEI) in Joint Venture with Schema Consultant through
direct appointment by Ministry of Transport and Communication at US$ 0.28 million which
was paid from the budget of airport program. The reviewer consultant was approved by CAFI
on 21 February 2014. As result cost estimate for the rehabilitation works was increased from
US$ 56.14 million to US$ 67 million.
In 2014, the Rehabilitation of Suai Airport Project was awarded to PT Waskita Karya
(Persero) Tbk with Jurutera P. Z. Sdn. Bhd as the Supervision Consultant. The construction of
support facilities for Suai Airport was awarded to CHL Industries. Details are provided in
Table 10.2:
64 | P a g e
Table 10.2.: Rehabilitation of Suai Airport and Construction of Infrastructure Facilities Project
PROJECT SUMMARY
Company Name PT Waskita Karya
(Persero) Tbk
Jurutera Perunding
Zaaba Sdn. Bhd
CHL Industries
Unip Lda -
Contract Signing Date 10 January 2014 12 December 2014
Commencement Date May 2014
Original Completion Date March 2016
Audit Court Endorsement Date May 2015 N/A N/A
Issue Notice to Proceed Date 20 May 2015
Actual Completion Date
Original Contract Value 67,691,189.95 3,923,070.00 4,388,204.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 67,691,189.95 3,923,070.00 4,388,204.00
Physical progress till quarter end % 16 16
Payment Schedules
2014 IF payments ($) 13,538,238.00 0.00 877,640.81
2015 IF payments ($) 3,471,422.14 0.00 0.00
Total to be paid ($) 17,009,660.14 1,484,375.95
Balance to be paid ($) 50,681,529.81 3,923,070.00 3,510,563.19
Source: MPS and Free Balance, 30 June 2015
Socialization and Identification of Land and Properties. MPRM through Timor Gap Team,
the socialization and identification of land and properties of the existing Suai Airport was
concluded in November 2014. With the CAFI's approved budget, compensation for two sub
villages will be implemented in two phases. The Phase I is the house construction of prototype
model 75 in the amount of US$ 51,072 per house or a total of US$ 3,830,381, and access road
in the amount of US$ 0.97 million. Phase II, on the other hand, is the construction of training
center. NPC, Ministry of Transport and Communication (MTC), MPRM and relevant
ministries are finalizing the procurement process for the proposed infrastructures.
Project Status. The allocated budget for upgrading of Suai airport in 2014 after virement was
US$ 13,538,238 from US$20 million. An advance payment of US$ 13,538,238 was paid to the
contractor no payment made for the Supervision Consultant in 2014. While, some amount of
US$ 2,785,106.16 was paid for land acquisition and livestock resettlement through Banco
Nacional de Commercio de Timor Leste (BNCTL) in November and December 2014 under
budget code 8080301. The land acquisition and livestock payment was approved by CAFI on
its meeting on 24 October 2014. MPRM and BNCTL still processing land acquisition payment
to the affected people, it will accommodate in next quarter report.
Further, NPC procurement process for Construction of Infrastructure Facilities for the Support
to the upgrading of Suai airport to CHL Industries Unip Lda through restricted tender, an
advance payment of 20% of total contract prices was made to CHL Industries on 16 December
2014. The project is under mobilization, site preparation and some preliminary works but no
disbursement was made for this contract in this reporting period.
65 | P a g e
The allocation budget for rehabilitation of Suai Aiport in 2015 is US$ 19 million and US$3.5
million was disbursed in this reporting period for construction works but no claim request by
the supervision company. The Physical progress for the upgrading of Suai Airport is about
20% and financial progress up to this reporting period was 25% including 20% advance
payment.
10.2.2 DESIGN CONSTRUCTION AND SUPERVISION OF DILI AIRPROT
Government has allocated $6 million in 2015 fiscal year to conduct study, design, and
rehabilitation works for Dili airport and it has rectified to US$ 1 million. For development of
Dili Airport, CAFI meeting dated 9 June 2015 in Oecusse approved construction of the new
airport of Dili by CHINA EXIM BANK loan financing with the Design Build and
Maintenance modality (DBM) in 2016. While, the relevant line ministry also informed that
they are prepare term of reference for detail engineering design and other relevant study for
Dili airport development.
66 | P a g e
11 INFORMATICS
11.1 MINISTRY TRANSPORT AND COMMUNICATION
The Ministry of Transport and Communication is intending to improve existing
communication system to provide better communication access to the people. 2015 budget
allocated for informatics program is shown in table 11.1.
Table 11.1: Budget allocation for Informatics Programs of 30 June 2015
Projecto Orçamento 2015 $'000
Original Revição após
Retificação
Despesa ate 30
Junho 2015
Saldo
Conectividade Nacional III - V 400 400 0,00 400
Melhoria da Conectividade por Satélite de 20
Mbps para 60/80 Mbps
500 500 0,00 500
Extenção do PCN II de Network Fibra-Óptica 400 400 0,00 400
Total 1.400 1.400 0,00 1.400
Source: Book 6, Rectification March 2015 and Free Balance Report 30 June 2015
Table 11.2: National Connectivity III-V and Maintenance of Internet connection between
Dili to 12 Districts
PROJECT SUMMARY
Status Retention
Company Name Timor Telecom,
SA
Supervised by Directorate General of
Transport and Communication
Contract Signing Date 1 January 2014
Commencement Date 1 January 2014
Original Completion Date 31 December 2014
Audit Court Endorsement Date NA
Issue Notice to Proceed Date
Actual Completion Date 29 October 2014
Original Contract Value 430,800.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 430,800.00
Physical progress till quarter end % 100
Payment Schedules
2014 IF payments ($) 387,720
2015 IF payments ($) 0.00
Total to be paid ($) 387,720
Balance to be paid ($) 43,080
Source: MPS and Free Balance, 30 June 2015
67 | P a g e
11.2 NATIONAL CONNECTIVITY
The National Procurement Commission (C.N.A) has completed the tender process of this
project by the end of 2014 fiscal year. CAFI meeting on 30 October 2014 approved payment
for maintenance national connectivity III and which contract was awarded to Timor Telecom
SA, with the total contract value of US$ 430,800. This contract is initially for internet satellite
connection and maintenance accommodation for connection between Dili and 12 districts
including circuits for these districts. Further, contract for national connectivity III – V is under
procurement process. No actual claimed has received by the MPS up to the end of second
quarter. The total budget allocation for this project is amounted to $0.4 million, which may not
be sufficient to pay this contract. The detail contracts and payment status shows in table 11.2.
11.3 SATELLITE INTERNET CONNECTIVITY UPGRADE
As per TORs and bid documents prepared for the projects, NPC completed the procurement
process and awarded the projects to the following firms in October 2014. The Satellite Internet
Connectivity Upgrade (from 20 Mbps to 60/80 Mbps) was contracted to WebSatMedia, Pte on
29 October 2014. 15% advance payment was made in 2014, fiscal year and remaining contract
balance is expected to be disbursed by the fiscal year of 2015. The allocated budget however,
is only amounted to US$ 0.5 which may not enough to cover the expected payment in 2015.
No disbursement in this reporting as no significant work progress achieved. The detail
contracts and payment status shows in table 11.3.
Table 11.3: Upgrade Modem and Internet Bandwidth and Support Materials Project
PROJECT SUMMARY
Status On-going
Company Name WebSatMedia Pte Ltd Supervised by Directorate General
of Transport and Communication
Contract Signing Date 29 October 2014
Commencement Date 29 October 2014
Original Completion Date No completion rate (based
on deliverable result)
Audit Court Endorsement Date NA
Issue Notice to Proceed Date
Actual Completion Date
Original Contract Value 1,048,665.49
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 1,048,665.49
Physical progress till quarter end %
Payment Schedules
2014 IF payments ($) 157,299.82
2015 IF payments ($) 0.00
Total to be paid ($) 157,299.82
Balance to be paid ($) 891,365.67
Source: MPS and Free Balance, 30 June 2015
68 | P a g e
11.4 EXTENSION OF PCN II AND NETWORK FIBER OPTIC
Similar to the previous to Telecommunication project, the TORs and bid documents were
submitted to the NPC for selecting to company to implement this project. However, the
project owner decides to delay the process tender and NPC is waiting for further notice from
the project owner to continue the tender process in the fiscal year of 2015.these projects. Total
budget of US$ 0.5 million has been committed for this project in the fiscal year of 2015.
69 | P a g e
12 PUBLIC BUILDINGS
There are 32 building projects under 2015 IF Budget of $13.7 million and budget was revised
to US$ 8.713 million in the budget rectification in March 2015. US$ 0.102 million was
disbursed up end the second quarter report. Summary of allocation for public building as
shown in table 12.1:
Table 12.1: 2015 Budget Allocations for Public Building Program
Project
Original
budget
allocation
2015 ($000)
Revised
Budget
($000)
Expenditure
as of 30 June
2015 ($000)
Balance
2015
($000)
Remarks
Programa de Edifícios Publicos 13,713 8,713 102 8,611
Construção do Edifício Principal da CNE 311 311 - 311 In progress
Preparação Desenho e Construção Edifício do Parlamento
Nacional
DED was postponed as
per requested project
owner
Construção da Residência Primeiro Presidente do
Parlamento Nacional 789 289 289
In progress
Construção Edifício do CFP 256 256 256 In progress
Construção do Novo Edifício da INAP 500 400 400 Plan for DED
Concepção, Construção e Supervisão de Edifício e
Instalações da Administração Pública em Díli 396 269 80 216
This budget Line is for
INAP project as per
CAFI decision
Construção do Edifício do CAC 1,500 800 22 788 DED, CAFI approved
additional works
Construção do Novo Edifício de Investigação Criminal 1,500 700 - 700 Postponed process
Construção de Novo Edifício dos Tribunais (STJ; TSAFC;
CSM) 1,000 600 - 600
Postponed process
Construção de Edifício do Ministério da Justiça 443 443 - 443 Will be concluded in 31
July 2015.
Reabilitação da Prisão de Suai - - - - -
Desenho Detalhado e Construção da Residência Defensoria
Pública em 12 Distritos - - - -
-
Construção do Edifício do Banco Comercial de Dili 410 310 - 310 DED in progress
Construção do Mercado de Manleuana Fase IV 250 250 - 250 No activities during this
reporting period
Construção de Novo Edifício do Ministério Comercio
Industria e Ambiente, Dili 900 500 - 500
Allocated budget will
use for Loes Project as
per CAFI decision
Estudo e Desenho (e Construção, Supervisão) do Centro
Comercial em Taibesi - - - -
No budget allocation
Construção do Mercado de Taibesi - - - - No budget allocation
Estudo e Desenho ( e Construção, Supervisão) de
Laboratório em Tibar 100 100 - 100
In progress
Estudo e Desenho (e Construção, Supervisão) do Centro de
Processamento de Lixo 250 150 - 150
In progress
Construção de Novos Mercados em Ainaro, Maliana,
Manatuto 750 450 - 450
In progress
Área de Estacionamento de Loes (Alargamento Ponte,
Estação de Veículos e Restaurantes) 900 500 - 500
In progress
Preparação do Desenho Detalhado (e Construção,
Supervisão) de Edifício da Residência Oficial do Presidente
da República
300 200 - 200
-
Construção de Novo Edifício da Inspecção Geral do
Estado (IGE) - - - -
No budget allocation
Construção de Centro Juvenil 485 335 - 335 -
Construção do Novo Edifício do Ministério da Educação
em Dili - - - -
No budget allocation
Construção do Edifício do MSS - - - - No budget allocation
Construção do Novo Edifício de Petróleo do MPRM - - - - No budget allocation
Construção Novo Edifício da Instituo do Petroleo e - - - - No budget allocated
70 | P a g e
Geologia
Construção de Novo Edifício do Ministério das Obras
Públicas - - - -
No budget allocation
Construção do Novo Edifício do Instituto de Gestão do
Equipamentos 600 450 - 450
-
Construção de Novo Edifício do Ministério da Agricultura
e Pescas em Dili 300 200 - 200
-
Construção do Banco Nacional de Desenvolvimento, Díli 1,773 1,173 - 1,173
Plan for construction
tender
Source: MPS record and Budget book 6 2015
Other design works and studies are described under the Design and Supervision of New
Projects program.
12.1 PROJECT STATUS
12.1.1 National Commission for Elections New (CNE) Office
The total budget allocated for new CNE Building in 2015 was US$ 0.311 million. Its
completion has been reported on the fourth extension in July 2014, and NDA recommended
the payment up to 97.82% of the contract amount. There are some additional items identified
and proposed that still under evaluation of the project owner. Project details are provided in
Table 12.2.
Table 12.2: Construction of CNE New Office Building Project
Estado do Projecto Em Andamento
Companhia Construção Supervisão
Atramor Company Lda. Vox da Vinci Engineering
Data do Contrato 16 Março 2011 8 Julho 2010
Data Original do Conclusão da Obra 28 Fevereiro 2012 31 Dezembro 2011
Valor Original do Contrato $ 2.699.999,99 $ 66.000,00
Adenda do Contrato Primeiro $ 202.032,35 $ 16.500,00
Adenda do Contrato Segundo $ 208.449,41 $ 77.872,00
Adenda do Contrato Terceiro $ 106.236,00
Data Revisão do conclusão da Obra 1 28 Fevereiro 2013 28 Fevereiro 13
Data Revisão do conclusão da Obra 2 31 Augusto 2013 31 Maio 2013
Data Revisão da conclusão da Obra 3 28 Fevereiro 2014 28 Fevereiro 2014
Data Revisão da conclusão da Obra 4 31 Julho 2014 31 Julho 2014
Valor Revisão do Contrato $ 3.110.481,75 $ 266.608,00
Progresso Fisico Atual 98,45%
Horario de Pagamento
Pagamento Pre-FI ($)
Pagamento FI 2011 ($) 654.968,26 66.000,00
Pagamento FI 2012 ($) 544.488,95 16.500,00
Pagamento FI 2013 ($) 898.277,87 77.872,00
Pagamento FI 2014 ($) 640.770,99 85.415,04
Pagamento FI Jan - Mar 2015 ($) - -
Pagamento FI Abr - Jun 2015 ($) - -
Total Pago ($) 2.738.506,07 245,787.04
Balanco do Contrato ($) 371.975,68 20.820,96
Source: MPS and Free Balance 30 June 2015
71 | P a g e
12.1.2 National Parliament Building
The project will serve as post-independence accomplishment of the Timorese People and
could enhance performance of functions of the parliament. NPC has completed tender for the
project but its awarding has been postponed as requested of the Project Owner. None
information on the contract issue provided.
12.1.3 Construction of Residence for the First President of the National Parliament
Towards the end of, the contract was awarded to Bobolait Unip Lda in the amount of US$
1,277,676.39. No payment was released until at the end of June 2015.
12.1.4 Civil Service Commission Office Building (CFP)
Contract for the project were awarded in October 2010. Due to technical problems, completion
date has been adjusted four times with additional funds provided as recommended by NDA.
President of CFP provide various solution and one of solution was CFP, NDA and MoPW to
codncut independent assessment cost for remain works if carry out by other contractor in the
CAFI meeting dated 13 and 24 April 2015. CAFI decided and wait for an independent
assessment result from NDA and Public Work to take further desicion. None disbursement in
this reporting period as no payment receive from NDA. Details are provided in table 12.3.
12.1.5 Public Administration Office
The project was conceived in support to government ministries on their need of administration
services and conducive workspace for inter-ministerial activities. The project location has not
been finalised yet, therefore, detailed engineer design was not carry out yet. The allocation
budget for 2015 US$ 0.396 million and rectified to US$ 0.296 million in late March 2015. The
allocation budget was used to pay Master Plan and Detailed Architecture and Engineering
Design of Trainning and Dormitory Building. US$ 0.80 million was executed up to end of
June 2015 for INAP Project.
12.1.6 New Construction of INAP Office Building
The project was intended to provide adequate workspace to support government
administration services of the Instituto Nacional da Administração Pública (INAP) activities.
The design commenced in June 2014 which for Master Plan and Detailed Architecture and
Engineering Design of Trainning and Dormitory Building and US$ 0.106 has paid under
budget code 8000105. And for design of New INAP Office Building and carry out its
construction work US$ 0.5 million was allocated in 2015 and rectified to US$ 0.4 million in
late March 2015. Contract and payment details are presented in Table 12.4.
72 | P a g e
Table 12.3: New Construction of CFP Office Building Project
Estado do Projecto Em Andamento
Companhia Timor Leste Independent Company LDA (TLIC Lda)
Descrição Construção do Edificio Construção do Moru
Data do Contrato 27-Oct-10 20-Dec-10
Data Original do Conclusão da Obra Outubro 2011 20-May-11
Valor Original do Contrato ($) 3.047.270,96 133.826,91
Adenda do Contrato Terceiro ($) 268.433,24
Data Revisão da conclusão da Obra 1 27-Oct-12
Data Revisão da conclusão da Obra 2 1-Jul-13
Data Revisão da conclusão da Obra 3 28-Feb-14
Data Revisão da conclusão da Obra 4 31-Oct-14
Valor Revisão do Contrato ($) 3,315,704.20
Progresso Fisico Atual 84%
Horario de Pagamento
Pagamento Pre-FI ($) 467.599,24 29.784,02
Pagamento FI 2011 ($) - 104.042,89
Pagamento FI 2012 ($) 1.096.646,34
Pagamento FI 2013 ($) 1.082.454,79
Pagamento FI 2014 ($) 265.594,72 -
Pagamento FI 2015 ($) - -
Total Pago ($) 2.912.295,08 133.826,91
Balanco do Contrato ($) 403.409,12 -
Source: MPS and Free Balance 30 June 2015
12.1.7 Design, Construction and Supervision of CAC Office
Currently the Anti-Corruption Commission (CAC) occupies a residential building not
adequate to accommodate 160 – 210 staff and voluminous documents. The required DED was
awarded to Imagem, Design and Arquitecture Lda (IDA) in JV with Vaz, Dotti & Silva
Unipessoal Lda with the original contract amount of US$ 233,600 with an additional cost of
US$ 23,243 approved on 15 November 2014. The design intended to be completed within 5
months. The project owner informed the scope of design has recommended including
basement that’s still under review. In addition the contract that already expired on 30
September 2014, project owner still review time extension proposal. A budget of US$ 1.5
million has been allocated for this project in 2015 and rectified to US$ 0.8 million in late
March 2015. US$ 22,081.04 was executed until the 30 June 2015. Details are presented in
table 12.5.
73 | P a g e
Table 12.4: Master Plan and Detailed Architecture and Engineering Design of Trainning and
Dormitory Building Project
Estado do Projecto Em andamento de preparação Plano Mestre e de dezeinho detalhada de
Arquitetura e de Engenharia
Companhia PT. BITA ENARCON ENGINEERING in joint venture with
Data do Contrato 18-Jun-14 ENARCO I Unipesoal Lda
Data Original do Conclusão da Obra 03-Jan-15
Data Revisão da conclusão da Obra 1
Valor Original do Contrato ($) 279.500,00
Contracto Amenamente
No. de Variação
Data Revisão da conclusão da Obra
Valor Revisão do Contrato ($) 279.500,00
Actual Data de Completação
Progresso Físico Actual 45%
Horario de Pagamento
Pagamento FI 2014 ($) 106.210,00
Pagamento FI 2015 ($) 79.657,50
Total Pago ($) 185.867,50
Balanço do Contrato ($) 93.632,50
Table 12.5: Design, Construction and Supervision of CAC Office Project
Estado do Projecto Em Andamento
Companhia Preparaçáo Desenho Detalhado
Imagem, design and Arquitectura, Lda (IDA) in Association
with Vaz, Dotti & Silva, Lda (VDS)
Data do Contrato 18-Mar-2014
Data Original do Conclusão da Obra 30-Sep-14
Valor Original do Contrato ($) 233.600,00
Contrato de Emendamento ($) 23.243,20
Número de variações
Data Revisão do conclusão da Obra 1 15 Julho 2015
Valor Revisão do Contrato ($) 256.843,20
Data de conclusão atual
Progresso Fisico Atual 55%
Horario de Pagamento
Pagamento FI 2014 ($) 99.864,00
Pagamento FI 2015 ($) 22.081,04
Total Pago ($) 121.945,04
Balanco do Contrato ($) 134.898,16
Source: MPS and Free Balance 30 June 2015
12.1.8 Construction of Criminal Investigation Office
The Government has initiated the process of strengthening the police force’s capacity to
conduct criminal investigations through recruitment, formation of Special Forces, and
provision of adequate office facilities including forensic and laboratory services. NPC carried
out procurement process for construction since 2014 and now at contract preparation and
check list for Audit Court approval stage late March 2015 but it was informed that Audit
74 | P a g e
Court does not endorse the contract. None endorsement of Audit Court due allocated budget
did not enough to cover payment in 2015. For construction and supervision work US$ 1.5
million was allocated in 2015 and it was rectified to US$ 0.8 million in March 2015. CAFI
meeting dated 24 April 2015 did not provide decision as Ministry of Justrice to write a letter
Audit Court that budget will be increased in 2016. There was no disbursement made under this
budget line until end of June 2015 as the project still not execute.
12.1.9 Construction of Tribunal Office (STJ, TSAFC, CSM)
The detailed design for the Tribunal Office was completed by DALAN Lda in May 2012
which was revised by NDA. NPC carried out procurement process for construction since 2014
and now at contract preparation and check list for Audit Court approval stage late March 2015
but none endorsement was provided. The 2015 budget for this project was US$ 1 million and
rectified to US$ 0.6 million. CAFI meeting dated 24 April 2015 did not provide decision and
asked Ministry of Justrice to write a letter Audit Court that budget will be increased in 2016.
There was no disbursement made until end of June 2015 as the project still not execute.
12.1.10 New Ministry of Justice Office Building
Construction of the project was awarded to G&S Lda in the amount of US $3.982 million. It
started on 8 November 2010 and should have been completed on 29 April 2012. CAFI on its
meetings decided extensions of the contract and approved additional costs. NDA
recommended several strategies while CAFI issued resolutions to facilitate the completion of
the project. The construction works still progressing, contractor proposed time extension to the
Ministry of Justice for approval. CAFI meeting 24 April 2015 approved to extend the contract
until 31 July 2015 and approved consultant DALAN to continue supervise the project with
performance based payment. US$ 0.433 million was allocated in 2015 to pay remain progress
payment of the contractor and consultant. None disbursement in this reporting period as no
claim receive. Details contract are reflected 12.6.
75 | P a g e
Table: 12.6: New Ministry of Justice Office Building Project
Estado do Projecto Em Andamento
Construção Supervisão
Companhia G & S Lda DALAN Enginaria, Estudo e Projeto
Data do Contrato 29-Outubro-2010 21-Sep-2010
Data Original do Conclusão da Obra 29-Abr-2012 29-Abr-2012
Valor Original do Contrato ($) 3.981.831,75 235.400,00
Adenda do Contrato Primeiro ($) 442.250,00 115.088,00
Adenda do Contrato Segundo ($) 115.088,00
No. de Variação 1 2
Data Revisão do conclusão da Obra 1 31-Aug-2013 31-Dec-2012
Data Revisão do conclusão da Obra 2 28-Feb-2014 28-Feb-2014
Data Revisão do conclusão da Obra 3 31-Outubro-2014
Valor Revisão do Contrato ($) 4.424.081,75 465.576,00
Progresso Fisico Atual 87,34%
Horario de Pagamento
Pagamento Pre-FI ($) 513.519,56 96.000,00
Pagamento FI 2011 ($) 566.878,64 35.100,00
Pagamento FI 2012 ($) 337.111,84 205.002,00
Pagamento FI 2013 ($) 1.130.372,71 50.086,30
Pagamento FI 2014 ($) 929.633,41 79.386,95
Pagamento FI 2015 ($) - -
Total Pago ($) 3.477.516.16 465.575,25
Balanco do Contrato ($) 946.565,59 0,75
12.1.11 Construction of Commercial Bank Office Building in Dili
The proposed project is the rehabilitation of the existing building of Banco Nacional de
Comércio de Timor-Leste, S.A. (BNCTL) and construction of three-storey building connected
to the existing structure. NPC carried out procurement process in 2014 and contract for
Consulting services for the detailed engineering design of new head office building for
National Commercial Bank of Timor Leste signed on 18 December 2014 and intend to be
completed with 6 months. The allocation budget for was US$ 0.410 million and it was
rectified to US$ 0.310 million in March 2015. No payment release in this reporting period as
the first claim of US$ 0.063 million reaches MPS on 31 of March 2015. The payment process
was hold due to the changing in the initial proposed of this project, from rehabilitation of
BNCTL office in Mandarin to the new construction of BNCTL head office. Moreover, the
budget allocated is not sufficient to cover the contract amount. It will go for CAFI decision.
The contract detail as shown in table 12.7.
76 | P a g e
Table: 12.7: Detailed engineering design of new head office building for BNCTL Project
Estado do Projecto Em Andamento
Companhia
Preparaçáo Desenho Detalhado
Joint Venture of PY Konsep Perunding SDN BHD and
Pires Architects Unip Lda
Data do Contrato 18-Dec-14
Data Original do Conclusão da Obra 18-Jul-15
Valor Original do Contrato ($) 660.701,32
Contract Amendment
No. of variations
Revised Completion Date
Revised Contract Value ($) 660.701,32
Actual Completion Date
Progresso Fisico Atual
Horario de Pagamento
Pagamento FI 2014 ($) -
Pagamento FI 2015 ($) -
Total Pago ($) -
Balanco do Contrato ($) 660.701,32
12.1.12 Construction of National Development Bank in Dili
The proposed project is to construct new national development bank in Dili. For its
construction works US$ 1.773 were allocated for 2015.
12.1.13 Construction of Commercial Bank Office Building in Dili
The proposed project is to construct new national development bank in Dili. For its construction works US$ 1.773 million were allocated for 2015 and rectified to US$ 1.173 million in March 2015. Project owner informed that DED including bill of quanity and construction cost has been completed and ready for construction tender process.
12.1.14 Construction of Manleuana Market Phase IV
Extension of Manleuana Market can contribute to the goals of the SDP. Allocated budget for
this project in 2015 was US $0.25 million. During the 2014 budget discussion it was decided
that a terminal be integrated to the market turning the project to be a multiministerial one
composed of MCIA, MoTT and MAP. While the preparation of tender documents is being
carried out by NPC, the Ministry of Commerce, Industry and Environment as the Project
Owner opted to purchase the land where the existing market is located. As the total area is
17,225m2
at US$ 740,675. The MCIA are planned to develop other facility of Manleuna, as
result no physical activities in this reporting period.
77 | P a g e
12.1.15 Construction of Taibesi Commercial Centre
This project intends to build a fully operational, hygienic, modern commercial centre. A
budget of US$ 0.15 million was allocated in 2014 to cover the preparation of DED. While the
TOR was for final verification before tendering, MCIA informed NDA to discontinue the
process and requested the urgent construction of Taibesi Market in preparation for the CPLP
Summit in July 2014. CAFI approved the budget through 2014 IF plus internal transfer and
virement to this project in the amount of US$ 9.991 million. The revised budget mentioned
was disaggregated to: US$ 2,555,740.42 for construction of vendor units Phase I, US$
2,705,771; for construction of vendor units Phase II, US$3,879,317; for construction of new
terminal, and; and US$850,077 for Agriculture sector.
Implementation various project proposed by several ministries alter those CAFI decisions in
the CAFI meeting dated 24 October 2014. Those proposals are 1) Ministry of Agriculture
proposed the amount of US$780,986 for construction of Fish and Meat Market at Taibesi and
Manleuana Market; 2) MCIA proposed for the construction of Parking area in the amount of
US$ 1.5 million; 3) Secretary State for Public Works proposed US$ 942,741 for the
construction of access road; 4) MCIA requested US$ 62,195.84 to cover the retention for the
additional works for Manleuana Market Phase II. Those proposals were approved.
The amount of US$ 5.5 million has been disbursed under this budget in 2014 as itemized
shown below but none payments make in 2015. Meanwhile, none allocation budget approve
for this project in 2015.
12.1.16 Ministry of Social Solidarity Office
This project was initiated by the Ministry of Social Solidarity (MSS) to improve their
functions on providing support to the disadvantaged members of the Timorese population. The
construction new MSS office building is contracted to PT. SASMITO JV CAMANASA
Unippesoal Lda with total original contract of US$ 3,966,000 on 11 April 2011and amended
US$ 222,096 with total revised contract of US$ 4,188,096. All payment made to the
contractor from 2011 to 2014. While the supervision services contracted to Joel Consultant
Unipessoal Lda, with total contract amount of US$ 86,500 on 30 April 2010 and completed on
11 May 2012. US$ 82,175 has been paid but US$ 4,325 yet claim. The project defect liability
period and completed in late 2014, base on final inspection approval of the National
Development Agency on 29 August 2014 retention payment was released. No allocation
budget for 2015.
78 | P a g e
Table: 12.7 Project Details: Rehabilitation of Taibesi Market (Emergency Project)
Estado do Projecto Completo
Em
Andamento Em Andamento Completo
Nome do Projectos
Construção
do Mercado
Taibesi Fase I
Construção
do Mercado
Taibesi Fase
II
Reabiltação da
Estrada de Acesso
ao Mercado de
Taibesi
Rehabilitation of
Meat and Fish
Market at Taibesi
and Manleuana,
Dili
Companhia GUANGSHA
UNIP. Lda
GUANGSHA
UNIP. Lda
Mendith
Construction Lda
Romante,
Unip.Lda
Data do Contrato 30-Nov-14 14-Nov-14 30-Jun-14
Data Original do Conclusão da Obra 14-Mar-15 31-Jul-14
Valor Original do Contrato ($) 2,703,593.92 1,961,639.00 942,720.92 780,986.45
Adenda do Contrato Primeiro
Adenda do Contrato Segundo
No. de Variação
Data Revisão do conclusão da Obra 1
Data Revisão do conclusão da Obra 2
Valor Revisão do Contrato
Progresso Fisico Atual 100% 88% 93% 100%
Horario de Pagamento
Pagamento FI 2014 ($) 2,433,234.53 1,545,052.13 791,778.15 702,887.81
Pagamento FI 2015 ($) - - - -
Total Pago ($) 2,433,234.53 1,545,052.13 791,778.15 702,887.81
Balanco do Contrato ($) 270,359.39 416,586.87 150,942.77 78,098.65
Source: MPS analysis and free balance report 30 June 2015
12.1.17 Construction of Institute for Management of Heavy Equipment Office and
Warehouse
The purpose of the project is to construct a new warehouse where the present administration
complex will be relocated. Budget in 2014 was US$ 0.7 million. With the delay in the
procurement process, CAFI on its meeting on 14 July 2014 decided to transfer the allocated
budget to Taibesi Comercial Centre budget line to cover payment for the emergency project of
Rehabilitation of Taibesi Market. For its construction works US$ 0.6 was allocated for 2015
but it was rectified to US$ 0.45 in March 2015.
12.1.18 New Resident of First President of National Parliament
The purpose of the project is to construct a new resident to first national parliament as the
current resident is suitable as a resident. The Renovation and New Construction of Residence
of First President of National Parliament has contracted to Bobolait Unip Lda with total
contract amount US$ 1,277,676.39 in late 2014, while the supervision works contracted to
Maidalo Unip Lda with total contract value of US$ 51,311.21. The construction work is
progressing and no payment claim in this reporting period as the claim from company is
79 | P a g e
processing to ADN. CAFI approved allocated US$ 0.789 million in 2015 and rectified to US$
0.289 million in March 2015.
12.1.19 Design, Construction and Supervision of New MAF Office Building
MAF intends to construct a Multi-Storey Office Building on its property immediately at the
south of its existing premises, east of Comoro River Rd (Figure 19.1). Size of land is
approximately 1.5 ha located at Moris Foun Aldeia, Suco Comoro, Dom Aleixo Sub-district,
Dili District. The proposed project would bring all National Directorates together which will
improve organizational coordination and staff productivity, and thereby improve its services
particularly to farmers. The detailed engineering and architectural design was awarded to PT.
Bita Enarcon and completed in 2014. For its construction and supervision works, CAFI
approved US$ 0.3 million and rectified to US$ 0.2 million in March 2015.
12.1.20 Detail Design for Residence of Official and Office of the President of Republic
US$ 0.3 million was allocated in 2015 for preparation of detailed design for residence of
official and office of the President of Republic of Timor Leste. As none significant actifity in
the first quarter report allocated budget was reqctified to US$ 0.2 million.
12.1.21 Construction of the New MCIE New Office Building
The Ministry of Commercy, Industry and Enverioment (MCIE) is planned to construction new
office building since 2014. The project aims to accomodate MCIA employes which are
currently sharing office space with the Ministry of Mineral and Natural Recources. The
proposed new MCIE office will be located in the current Comoro Market. The detailed
engineering and architectural design and other relevant survey are progressing and implement
under budget line for design and supervision of new project. Detailed design expected to be
completed this year. For its construction and supervision works US$ 0.9 million and it
rectified to US$ 0.5 million in March 2015.
12.1.22 Construction of New Markets in Ainaro, Maliana, Loes and Manaturo
The Ministry of Commercy, Industry and Enverioment (MCIE) is planned to improve various
market around the country. The objective of the project is to modernize the existing markets
around the country with adequate space for vendors and customers under safe and hygienic
conditions, with toilets and office space for the Market Management Unit. With the new
markets, opening and closing time can be properly regulated. The detailed engineering and
architectural design and other relevant survey are progressing and implement under budget
line for design and supervision of new project. Detailed design expected to be completed this
year. For its construction and supervision works US$ 0.75 million and it rectified to US$ 0.45
million in March 2015.
80 | P a g e
12.1.23 Construction of Rest Place in Loes
The Ministry of Commercy, Industry and Enverioment (MCIE) is planned to improve and
construct parking area and rest place in Loes including enlargement part of bridge, vehicles
transist and restaurants station. For its design and survey works budget were allocated in
design and supervision of new project budget line. For its construction and supervision works
US$ 0.9 million was allocated in 2015 and it rectified to US$ 0.5 million in March 2015.
However, in the CAFI meeting dated 13 and 24 April 2015, Minister of MCIE proposed
construction rest place in Loes will take part of preparation of 500 years celebration Portogues
arrival in Oecusse. In addition to that, MCIE proposed to construct transit station, rest place
and restorant with proposed budget of US$ 1.15 million. CAFI meeting 24 April 2015
approved MCIE proposal with notes to review implementation process with relevant ministry
including design, BOQ and cost need verified by NDA.
12.1.24 Construction and Supervision of Laboratory in Tibar
The Ministry of Commercy, Industry and Enverioment (MCIE) is planned to carry out study
and design before construct laboratory in Tibar. The aim is to provide beter laboratory
building and facility to conduct necessary test for comenrce goods and material. For study and
design works US$ 0.1 million was allocated in 2015.
12.1.25 Construction Youth Center
This project is amid to construct a youth center building to provide better facility and space to
accomdate relevant activity. For study and design of this project US$ 0.485 million was
allocated in 2015 and it’s was rectified to US$ 0.335 in March 2015.
81 | P a g e
13 EDUCATION
Various empirical studies3 show the clear link between education and productivity. These
studies also show that to avoid the poverty trap and for efficient adoption of technologies,
enhancement of human capital capability through basic and advanced schooling is crucial. At
this stage of development, investments should provide an appropriate balance between
provision of general education (primary and secondary schooling) and specific education
(tertiary education, including technical and vocational training).
The National Education Strategic Plan4 for 2011-2015 collates corporate thinking and assesses
the situation and challenges that affect MoE’s ability to meet the country’s obligations towards
education development. It provides a sector-wide national plan to guide implementation at all
levels in the whole country. It was developed using a consultative process involving people at
all levels within the Ministry of Education, the regions, development partners and other key
stakeholders.
From IF Fund, a total of US$ 7.962 million has been allocated in 2015 for Education Sector as
apportioned to the following: US$ 3.262 million for Polo School; US$ 2 million for
Polytechnic School; US$ 2 million for National University; US$ 0.7 million for Construction
of fishery Academy Manatuto and US$1 million for study & detail design of Institute of
superior Aileu.
As per CAFI decision on its meeting dated 13 and 24 April 2015 approved to transfer US$ 1
million to roads program (compensation of land and properties budget line) and US$
1,067,232 agriculture and fishery program (construction and supervision of Oebaba irrigation
scheme phase II). The revised budget for education program was USD 5.895 million. Budget
allocation and execution rates are summarised in Table 13.1.
3 For an overview and references see: Asian Development Bank, A Survey on the Relationship between Education
and Growth with Implications for Developing Asia, 2010
4Ministry of Education, Timor-Leste, National Education Strategic Plan 2011 – 2030
82 | P a g e
Table 13.1; Summary of Budget Allocation and Execution as of 30 of June 2015
Project
Allocation
2015
('$000)
Revised
Budget
('$000)
Expenditure
as of 30
June 2015
('$000)
Balance
2015
('$000)
Remarks
Construção de Nova Escola Polo de Baucau 165 165 - 165 In progress
Construção de Nova Escola Polo de Same 269 269 - 269 In progress
Construção de Nova Escola Polo de Maliana 211 211 - 211 In progress
Construção de Nova Escola Polo de Ermera 398 398 - 398 In progress
Construção de Nova Escola Polo de Manatuto 219 219 - 219
Reactive
contract
Construção de Escolas Politécnicas de Lospalos
e Suai 2,000 1,300 - 1,300
Study and
design
Construção e Supervisão da Relativamente a
Universidade Nacional (Dili) 2,000 2,000 968.012 1,032
DED in
progress
Construção de Nova Escola Polo de Lospalos 500 200 200
DED
completed
Construção de Nova Escola Polo de Liquica 500 200 200
DED
completed
Construção de Nova Escola Polo de Aileu 500 200 200
DED
completed
Construção de Nova Escola Polo de Suai 500 500 500
DED
completed
Construção de Escolas Politécnicas de Aileu e
Betano - -
Construção do Instituto Politécnico de
Manatuto (Indústria Pesqueira) 700 233 233
Study and
design
Construção de Escolas de Referência em Díli,
Ainaro e Viqueque - - -
Total 7,962 5,895 968.012 4,927 16.42%
Source: Free Balance, 30 June 2015.
13.1 CONSTRUCTION OF NEW POLO REFERENCE SCHOOLS
Five Polo Reference Schools located in different districts are under construction with the
physical progress as follows: Baucau 80%, Maliana 100%, Manufahi 95%, Manatuto 60% and
Ermera 98%. It was noted the contract for Polo School to Manatuto Samboio Unipessoal Lda
was terminated based on CAFI decision dated 12 May 2014.
CAFI meeting dated 13 April 2015 decided and approved time extension for Polo School
Maliana and Manufahi which under verification of the project owner. CAFI meeting 13 April
2015 decided Ministry of Education (MoE) and ADN to review status construction of Polo
School Manatuto and result of verification with appropriate scenario to resolve the problem
shall present in next CAFI meeting. As per CAFI decision, the MoE has completed
verification Polo School Manatuto and reactive contract to Samboio Unipessoal Lda and will
inform to next CAFI meeting. The MoE also planned to extend time extension to Baucau and
Ermera Polo School. Details are presented in Tables 13.2-6.
83 | P a g e
For the next phase, the Ministry of Education will continue construction of schools in other
districts such as Lospalos, Suai, Aileu and Liquica. The program will also be carried out as
another phase for the remaining districts, namely: Dili, Ainaro and Viqueque. All the new
projects are in document preparation process for bid.
Table 13.2.: Baucau Reference School Project
PROJECT SUMMARY Completed Implmentatio process
Company Contracted Waimori Unip. Lda SANIRA UNIP. LDA
Date of Contract 17-Oct-12 December 2012
Start Date (Notice to Proceed) 15-Mar-13
Original Completion Date 17-Mar-12 15-Nov-13
Original Contract Value 150,219.61 677,203.53
Contract Amendment and No. of variations
Revised Completion Date - 1 28-Feb-2014
Revised Completion Date - 2 1-Aug-2014
Revised Completion Date - 3 3-Oct-2014
Revised Completion Date - 4 31-Dec-2014
Revised Completion Date - 5 1-Jul-2015
Revised Contract Value 677,203.53
Actual Completion Date
Present physical completion status 100% 80%
Payment Schedule
2011 IF payments ($) 49,514.49 -
2012 IF Payments ($) 85,683.15 -
2013 IF payments ($) 15,021.97 211,665.53
2014 IF payments ($) - 236,273.36
2015 IF payments ($) -
Total to be paid 150,219.61 447,938.89
Contract Balance ($) - 229,264.64
Table 13.3: Same Reference School Project PROJECT SUMMARY Completed Implementation Process
Company Contracted Dino Unip Lda Faneky UNIP LDA
Date of Contract 17-Oct-12 December, 2012
Start Date (Notice to Proceed) 15-Mar-13
Original Completion Date 17-Mar-12 15-Nov-13
Original Contract Value 196,868.56 664,242.87
Contract Amendment
No. of variations
Revised Completion Date - 1 28-Feb-2014
Revised Completion Date - 2 1-Aug-2014
Revised Completion Date - 3 1-Nov-2014
Revised Completion Date - 4 31-Jan-2015
Revised Completion Date - 5 1-Apr-2015
Revised Contract Value 664,242.87
Actual Completion Date
Present physical completion status 100% 95.0%
Payment Schedule
2013 IF payments ($) 9,843.43 194,835.05
2014 IF payments ($) - 372,142.05
2015 IF payments ($) -
Total to be paid 196,868.56 566,977.10
Contract Balance ($) - 97,265.77
Table 13.4: Reference School Project in Maliana
84 | P a g e
PROJECT SUMMARY Completed Implementation Process
Company Contracted LYGELINA ALEXIX Unip Lda HOLGAPA LDA
Date of Contract 17-Oct-12 December, 2012
Start Date (Notice to Proceed) 15-Mar-13
Original Completion Date 17-Mar-12 15-Nov-13
Original Contract Value 166,180.07 651,906.02
Contract Amendment and No. of
variations
Revised Completion Date - 1 28-Feb-2014
Revised Completion Date - 2 1-Aug-2014
Revised Completion Date - 3 1-Nov-2014
Revised Completion Date - 4 31-Jan-2015
Revised Completion Date - 5 1-Apr-2015
Revised Contract Value 651,906.02
Actual Completion Date
Present physical completion status 100% 100%
Payment Schedule
2011 IF payments ($) 68,362.63 -
2012 IF Payments ($) 76,662.02 -
2013 IF payments ($) 21,155.43 141,316.27
2014 IF payments ($) 380,562.24
2015 IF payments ($) -
Total to be paid 166,180.07 521,878.51
Contract Balance ($) - 130,027.51
Table 13.5: Ermera Reference School Project
PROJECT SUMMARY Implementation Process
Company Contracted DINO CONSTRUCTION UNNIPESSOAL LDA
Date of Contract 12-Dec-12
Start Date (Notice to Proceed) 15-Mar-13
Original Completion Date 15-Dec-13
Original Contract Value 832,022.17
Contract Amendment
No. of variations
Revised Completion Date - 1 28-Feb-2014
Revised Completion Date - 2 1-Aug-2014
Revised Completion Date - 3 1-Nov-2014
Revised Completion Date - 4 31-Jan-2015
Revised Completion Date - 5
Revised Contract Value
Actual Completion Date
Present physical completion status 85%
Payment Schedule
2013 IF payments ($) 408,705.93
2014 IF payments ($) 282,148.11
2015 IF payments ($) -
Total to be paid 690,854.04
Contract Balance ($) 141,168.13
85 | P a g e
Table 13.6.: Manatuto School Extension Project
PROJECT SUMMARY Implementation on hold
Company Contracted SAMBOIO UNIPESSOAL LDA
Date of Contract December, 2012
Start Date (Notice to Proceed) 1-Feb-13
Original Completion Date 15-Dec-13
Original Contract Value
870,892.2
6
Contract Amendment
No. of variations
Revised Completion Date - 1 28-Feb-2014
Revised Completion Date - 2 1-Aug-2014
Revised Completion Date - 3
Actual Completion Date
Present physical completion status 60%
Payment Schedule
2013 IF payments ($) 252,384.58
2014 IF payments ($) 99,559.73
2015 IF payments ($) -
Total to be paid
351,944.3
1
Contract Balance ($)
518,947.9
5
Source: Free Balance 30 June 2015.
13.2 CONSTRUCTION OF POLYTECHNICS
The development of Polytechnics in Timor Leste is focused on the development of facilities
which will promote the utilization of natural resources through improvement of human
resource capabilities. For the Detailed Engineering Design of Polytechnics School, the
contract was awarded to LAPI-ITB, Indonesia through single source procurement as per
Council of Minister’s decision in 2013. Details are presented in Table 13.7.
The 2015 Budget for the construction of polytechnic schools was US$2 million to covers
balance of the previous contract of study and design and some amount to initiate the physical
construction. These include Engineering College for Suai, Agriculture College for Manufahi,
Services Industry for Tourism and Hospitality for Lospalos, excepted Academy for Fishing
Industry at Manatuto were allocated separated budget. Further, CAFI meeting dated 13 and 24
April 2015 decided and approved to transfer US$ 0.7 to compensation of land and properties
budget line of the road program. The revised budget for this project was US$ 1.3 million.
There are no disbursements in the end of this reporting period as remain payment only for 5%
retention.
86 | P a g e
Table 13.7: Construction of Polytechnics at Lospalos, Same, Manatuto and Suai Project
PROJECT SUMMARY Completed and remain retention
Company Name LAPI-ITB, Indonesia
Contract Duration (months) 6
Contract Signing Date 21-Feb-2014
Original Completion Date 20-Aug-2014
Audit Court Endorsement Date -
Issue Notice to Proceed Date -
Actual Completion Date
Original Contract Value 2,500,000.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
Final Contract Value 2,500,000.00
Physical progress till quarter end % 100
Payment Schedules
2014 IF payments ($) 2,375,000.00
2015 IF payments ($)
Balance ($) 125,000.00
13.3 NEW NATIONAL UNIVERSITY COMPLEX
The establishment of 361-hectare university complex in Hera has been conceptualized in
2011. CAFI determined that further project preparation was required before funds can be
allocated from the IF and therefore no funds were allocated in 2011. The additional
requirements to be satisfied for the project preparation was completion of a Master Plan for
the establishment and development of the proposed university, including:
Projections of demand for classrooms and facilities; required curricula;
Assessment of staffing requirements; identification and design of associated
infrastructure requirements; business plan for the long term sustainable operation of
the facility;
Phased design and construction of the complex allowing time to refine technical and
architectural design and social suitability;
Opportunities for potential financial support from external sources.
The 2015 Budget allocated for the Study and Detailed Engineering Design of the new
complex is US$2 million to covers balance of 3 projects and up to end of to June 2015
US$960,012 or 48% have been executed from allocated budget. Detail of contract as shown in
table 13.8.
87 | P a g e
Table 13.8: UNTL Projects Project
PROJECT SUMMARY Under implementation Stage
Project Name Detail Architecture and
engineering design of
New Faculty of
Engineering Building of
UNTL
Detail Architecture and
Engineering Design of
New Faculty of
Agriculture Building of
UNTL
Urban Detail Plan
for Sector 1 of
UNTL (Urbanism
and Infrastructures)
Company Name Philkoei International
Inc.
Dalan-Engenharia,
Estudos e Projectus Lda.
Bernabad
Arquitecturas S.I.P
Spain
Contract Signing Date 23-Jun-2014 3-Jun-2014 23-Jun-2014
Commencement Date
Original Completion Date 22-Dec-2014 2-Jan-2015 22-Dec-2014
Audit Court Endorsement Date
Issue Notice to Proceed Date
Revise Completion Date
Original Contract Value 670,000 741,600 820,000.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
Final Contract Value 670,000 741,600 820,000.00
Physical progress till quarter end
%
40 70 70
Payment Schedules
2014 IF payments ($) 63,650.00 70,452.00
2015 IF payments ($) 422,712.00 545,300.00
Total to be paid ($) 63,650.00 493,164.00 545,370.00
Balance to be paid ($) 606,350.00 248,436.00 274,630.00
Source: Free Balance 30 June 2015.
88 | P a g e
14 HEALTH
The 2015 Budget for the health programs was US$ 3.996 million and revised to US$ 4.380
million as per CAFI approval dated 24 April 2015. No disbursements made in the second
quarter report as the payment under process to NDA. The details are presented in table 14.1:
Table 14.1: Summary budget allocation for health program
Projecto
Alocação
Orçamento
Original
2015 ('$000)
Virement e
transferência
Interna
('$000)
Alocação
Orçamento
Revição
2015 ('$000)
Despesas
até 30 de
Junho
('$000)
Saldo
2015
('$000)
Observações
Construção do Hospital de Baucau 1,629 2,751 4,380 - 4,380 Em andamento
Construção do edífício do da Unidade de
Cuidado Intensivo (ICCU) HGV - -
-
-
Plano para
DED
Reabilitação e construcao do Edífíciodo
Antigo Hospital Dr. Antonio Carvalho, ICCU,
Sames, Cuidadso Intensivos e Urgências 850
(850) -
- -
Plano para
DED
Construção de Edifícioda Unidade de
Pediatria, Hospital Nacional Guido Valadaraes 1,517
(1,517) -
- -
DED em
andamento
Total 3,996 384 4,380 - 4,380 0.00%
Sources: Free Balance Report, 30 June 2015
14.1 CONSTRUCTION OF BAUCAU REFERRAL HOSPITAL
The Baucau Referral Hospital Project approximately occupies a 2,500m2
area located at 2km
west of Baucau. Due to failure of the first contractor to perform the work, it was retendered
and awarded to Ensul Corporation, Ltd. in December 2010 for completion of the project in
May 2012. Construction Supervision and Contract Management is being handled directly by
the MoH Project Management Unit.
As several issues have been encountered, recommendations were made by ADN, MoP and
MoH to the contractor for the completion of the project while several contract extensions have
been approved by CAFI. At its meeting on 24 October 2014, extension of contract was
approved until 30 June 2015. CAFI instructed ADN and MOP to verify the additional amount
before recommending the signing of the contract. To complete remain scope works under
current contract, US$ 1,629 in 2015.
Further, Minister of Health proposed to have an additional budget of US$ 0.384 million for
5% retention payment which will release end of the year and proposed virement and an
internal transfer with health program in the CAFI meeting dated 24 April 2015. The proposal
of MoH is to secured allocated buget for 2015 payment. CAFI approved proposal of the MoH
with virement of US$ 0.384 million from construction of UPF Police Building in Bobonaro,
Covalima and Oecussi Nubadak project from Security and Defence Program. Thus the revised
budget after virement and internal transfer was US$ 4.38 million. None disbursement up to the
end of June 2015 as the claim are still processing to NDA. Project details are provided in
Table 14.2.
89 | P a g e
Table 14.2: Construction of Baucau Referral Hospital Project
Estado do Projecto Em Andamento
Companhia Ensul Esphera Engenharia Corporation Ltd
Data do Contrato 6-Dec-2010
Data Original do Conclusão da Obra 6-Maio-2012
Valor Original do Contrato ($) 8.350.580,00
Adenda do Contrato ($) 605.602,30
No. de Variação 1
Data Revisão do conclusão da Obra 1 30-Dec-12
Data Revisão do conclusão da Obra 2 31-Dec-13
Data Revisão do conclusão da Obra 3 15-Apr-14
Data Revisão do conclusão da Obra 4 31-Dec-14
Data Revisão do conclusão da Obra 5 30-Jun-15
Valor Revisão do Contrato ($) 8.956.182,30
Progresso Fisico Atual 79,61%
Horario de Pagamento
Pagamento Pre-FI ($) 1.670.116,00
Pagamento FI 2011 ($) 1.922.389,33
Pagamento FI 2012 ($) 1.324.366,26
Pagamento FI 2013 ($) 237.877,03
Pagamento FI 2014 ($) 1.428.780,43
Pagamento FI 2015 ($) -
Total Pago ($) 6.583.529,05
Balanco do Contrato ($) 2.372.653,25
Sources: MSP and Free Balance Report, 30 June 2015
1.4. Construction of Intensive Care Cardiac Unit at Guido Valaderes National Hospital
The new ICCU at HNGV will double the present capacity of the hospital with separate male
and female 10–bed cardiology wards, 5-bed cardiac unit and facilities for patients of an
expanded intensive care cardiac unit. The building will also include operating theatres, ECG,
treadmill, on-call doctor’s rest room, consultation rooms and a place for specialists and
nurses. For development relevant facilities, US$ 0.85 million was allocated in 2015. As no
activity for this project, CAFI meeting dated 24 April 2015 approved Ministry of Health
proposal to transfer all allocated budget to the Construction of Hospital Referal in Baucau.
14.2 CONSTRUCTION OF PEDIATRIC BUILDING AT GUIDO VALDERES
NATIONAL HOSPITAL
The three-storey facility will significantly enhance the provision of Neo-natal services,
Pediatric Services and Consultation services. The building of 2,500 m2
area will include
standard wards and VVIP wards, consultation rooms, sanitation rooms, meeting room, staff
room, neo-natal intensive care unit, waiting rooms and children’s play area. Construction of
Iintensive Care Cardiac Unit and Pediatric Building will also be accommodated in the same
site. The tender for DED was completed in early 2014 and contracted to Philcoei International,
Inc. In JV with Luis and Associates, Co. The project intended to be completed within 5
90 | P a g e
months but the project was not completed as scheduled and it was extended to 30 November
2014. The MoH reported in the CAFI meeting dated 24 April 2015 that no payment will be
made this year, therefore, CAFI approved MoH proposal to transfer all allocated budget to the
Construction of Hospital Referal in Baucau. The details of contract provided 14.3.
Table 14.3.: Serviço Consultaria de Desenho Detalhado do Pediatria e ICCU em Hospital
Nasional Guido Valadares Project
Estado do Projecto Em Andamento
Nome de Sub Projeto Preparaçáo Desenho Detalhado
Companhia Philcoei International, Inc. In JV with Luis and Associates, Co
Data do Contrato 5 Maio 2014
Data Original do Conclusão da Obra 18 Outubro 2014
Data Revisão do conclusão da Obra 1 30 Novembro 2014
Valor Original do Contrato ($) 230.000,00
Alteração de Contracto
Número de variações
Revisado Data de Conclusão
Valor Revisão do Contrato ($) 230.000,00
Data Conclusão Actual
Progresso Fisico Atual
Horario de Pagamento
Pagamento FI 2014 ($) 152.950,00
Pagamento FI 2015 ($) -
Total Pago ($) 152.950,00
Balanco do Contrato ($) 77.050,00
The current detailed design for Paediatric and ICCU is nearly completed. While, the other
health projects such as Rehabilitation and Construction of Rr. Antonio Carvalho Hospital,
Lahane and Sames are currently under tender by the project owner.
91 | P a g e
15 MILLENNIUM DEVELOPMENT GOALS PROGRAM
15.1 GENERAL
The SDP states that “A key component of the Millennium Development Goals Suco Program
will be the building of houses for vulnerable people. Under the program, five houses will be
built in each of the 2,228 aldeias every year, resulting in more than 55,000 houses being built
by 2015”. 5To expedite this target the program has been included in the IF portfolio since its
establishment in 2011. For construction of Social Community Housing, the government has
allocated US$ 8.5 million in 2015. US$ 2 million was deducted in late March 2015 as part of
budget rectification. Further CAFI meeting dated 13 and 24 April decided and approved to
transfer US$ 1.5 million to the compensation of land property of IF project listed in roads
program. The current revised budget for this program was US$ 5 million only. The Table 15.1
shows budget allocation from 2011 to 2015 and table 15.2 for details of budget allocation and
status of disbursement:
Table 15.1.: Budget allocation 2011 to 2015
Year Budget Allocation (US$) Budget Execution (US$) Execution Rate (%)
2011 51,207,000.00 8,689,868.00 16.97
2012 117,517,000.00 12,833,068.16 10.92
2013 46,263,000.00 7,129,370.31 15.41
2014 5,921,000.00 5,920,026.30 99.98
2015 5,000,000.00 0.00 0.00
Total 34,572,332.77
Source: MPS Analysis and Free Balance as of 30 June 2015
Table 15.2.: Budget allocation and disbursement status for MDG program as of 30 June 2015
Project
Original Budget
Allocation 2015
('$000)
Revised budget
after rectification
and virement - 2015
('$000)
Expenditure
as of 31
March 2015
('$000)
Balance
2015 ('$000)
Água e Saneamento 1,000 1,000 0 1,000
Habitações sociais/comunitárias (5
casas por aldeia, no total de 11.145
casas)
7,500 4,000 0 4,000
Total 8,500 5,000 5,000
Source: MPS Analysis and Free Balance as of 30 June 2015
5 Strategic Development Plan (page 111)
92 | P a g e
15.2 PROJECT PROGRESS
The total original budget allocated for MDG Suco Programs for 2015 was US$ 8.5 million
where as US$1 million allocated for Water and Sanitation and the US$7.5 million was
earmarked for Community Housing Program. The disbursement from December 2011 up to
date, US$ 34.6 million has been expended. ADN as the project owner, design and in-charge of
the construction supervision reported that the project.
Extraordinary CAFI Meeting held on 17 June 2015 has decided to extended contract for Carya
Timor Leste in joint venture with Jonize unipessoal Lda and also decided to reduce amount of
contract from $145,742,519.66 to $48,265,685.10. There is no significant physical and finance
progress up to end of June 2015. The contract amendment is under preparation of ADN.
Details are presented in Table 15.3.
Table 15.3.: Construction of Social Community Housing Project Status
PROJECT SUMMARY Em Andamento
Carya Timor Leste JV with Jonize
Companhia Construction
Data do Contrato Original 6-Oct-2010
Data Original do Conclusão da Obra 5-Oct-2011
Original Contract Value ($) 99,994,406.00
Adenda do Contrato 1 (13,045,376.30)
Adenda do Contrato 2 17,378,859.00
Adenda do Contrato 3 41,464,977.00
Revisão do Valor de Contrato 1 86,898,684.00
Revisão do Valor de Contrato 2 104,277,543.06
Revisão do Valor de Contrato 3 145,742,519.66
Valor Contrato final 145,742,519.66
Data Revisao do Conclusão da Obra 1 11-Nov-2012
Data Revisao do Conclusão da Obra 2 17-Oct-2013
Data Conclusão Actual 17-Oct-2014
Progrreso Fijico Atual 26.18%
Horario do Pagamento
Pagamento Adiantamento FI 2011 ($) 8,689,868.00
Pagamento FI 2012 ($) 12,833,068.16
Pagamento FI 2013 ($) 7,129,370.31
Pagamento FI 2014 ($) 5,920,026.30
Pagamento FI 2015 ($) 0.00
Total Pago excluindo Adiantamento ($) 25,882,464.77
Total Pago incluindo Adiantamento ($) 34,572,332.77
Balanco do Contrato ($) 111,170,186.89
Source: Free Balance 30 June 2015.
93 | P a g e
15.3 DISBURSEMENT FOR HOUSING AND FACILITY
The final contract amount for MDG Social Housing is US$145.7 million to cover the costs for
road and drainage, public facility, water and sanitation and prefab houses. More than 17% of
the budget has been disbursed for houses, 6.1% for road & drainage, 2.5% for public facility
and only 0.3% for water and sanitation. The disbursement shows in table 15.4 is including
deduction for advance payment and 10% retention. Details are presented in Table 15.4.
Table 15.4: Disbursement of Housing and Facility -MDG Project, as of 30 June 2015
No Facility Contract Value ($) Amount Disbursement (US$) Percentage (%)
1 Prefab Houses 90,661,714.32 25,144,196.69 17.3
2 Road & Drainage 15,969,735.94 8,845,989.12 6.1
3 Public facility 16,759,124.88 3,676,051.09 2.5
4 Water and sanitation 22,351,909.03 488,244.40 0.3
Total 145,742,484.17 38,154,481.30 26.2
Source: A.D.N. report and MPS Analysis 30 June 2015
Table 15.5: Number of Locations Used in Each District and Housing Units Installed
No District Quantity of
location
Quantity of houses (Unit)
Total 41.80 m2 55.20 m
2 55.41 m
2
1 Aileu 2 77 42 - 119
2 Ainaro 1 19 33 - 52
3 Baucau 1 - 200 - 200
4 Bobonaro 1 30 22 - 52
5 Lautem 1 90 60 - 150
6 Liquica - - - - -
7 Manufahi 2 73 94 - 167
8 Manatuto 2 129 78 - 207
9 Dili 3 24 3 2 29
10 Ermera 1 145 117 - 262
11 Covalima 10 458 367 21 846
12 Viqueque 3 32 180 289 501
13 Oecusse - - - - -
Total 27 1,077 1,196 312 2,585
Sources: MPS analysis
15.4 HOUSING DEVELOPMENT
Prefabricated houses are installed in 27 locations in 11 districts, namely: Aileu, Ainaro,
Baucau, Bobonaro, Lautem, Manufahi, Manatuto, Dili, Ermera, Covalima and Viqueque. Out
of 2,585 units constructed, 846 units or 34% are in10 locations in Covalima. With the planned
11,140 units of MDG Suco Houses to be installed, 23.2% have been completed. Tables 15.5
specify the locations and housing units installed as of end-November 2014.
94 | P a g e
15.5 FACILITY DEVELOPMENT
Under the same program, basic facilities such as infant schools, clinics, chapels, mini markets,
community centres, police stations, public laundries, roads, water and sanitation are also being
provided. Currently, these communities are within ten districts, namely Bobonaro, Covalima,
Manufahi, Aileu, Baucau, Ermera, Viqueque, Lautem, Manatuto and Liquica. Details are
presented in Table 15.6. Construction of facilities in Batugade was 100% completed while
similar facilities intended for the rest of the districts are still under construction.
Table 15.6: Public Facility Development per location up to day
No Location
Facilities (unit)
Chapel Mini
Market
Community
Centre
Public
Laundry
Security
Office Clinic
TOTAL
1 Batugade, Bobonaro 1 1 1 1 1 1 7
2 Dais, Covalima 1 0 1 1 0 1 5
3 Betis, Covalima 1 0 1 0 1 4
4 Kota Foun, Covalima 0 1 1 0 0 0 2
5 Samfuk, Covalima 1 0 1 2 0 1 6
6 Tulaedu, Covalima 1 0 1 1 1 5
7 Matai Balekasak, Covalima 0 1 1 1 0 1 5
8 Haemanu, Covalima 1 1 2 1 6
9 Betano, Manufahi 0 0 1 2 0 1 5
10 Liurai, Aileu 1 1 1 1 0 1 6
11 Malere, Aileu 0 0 0 2 0 0 2
12 Lanud, Baucau 1 0 1 0 1 4
13 Fatukero, Ermera 1 0 1 2 0 1 6
14 Umaboco, Manatuto 1 0 1 0 1 4
15 Manatuto 0 1 1 0 1 4
16 Mehara, Lautem 1 0 1 0 0 1 4
17 Luca, Viqueque 1 0 1 0 0 1 4
18 Cararas Uma Ki'ik Viqueque 1 1 1 1 0 0 5
19 Cailoi, Viqueque 1 1 1 4
20 Lisadila gisu, Liquica 1 1 2 1 6
Total 15 7 18 16 1 17 94
Source: MPS analysis
95 | P a g e
16 SECURITY AND DEFENCE
The main goal of the program is to enhance security in the country and defence services for
the people of Timor Leste. From IF, the budget allocated in 2015 was US$ 11.046 million.
From that amount 7,389 million for Security and 3,657 million for Defence. CAFI meeting
dated 13 and 24 April 2014 decided and approved transfer US$ 60,243 to road program and
US$ 384,000 to health program and revised budget was US$10.021 million. The details
allocation budget and it disbursement are provided in Tables 16.1.
Table 16.1: Budget allocation and execution as of 30 June 2015
Nome de Projecto Orçamento
Original
2015 ('$000)
Orçamneto
após
Virement
2015 (‘000)
Execução ate 30 Junho
2015
Saldo
2015
('$000)
Taxa de
execução
(%)
A. Seguransa 11 Esquadras 1.129,00 1.129,00 7,00 1.122,00 0,62 Quarteis de Distrito 1.181,67 1.181,67 0,00 1.181,67 0,00 Melhoramentu Infrastrutura PNTL 1.377,91 1.377,91 347,84 1.030.07 0,00 Construcao da Quarter General de Edificio da
PNTL em Caicoli, Dili 2.300,00 2.300,00 0,00 2.300,00 0,00
Construcao de Barracas de Policia d aUPF de
4 Composto de UPF em Bobonaro, Covalima,
Nubadak e Oequsse
1.000,00 616,00 1.000,00 0,00
Construcao de Barracas de UPM, UPM
trainning centre, sede de UPM em Atsabe
Maliana
400,00 400.00 400,00
Total Seguransa 7.388,58 7.004,58 354,84 7,381.58 0,09 B. Defesa
Construcao Policia Militar Fase II 445,00 445,00 0,00 445,00 0,0 Posto FFDTL 1,000,00 939,76 0,00 1.000,00 0,0 Desnho detalhados e Construcao Edificio
Comando Componente Naval 550,00 550.00 222.99 550,00 0,0
Edificio Componente Apopio Servicos
Promucao e Treino 415,00 415,00 0,00 415,00 0.0
Construcao do Instituto de Defesa Nasional 529,00 529,00 0,00 529,00 0,0
Construcao comando F-FDTL e Edificio
Ministerio da Defesa em Fatuhada 200,00 200,00 200,00 0,0
Construcao posto seguransa F-FDTL (Atabae,
Ferik Sare, Ermera, Ainaro e Uatulari) 518,00 518,00 0,00 518,00 0,0
Total defesa 3.657,00 3.596,76 222,99 3,657.00 0,0 Total 11.045,58 10.601,34 577,83 11,038,8 0,0 Source: MPS and Free Balance, 30 June 2015
16.1 EIGHT DISTRICT HEAD QUARTERS OF PNTL
Eight (8) District Head Quarters of PNTL listed in book six (6) since 2011 and 2 new project
in 2012 which was executed through this budget line. In 2011, four separate contracts for
District HQs were entered into by the government and national contractors in the amount of
US$615,944.41. From four PNTL HQ contract made in 2011, three have completed in 2012
all payment made to the company, while Dili HQ was 70% completed which was then
suspended due to some political concerns. Hence, Dili HQ has begun new assessment by
PNTL to be redesign and reconstruction.
96 | P a g e
In 2012, another four contracts were approved in the amount of US$661,147.24. The other
four PNTL HQs are located in Ainaro, Baucau, Lautem and Oecusse with the status presented
below in the table 16.2. For the payment of retention payment and new construction PNTL
HQ in Aileu and Liquisa District and other support facilities, CAFI approved allocated US$
1.182 in 2015. No disbursement in this reporting period as the contractor still not submit their
claim to the project owner and new project still not tender yet. Detail of contract summarised
in table 16.2.
Table 16.2: Status of Four District PNTL HQ Project contracted in 2012
PROJECT SUMMARY Completed Implementation Process
Project Location Oecusse District Ainaro District Baucau District Lautem District
Company(s) Grand Enclave
Unipessoal Lda
Misando
Construction
Unipessoal Lda
Wingstone
Construction
Unipessoal Lda
Wingstone
Construction
Unip Lda
Date of Contract 22-Nov-2012 22-Nov-2012 22-Nov-2012 22-Nov-2012
Contract Duration (days) 150 150 150 150
Notice to Proceed Date 18-Feb-2013 18-Feb-2013 18-Feb-2013 18-Feb-2013
Original Completion Date 18-Jul-2013 18-Jul-2013 18-Jul-2013 18-Jul-2013
Revised Completion Date 1 30-Sep-2013 30-Sep-2013 30-Sep-2013 30-Sep-2013
Revised Completion Date 2 31-Dec-2013 31-Dec-2013 31-Dec-2013 31-Dec-2013
Original Contract Value, inc 148,752.06 152,395.18 180,000.00 180,000.00
supervision ($)
No of variations - - - -
Final Contract Value ($) 148,752.06 152,395.18 180,000.00 180,000.00
Final contract completion date
Actual completion date
Present physical completion status 100% 100% 94% 91.69%
Payments schedule
2012 IF Payments ($) - - - -
2013 IF Payments ($) 133,876.93 51,392.09 63,779.40 -
2014 IF Payments ($) 14,875.13 85,763.57 88,857.00 125,294.36
2015 IF Payments ($) - - - -
Total to be paid ($) 148,752.06 137,155.66 152,636.40 125,294.36
Contract Balance ($) - 15,239.52 27,363.60 54,705.64
Source: MPS Analysis and Free Balance as of 30 June 2015
16.2 ELEVEN SQUADRONS OF PNTL
Eleven PNTL Squadron projects listed in 2011 IF budget book where as two PNTL Squadron
structures with funds from the Line Ministry was completed in 2011. The newly constructed
PNTL Squadron Office Buildings located at Atsabe, Fohorem, Laleia and Metinaro with IF
funds with total contract amount of US$ 284,807.48 commenced in late 2011 and completed
in 2012, all payment are made to the companies.
The four PNTL Squadron Buildings located at Baucau Vila, Bazartete, Lospalos and Letefoho
which were tendered in late 2012 and have been already completed. The Defects Liability
Period is completed excepted for Letefoho and Lautem. For the payment of retention payment
97 | P a g e
and construction PNTL Squadron in Laclo, Vera-Cruz and Don Aleixo Sub District and other
facilities, CAFI approved allocated US$ 1.129 in 2015. No disbursement in this reporting
period as the one of payment still process to Treasury. Status of projects is shown in Table
16.3.
Table 16.3: 4 PNTL Squadrons Project contract awarded in 2012
PROJECT SUMMARY Completed Retention Period
Project Location Baucau Vili, Baucau
District East Timor
Bazartete,
Liquisa District
Letefoho, E rmera
District
Lospalos,
Lautem District
Company East Timor Crocodile
Unip. Lda
Café Hun
Unipessoal Lda
Misando Const.
Unip. Lda
Lero Company
Unipessoal Lda
Date of Contract 22-Nov-2012 22-Nov-2012 22-Nov-2012 22-Nov-2012
Contract Duration (days) 150 150 150 150
Notice to Proceed Date 18-Feb-2013 18-Feb-2013 150 18-Feb-2013
Original Completion Date 18-Jul-2013 18-Jul-2013 18-Jul-2013 18-Jul-2013
Revised Completion Date 1 30-Sep-2013 30-Sep-2013 30-Sep-2013 30-Sep-2013
Revised Completion Date 2 31-Dec-2013 31-Dec-2013 31-Dec-2013 31-Dec-2013
Original Contract Value, inc 132,000.00 129,891.43 102,043.93 132,000.00
supervision ($)
No of variations - - - -
Final Contract Value ($) 132,000.00 129,891.43 102,043.93 132,000.00
Actual completion date
Present physical completion status 100% 100% 100% 100%
Payments schedule
2013 IF Payments ($) 106,217.12 116,902.30 85,062.84 103,674.71
2014 IF Payments ($) 25,782.88 12,985.95 6,776.69 -
2015 IF Payments ($) - - - 7,142.29
Total to be paid ($) 132,000.00 129,888.25 91,839.53 110,817.00
Contract Balance ($) 0.00 3.18 10,204.40 21,183.00
Source: MPS Analysis and Free Balance as of 30 June 2015
16.3 FIVE BAIROS OF PNTL
The Government through the Secretary of State for Security is improving Bairos PNTL
Infrastructures. A budget of US$1.378 million was allocated in 2015 for the Bairos in Aileu,
Ermera, Liquica, and Manufahi. Projects started in 2013 but however for Ermera and Aileu
projects rewarded in 2014 after previous company showed incapacity on implementation
process.
The accomplishments as of end of June 2015 were 63% for Ermera, 63% for Liquica, 71.51%
for Manufahi 66%, and 5% for Aileu. None significant physical progress for construction of
Bairos PNTL in Aileu, because some part of work was demolishes by ADN as it does not
fallow technical specification. None significant physical progress for construction of Bairos
PNTL Manufahi up end of this reporting period. Detail of contracts and payment are
summarised in table 16.4.
98 | P a g e
Table 16.4: Bairos of PNTL Project (2012 contracts)
PROJECT SUMMARY Ongoing Ongoing Ongoing Ongoing
Project Location Ermera District Liquisa District Manufahi District Aileu District
Company
Concorcio Group
Salak Lda.
Holuli
Unipessoal Lda
Tom's Building
Lda Arvec Unip. Lda
Date of Contract 27-Jun-2014 5-Dec-2012 5-Dec-2013
Contract Duration (days) 365 365 365 365
Notice to Proceed Date 18-Feb-2013 18-Feb-201
Original Completion Date 26-Jun-2015 18-Feb-2014 18-Feb-2014 1-Mar-2014
Date of Amendment Contract No.1 21-Jul-2014
Revised Completion Date no.1 18-Aug-2014 18-Aug-2014
Original Contract Value, inc supervision 1,267,261.98 997,544.45 943,482.95 1,146,037.02
No of variations - 305,298.72 307,601.04 -
Final Contract Value ($) 1,267,261.98 1,302,843.17 1,251,083.99 1,146,037.02
Revised completion date no.2 31-Dec-2015 31-Dec-2015
Revised completion date no.3 31-Jun-2015
Actual completion date
Present physical completion status 63% 71.51% 66% 5%
Payments schedule
2013 IF Payments ($) - 402,838.37 509,480.79
2014 IF Payments ($) 457,335.36 285,442.90 233,663.10 46,606.82
2015 IF Payments ($) 226,639.40 121,202.91 - -
Total to be paid ($) 683,974.76 809,484.18 743,143.89 46,606.82
Contract Balance ($) 583,287.22 493,358.99 507,940.10 1,099,430.20
Source: MPS Analysis and Free Balance as of 30 June 2015
16.4 CONSTRUCTION OF HEAD QUARTER OF PNTL DILI
The design of Head Quarter of PNTL Dili was prepared by Tachsindo Aliminum Unip Lda.
This project was approved by CAFI on its meeting held on 22 of August 2014. The design
consultant commenced the services from 1 May 2014 and completed on 1 November 2014
with total contract amount of US$ 479,670, all payment made in late November 2014. While
tender for construction still on under bid preparation by NPC and land acquisition and
property of affected under identification of Ministry of Interior and Land and property. CAFI
meeting 24 April 2015 decided and approved to use part of allocation budget for the land
acquisition and property of affected people.
16.5 MARITIME POLICE OFFICE BUILDING
The Rehabilitation of Office Building and Construction of Boat House for the Maritime Police
in Dili was contracted on 10 December 2013 to Lelo Construction Unipessoal Lda with total
contract amount of US$ 0.119 million and completed on 30 September 2013. All payment has
been made to the company.
99 | P a g e
Table 16.5: Supply and Installation of Kitchen equipment of Navy Compound Project
PROJECT SUMMARY Implementation Process
Company Crown Unipessoal Lda
Date of Contract 4-Jul-2014
Notice to Proceed Date
Original Completion Date 4-Oct-2014
Date of Amedment Contract No.1 4-Oct-2014
Revised Completion Date 4-Apr-2015
Original Contract Value, inc supervision ($) 255,550.00
No of variations -
Final Contract Value ($) 255,550.00
Present physical completion status 100%
Payments schedule
2014 IF Payments ($) 222,993.00
2015 IF Payments ($) 222,993.00
Total to be paid ($) 222,993.00
Contract Balance ($) 32,557.00
Source: MPS Analysis and Free Balance as of 30 June 2015
16.6 HERA BARRACKS
The Hera Barracks Project involved the construction of residential structures in the naval base
at Hera, Dili. The construction works contracted to Ensul Esphera Engenharia with original
contract US$ 2.5 million on 10 October 2010 with two variation orders at US$ 1,489,283.43
and the revised contract was US$ 3,989,283.43. The construction work was originally to be
completed on 31 December 2012 but due to site issues and additional works the project was
delayed and completed in April 2013 and inaugurated on 26 April 2013. While consultant
supervision contracted to JKC Consultant Enginnering Unipessoal Lda with original contract
US$ 96,950 on 10 October 2010 with two variation orders at US$ 46,280 and the revised
contract was US$ 143,230. All payment has made to the contractor and consultant.
While Supply and Installation of Kitchen equipment of Navy Compound FFDTL which not
includes in the previous contracts of Hera Barracks Project. The Secretary of State of Defence
presented this proposal and approved by CAFI on its meeting held on 24 of October 2014 and
recommended to use budget line for detail design and construction for navy compound
building for the payment. US$ 222,993 has been paid in this reporting period. Project details
are presented in Table 16.5.
16.7 MILITARY POLICE OFFICE
The government has sustained the program on the improvement of Military Police Office
Buildings and related infrastructures since 2011. A budget of US$ 0.445 million was
earmarked in 2015 for Phase III components. The project have been awarded to Dany “STRA’
Construction with total amount contract $887,316.79 and there was no expenditure at 2nd
quarter report.
100 | P a g e
As per CAFI meetings held on 12 of May 2014, F-FDTL emergency projects were approved
using Military Policy Office Building Budget and had been completed as presented in table
16.6.
Rehabilitation of F-FDTL Barrack in Baucau at US $85,288.59 plus $63,176.73
Maintenance and Naval Services (Ship bridges, deck and water pump installation
in Hera at US$41,641.60.
Construction of water tank in Metinaro (3.00m x 3.00m 5 units in Metinaro) at
US$56,159.63.
Water Tank Canopy in Baucau (5.00m x 5.00m units) at US$65,131.05
Water supply installation for F-FDTL Post in Tiliomar, Covalima at
US$208,050.77.
Table 16.6: F-FDTL 2014 Emergency Projects Project
PROJECT SUMMARY
Rehabilitation
of F-FDTL
Barrack in
Baucau
Maintenance
and Naval
services in
Hera
Construction
of water tank
in Metinaro
Water Tank
Canopy in
Baucau
Water supply
installation for F-
FDTL Post in
Tiliomar
Status Completed Completed Completed Completed Implementation
Contractor
Wingstone
Unip Lda
Wingstone
Unip Lda
Wingstone
Unip Lda
Wingstone
Unip Lda
Wingstone Unip
Lda
Date of Contract Original
Contract with
SED
Contract with
SED
Contract with
SED
Contract with
SED Contract with SED
Original Completion Date
Contract with
SED
Contract with
SED
Contract with
SED
Contract with
SED Contract with SED
Contract Amount 631,767.32 41,641.60 56,159.63 65,131.05 208,050.77
Actual completion date
Present physical completion status 100% 100% 100% 100% 22%
Payments schedule
Pre IF payments for Advance 483,302.00 - - - -
2014 IF Payments ($) 148,465.32 41,641.60 56,159.63 65,131.05 41,265.41
2015 IF Payments ($) - - - - -
Total to be paid ($) 631,767.32 41,641.60 56,159.63 65,131.05 41,265.41
Contract Balance ($) - - - - 166,785.36
Note: MPS and Free Balance, 30June 2015
16.8 CONSTRUCTION OF F-FDTL POSTS
16.8.1 F-FDTL Posts in Tiliomar and Tunubibi
The 2015 budget for the construction of F-FDTL posts was US$ 1 million. These posts were
awarded to local contractors in October 2011 both under the supervision of Vox da Vinci. With
the inadequate financial and technical capacity of the original contractor for the Tilomar post,
it was retendered and was completed by Surik Saki Rai Unipessoal Lda. Tunubibi Post, on the
other hand, was contracted to Bobolait Construction in the amount of US$347,604.61 with an
additional cost of US$ 303,033.74 to address problem on access road based on CAFI decision
dated 13 and 14 of November 2013 and approved proposed additional works. The second
additional works of US$592,865.30 for the access road including electricity and water supply
installations was approved by CAFI on 24 of October 2014.
101 | P a g e
The rehabilitation of Post of the F-FDTL in Tilormar has been 100% completed, US$
177,501.4 from total contract amount of 180,689.83 paid to the company and US$ 3,188.43 is
for unclaimed item as per ADN recommendation. Further, revised contract amount for
rehabilitation of Post of the F-FDTL in Tunubibi was US$ 1,243,503.65 and US$ 930,485.30
was paid to the company. While the revised contract for consultant supervision was US$
180,540.00, the services have been 100% completed. US$ 163,845.00 paid to the consultant
while US$ 16,695 is for unclaimed item as per ADN recommendation. ADN reported that
only 75% of total additional cost for amendment 2 was executed as no supervision was carry
out for Post F-FDTL in Tilormar. Details are shown in the table 16.7.
Table16.7: F-FDTL Posts in Tunubibi and Tilomar Project
PROJECT SUMMARY Completed Implementation Process
Project name
F-FDTL Posts in
Tunubibi
F-FDTL Posts in
Tunubibi
F-FDTL Posts in Tunubibi
and Tilomar
Company
Surik Sake Rai
Construction
Bobolait Construction
Unip. Lda
Vox da Vinci Consultant
Engineer
Date of Contract 3-Dec-2012 25-Oct-2011 3-Dec-2012
Original Completion Date 20-Mar-2013 25-Mar-2012 20-Mar-2013
Amendment No. 1 and Date 5-Oct-2013 5-Oct-2013
Revised completion Date 31-May-2013 13-Mar-13 31-May-2013
Original Contract Value, inc supervision ($) 148,805.46 347,604.61 66,620.00
Revised Contract Value 1 31,884.37 303,033.74 47,140.00
Revised Contract Value 2 - 592,865.30 66,780.00
Final Contract Value ($) 180,689.83 1,243,503.65 180,540.00
Actual completion date 30-Sep-13 30-Nov-13 30-Nov-13
Present physical completion status 100.00% 84% 100%
Payments schedule
2011 IF payments ($) - 52,140.69 0
2012 IF Payments ($) - - 0
2013 IF Payments ($) 162,620.85 555,181.95 113,760.00
2014 IF Payments ($) 14,880.55 323,162.66 50,085.00
2015 IF Payments ($) 0.00 - -
Total to be paid ($) 177,501.40 930,485.30 163,845.00
Contract Balance ($) 3,188.43 313,018.35 16,695.00
Source: MPS and Free Balance, 30 June 2015
16.8.2 F-FDTL Post in Atauro
NPC completed tender for rehabilitation F-FDTL Post project in Atauro, contract was awarded to Bobolait Unip. Lda on August 2014. The contract agreement was signed on 1
st September
2014 with duration of six months. The physical progress currently achieved 50% but no payment receives during this reporting period. Details of contract provided in the table 16.8.
102 | P a g e
16.9 CONSTRUCTION OF F-FDTL HEAD QUARTER COMMAND TRAINING
CENTRE IN METINARO
The project started on 5 August 2013 by Young Jin
Construction with Pires Architect as the Supervision
Consultant. Target project duration was 365 days,
however due to some delays the contract has been
extended until 31 December 2014. CAFI approved
allocation of US$ 0.415 for 2015. Physical progress
as of end June 2015 was 100% completed but no
disbursement in this reporting as the claim from
company still prepare their claims to the under
verification of the project owner. Details are
provided in Table 16.9.
Completion photograpy end June 2015
Table16.8: F-FDTL Posts in Oecussi and Atauro Project
PROJECT SUMMARY Implementation process
Company Bobolait Unip,lda
Date of Contract Signature 1-Sep-2014
Contract Duration (days) 6 months
Notice to Proceed
Original Completion Date 1-March-2015
Actual completion date
Original Contract Value ($) 1,204,448.91
No of variations -
Final Contract Value ($) 1,204,448.91
Present physical completion status 30%
2013 IF Payments ($)
2014 IF Payments ($) 325,665.73
2015 IF Payments ($) -
Total to be paid ($) 325,665.73
Balance of Contract ($) 878,783.18
Source: MPS and Free Balance, 30 June 2015
16.10 CONSTRUCTION OF NATIONAL DEFENCE INSTITUTION OFFICE BUILDING
Since 2013, the studies and design of the National Defence Institution Office Building has
been budgeted in the amount of US$ 0.500 million and 2014 was US$0.20 million but there
was no budget execution for that period.
In early March 2015 the tender completed and contract awarded to PT Perentjana Djaja with
total contract US$704,133.51 for Consulting Services of Detailed Architecture and
Engineering Design of Master Plan of New Campus of National Institute of Defence.
Budget allocation for the construction of the structure in 2015 was US$529,000.00 however
there was no disbursement made as of 30 June 2015.
103 | P a g e
Table 16.9: Construction of F-FDTL Head Quarter Training Centre Project
PROJECT SUMMARY Implementation process Implementation process
Company Young Jin Construction Inc PIRES Architec Unip. Lda
Date of Contract Signature 28-Jun-2013 3-Nov-2013
Contract Duration (days) 365 365
Notice to Proceed 5-Aug-2013
Original Completion Date 5-Jul-2014 3-Oct-2014
Actual completion date 31-Dec-2014 30-Dec-2014
Original Contract Value ($) 2,476,554.51 104,208.00
No of variations - 49,569.12
Final Contract Value ($) 2,476,554.51 153,777.12
Present physical completion
status 100% 100%
2012 IF payments ($) -
2013 IF Payments ($) 495,310.90
2014 IF Payments ($) 1,188,641.66 107,643.98
2015 IF Payments ($) - -
Total to be paid ($) 1,683,952.56 107,643.98
Balance of Contract ($) 792,601.95 46,133.14
Source: MPS and Free Balance, 30 June 2015
104 | P a g e
17 SOCIAL SOLIDARITY
Projects under Social Solidarity involve construction of district offices and buildings,
establishment of recreational parks, preservation of historical sites and monuments in honour
of the martyrs of the national liberation. In this social solidarity program, two projects were
listed under the Social Solidarity Program, however no budget allocation in 2015. The contract
detail shows that construction of Nikolau Lobato Monument at Dili Airport round-about
payment still not completed.
17.1 CONSTRUCTION OF PRESIDENT NICOLAU LOBATO’S MONUMENT
The construction cost and the life-size statue of President Nicolau Lobato contracted to
Nananiu Unipessoal Lda with total contract amount of US$ 1,581,623.80. ADN as the project
owner and in-charge of the construction supervision reported that the project was 100%
completed. The payment recommendation letter and inspection report of ADN dated 28
August 2014 stated the actual accomplishment only achieve US$ 1,564,500.90, therefore
payment made to the company as per actual works completed or 99%, while balance of
contract at US$ 17,122.90 categories as un-claimed amount. Payment progress is shown in
Table 17.1.
Hence, CAFI meeting 22 August 2014 approved an additional fund of US $1 million taken
from MDG program. The amount was used in the construction of airport’s welcome gate and
improvement of the parking area. This additional work was contracted to Pantarhei
Unipessoal Lda Company in the amount of US $1 million. The payment recommendation
letter and inspection report of ADN dated 5 November 2014 shows the actual
accomplishmdent only achieved 99.37% or 994,007.79 and US$ 6,324 is for un-claimed
amount. Remain payment for 10% retention was US$ 99,407.78 which will release in 2015
but no allocation for 2015. None disbursement in this reporting perios as no claim submit to
MPS.
Table 17.1: Status of President Nicolau Lobato Monument and Welcome Gate Project
Estado do projecto Completo Retenção
Estado Físico Construtor Consultor Supervisão
Nome do Projecto: Construction of President
Nicolau Lobato Monument
Construction of Welcome gate Airport, Parking area,
Supply and Install Statua Nicolau Lobato at Rotunda
Comoro
Empresa: Nananiu Unipessoal Lda Pantarhei Unipessoal Lda
Data do Contracto: 16 de Julho 2012 14 de Fevereiro 2014
Data do InÍcio de obra 16 de Julho 2012 18 de Fevereiro 2014
Data de Conclusão Inicial: 30 de Janeiro 2013 31 de Julho 2014
Valor Contrato Inicial (US$): 1.581.623,8 10.00.401,79
Data de Conclusão revisto: 12. 13 de Julho 2013 15 de Julho 2014
Valor contrato revisto (US$): 1.581.623,8 10.00.401,79
Progresso Fisico actual:
Procento 100% 100%
Pagamentos / Estado Financeira
Pagamento Não FI (US$): 287.981,70
Pagamento FI 2011 (US$): 1.116.564,94
Pagamento FI 2012 (US$):
105 | P a g e
Pagamento FI 2013 (US$):
Pagamento FI 2014 (US$): 159.954,27 894.670,01
Pagamento FI 2015 (US$): 0.00
Total Pago (US$): 1.564.500,91 894.670,01
Balanço do Contrato (US$): 17.122,89 105.731,78
Source: MPS and Free Balance as of 30 June 2015
106 | P a g e
18 TASI MANE
The Tasi Mane Development Program is a strategic investment program made by the
government in order to initiate and accelerate the economic development in the Southern
coast zone of the country that has identified in the National Strategic Development
The Tasi Mane program comprises of analytical studies and infrastructure projects that have
an objective in supporting the petroleum-led development of Timor-Leste. The original
allocated budget for 2015 was US$ 35.081 million. Status of projects and budget execution as
of 30 June 2015 are presented in the table 18.1:
Table 18.1: Summary Budget Allocation for Tasi Mane Program
Project
Original
Budget
Allocation
2015 ('$000)
Revised
Budget
Allocation
2015 ('$000)
Expenditure
as of 30
June 2015
('$000)
Balance
2015
('$000)
Remark
Betano Petrochemical Detailed Studied
for the Geotechnical and Marine Survey
- Betano Refinery FEED
1,000 0 0 No further study
Preliminary, Detailed Design
Environment and Social Economic
Assessment for Highway Roads from
Suai to Beaco
12,500 12,500 12,500 Site socialization
for land and
properties for
first phase
Design of Construction and supervision
for development of infrastructure on the
south Coast in Suai - Supply Base
20,381 20,381 20,381
DB tender nearly
completed
Detailed Survey for Local Development
of Infrastructure Southern Coast in
Beaco for Pre FEEB LNG
1,000 1,000 On-going
Concept, design and supervision for
development of infrastructure on the
south coast in Beaco
No issues in this
report
Gas pipeline route analysis for
development of infrastructure on the
south coast
No issues in this
report
Environmental Studies (S/B/B) for the
development of infrastructure on the
south coast
No issues in this
report
Urban planning design in Suai 1000 1000 1000 No information
Study and survey water supply from
Data Rua and Tolu in Suai
200 200 200 On-going
Total 35,081 35,081 35,081
Source: MPS and Free Balance, 30 June 2015
Following are the status of individual projects of the Tasi Mane Program:
107 | P a g e
18.1 BETANO PETROCHEMICAL FACILITIES – DETAILED GEOTECHNICAL AND
MARINE SURVEYS
The development of petrochemical facilities in the southern coast includes geotechnical
investigation, marine survey and design of Betano crude oil Refinery, as the project was listed
in the IF program since 2011. In addition to that, an agreement has been signed between the
GoTL and Timor Gap and Petroleo EP Company (Timor Gap E.P.) to undertake detailed
studies and design on Betano Refinery Font End Engineering Design (FEED) as listed below
with total cost of US$4.9 million.
Betano Refinery Front End Engineering Design (FEED), US$3.2 million;
Land survey including topography and soil investigations, US$0.25 million;
Land development design, US$0.25 million;
Market study. US$0.15 million;
Environmental Impact Assessment (EIA) and Health Impact Assessment
(HIA),US$0.75 million;
Timor Gap and Petroleo E P Company fees, US$0.3 million.
It was learned from Timor Gap project that by the end of 2014, Timor Gap EP Company has
completed the detailed studies and Front Engineering Design (FEED) on Betano Refinery
project. Full payment was made with the two installments of payment, where first payment
that cover 50% of the contract made in July 2012, while the second payment instalment made
in August 2013 for the remaining 50% contract value. However, no final completion report on
the detailed studies and FEED of Betano Refinery project including financial execution report
as per contract submit to MPS.
The Timor Gap E.P. was requested to submit the final completion report for the work through
Ministry of Petroleum and Mineral Resources (MPRM) to CAFI on 10 December 2014.
However, no action has been taken by the project owner so the MPS has sent follow letter on
23 June 2015 to retrieve the final completion report to MPRM. US$ 1 million was allocated
for 2015 for geotechnical investigation survey, however, MPRM and Timor Gap E.P.
informed that there will no other geotechnical investigations to be carried out. As per MPRM
request, CAFI meeting 24 April 2015 approved internal transfer allocation budget to Detailed
Survey for Local Development of Infrastructure Southern Coast in Beaco to pay Pre FEEB
LNG contract.
18.2 DESIGN, CONSTRUCTION AND SUPERVISION OF THE SUAI–BETANO-
BEACO HIGHWAY ROADS
The objective of the project is to provide high quality access roads between the town, port and
airport at Suai and the proposed oil and gas industry facilities in Betano (Manufahi) and
Beaco (Viqueque). A contract for preliminary design and follow-up Detailed Engineering
Design, Environmental Impact, Social Impact Assessment and Economic Feasibility Studies,
108 | P a g e
of a four-lanes highway from Suai to Betano via Beaco was awarded to PT Virama Karya (in
association with Multi Arch Consulting Lda) with total contract value of US$ 1,324,932 on
10 December 2010 and completed by December 2011. The payment for the design consultant
was made in the amount of US$ 132,493.2 through pre infrastructure fund and US$
1,192,438.8 under IF.
NPC handled the procurement of Contractor and Supervision Engineer for Section 1: Suai –
Fatukai/ Mola Km Sta.3 +920 to Sta 34+275. Due to no urgency of this project, the
Government did not allocate budget in 2014 for its implementation as well as the socialization
for lands and properties in the new road alignment. However, Government has decided to
carry out its procurement works for first section in 2014, that’s planed to be implementing in
2015. For the construction and supervision of section one, Government has allocated US$ 12.5
million for 2015.
On 28 January 2015, NPC informed that contract for the section to be contracted to China
Overseas Engineering Group Co., Ltd in joint venture with China Railway First Group Co.,
Ltd with total contract prices of US$ 298,100,257.9. The contract for section 1 was signed by
Ministry of Public Works and contractor on 11 February 2015. As requested by NPC, the
budget declaration and budget availability has provided on 23 February 2015. NPC processing
audit court review and endorsement and its contract endorsed on 26 March 2015. The contract
for construction supervision will be awarded to Catahira Engineering, draft of contract has
sent to MoPW on 19 of March 2015.
CAFI meeting dated 13 April 2015 approved contract award to China Overseas Engineering
Group Co., Ltd in joint venture with China Railway First Group Co., Ltd. The approval of
CAFI with notes that MPWTC need review budget allocation from other program and transfer
to this project to cover advance payment and plan next year budget allocation. Moreover, the
construction works are not start yet as the MPRM, MPWTC, Local Government and relevant
agency still conducting socialization of land acquisition and properties of affected people by
the first phase project. Meanwhile, MPWTC, MPRM and Loan Unit of the Ministry of
Finance are reviewing loan financing proposal from China EXIM Bank for this first phase
project.
18.3 DESIGN, CONSTRUCTION AND SUPERVISION OF SUAI SUPPLY BASE
Eastlog Holdings Pte Ltd. completed the commercial and financial feasibility study as well as
the detailed engineering design for Suai Supply Base in May 2011. The Technical and
Commercial Feasibility Studies which included “Front End Engineering Design” (FEED)
concluded that SSB construction is viable. Payment of US$1.5 million was made to the
consultant from the IF in 2011 in addition to US$1.9 million paid prior to the establishment of
the IF. In addition, a payment of US$ 483,129 was made to SERN for “Early Works” on the
preparation of the project sites. Table 56 presents the contract and payment details to
EASTLOG HOLDINGS Pte Ltd.
109 | P a g e
Eastlog Projects Limited as the Supervision Consultant also provided services during the Pre-
Construction. The services were also including preparation of design and construction bid
documents including technical and finacial evaluation, contract preparation and other
releveant services. The amount of US$ 494,792 was paid to the consultant in 2013 and US$
989,583.65 in 2014.
Meanwhile, the Supervision Contract (2nd
phase) of approximately 30 month period is
estimated at US$ 4,354,177.00. TG-EP informed that they received additional cost for
supervision works which still under review. The contract negotiation with the audit court’s
endorsement will follow accordingly. No disbursements in this reporting period as the
company still prepare their claim to Timor Gap and MPRM, and Design and Costruction of
SSB contract are not finalise yet.
Estimated cost for design and build was adjusted from US$ 300 million to US$ 475 million
due to additional liquid berth (ALB) works for Betano Refinery Projects by MPRM. Further,
on 9 April 2015, MPRM has submitted revised budget estimate for SSB design and
construction including supervision services for period of 2015 to 2018 was US$ 736.16
million. The tentative advance payment to be released is about 20% of the final contract value
when all procurement process includes Audit Court endorsement completed.
The design and construction bid documents i.e. technical evaluation have been completed.
NPC, MPRM and EASTLOG PROJECTS LIMITED (Consultant) have completed financial
proposal opening and evaluation. On 18 June 2015, NPC and Timor Gap E.P informed that
Council of Ministry has approved selected company (Hyundai – South Korea), letter of
acceptance expect to be issue late of June 2015 or early July 2015 following Audit Court
Camber which will take about a month, the project expect to be commenced in November
2015 and will be completed within Three (3) years, US$ 15 million for first installment of
advance payment will release around November 2015 and remain shall release in 2016.
In addition to the payment schedule set in the contract, NPC and TG-EP stated that it required
adequate budget allocation for 2016 which should at least US$ 250 million to cover remain
advance payment and progress payment, US$ 250 million for 2017 and US$217 million for
2018. NPC explained that Hyundai is experienced company and have provided very
comprehensive implementation methodology so they will complete works as per approved
time schedule.
Preparatory works including land acquisition commenced in November 2011. The acquired
1,113 hectare area was formally handed-over to the Government by Suai Community
(Camenasa Village) on 11 April 2013 to be used by the SSB and Industrial State for 150 years
and in return the Community will receive 10% share from SSB profit. In addition to land
acquisition, livestock and resettlement payment was proposed by MPRM and approved by
CAFI on 24 October 2014. MPRM, Land Property of Ministry of Justice, Local Authorities
and affected people have finalized the agreements and contracts for payment. Subsequently,
the amount of US$ 3,556,450 requested by MPRM was paid through Banco Nacional de
Commercio de Timor Leste (BNCTL) on 12 December 2014 under budget code 8080301.
110 | P a g e
BNCTL, MPRM, Timor Gap, Land and Property and Local Authority still process payments
to affected people. Details are provided in the table 18.2:
18.4 DETAILED SURVEY FOR LOCAL DEVELOPMENT OF INFRASTRUCTURE OF
SOUTHERN COAST IN BEACO
The GoTL allocates fund for site investigation to support the Front End Engineering and
Design (FEED) of the LNG Plant Project. Toke Oil and Gas in Joint Venture with EGS
performed the investigation under the supervision of Pipeline Task Force Team that was
formed by SERN with the assistance of HR Wallingford Consultant.
Financial status. The contract of Toke Oil and Gas / EGS was signed in November 19, 2010
with the contract value of US$ 6,639,517. Amounted to US$ 6,506,956.17 was paid from
2011 to 2013 with an unclaimed amount of US$ 132,557.83. All the reports were completed
and submitted to TG-EPC and MPMR. To carry Pre-FEED LNG in Beaco, US$ 5 million was
allocated for 2014. As the procurement process for Pre-FEED LNG did not finalise in 2014.
CAFI meeting 24 October 2014 approved to transfer US$ 2,361,244.5 to pay the land
acquisition, livestock and resettlement for the Suai Supply Base Project; US$ 37,926.23 was
paid for land acquisition, livestock and resettlement for the Suai Airport Project, and; the
balance of US$ 2,600,829.27 was transferred to electrical program to cover 2014 payments.
MPRM and Timor Gap E.P.C. completed the TOR for Pre-Front Engineering Design (Pre-
FEED) for LNG Plant in late July 2014 and were verified by National Development Agency
(NDA). NPC than carried out the tender since July 2014 and the intent to award published on
11 March 2015. The projects contracted to AMEC Foster Wheeler Energy Limited Consultant
on 22 April 2015 and intend to be completed within 20 months. The studies and design works
is progressing and first payment at US$ 0.95 was received at MPS on 24 June 2015 under
process. As no budget allocation for 2015, CAFI meeting dated 24 April 2015 has approved an
internal transfer of US$ 1 million from Betano Petrochemical Detailed Studied budget
proposed by MPRM. Details are provided in the table 18.3:
Table 18.2: Suai Supply Base (SSB) Project
PROJECT SUMMARY
Status Completed On-going Tender stage
Company Name EASTLOG
HOLDING Pte.
Ltd. - Studies
EASTLOG
PROJECTS
LIMITED
(Consultant)
Design and
Construction
Contract Signing Date 10 Dec 2010 17 January 2013
Commencement Date
Contract Amendment 1 Date 8 May 2013
Original Completion Date 17 June 2011
Audit Court Endorsement Date NA 23 May 2013
Issue Notice to Proceed Date
Actual Completion Date 17 June 2011
Original Contract Value 3,400,000.00 6,958,346.00
111 | P a g e
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 3,400,000.00 6,958,346.00
Physical progress till quarter end % 100 25
Payment Schedules
Pre IF payments ($) 1,900,000.00
2011 IF payments ($) 1,500,000.00
2012 IF payments ($)
2013 IF payments ($) 494,792.30
2014 IF payments ($) 989,583.65
2015 IF payments ($) 0.00
Total to be paid ($) 3,400,000.00 1,484,375.95
Balance to be paid ($) 0.00 5,473,970.05
Source: MPS and Free Balance, 30 June 2015
Table 18.3: Pre-FEED LNG Plant in Beaco Project
PROJECT SUMMARY Final report submitted to
Timor Gap E.P. and MPRM
On-going
Company Name Toke Oil and Gas / EGS
Ltd. - Studies
AMEC Foster Wheeler
Energy Limited
Consultant
Contract No. STA-SERN-001/2010
Contract Signing Date 19 November 2010 22 April 2015
Commencement Date
Contract Amendment 1 Date
Original Completion Date 19 April 2012 22 February 2017
Audit Court Endorsement Date NA NA
Issue Notice to Proceed Date
Actual Completion Date 17 July 2013
Original Contract Value 6,639,517.00 3,800,000.00
Contract Amendment
a. Amendment 1 (Cost / Duration)
b. Amendment 2 (Cost / Duration)
Final Contract Value 6,639,517.00 3,800,000.00
Physical progress till quarter end % 100 20
Payment Schedules
Pre IF payments ($) 1,200,000.00
2011 IF payments ($) 4,953,867.17
2012 IF payments ($) 0.00
2013 IF payments ($) 353,092.00
2014 IF payments ($)
2015 IF payments ($) 0.00
Total to be paid ($) 6,506,959.17 0.00
Balance to be paid ($) 132,557.83 3,800,000.00
Source: MPS and Free Balance, 30 June 2015
112 | P a g e
18.5 CONCEPT AND SUPERVISION FOR DEVELOPMENT OF INFRASTRUCTURE –
BEAÇO
Toke Oil and Gas / EGS Joint Venture completed the marine site surveys and pre-FEED for
the marine facilities in 2012 under the supervision of HR Wallingford Consultant. The amount
of US$ 1,241,416.79 was paid to the consultant with the total unclaimed cost of US$ 6,583.21.
CAFI approved the proposal of MPRM on 26 April 2012 to make an agreement with Timor
Gap and Petroleo EP Company (Timor Gap) to carry out Consultancy Services for the TIMOR
LNG Marine Facility Front End Engineering Design (FEED) in Beaco, Viqueque, Timor
Leste. Subsequently, the GoTL and Timor Gap and Petroleo EP Company (Timor Gap) signed
agreement on 1 June 2012 in the amount of US$3.5 million to undertake FEED studies
inclusive of the survey and engineering design, which will be done closely with the consultant
HR Wallingford covering the following activities.
Design Review, US$0.53 million;
Optimization, US$0.65 million;
Engineering Design, US$0.70 million;
Cost and EPC Package, US$0.21 million;
Metocean Survey Support, US$0.12 million;
Additional Metocean and Sediment Survey, US$0.70 million;
Sediment Survey Support, US$0.12 million;
Quarry Assessment, US$0.15 million;
Contingency, US$0.20 million;
Timor Gap and Petroleo E. P. Company fees, US$0.300 million.
Half of the total contract value has been paid to Timor Gap in June 2012 with the remaining
50% balance paid in Aug 2013. The project owner is required to submit completion report to
the CAFI. For this purpose, the letter regarding final completion report and financial execution
has been sent to MPRM on 10 December 2014. However, no action has been taken by the
project owner so the MPS has sent follow letter to MPRM on this matter on 23 June 2015.
There was no allocated budget for this project in 2015. Details of contract are provided in the
table 18.4:
18.6 WATER SUPPLY IN DATO RUA TO TOLU
To provide better water supply and drinking water to major infrastructure projects in Suai such
as Supply Base and Airport, CAFI approved the amount of US$ 0.3 million for the survey and
study water supply from Dato Rua and Tolu in Suai. While the project is still in the
procurement stage, the allocated budget for 2014 was transferred to electricity program.
The NPC completed procurement process and contract award to Pakistan Engineering
Services (PES) (Pvt.) Ltd. JV with Archtimor Engineering Consultants and JKC Consultant
Engineering 30 April 2015. The project intends to be completed within 5 months after issue of
113 | P a g e
notice to proceed by the project owner. For survey, study and design this project US$ 0.2
million was allocated for 2015. No disbursement in this reporting period as the works in the
preparation for site mobilization and preliminary stage.
18.7 URBAN PLANNING IN SUAI
To provide better support facility to major infrastructure project in Suai such as Supply Base
and Airport, CAFI approved the US$ 2 million for Urban Planning in Suai. While the Ministry
of Public Works (MoPW) and MPRM are still finalizing the TOR, CAFI approved the transfer
of budget to electricity program to cover 2014 payments. For study and design Suai Urban
Plan, US$ 1 million was allocated for 2015.
Table 18.4: TIMOR LNG Plant – Pre FEED LNG and FEED in Beaco Project
PROJECT SUMMARY Supervision and Field Work
Support for MSI & Pre-FEED for
Marine Facility is completed, final
report submitted to Timor Gap E.P.
and MPRM
Marine Facility and
FEED final Completion
Report including budget
execution no submit yet
Contract No. 2012/0001
Company Name HR Wallingford consultant Timor Gáp and Petróleo,
E.P.
Contract Signing Date 12 January 2011 1 June 2012
Commencement Date
Contract Amendment 1 Date
Original Completion Date 12April 2012 1 June 2013
Audit Court Endorsement Date NA NA
Issue Notice to Proceed Date
Actual Completion Date 18 September 2013 8 July 2013
Original Contract Value 1,200,000.00 3,500,000.00
Contract Amendment
a. Amendment 1 (Cost / Duration) 48,000.00
b. Amendment 2 (Cost / Duration)
Final Contract Value 1,248,000.00 3,500,000.00
Physical progress till quarter end % 100 100
Payment Schedules
2011 IF payments ($) 975,656.14
2012 IF payments ($) 265,761.29 1,750,000.00
2013 IF payments ($) 1,750,000.00
2014 - 2015 IF payments ($)
Total to be paid ($) 1,241,417.43 3,500,000.00
Balance to be paid ($) 6,582.57 0.00
Source: MPS and Free Balance, 30 June 2015
114 | P a g e
19 DESIGN AND SUPERVISION OF NEW PROJECTS
19.1 GENERAL
This program caters for the design of new projects separate from the budget allocated for
construction. There are 27 projects from various programs listed in 2015 IF budget in the
amount of US$ 6.232 million to be used in the preparation of DED and US$ 1,957,430 for the
supervision of projects and total allocated budget was rectified to US$ 7.189 million in March
2015. There is one project named Design, Construction and Supervision of Port Pesquiro in
Metinaro still progressing but no allocation in 2015, in this matter MAF will review other
allocated project for the remain payment. The public building projects are summarised inTable
19.1.
19.2 PROJECT STATUS
19.2.1 Detailed Design of Ministry of Commerce, Industry and Environment New
Office Building
This project aims to accomodate MCIA employes which are currently sharing office space
with the Ministry of Mineral and Natural Recources. It will be located in the current Comoro
Market with 2015 budget allocation of US$ 1 million for the DED. The contract was awarded
to Philkoei International, Inc. in JV with Arch Haus Asia Consultant Inc. in the amount of
US$ 270,000. Work commenced in May 2014 and intends to be completed on 11 November
2014. The allocation budget for this project in 2015 was US$ 0.1 million. The details contract
as summarized in table 19.2.
19.2.2 Detailed Design of MCIA Training Centre
NPC has completed the tender for the DED of MCIA Training Centre with the contract
awarded to Vitor Hugo Coordenacao e Gestao de Projectos in JV with Quadramor Timor in
the amount of US$ 216,700. The work commenced in May 2014 and due for completion on 16
October 2014. However, design works still yet completed and no payment made up to date,
the project owner is reviewing status of this contract. The allocation budget for this project in
2015 was US$ 0.15 million. The details contract as summarized in table 19.2.
115 | P a g e
Table19.1: Public Building Project under Design and Supervision Program Project
No. Dono
Projecto Desenho e Estudos Novas Infraestruturas -FI
Orçãmento
Original -
2015
('$000)
Orçamento
Ratificativo
2015
('$000)
Despesas
ate 30 de
Junho 2015
('$000)
Saldo 2015
('$000)
1 MTC
Preparação de Conceitos e Desenhos/Estudos
Detalhados para Reabilitação dos Portos Regionais 300.00 300.00 0.00 300.00
2 MOP Instituto de Gestão de Equipamento 100.00 100.00 84.08 15.93
3 MCIA
Construção dos Novos Mercados de Ainaro,
Maliana e Manatuto 100.00 100.00 49.52 50.48
4 MCIA Construção do Novo Edifício do MCIA 100.00 100.00 0.00 100.00
5 MCIA Construção do Mercado e Terminal de Loes 150.00 150.00 0.00 150.00
6 MCIA
Construção do Centro de Cooperativas para
Pequenos Empresários 150.00 150.00 0.00 150.00
7 MAP
Construção do Novo Edifício do Ministério
Agricultura e Pescas, Dili - - 0.00 -
8 MAP Construção e Supervisão de Irrigacão de Buluto 100.00 100.00 0.00 100.00
9 MAP Construção e Supervisão de Irrigacão de Galata 100.00 100.00 0.00 100.00
10 MAP Construção e Supervisão de Irrigacão de Dardau 100.00 100.00 0.00 100.00
11 MAP Construção de Irrigacão de Maukola 100.00 100.00 0.00 100.00
12 MAP Construção e Supervisão de Irrigacão de Beikala 100.00 100.00 0.00 100.00
13 MAP
Concepção, Construção e Supervisão de Porto
Pesquiro, Metinaro - - 0.00 -
14 MOP Construção da Ponte Bidau Motaklaran 200.00 200.00 0.00 200.00
15 MOP Construção da Ponte Ritabou 130.00 130.00 0.00 130.00
16 MCIA
Plano Meste da Área de Tasi Tolu, Reflorestação e
Proteção Ambiental 270.00 270.00 65.87 204.13
17 MAE
Construção de Novos Edifíciosdo Ministério da
dministrção Estatal e Ordenamento Território (5
Andares)
500.00 500.00 0.00 500.00
18 MAE
Preparação Desenho Dethlado e Construção do
Edificios de Administrção Municipal em 9
Distritos (Aileu, Ainaro, Dili, Ermera, Lautem,
Manatuto, Manufahi, Oecusse e Viqueque)
500.00 500.00 0.00 500.00
19 MAE
Construção Edificio Asembleias Municipal em 11
Distritos 9 (Aileu, Ainaro, Baucau, Bobonaro,
Covalima, Ermera, Lautem, Liquica, Manatuto,
Manufahi, Viqueque)
500.00 500.00 0.00 500.00
20 MCIA
Desenho e Construção do Novo Mercado
Municipal em Suai, Covalima 266.00 266.00 0.00 266.00
21
MAE /
STAE
Construção do Novo Edifico do Secretaria Técnico
de Administração Elitorral, Dili 466.00 466.00 0.00 466.00
22 SEPI
Construção do Novo Edificio Secretaria de Estado
para a Promação da Igualdade 600.00 600.00 0.00 600.00
23 RTTL
Rehabilitação dos Estúdos e Escritório da RTTL,
EP 100.00 100.00 0.00 100.00
24 SECOMS Construção da Casa da Impresa 100.00 100.00 0.00 100.00
25 MT Museu do Aipelo e Centro Cultural de Liquiçá 100.00 100.00 0.00 100.00
26 MT Museu de Dair 100.00 100.00 0.00 100.00
27 ME
Preparação Estudo, e Desenho Dethlado Instituto
Sperior Aileu,Servicos Saude, Electricidade 1,000.00 1,000.00 0.00 1,000.00
Sub Total Desenho e Estudos 6,232.00 6,232.00 199.46 6,032.54
Supervisão 1,957.43 957.43 0.00 957.43
Total Global 8,189.43 7,189.43 199.46 6,989.97
Source: MPS analysis and Free Balance Report dated 30 June 2015
116 | P a g e
19.2.3 Detailed Design of New Market of Ainaro Phase I, Maliana and Manatuto Phase
II
Objective of the project is to modernize the existing markets around the country with adequate
space for vendors and customers under safe and hygienic conditions, with toilets and office
space for the Market Management Unit. With the new markets, opening and closing time can
be properly regulated.
The DED was awarded to Sitios e Formas – Projecto e Consultoria Lda in the amount of US$
208,500 where commenced in Sep 2014 and intended to be completed on 12 February 2015.
However, DED still yet finalise the project owner (MCIA) are review status of the original
contract before extend contract or not. The budget allocation for this project is US$ 0.1 million
to cover remain design contract. The details contract as summarized in table 19.2.
Table:19.2.: 3 Design and Supervision Program Project Contracts – MCIA
Estado do Projecto Em Andamento
Nome do Projectos Desenho Detalhado do Centro
Treinamento do MCIA
Desenho
Detalhado do
Novo Edificio do
MCIA
Desenho Detalhado
do Mercado Ainaro
Fase I, Maliana Fase
II e Manatuto Fase II
Companhia Vitor Hugo Coordenacao e
Gestao de Projectos,S.A. in
joint venture with Quadromor
Timor - Sistemas de
Engenharia, S.A.
Philkoei
International Inc.
in JV with Arch
Haus Asia
Consultant, Inc
Sitios e Formas -
Projecto e
Consultaria Lda
Data do Contrato 16-May-14 28-May-14 29-Aug-14
Data do InÍcio (Aviso de Proceder) 30-May-14 11-Jun-14 12-Sep-14
Data Original do Conclusão da Obra 16-Oct-14 11-Nov-14 12-Feb-15
Valor Original do Contrato ($) 216,700.00 270,000.00 208,500.00
Contract Amendment
No. of variations
Revised Completion Date
Revised Contract Value 216,700.00 270,000.00 208,500.00
Actual Completion Date
Progresso Fisico Atual 40% 40%
Horario de Pagamento
Pagamento FI 2013 ($) -
Pagamento FI 2014 ($) - 102,600.00 29,711.25
Pagamento FI 2015 ($) 49,518.75
Total Pago ($) - 102,600.00 29,711.25
Balanco do Contrato ($) 216,700.00 167,400.00 178,788.75
19.2.4 Detailed Design for Ministry of Agriculture and Fisheries New Office Building
MAF intends to construct a Multi-Storey Office Building on its property immediately south of
its existing premises, east of Comoro River Rd (Figure 19.1). Size of land is approximately
117 | P a g e
1.5 ha located at Moris Foun Aldeia, Suco Comoro, Dom Aleixo Sub-district, Dili. The
proposed project would bring all National Directorates together which will improve
organizational coordination and staff productivity, and thereby improve its services
particularly to farmers.
The design contract was as awarded to PT. Bita Enarcon in the amount of US$495,300 and
470,535 was paid to company remain 5% retention but no allocation budget for 2015. The
Ministry of Agriculture and Fishery will review allocated but other project to for remain
payment. Details are provided in Table 19.3
19.2.5 Detailed Design for Terminal and Market Loes
The TOR was reviewed by ADN and has been submitted to NPC for tendering. However, as
reported by NPC, MCIA as the project owner postponed the project with no clear reason.
CAFI meeting dated 24 April 2015 approved MCIE proposed to construct terminal station and
market in Loes with allocate budget to this ministry.
19.2.6 DED for Institute for Management of Heavy Equipment Office and Warehouse
The project will be a modern multi-purpose building with sufficient office space to
accommodate 200 - 250 staff including other buildings and parking lots. During this reporting
period, NPC has succesfully completed the tender with Scope Australia Pty Ltd. as the
winning bidder at US$ 295,000. Details are shown in Table 19.3.
19.2.7 Detailed Design for Construction of Fishing Port at Metinaro
The tender for Study and Detailed Engineering Design has been completed and contract has
been signed by Consulmar – Projectistas e Consultores, Lda Portugal in JV with Engipro,
Timor Leste. The studies are progressing. Meanwhile, MAF is preparing the Terms of
Reference for market and socio-economic studies as additional components of the contract.
The details of contract as shown in table 19.3.
Table 19.3: 3 Various Master Plan and Detail Design Contract Estado do Projecto Completo Em Andamento Em Andamento
Nome do Projectos
Desenho
Detalhado do
Novo Edificio do
MAP
Desenho Detalhado
de Engenharia do
Complexo de
Edificios, Oficina e
Armazens do IGE.
Desenho Detalhado de
Porto Pesquiro, Metinaro
Plano Mestre e
Dezeinho Detalhado
para a Proteção
Ecológica de Tasi Tolu
Companhia PT. BITA
ENARCON
Scope Australia Pty,
Ltd
Consulmar – Projectistas e
Consultores, Lda Portugal
and Engipro, Timor Leste
Joint Venture
Gustavo da Cunha -
Consultores, Profico
Ambiente and Profico
- Joint Venture
Data do Contrato 1-Oct-13 26-Mar-14 19-Jul-14 28-May-14
Data do InÍcio (Aviso de Proceder) 7-Oct-13 9-Apr-14 Dec-2014
Data Original do Conclusão da Obra 7-Apr-14 9-Aug-14 12-Nov-14
Valor Original do Contrato ($) 495,300.00 295,000.00 273,270.70 693,341.00
Contract Amendment
No. of variations
Revised Completion Date
118 | P a g e
Revised Contract Value ($) 495,300.00 295,000.00 273,270.70 693,341.00
Actual Completion Date
Progresso Fisico Atual 100% 100% 40% 10%
Horario de Pagamento
Pagamento FI 2014 ($) 470,535.00 196,175.00 109,308.28 -
Pagamento FI 2015 ($)
84,075.00
65,867.40
Total Pago ($) 470,535.00 280,250.00 109,308.28 65,867.40
Balanco do Contrato ($) 24,765.00 14,750.00 163,962.42 627,473.60
Source: MPS analysis and free balance report, 30 June 2015
19.2.8 Master Plan and Detailed Design for Ecological Protection and Improvement of
Tasitolu
In 2013, the government allocated US$ 500, 000 for the
conduct of study on ecological protection of Tasitolu.
The Ministry of Commerce, Industry, and Environment
(MCIA) conducted due diligence in selecting the
consultant team to plan and prepare the conceptual
design for Tasitolu Ecological Protection and Lake
Improvement.
NPC completed procurement process for marter plan and detailed design for ecological
protection in Tasi Tolu in 2014 and contract awarded to Gustavado da Cunha, Profico
Ambinent in Joint Venture with Profico in the amount of US$ 693,341 and to be completed
within 8 months. Upon receipt of the Purchase Order, the payment for the 10% progress will
be processed. The allocation budget for 2015 was US$ 0.27 million, which will not sufficient
if the project is to be completed by this year. Payment that covers 10% of progress was
claimed last year (2014) was made to company. The study and design work still progressing
and expected to be completed this year. Detail of contract is presented in the table 19.3.
119 | P a g e
20 TRANSPORT PROGRAM
20.1 GENERAL
The Government through Minister of Transport and Communication are planned to develop
and improve air and sea transports facilities in order to provide better services to people.
Transport and Communication is planned to purchase new shipment to accommodate
passenger from Dili to Atauro and Dili to Oecusse. Therefore, government has allocated US$
12 million to purchase new shipment in 2015.
21 TOURISM SECTOR PROGRAM
There are two projects listed under this program with a total budget of US$ 2.0 million. These
Projects are:
Preparation of DED, Construction and Supervision of “Centro de Águas Termais de
Marobo e Atauro”
Preparation of DED, Construction and Supervision of “Lagoa de Maubara”
These projects were initiated by the Prime Minister to develop and improve tourism industry
in Timor Leste to attract both Timorese and foreign visitors. However, the Ministry of
Tourism as the project owner proposed to utilize the budget for the rehabilitation of parks in
Dili as a matter of urgency in preparation for the Timor-Leste hosted CPLP Summit in July
2014. CAFI approved the amount of US$ 1.4 million on 16 June 2014 and another US$ 2.13
million for the commemoration of 500 years - Oecusse which was approved on 10 September
2014. From the project that approved all completed remain retention payment.
Meanwhile for the execution of hot water in Marobo and Atauro, and Logoa in Maubara,
Ministry of Tourism and Culture still preparing TOR study and design. The allocation for
2015 was US$ 1 million and CAFI meeting dated 24 April 2014 approved virement of US$
2.56 million to the turism program based on request from Minister of Tourism. The total
revised budget allocation was US$ 3.56 million. The additional budget were transfer: US$ 0.7
million from construction polytechnic school in Lospalos and Suai and US$ 0.3 million Polo
School Lospalos of Education Program, US$ 1.5 million from MDG housing program, and
US$ 60,243 Post F-FDTL Tunubibi and Tilomar Project from Security and Defence Program.
The proposed budget from Ministry of Tourism is intend to pay construção de esculturas em
bronze alusivas á chegada dos portuguêse a Lifau em 1515 project which required US$
2,560,243 to pay Cairavela from Portugal. The relevant supply of goods and services for
construção de esculturas em bronze alusivas á chegada dos portuguêse a Lifau em 1515
contract was made on 24 November 2014 but no payment was made. Subsequenly, 50% or
US$ 1,280,121.70 from total contract amount of US$ 2,560,243.40 was paid to the company.
The Details of emergency projects are presented in Tables 21.1, 21.2 and 21.3.
120 | P a g e
Table 21.1: Emergency rehabilitation of various Garden and Monument Projects
Estado do Projecto Em Andamento
Nome do Projectos
Reabilitation
of Jardim 5
de Maio in
Motael
Reabilitatation
Cristo Rei
Compound &
Area Branca
Beach
Rehabilitation
of Jardim Dr.
Arthur do
Canto
Resende,
Farol
Reabilitation of
Garden-Time
Monument, Hand
Monument and
Colmera Garden
Companhia Morrison,
Unip.Lda
Lucky Strike,
Unip.Lda
Labilay,
Unip.Lda
Rozy Construction
Unip. Lda
Data do Contrato
Data Original do Conclusão da Obra
Valor Original do Contrato ($) 191,215.27 122,174.40 37,927.48 136,765.73
Adenda do Contrato Primeiro
Adenda do Contrato Segundo
No. de Variação
Data Revisão do conclusão da Obra 1
Data Revisão do conclusão da Obra 2
Valor Revisão do Contrato ($) 191,215.27 122,174.40 37,927.48 136,765.73
Progresso Fisico Atual 97% 96.19% 100% 98.20%
Horario de Pagamento
Pagamento FI 2014 ($) 166,188.59 105,770.03 34,134.73 120,873.66
Pagamento FI 2015 ($)
Total Pago ($) 166,188.59 105,770.03 34,134.73 120,873.66
Balanco do Contrato ($) 25,026.68 16,404.37 3,792.75 5,892.07
Table 21.2: Emergency rehabilitation of various Garden, Convention Centre and
Monument Projects Estado do Projecto Em Andamento Completo
Nome do Projectos Rehabilitation of
Farol Tower
Garden
Reabilitation of
Centro de
Convenções de
Dili
Jardim
Aeroportu /
Sala Interior
do VIP
Consulting Services for
the detailed design of
Dili Gardens (7
Packages)
Consulting Services for
the Detailed Design of
Monument Lifau,
Oecusse District
Companhia Double Star,
Unip.Lda
Haksolok Java
Motor (HJM),
Unip. Lda
Maubere
Spirit,
Unip.Lda
PZ' Design Consultan,
Lda
PZ' Design Consultan,
Lda
Data do Contrato
Data Original do Conclusão da Obra
Valor Original do Contrato ($) 56.348,35 272.894,70 249.218,64 60.884,02 63.638,64
Adenda do Contrato Primeiro
No. de Variação
Data Revisão do conclusão da Obra 1
Valor Revisão do Contrato ($) 56.348,35 272.894,70 249.218,64 60.884,02 63.638,64
Data conclusão da Obra actual
Progresso Fisico Atual 100% 100% 100% 100% 100%
Horario de Pagamento
Pagamento FI Oct - Dez 2014 ($) 50.713,52 245.605,23 224.296,78 60.884,02 63.638,64
Pagamento FI 2015 ($)
Total Pago ($) 50.713,52 245.605,23 224.296,78 60.884,02 63.638,64
Balanco do Contrato ($) 5.634,84 27.289,47 24.921,86 - -
121 | P a g e
Table 21.3: Construção de esculturas em bronze alusivas á chegada dos portuguêse a Lifau
em 1515 Project
PROJECT SUMMARY
Status
Supply of Goods and Related Services construção de esculturas
em bronze alusivas á chegada dos portuguêse a Lifau em 1515
Company Name Fundição de Bronzes de Arte Lage, Lda
Contract Sigining Date 24-Nov-2014
Commencement Date
Original Completion Date
Date of Amendment 1 16-Apr-2015
Audit Court Endorsement Date N/A
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 2,560,243.40
Contract Amendment 0.00
a. Amendment 1 (Cost/Duration)
Final Contract Value 2,560,243.40
Physical progress till quarter end % 50%
Payment Schedules
2014 IF Payments ($) 0.00
2015 IF Payments ($) 1,152,109.53
Total Paid 1,152,109.53
Balance to be Paid 1,408,133.87
Source: MPS analysis and Free Balance report, 30 June 2015
122 | P a g e
22 FINANCE SYSTEM AND INFRASTRUCTURE
SUPPORT PROGRAM
This program mainly espouses the Ministry of Finance IT System and the completion of the
New Ministry of Finance Building. The MoF office building is completed in 2014 with only
retention payments to be disbursed in 2015. However, the interior works, IT, database, etc.
works still in the procurement stage. There are 14 projects listed under this program with a
total budget allocation of US$ 19.135 million in 2015. Details budget allocation and
disbursement shows in table 22.1.
Table 22.1: Budget allocation and disbursement status of 2015
No. Nome de Projecto
Orçãmento
Original -2015
('$000)
Despesas ate
de 30 de June
de 2015
('$000)
Saldo
2015
('$000)
1
Alojamentos dos Oficiais dos Postos Integrados das Áreas
Fronteiriças de Batugade 373,30 -
373,30
2
Construção dos Postos Integrados de Oesilo e Tunubibi,
MdF 500,00 -
500,00
3
Concepção, Construção e Supervisão do Novo Edifício do
Ministério das Finanças em Díli 3.500,00 -
3.500,00
4 FreeBalance 3.500,00 1,074.67 2.425,33
5
Desenho, Construção e Supervisão do Novo Edifícios da
Alfândega e Imposto, MdF em Díli 248,90 -
248,90
6 Trabalhos de Acabamentos do Novo Edifício -MDF 300,00 - 300,00
7 Trabalhos de Construção Interiores do Novo Edifício -MdF 1.000,00 - 1.000,00
8 Equipamento (Mobiliarios) 1.000,00 - 1.000,00
9 Servicos Audiovisuais 1.262,50 - 1.262,50
10 Instalação de Centro de dados e Seguranca 2.038,00 - 2.038,00
11 Construção de Centro de Dados e Instalações de Informática 3,162,50 - 3,162,50
12
Sistema "Back-Up" do Novo Edifício do Ministério das
Finanças 750,00 -
750,00
13 ASYCUDA 750,00 - 750,00
14 Ferramentas e Sistema de Impostos Internos 750,00 - 750,00
Total 19.135,20 1,074.67 18,060.53
Source: MPS report and Free Balance, 30 June 2015
123 | P a g e
22.1 INFORMATICS SYSTEM
Budget allocations for the IT Programs in 2015 are shown table 22.2:
Table 22.2: Budget allocation for IT Program under MOF in the FY-2015
Project Name 2015 Budget ($000)
Freebalance 3.500
System Back-up data at the Ministry of Finance New Building 750
Asycuda 750
Audio Visual Services at the Ministry of Finance New Building 1.263
Installation of the security of Data Center at Ministry of Finance New Building 2.038
Construction and Installation of Data Center and Information Technology at MOF new Building 3.163
SIGTAS 750
Total 12.214
Table 22.3: Interior Design and Instalment status
Estado do Projecto Em Andamento
Companhia Design & Supervision
HBO+EMTB Interiors Pte, Ltd, Singapore
Data do Contrato 14-Jan-14
Data Original do Conclusão da Obra 14-Mar-14
Data Original do início da Obra 14-Jan-14
Audit Court Endorsement Date
Issue notice to Proceed Date
Valor Original do Contrato ($) 614.000,00
Contract Amendment
No. of variations
Revised Completion Date
Valor Revisão do Contrato ($) 614.000,00
Actual Completion Date
Progresso Fisico Atual 100%
Horario de Pagamento
Pagamento FI 2014 ($) 614.000,00
Pagamento FI Jan - Mar 2015 ($) -
Total Pago ($) 614.000,00
Balanco do Contrato ($) -
22.1.1 IT Design of New Ministry of Finance Building
The Detailed Design for the IT system of the New Ministry of Finance Building was
completed in February 2014 and payment was made during the second quarter of 2014. The
following table 22.3 shows the progress of payments to HBO+EMTB Interiors PTE Ltd.
While for supply, installation, configuration, testing and commissioning of IT equipments to
new Ministry of Finance Building is in the invitation to the interest bidder. The tender
expected to be carried out with two months.
124 | P a g e
22.1.2 ASYCUDA WORLD
Automation of System Customs Data (ASYCUDA) is a soft infrastructure system, a property
of and established by UNCTAD for the government of Timor Leste to manage tariff collection
from export-import activities. On software and hardware upgrading, training and capacity
building, UNCTAD has been tapped to supervise the work in the amount of US$ 1.369
million. Half of the cost has been paid to the company in October 2014 as advance payment
using the US$ 1 million in 2014 and remain will pay as per contract. Details of payments are
provided table 22.4:
Table 22.4: ASYCUDA WORLD status
Estado do Projecto Em Andamento
Companhia Design & Supervision
UNCTAD
Data do Contrato 15-Jul-14
Data Original do Conclusão da Obra 26 months after the commencement date
Data Original do início da Obra 15-Jul-14
Audit Court Endorsement Date
Issue notice to Proceed Date
Valor Original do Contrato ($) 1.369.000,00
Contract Amendment
No. of variations
Revised Completion Date
Valor Revisão do Contrato ($) 1.369.000,00
Actual Completion Date
Progresso Fisico Atual 50%
Horario de Pagamento
Pagamento FI 2014 ($) 684.500,00
Pagamento FI 2015 ($) -
Total Pago ($) 684.500,00
Balanco do Contrato ($) 684.500,00
22.1.3 SIGTAS
The Standardized Integrated Tax Administration System (SIGTAS) in Timor Leste is
essential in order to improve tax compliance and increase revenue collection of taxes. The IF
budget allocated in 2015 is US$ 0.75 million. As per current tender status provided NPC on
24 March 2015 it shows that the project in the preparation of Request for Proposal and
publication scheduled in early April 2015. Up to the end of June there was no company
selected.
22.1.4 Free Balance
Since 2010, the Government has engaged the services of Free Balance, Inc. to support the
sequenced improvement of the Public Financial Management (PFM) system through the
introduction and application of Government Resource Planning (GRP) software. On
November 11, 2014, the Council of Ministers (COM) approved the 2014 contract between the
government of Timor Leste and Free Balance, Inc., to continue accelerate the management of
public financial management system. More should be done in order to transfer the knowledge
125 | P a g e
and expertise to Timor Leste nationals in order to assure the sustainability of Timor Leste
financial management system in the future. This allocated budget pay for IT Services and
Technical Support which is US$ 61,114 was paid for technical support up to end of June 2015.
The following table 22.5 shows the progress of payments in 2011, 2012, 2013, 2014 and 2015.
Table 22.5: Status Free Balance Contract and Payments
Estado do Projecto Em Andamento
Compania Freebalance Inc
Data do Contrato 20-Feb-12
Data Original do Conclusão da Obra 30-Jun-13
Data Original do início da Obra 1-Jan-10
Audit Court Endorsement Date
Valor Original do Contrato 2011 ($) 5.666.420,00
Contracto Amenamente
Contracto Amenamente 2012 ($) 4.912.715,00
Contracto Amenamente 2013 ($) 4.980.000,00
Contracto Amenamente 2014 ($) 4.201.517,00
Outros custos (2011-2014) ($) 1.316.216,00
Contracto Amenamente 2015 Extended under the same contract value in 2014
Valor Final do Contracto ($) 21.076.868,00
Data Final termina contracto 31-May-15
Data Actual termina Obra 31-May-15
Físico actual
Horário de Pagamento
Pagamento Pre FI ($) -
Pagamento FI 2011 ($) 4.309.424,66
Pagamento FI 2012 ($) 3.949.464,25
Pagamento FI 2013 ($) 4.028.790,05
Pagamento FI 2014 ($) 6.476.797,59
Pagamento FI Abr-Jun 2015 ($) 1.013.559,44
Total Pago ($) 19.778.035,99
Balanço Contracto ($) 1.298.832,01
22.1.5 Interior Design for MoF New Building
This project is mainly to support the finalization of the MoF new building including interior
design, purchasing of the equipment and the installation of the interior equipment itself. The
Budget allocated for this project is US$ 3.5 million. During this reporting period, the
expenditure of this budget line was for the design of the interior which was tendered in 2013
and awarded to HBO + EMTB Pte Ltd – Singapore Company at US$ 0.7 million. While the
supply installation & Commissioning of fitment for interior design of New MOF Building in
the contract finalisation and sign of NPC. Details are presented in Table 22.6.
126 | P a g e
Table 22.6: Interior Design and Works of New MoF Building Project PROJECT SUMMARY Completo Em Aproviçionamento
Companhia
Desenho Detalhado e Supervijaun
do instalasaun de Equipamento Serviços Interior e
Instalação de Equipamentos
HBO + EMTB Pte Ltd - Singapore
Data do Contrato 2-Oct-13
Data Original do Conclusão da Obra 2-Oct-14
Data Revisão do conclusão da Obra 3 31-Dec-13
Valor Original do Contrato ($) 738,818.00
Contract Amendment
No. of variations
Revised Completion Date
Actual Completion Date
Progresso Fisico Atual 100%
Horario de Pagamento
Pagamento Pre-FI 2013 ($) 140,375.42
Pagamento FI 2014 ($) 598,442.58
Pagamento FI 2015 ($) -
Total Pago ($) 738,818.00
Balanco do Contrato ($)
22.1.6 Housing Accommodation for Integrated Border Post Officers in Batugade
The project was designed to provide accommodation for Integrated Border Post Officers and
their immediate family members at the territorial border of Timor-Leste. Terms of Reference
for tendering the design consultant was prepared and submitted to ADN for final review
before tendering. As reported by the Project Owner, tender is being carried out by NPC and
bids were submitted on 7 July 2014. It was expected that the contract will be awarded before
the end of the year 2015. The allocated budget for this year is US$ 0.373 million. None update
information on this project.
22.1.7 Construction of Integrated Border Post in Oesilo and Tunubibi
These border posts will facilitate the movement of people and goods between Timor-Leste
across the land borders with Indonesia. With the trade-dependent neighbouring countries,
trade and communications will be enhanced and therefore boost the economic, social and
security development. Detailed Design is with ADN for final verification. As reported by the
Project Owner, tender is being carried out by NPC with bid submissions received by 11 July
2014. However, current tender status provided by NPC on 24 March 2015 shows that
construction multi-function border post in Tunubibi in Tunubibi, Maliana and in Oesilo -
Oecuse is planned for re-bid. For re-bidding NPC still waiting revised technical specification,
BOQ and drawing from ADN. Next tender expected be completed within 2 to 3 months in
2015. The allocated budget for this year is US$ 0.5 million. None update information on this
project.
127 | P a g e
22.1.8 Design, Construction and Supervision of Custom and Revenue New Building
The allocated budget in this year for this project is US$ 0.2 million. The budget is to cover
preparation of Detail Engineering Design of this project. TOR and Concept design has been
sent to ADN for final verification and tendering. Project Owner reported that Tender
underway, it assumed that the tender process will be completed and award within 3 months.
The allocated budget in 2015 was US$ 0.249 million. The budget is again to cover
preparation of Detail Engineering Design of this project. In 2014, TOR and Concept design
has been sent to ADN for final verification and tendering. As per current tender status
provided NPC on 24 March 2015 it shows that procurement status in the contract award stage
and not finalise yet. Allocated budget for 2015 was US$ 0.249.
128 | P a g e
23 YOUTH AND SPORT PROGRAM
The program includes the construction of Stadia in four districts, National Outdoor Sports
Stadium and Multi-Function Sport Facilities with 2015 budget of US$ 2.75 million. Details of
2015 budget allocation and disbursement as of 31 March 2015 as shown in table 23.1.
Table 23.1: Summary 2015 budget allocation and disbursement status
Project
Original Budget
Allocation 2015
('$000)
Revised Budget
Allocation 2015
('$000)
Expenditure
as of 30
June 2015
('$000)
Balance
2015
('$000)
Design, Construction and Supervision of
National Outdoor Sports Stadium
250 250 - 250
Multi-Function Indoor Sports Facility 500 500 - 500
Construction of new Football stadia in Maliana 500 500 - 500
Construction of new Football stadia in Manatuto 500 500 - 500
Construction of new Football stadia in Baucau 500 500 - 500
Construction of new Football stadia in Gleno
Ermera
500 500 - 500
Total 2,750 2,750 - 2,750
Source: MPS and Free Balance, 30 June 2015
23.1 PROJECT STATUS
23.1.1 Design, Construction and Supervision of National Outdoor Sports Stadium
The project objective is to facilitate and boost the youth in developing skills in various sports
and other activities at local, national and international level. The arena will have a maximum
capacity of 45,000 spectators, international standard football field, athletics field and support
facilities such as cafeteria, water and sanitation facilities, conference room, offices, parking
spaces, and communications and security systems.
It was learned from State for Youth and Sports (SEJD) that they planning to improve current
facility i.e. light, tribune, seat for VIP, entrance gate, etc in order to respond FIFA
requirement. CAFI meeting dated 13 of April 2015 approved an estimate budget from
secretaty of state for imidiate rehabilitation of national stadiun in Dili at US$ 0.35 million but
it required ADN verification and shall present in to next CAFI meeting. The allocation budget
for 2015 was US$ 0.25 million.
23.1.2 Multi-Function Indoor Sports Facility
This project complements the construction of the outdoor sports stadium that is to provide an
international standard facility for indoor sports including gymnastics, basketball, volleyball
and badminton. The DED commenced in 2014 and completed, 92% payment was made to the
company and 8% for unclaim item. The allocation budget for this project in 2015 was US$ 0.5
million. Details of contract and payment reflected in Table 23.2.
129 | P a g e
Table 23.2: DED for Multi-Function Indoor Sports Facility Project
Estado do Projecto Completo
Nome do projecto DED for Multi-Function Indoor Sports Facility Project
Companhia Salu Coorporation Lda
Data do Contrato 9-Apr-11
Data Original do Conclusão da Obra 9-Sep-11
Data Revisão do conclusão da Obra 1 31-Jan-13
Data Revisão do conclusão da Obra 2 31-Oct-13
Data Revisão do conclusão da Obra 3 31-Dec-13
Data Revisão do conclusão da Obra 4 31-Dec-14
Valor Original do Contrato 855,000.00
Contract Amendment
No. of variations
Data Revisão do conclusão
Revisão Valor de Contacto 855,000.00
Data conclusão actual
Progresso Fisico Actual 100%
Horario de Pagamento
Pagamento Pre-IF ($) 128,250.00
Pagamento FI 2013 ($) 363,375.00
Pagamento FI 2014 ($) 292,374.97
Pagamento FI 2015 ($) -
Total Pago ($) 783,999.97
Balanco do Contrato ($) 71,000.03
Noted: Balance of US$ 71,000.03 is for unclaim item
As no rehabilitation work planed to be implement this year in this budget line, CAFI meeting
21 May 2015 approved the secretary of state proposal to utilize allocation budget US$ 0.25
million for the construction supervision of new construction of the football stadium and
tribune building in four districts (Maliana, Gleno, Manatuto and Baucau) and rehabilitation of
the national stadium in Dili.
23.1.3 Construction of 4 Football Stadia (Baucau Maliana, Manufahi and Ermera)
2015 budget allocated for each project was US$ 0.5 million. Geotechnical survey and DED of
these projects were undertaken by Salu Corporation Lda Company. The tender status as of
end June 2015 for four foot ball stadium in Gleno-Ermera, Manatuto, Baucau and Manatuto
has been completed and contract signed. While tender for consultant supervision of these
stadiums still progressing by NPC. None disbursement in this reporting period as these project
are in the preparation and mobilization stage. Details of each contract as shown in the Table
23.3:
130 | P a g e
Table 23.3: Rehabilitation of football stadium in Maliana
Project Name Rehabilitation of football stadium and new construction
of tribune building in Maliana
Status Project in the mobilization and preliminary works
Company Name Maliana Brothers Lda
Contract Signing Date
Commencement Date
Original Completion Date
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 1,177,500.31
Contract Amendment
a. Amendment 1 (Cost/Duration)
b. Amendment 2 (Cost/Duration)
Final Contract Value 1,177,500.31
Physical progress till quarter end % 5%
Payment Schedules
Pre IF Payment ($) 0
2015 IF Payments ($) 0
Total Paid 0
Balance to be Paid 1,177,500.31
Table 23.4: Rehabilitation of football stadium in Gleno, Ermera
Project Name Rehabilitation of football stadium and new construction
of tribune building in Gleno, Ermera
Status Project in the preparation of site mobilization
Company Name Maferdy Unipesoal, Lda
Contract Signing Date May 2015
Commencement Date
Original Completion Date 365 Days
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 1,168,997.63
Contract Amendment
a. Amendment 1 (Cost/Duration)
b. Amendment 2 (Cost/Duration)
Final Contract Value 1,168,997.63
Physical progress till quarter end % 0
Payment Schedules
Pre IF Payment ($) 0
2015 IF Payments ($) 0
Total Paid 0
Balance to be Paid 1,168,997.63
131 | P a g e
23.5: Rehabilitation of football stadium in Manatuto
Project Name Rehabilitation of football stadium and new construction
of tribune building in Gleno, Ermera
Status Project in the preparation of site mobilization
Company Name Maferdy Unipesoal, Lda
Contract Signing Date May 2015
Commencement Date
Original Completion Date 365 Days
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 2,362,976.44
Contract Amendment
a. Amendment 1 (Cost/Duration)
b. Amendment 2 (Cost/Duration)
Final Contract Value 2,362,976.44
Physical progress till quarter end % 0
Payment Schedules
Pre IF Payment ($) 0
2015 IF Payments ($) 0
Total Paid 0
Balance to be Paid 2,362,976.44
Table 23.5: Rehabilitation of football stadium in Baucau
Project Name Rehabilitation of football stadium and new construction of tribune building
Baucau
Status Project in the mobilization and preliminary works
Company Name Fin-Los Unipesoal, Lda in JV with Hoven Unipesoal Lda
Contract Signing Date
Commencement Date
Original Completion Date
Issue notice to Proceed Date
Actual Completion Date
Original Contract Value 762,563.31
Contract Amendment
a. Amendment 1 (Cost/Duration)
b. Amendment 2 (Cost/Duration)
Final Contract Value 762,563.31
Physical progress till quarter end % 7%
Payment Schedules
Pre IF Payment ($) 0
2015 IF Payments ($) 0
Total Paid 0
Balance to be Paid 762,563.31
132 | P a g e
24 PUBLIC PRIVATE PARTNERSHIP
In 2013, the necessary laws and regulations for Public-Private Partnerships have been
finalized including the PPP Project Cycle. This was approved by the Council of Ministers and
promulgated by the President of RDTL (Decree-law 02/2014 and 08/2014). By 2014, Timor-
Leste has more flexibility in selecting investment packages as the legal framework for PPP is
already in place.
The PPP Unit has been established under the Ministry of Finance, and in the 3rd
quarter, two
National Staff were recruited, one a Financial Officer and the second one an Infrastructure
Officer bringing higher capacity to the Unit. However, there is still a general mistrust of the
various government stakeholders on the PPP modality and the benefits that can be generated
by the development of infrastructure projects through this scheme. This distrust makes the
process longer than anticipated, which resulted in delays in PPP project cycle.
As a strategy to present and discuss the advantages and disadvantages of this modality for the
development of crucial infrastructures, this year the PPP Unit participated as speaker in three
national and international events about Public-Private Partnerships, one was organized by a
law firm and the other two were organized by the Timor-Leste Parliament, together with other
several international entities like the Portuguese PPP Unit and the Philippines PPP Centre. The
PPP Unit also participated in an International Conference on Meeting Challenges through
Better Governance and Management towards Sustainable PPPs in Seoul, Korea.
A training program in three modules was also developed for the MPS and PPP Unit to create
capacity inside these units to deal with the complexity of the PPP Projects. The first and
second module was given in June and October 2014, respectively, which has been extended to
selected personnel from relevant entities like the Ministry of Finance Legal Department,
Ministry of Transport and Communications, Aportil, Ministry of Public Works and Ministry of
Health. The third module was rescheduled to 2015.
As of end-2014, there are six projects progressing following the PPP Project Cycle, these are:
Tibar Bay Port, in the Procurement Stage;
Instituto Superior Aileu, in the Procurement Stage;
Dili Water Supply System, in the Feasibility Stage;
Diagnostic Services in the Health Sector, in the Feasibility Stage;
Petroleum House, in the Feasibility Stage; and
Electricity Sector, in the Initial Stage.
Progress of each project is summarized below.
133 | P a g e
24.1 TIBAR BAY PORT
The PPP modality chosen for Tibar Bay Port was a 30-year concession, including the design,
construction, operation and maintenance of the port infrastructure. The infrastructure must
include the following:
Berth with 630m length, capable of anchoring at the same time two vessels with a
capacity of 3,500-4,000 TEU6 (Panamax),
Entry channel with 200m width and minimum depth of 20m,
600m diameter ship maneuvering basin inside the bay with minimum depth of 20m,
Container parking terminal to be built in two phases with a final capacity between
500,000 to 600,000 TEUs,
Buildings and facilities necessary and appropriate equipment for ship/shore container
transfers and also for container stacking and stack / road vehicle transfers.
As of end-2014, the second draft of the Contract Agreement has been received which will be
submitted to the bidders during December. Pre-qualified bidders are POSNCO (DP World) –
United Arab Emirates; Mota-Engil/Besix – Portugal/Belgium; Bolloré-SDV – France/Timor-
Leste, and; ICTSI - Philippines. Summary of related accomplishments for the year and follow-
up activities are presented below:
Table 24.1: Project Name: Tibar Bay Port Activity Current Status
Approval of the Feasibility Studies and decision to proceed to
Procurement
Completed
Expression of Interest received Completed
Pre-qualification advertisement Completed
Bidders pre-qualified Completed
Invitation for Bids / Issuance of Instructions to Bidders and
Draft Bidding Documents
Completed
Communication of Draft Concession Agreement Completed
Clarification Requests Submission Deadline Ongoing
Pre-Bid Meetings (one or more as required) Completed
Amendment to Bidding Documents Issuance On-going - Expected December 2014
Final Bidding Documents Issuance January 2015
Bid Submission Deadline March 2015
Bid Opening March/April 2015
Opening of Technical and Financial Bid Envelopes March/April 2015
Signature of the Contract May 2015
Construction starts Expected Early 2016
Operation starts Expected Early 2019
6TEU – Twenty-foot equivalent units, thus a 40 ft long container = 2 TEU
134 | P a g e
Preliminary data indicate that the cost will range from US$ 300 Million to US$ 400 Million to
develop the Tibar Bay Port and a percentage of this value should be the counterpart of the
GoTL.
24.2 INSTITUTO SUPERIOR OF AILEU
The Education and training are the keys to improving the life opportunities of the Timorese
people and enables them to reach their full potential. They are also vital to Timor-Leste’s
economic development and growth. The Strategic Development Plan identified as one of the
critical issues for the higher education: “The establishment of polytechnics to offer technical
higher education that is specific to Timor-Leste’s development needs.”
An unsolicited proposal was presented to the GoTL by a private entity on July 2013 to build
and manage a Higher Institute in Aileu (ISA) to teach six technical and higher courses during
15 years. The feasibility study was made, the results were presented and approved by CAFI in
September 2014 and it was decided to proceed to the procurement stage. The project is now
with the National Procurement Commission that will define the type of modality to be used for
procurement.
24.3 DILI WATER SUPPLY SYSTEM
The Government of Timor Leste (GoTL) has a goal to provide all urban households with
access to a safe and secure piped 24-hour water supply. Today only 36% of households in Dili
are legally connected to the water supply system, and 22% of those households receive 24
hours of supply per day. This current low level of service is having a significant impact on
community health and is constraining economic development.
The government recognizes that rapid and sustainable improvements in service delivery will
require a combination of increased investment, reintroduction of water charges and substantial
improvement in management, planning and operational systems. To address these challenges
and need, the Government with ADB (Asian Development Bank) assistance conducted a pre-
feasibility assessment to the Dili Water Supply System completed in August 2013 under the
Public-Private Partnership (PPP) modality. As a consequence of the results, the GoTL resolved
to pursue a more detailed investigation for possible private sector participation in the Dili
Water Supply sector through a PPP modality.
Consultants for the Feasibility study were selected through an International Tender. Feasibility
study started in November and the Inception Report of Phase I will be presented in December
2014. The overall Feasibility Study is expected to conclude in June 2015. The final report will
be presented and approved by CAFI in July 2015.
135 | P a g e
24.4 DIAGNOSTIC SERVICES IN THE HEALTH SECTOR
Timor-Leste’s Constitution embraces medical care as a fundamental right for all citizens and
imposes a duty on the government to promote and establish a national health system that is
universal, general, free of charge and, as far as possible, decentralized and participatory.
Although the health system has been rebuilt since 1999, services and health outcomes of
Timorese people remain poor. Service delivery is constrained by limited capacity within the
Ministry of Health – insufficient knowledge, skills and experience are key issues – and poorly
developed infrastructure. The Ministry is aware of the challenges it faces and has identified a
number of areas where it believes that PPPs may play a role in improving health services.
A working team was assigned with members from the Ministry of Health, the PPP Unit /
Major Projects Secretariat and the IFC to identify the possible projects and the conclusions
were presented in June this year. As identified, the Diagnostic Services is the best option to
proceed to the PPP project cycle.
In August 2014, CAFI approved the conduct of the Pre-Feasibility Study. IFC has been
selected to undertake the work with its contract signed in December 2014. Pre-Feasibility
study started in December 2014 and the final report is expected to be approved by CAFI in
May 2015.
24.5 PETROLEUM HOUSE
Existing Ministry, Timor Gap and other strategic units are presently accommodated in
different locations at various agency offices which reduce the efficiency of its operations and
communications. Petroleum House is proposed as an office hub for Government and industry
to serve as a centre for national and international Petroleum commercial activities. EOIs were
received as of end of October and CAFI approved to proceed to Feasibility Study. The Terms
of Reference to hire consultants is being drafted and tender expected to start in the beginning
of 2015.
24.6 ELECTRICITY SECTOR PPP PROJECTS
The Democratic Republic of Timor Leste (TL) has made tremendous progress in the power
sector in recent years. The Government of Timor Leste (GoTL) has emphasized power sector
development as a key driver of economic growth and poverty reduction. Since 2008, the
GoTL, through its electric utility, Electricidade de Timor Leste (EdTL), has invested nearly
US$ 1 billion to replace old, inefficient diesel-operated generators and install a single
transmission and distribution system from a collection of isolated systems. The results of the
investment have been impressive. Electricity coverage increased from 21% in 2003 to 71% in
2014, and installed generating capacity more than tripled, giving TL enough capacity to
connect all households and easily meet peak demand for the next decade.
136 | P a g e
However, substantial challenges remain which put the GoTL’s accomplishments at risk. A high
percentage of the electricity generated is not billed to customers, technical losses are high and
the installation of meters has not kept pace with the installation of new connections.
Generators remain almost entirely dependent on diesel imports for fuel, resulting in a high cost
of supply. Substantial investment needs also remain, especially at the distribution level (20kV
and lower voltages). The GoTL’s Strategic Development Plan (SDP) for 2015-2030 targets
100% electrification by 2015, requiring a continuation of investment in new distribution. The
existing network also needs attention. Outages still occur in Dili where the network is old and
was designed as a stand-alone system after TL gained independence in 2002.
The GoTL recognizes that, in order to sustain its successes in the sector, EdTL must begin to
operate on a more commercial basis. Government subsidizes roughly 85% of operating
expenditure in the sector. The amount of subsidy required will grow unless losses can be
reduced and generation costs can be reduced. The GoTL also recognizes that the solution may
lie in changes to the institutional, legal and regulatory arrangements in the sector. EdTL
remains a department within the Ministry of Public Works (MPW) and as a result lacks the
autonomy, incentives and commercial practices necessary to address many of the challenges it
faces. EdTL staff, moreover, lack the training required to properly maintain the system without
external support.
The diesel generators and transmission system are currently being operated by foreign
companies under (O&M) contract which run through the end of 2016. The GoTL wants to
consider whether such contracts or similar Public Private Partnership (PPP) arrangements can
help it achieve and sustain its objectives in the sector.
Meanwhile, through grant, ADB supported the PPP Unit and EDTL in identifying possible
projects for PPP modality in this sector beyond 2016 when the O&M contracts end. The
results were presented in November 2014 to CAFI and the GoTL will decide whether to
proceed or not to Pre-Feasibility Study for a PPP modality.
137 | P a g e
25 LOAN FUNDED PROJECTS
Government is currently implementing effectively four loan agreements with its development
partners, these are:
Road Network Upgrading Project (RNUP) for Rehabilitation and Upgrading of Dili-
Liquica and Tibar-Gleno Roads (signed by GOTL and ADB in 2012)
National Road No. 1 Upgrading Project, Dili - Baucau Road (signed by GOTL and
JICA in 2012)
Road Network Upgrading Sector Project (RNUSP) for Upgrading Manatuto-Natarbora
Road (signed by GOTL and ADB in November 2013).
Additional Financing for the Road Climate Resilience Project Upgrading of Dili-
Ainaro Road (signed by GOTL and WB in November 2013)
The total allocated budget for 2015 is amounted to $70, million (excluding government
co-financing) to finance the above mentioned four projects and also soon to be
implemented loan funded project from EXIM bank of China. Government is at the final
stage of signing the loan agreement with the EXIM of China, where the fund will be used
to finance the Dili drainage upgrading work. The detail budget allocation of each loan
funded project in the fiscal year of 2015 is presented in the following table 25.1.
Other remaining proposed loan funded project such as additional loan from the ADB to
finance Tasitolu-Tibar junction, Baucau- Lautem and Baucau – Viqueque which will
implement through ADB loan in the study and design stage, Construction of Highway in the
south coast corridor are still in the procurement and preparation stages, respectively. More
detail description of each project, including the progress achieved by the end of second quarter
of 2015 fiscal year is presented in the following sub-sections.
25.1 ADB LOAN: ROAD NETWORK UPGRADING PROJECT-ADB LOAN
NOS.2857-TIM AND 2858-TIM (SF)
There are two sources of loan assistance for the implementation of Road Network Upgrading
Project (RNUP), one from the ADB’s Ordinary Operations Fund (OCR) (with Loan No. 2857-
TIM), and the second one from the Asian Development Fund (Loan No. 2858-TIM). For this
reason, two Loan Agreements between the parties have some differences in their terms and
conditions. These were signed on 2 May 2012 and became effective on 13 June 2012 in which
the commitment charges also commenced. Breakdown of funds is presented in the table 25.2:
138 | P a g e
Table 25.1: 2015 Budget Allocation for Loan Funded Project
Projecto
Alocação
Orçamento
Original 2015
($000)
Saldo
($000)
Total 70.000 70.000
Construção e Supervisão de Estradas Dili-Liquiça (L) e Alinhamento de
Estradas desde Cruzamento Tibar a Rotunda Lafatic Quatro Vias
9.500 9.500
Construção e Supervisão Estradas Tibar-Gleno (L) 8.000 8.000
Construção e Supervisão de Estradas Dili-Manatuto-Baucau (L) 11.550 11.550
Construção e Supervisão de Estradas Manatuto-Natarbora (L) 14.250 14.250
Construção e Supervisão de Estradas Aileu-Maubisse e Ainaro (L) 11.700 11.700
Construção e Supervisão de drenagem de Dili (Esgoto) (L) 5.000 5.000
Construção e Supervisão de Estradas Ainaro-Cassa (L)
Construção e Supervisão de Estradas Aituto-Hatubuiliko-Letefoho-Ermera-
Gleno (L)
Construção e Supervisão de Estradas Kuncing-Solerema (L)
Construção e Supervisão do Aeroporto Internacional Nicolau Lobato [Pista +
Termina Fase I)]
Construção e Supervisão de Estradas Baucau-Lautem
Construção e Supervisão detalhadas relativamente a Estradas e Pontes -
Auto Estrada Suai-Betano-Beaco (L-CF)
10.000 10.000
Table 25.2 Breakdown of Funding – ADB Road Network Upgrading Project
Component
ADB – OCR (US$)
Under Loan No. 2857-
TIM
ADB - ADF (US$)
Under Loan No.
2858-TIM(SF)
GoTL (US$)
Civil works (including environment and
social mitigation)
19,990,000 5,740,000 11,580,000
Consulting services: 5,500,000 1,800,000
a) Project Management
b) Design and Supervision
Equipment 100,000
Charges 600,000 120,000
Unallocated 4,700,000 1,390,000 2,080,000
TOTAL 30,850,000 9,150,000 13,660,000
The financial counterpart of the government, on the other hand, is being paid through the
Infrastructure Fund. Based on forecast, the annual payments to be made on the duration of the
project are presented in the table 25.3:
Table 25.3 Forecasted Government Annual Payment for RNUP- Civil Works
Year 2013 (Actual) 2014 (Actual) 2015 (as of 2nd
Quarter) 2016
US$ million 1.799 1.390 7.000 3.834
The following sections provide the status of RNUP Projects as of end of June 2015:
139 | P a g e
25.1.1 Road rehabilitation and maintenance
Dili-Liquiça and Tibar-Gleno are the two main road sections connecting Dili and Tibar Bay
Port. These also serve as the arterial road to the Indonesian border and linkage to major coffee
producing areas of Ermera and Liquiça. Detailed Engineering Design and Feasibility Studies
were previously completed through and ADB Grant (0180-TIM).
R-3 Tibar – Liquica Road
R-3 Road, Dili – Liquica Section is 28.7 km long and rehabilitation works originally
addressed the section from the Dili Airport roundabout at Sta 6+628.The contract for the
works was awarded to Constructora San Jose S.A. with a Notice to Commence on 14
November 2013. As of end of June 2015, MPW-PMU reported that the physical progress has
just reached 23.67% with an expenditure of US$ 7.80 million or approximately 38.01% of the
total contract amount for civil works.
Source of Photo: MPW-PMU, 18 June 17, 2015- Compaction of newly laid Bituminous Asphalt Concrete at
L/S Sta. 26+660 & Completed Bituminous Asphalt Concrete Pavement at B/S Sta. 26+660.
Meanwhile a design review and follow-up feasibility study by the supervision engineer,
Katahira and Engineers International, determined that the section from the Dili Airport to
Tibar Junction of the Tibar-Gleno Road would generate significant economic benefits from
widening from two to four lanes between the airport roundabout and the proposed new port in
Tibar together with major realignment of 3.2 km between Tacitolu and Tibar.
In order to expedite implementation, the San Jose contract will be changed such that their
scope commences at the Tibar – Gleno road junction, a new contractor is procured for works
on the realigned section between this junction and Tacitolu under a Supplementary Loan
agreement and the section between the Airport Roundabout and Tacitolu, which requires
extensive resettlement is awarded to a third contractor and funded 100% by GoTL. Details
project information presented in the table 25.4.
140 | P a g e
Table 25.4: RNUP for Rehabilitation and Upgrading of Dili-Liquica Road Project
Civil Work Contract Amount
(US$)
Funded Proportion
of %
Previous Progress 2014
(US$)
Disburdement Progress 2015 (US$) Remarks
Contractor Q1 Q2 Q3 Q4
Constructora San Jose S.A
* ABD Loan 2857/2858
20,516,415.26
69.33%
4,155,291.90
738,226.89
23.67% completed
* Government Funding 30.67% 1,505,589.96 397,760.10
Consultant Design &
Supervision (100%)
Contract
Amount
Proportion
of %
Previous
Progress 2014
Disbursement Progress 2015 Remarks
Q1 Q2 Q3 Q4
Katahira & Engineer International
5,494,248.00
(100% 3,956,957.41
475,289.55
72.02% completed
Source: MPS analyisis, 30 June 2015
R-4 Tibar-Gleno Road
The 32kms long R-4 Tibar – Gleno Road rehabilitation requires total funding of US$29.29
million. It is being implemented by PP Ltd of Indonesia with a Notice to Commence dated 21
October 2013. The contractor has completed verification surveys and much of the excavation
and embankment works where widening is necessary. Total accomplishment as of end June
2015 is reported at 35.04%. The total expenditure as of end-June 2015 was US$ 14.66 million
or approximately 49.36 % of the total contract amount for civil works.Payment claims have
been received by MPS for processing. Details project information presented in the table 25.5.
Source of Photo: MPW-PMU, 24 June 2015 - Rate of application of Completed Asphalt Concrete Pavement
28+540).
141 | P a g e
25.1.2 Roads under detailed design
Under the same loan program from ADB is the Feasibility Study and Detailed Engineering
Design for Rehabilitation of Manatuto- Laclubar - Natarbora Road with a total length of 81
kms has been completed. Hence, Feasibility Study and Detailed Engineering Design for Road
Upgrading Four Lines from Dili to Tibar Port are progressing.
Table 25.5: RNUP for Rehabilitation and Upgrading of Tibar - Gleno Road Project
Civil Work Contract Amount
(US$)
Proportion
of %
Previous Progress 2014
(US$)
Disbursement Progress 2015 (US$) Remarks
Contractor Q1 Q2 Q3 Q4
PT.PP (Persero) Tbk * ABD
Loan 2857/2858 29,292,168
69.33% 5,296,442.84 2,145,161.47 35.04%
completed * Government Funding 30.67%
2,122,476.21
1,102,785.20
Consultant Design &
Supervision (100%)
Contract
Amount (US$)
Proportion
of %
Previous
Progress 2014 (US$)
Disbursement Progress 2015 (US$) Remarks
Consultant Q1 Q2 Q3 Q4
Katahira & Engineer International
5,494,248.00 100% 4,037,722.86
541,158.96
73.49% completed
Source: MPS analyisis, 30 June 2015
25.2 ROAD NETWORK UPGRADING SECTOR PROJECT (RNUSP) - ADB LOAN
NOS. 3020-TIM AND 3021-TIM
25.2.1 Road rehabilitation and maintenance
Manatuto - Laclubar - Natarbora Road has been divided into two packages: Package 1 covers
Manatuto-Laclubar Junction (35kms), and Package 2 traverses Laclubar Junction-Natarbora
(47kms). The design component was funded under ADB Loans 2857/2858-TIM while the
construction works will be financed through ADB Loans 3020-TIM/3021-TIM. Breakdown of
funds and government share for the project are presented in the table 25.6 - 7:
Table 25.6: Breakdown of Funds (3020-TIM/3021-TIM) Project
Component
ADB – OCR (US$)
Under Loan No.
3020-TIM
ADB - ADF (US$)
Under Loan No.
3021-TIM
GoTL
(US$)
Civil works (including environment and social
mitigation)
31,890,000 59,540,000
Consulting services:
a) Project Management 800,000
b) Design & Supervision 450,000 6,810,000
c) Public Transport and Road Safety Action Plan 800,000
Environmental and Social Mitigation 1,500,000
Equipment 400,000
Charges 1,200,000 310,000
Unallocated 6,460,000 880,000 12,210,000
TOTAL 40,000,000 10,000,000 73,250,000
142 | P a g e
Table 25.7: Forecasted Government Annual Payment (RNUSP) - Civil Works Project
Year 2015 2016 2017
US$ million 8.000 8.070 1.190
Construction cost of Package 1 (Manatuto-Laclubar Junction) is
US$ 28.01 million. The project was procured by NPC and has
been awarded to RD Junior Construction/Hebei Road and
Bridge Group Co. Ltd. The contract has been approved by Court
of Audit end of October 2014. Notice to Commence has been
issued to the Contractor on 17 November 2014. The actual
commencement of work has been scheduled for 15 January
2015.
There are several issues on the land and properties during the project implementation were
delayed some loan financing projects. PMU, Land and Property, and Local Authority are
identified land and property and affected people by on-going loan projects including payment
process. CAFI meeting dated 13 and 24 April 2015 has approved additional budget to pay
land aqusation and properties that affected by the loan projects. The project in the mobilization
of equipments, material and manpower and start preparatory works. Disbursement up to end of
June 2015 was 15% of total contract price which for advance payment was claimed by the
contractor. Contract and payment information is presented in table 25.8.
Table 25.8: RNUSP, Upgrading and Maintenance of Manatuto-Laclubar Junction Road
Project (sta. 65+235 to sta 100+355)
Civil Work Contract
Amount (US$)
Proportion
of %
Previous
Progress 2014 (US$)
Disbursement Progress 2015 (US$) Remarks
Contractor Q1 Q2 Q3 Q4
RD Interior Junior Construction/
Hebei Road and Bridge Group
Co. Ltd. * ABD Loan 3020/3021
28,011,854.94 39.50% 1,624,152.40
Paymeny
for 15%
Advance Payment
* Government Funding 60.50% 2,487,625.84
Consultant Design & Supervision (100%)
Contract
Amount
(US$)
Proportion of %
Previous
Progress 2014
(US$)
Disbursement Progress 2015 (US$) Remarks
Q1 Q2 Q3 Q4
Katahira & Engineer
International * ABD Loan 2857/2858
5,494,248.00 100%
541,158.96
73.49%
Source: MPS analyisis, 30 June 2015
Package 2 (Laclubar Junction-Natarbora) construction contract costs US$31.53 million. The
Contract has been awarded to China Nuclear Industry 22nd
Construction Co. Lda. It was
learned from PMU that Audit Court has been provided endorsement to the contract. Civil
works in the preparatory for site mobilization has achived 3.34% and it was learned from
PMU that contractor does not want claim for 15% advance payment. The contractor intend to
request for progress payment when the physical works reach 10%.
143 | P a g e
Construction Supervision for civil works of both packages has been awarded to Sinotech
Engineering Consultants Ltd in Joint Venture with PT. Inacon Luhur Pertiwi, PT. Pilar Pusaka
Inti and Salu Corporation. Contract amount for the work isUS$ 4.234 million. The
Supervision Consultant will mobilize before the start of the civil works.
25.3 ROADS UNDER DETAILED DESIGN
There are also road sections to be designed under the loan and these comprised of Baucau -
Lospalos and Baucau - Viqueque for a total length of 169 kms. The Contract for Consultancy
Services for the design of the road has been awarded to Dongsung Engineering Co., Ltd in
Joint Venture with Kunhwa Engineering and Consulting Co., Ltd in the amount of US$2.467
million. Detailed Design works started on 9 October 2014 and to be completed by October
2015. Detail of payment is presented in table 25.9.
Table 25.9: DED for RNUSP, Upgrading and Maintenance of Baucau – Lospalos and
Baucau - iqueque Road Projects
Consultant Design Contract Amount
(US$)
Proportion
of %
Previous Progress 2014
(US$)
Disbursement Progress 2015 (US$) Remarks
Q1 Q2 Q3 Q4
Dongsung Engineering Co., Ltd in Joint Venture with Kunhwa
Engineering and Consulting
Co., Ltd. * ABD Loan 3020/3021
2,466,998 100% 224,368.00 708,664.87
37.82% completed
Source: MPS analyisis, 30 June 2015
25.4 JICA LOAN: NATIONAL ROAD NO.1 UPGRADING PROJECT-DILI-BAUCAU
This section of N-1 Roads is an important road connection between the three main cities on
the north coast. A total of 116 km stretch will be upgraded through a loan from Japan
International Cooperation Agency JICA) in the amount of JpY 5,278 million or US$ 62.72
million at the time of Loan Agreement signing. The GoTL contribution to the project was
originally estimated at $23.9 million, as presented in Table 25.5 with the forecasted
government annual payment shown in Table 25.6. These estimates were prepared prior to the
completion of Detailed Engineering Design (DED) which was included in the Loan assisted
project.
Due to several issues like Yen depreciation, which caused the JICA contribution to fall to less
than US$ 50 million, and unit price and BoQ revisions resulting from the DED, the total cost
for the civil works to complete the full stretch of the road rose to US$121.42 million with an
additional Government investment of US$ 65.92 million.
Nippon Koei Group of Companies prepared the DED and will continue as Supervision
Engineer when construction commences. NPC has completed the prequalification stage for
contractors for Package 1 (Hera-Manatuto road section). The tender of this package is ongoing
and civil works is expected to start second quarter of 2015. For Package 2 (Manatuto-Baucau
road section), the project is scheduled to commence by third quarter of 2015 but may be
delayed pending completion of a review of the pre-qualification procedures by NPC in
144 | P a g e
cooperation with JICA. JICA’s approval of bidding documents has been on hold until the
formal justification from the Government regarding the sourcing of the additional fund needed
to complete the whole section has been received.
On 22 August 2014, CAFI confirmed that the Government has to assume the additional
funding required for the civil works in accordance with the terms of the Loan Agreement. The
breackdown of JICA, GoTL counterpart fund and annual forcast are presented in table 25.10 -
11.
Table 25.10: Breakdowns of JICA Loan and GoTL Counterpart -Civil Works
Component JICA LOAN GoTL JPY (million) USD (million) JPY (million) USD (million)
Civil Works 3.571 46.50 1.190 15.49 Consulting Services 0.638 8.31 N/A N/A Price Escalation 0.517 6.73 0.174 2.27 Administration Costs N/A N/A 0.331 4.31
IDC 0.107 1.39 N/A Contingencies 0.408 5.31 0.137 1.78
Committment Charge 0.037 0.48 N/A Tax and Duties N/A N/A 0.5 0.07
TOTAL 5.278 68.72 1.837 23.92 Note: USD/JPY=76.8
Table 25.11: Forecasted Government Annual Payment for N-1 - Civil Works
Year 2015 2016 2017 2018 2019
US$ million 4.000 28.850 31.020 12.600 1.930
25.5 ROAD CLIMATE RESILIENCE PROJECT- (WB LOANS) – IDA CREDIT 5303-
TL AND IBRD LOAN 8290-TL
The Dili - Ainaro Road section is 112kms long and rehabilitation is packaged into five lots.
The first lot of approximately 10kms is being funded under the IDA Grant in the amount of
US$20 million with a government counterpart of US$3.0 million.
145 | P a g e
Table 25.12: Breakdown of Funds for Road Climate Resilience Project (RCRP)
Component Disbursement
Category
Original Cost Additional Finance Total
IDA GOTL IDA
Credit
IBRD
Loan GoTL
Sub-
Total
World
Bank GoTL
A. Climate
Resilitent
Road
Infrastructure
(1) Works under Part 1
and Part 2
11.76
3.00
19.50
14.00
52.00
85.50
45.26
55.00
(2) Good, Consulting
Services, Non-
Consulting Services,
Incremental Operating
Costs and Trainning
for Part 1, 2, 3, and 4
7.25
-
2.50
-
-
2.50
9.75
-
Sub-Total
19.01
3.00
22.00
14.00
52.00
88.00
55.01
55.00
B.
Maintenance
and
Emergency
Planning and
Response
(2) Good, Consulting
Services, Non-
Consulting Services,
Incremental Operating
Costs and Trainning
for Part 1, 2, 3, and 4
-
- -
1.00
-
1.00
1.00
1.00
C. Project
Support and
Trainning
(2) Good, Consulting
Services, Non-
Consulting Services,
Incremental Operating
Costs and Trainning
for Part 1, 2, 3, and 4
0.99
-
1.00
-
-
1.00
1.99
-
D. Feasibility
Study for
Additional
Road
Segments
(2) Good, Consulting
Services, Non-
Consulting Services,
Incremental Operating
Costs and Trainning
for Part 1, 2, 3, and 4
-
-
2.00
-
-
2.00
2.00
-
Total
20.00
3.00
25.00
15.00
52.00
92.00
60.00
56.00
(1) Works under Part 1
and Part 2
19.50
14.00
52.00
85.50
(2) Good, Consulting
Services, Non-
Consulting Services,
Incremental Operating
Costs and Trainning
for Part 1, 2, 3, and 4
5.50
1.00
-
6.50
(3) Front-End Fee
To be able to complete the rehabilitation of the entire stretch from Dili to Ainaro Road, the
World Bank has provided additional financing of US$40 million of which US$25 million is
through IDA credit and US$15 million through the IBRD Loan. Correspondingly, a
counterpart fund of US$52 million has to be allocated by the Government. Breakdown of
funds for the project highlighting the additional financing is presented in Table 25.12. Table
25.13 provides the forecasted government annual payment for RCRP -Civil Works.
146 | P a g e
Table 25.13: Forecast Government Annual Payment for RCRP -Civil Works
Year 2015 2016 2017
US$ Million 7.00 21.24 3.05
Source: MPS analyisis, 30 June 2015
Status of each package is as follows:
25.4.1 Lot 1: Halilaran to Laulara Road Section (10 kms)
Sources: PMU, stone masonry
Sta.11+805 - Sta. 11+810
Cost of the project is US$11.03 million which was awarded to
China Shandong International Economic and Technical Cooperation
Group, Ltd (CSI). While the Audit Court has issued the clearance
for the contract, the Notice to Commence was issued on 25 June
2014. The contract became effective on August 8, 2014. The
contractor has performed preliminary works, ditch excavation, road
improvement, and stone masonry along the road from Halilaran to
Laulara with overall accomplishment as June 30, 2015 was
$403,359.82 equivalent to 3.66%.
25.4.2 Lot 2: Laulara to Solerema Road Section (22.6 kms)
The design of the project has been completed, however, the tendering of civil works is
deferred until the total cost of the contract for the four lots (Lots 1, 3, 4 and 5) have been
determined to allow the financing of this road section. Maintenance work for the alignment
will be undertaken prior to civil works which is expected to start by following quarter of 2015
or as soon the budget becomes available.
25.4.3 Lot 3: Solerema to Bandudatu Road Section cost (30 kms)
Cost of the project is US$28.82 million which has been awarded
to Chongqing International Construction Corporation (CICO).
Audit Court has issued the clearance for the contract and Notice to
Commence was issued on July 16, 2014. The contract became
effective on 15 September 2014. The physical progress up to end
of June 2015 only reach 3.54% and disbursement made was US$
5.21 million or 22.06 of the total contract price. The progress of
civil work shown at photo source by Katahira Consultant -
PMU/MPWTC on June 26, 2015. Contractor did the construction
of retaining wall at Sta.51+700.
Supervision of construction for Lot 3 has been awarded to Katahira & Engineers International
in the amount of US$ 2.76 million. This supervision contract was made through single source
selection as per agreement between the Government and the World Bank. Payment
information is presented in table 25.14.
147 | P a g e
Table 25.14: Lot 3 from Solerema to Bandudatu Road Section (30 kms) Project
Civil Work Contract
Amount
(US$)
Proportion
of %
Previous
Progress
2014 (US$)
Disbursement Progress 2015 (US$) Remarks
Contractor Q1 Q2 Q3 Q4
Chongqing
International
Construction
Corporation (CICO) *
WB - Loan 5303/8290
Lot 3.
28,823,606 40% 858,156 858,156 367,241
First
Progress
Payment
(3.54%)
* Government Funding 60% 1,287,234 1,287,234 550,862
Consultant Design &
Supervision (100%)
Contract
Amount
Proportion
of %
Previous
Progress
2014
Current Progress 2015 Remark
Q1 Q2 Q3 Q4
Katahira & Engineer
International
2,763,984
(100%) of
ADB
Loan
433,890
15.70%
25.4.4 Lots 4 (25kms): Bandudatu to Aituto Road Sections
The cost for Lot 4 is US$ 28.138 million and contract was awarded to Chongqing
International Construction Corporation (CICO) through international competitive bidding.
The contracts have been submitted to Court of Audit for approval and works are expected to
start by second quarter of 2015. Payment information is presented in table 25.15.
Table 25.15: Lot 4 from Solerema to Bandudatu Road Section (30 kms) Project
Civil Work Contract
Amount
(US$)
Proportion
of %
Previous
Progress
2014
(US$)
Disbursement Progress 2015
(US$) Remarks
Contractor Q1 Q2 Q3 Q4
Chongqing International
Construction Corporation
(CICO ) * WB - Loan
5303/8290 Lot 4. 28,138,737
40% 834,712
1st half
advance
payment
(7.5%) * Government Funding 60% 1,252,068
Consultant Design &
Supervision (100%)
Contract
Amount
Proportion
of %
Previous
Progress
2014
Current Progress 2015 Remark
Q1 Q2 Q3 Q4
Egis International in JV
with Egis International
Indonesia and Lelo
Engineering
3,213,787 100%
Source: MPS analyisis, 30 June 2015
148 | P a g e
25.4.4 Lots 5 (23kms): Aituto to Ainaro Road Sections
The cost for Lot 5 is US$ 26.875 million and contract was awarded to Chongqing
International Construction Corporation (CICO) through international competitive bidding.
The contracts have been submitted to Court of Audit for approval and works are expected to
start by second quarter of 2015. Payment information is presented in table 25.16.
Table 25.16: Lot 5 from Aituto to Ainaro Road Section (30 kms) Project
Civil Work Contract
Amount
(US$)
Proportion
of %
Previous
Progress
2014 (US$)
Disbursement Progress 2015 (US$)
Remarks
Contractor Q1 Q2 Q3 Q4
Chongqing International
Construction Corporation (CICO )
* WB - Loan 5303/8290 Lot 5. 26,875,070
40% 797558.12
1st half advance
payment (7.5%)
* Government Funding 60% 1,196,337
Consultant Design & Supervision
(100%)
Contract
Amount
Proportion
of %
Previous
Progress
2014
Current Progress 2015
Remark
Q1 Q2 Q3 Q4
Katahira & Engineer International 3,213,787 100%
Source: MPS analyisis, 30 June 2015
25.4.5 Roads under detailed design
Detailed Engineering Designs are being completed through IDA Grant No. H683-0TP for the
following road sectionse: Comoro-Solerema (23.8Kms), Aituto to Hautubuliku to Letefoho to
Gleno (60kms) and Ainaro-Casa (21kms).
Design of Comoro-Solerema (23.8 kms) has already been completed. Aituto to Hatubuiliku to
Letefoho to Gleno (60kms) and Ainaro-Casa (21kms) as branch roads of Dili-Ainaro with total
length of 81kms are under procurement by NPC for Feasibility Study and Detailed Design.
The Government, however, will further determine which road will be constructed.
25.6 SAFEGUARDS COMPLIANCE
Development partners instituted safeguards and sustainability policies to prevent and mitigate
adverse impacts of its projects on people and the environment. On the above projects, MPW-
PMU oversees the compliance on safeguard requirements, status of which is briefly presented
in table 25.17 below:
25.6.1 Resettlement Plan
CAFI approved the budget for implementation of Resettlement Plan for Loan Projects (ADB,
WB and JICA) on August 22, 2014. Due to new procedural system of payment being
introduced by the Ministry of Finance where payment is to be deposited to the individual
account of APs, there is another round of consultation required with APs to explain further the
new procedure for RAP implementation. It is expected the budget for Resettlement Plan is
available by second quarter of 2015 and payment for APs some location still under
149 | P a g e
verification PMU of Loan and US$ 381,081.73 under raising of Purchase Order (PO) by NPC
and it expexted to be concluded by following quarter report 2015.
25.6.2 Environmental Compliance
In coordination with the MPW-PMU, the status of compliance of loan-funded projects with
the Environmental Licensing Law (Decree Law 05/2011) is tabulated below:
Table 25.17 Status of Environmental Compliance of Loan-Funded Projects
Loan-Funded Projects Date of Issuance of
Environmental License
Status of Environmental
Management Plan (EMP)
Implementation
RNUP (R-3) Dili – Tibar – Liquica
Road
19 September 2014(Renewal of
original license after 2 years.)
On-going (progress monitoring based
on EMP in contract).
RNUP (R-4) Tibar – Gleno Road 02 October 2014(Renewal of
original license after 2 years.)
On-going (progress monitoring based
on EMP in contract).
TLRCRP (Lot 01 and Lot 2)
Hali Laran – Laulara Section
17 December 2012 On-going (progress monitoring based
on EMP in contract).
Lot 3
Solerema – Bandudatu Section
On-going (progress monitoring based
on EMP in contract).
Lot 4
Bandudatu – Aituto Section
Commence date on March 2015 Project construction will start after
Contract signing by MPW
Lot 5
Aituto – Ainaro Section
Project construction will start after
Contract signing by MPW
RNUSP
Manatuto –Laclubar Road
02 July 2014 Project construction will start on 15
January 2015
RNUSP Laclubar – Natarbora Road 02 July 2014 Project construction will start on
March 2015
RNUP Tasitolu Tibar Project Application is under
evaluation process by NDE
NRP -Dili Manatuto (JICA) Project Application is under
evaluation process by NDE and
the Project will commence on
August 2015
The Project is still under procurement
process by NPC
NRP- Manatuto Baucau (JICA) No schedule yet. It will be
determined by the Council of
Ministers
The PMU prepared EMP under
Contract
150 | P a g e
26 PROJECT PROPOSALS FOR 2016 FINANCING
26.1 RECEIPT OF PROJECT BRIEFS
CAFI agreed a deadline of May 30 2015 for the submission of Project Briefs for new projects
to be submitted to the Major Projects Secretariat. As of that date only nine Projects Briefs had
been submitted and MPS accepted submissions for a further month. A summary of the
number of submissions by project proponent is shown in Table 26.1.
Table 26.1: Project Brief Submissions by Project Proponents
Ministry
No. of Project Brief Submitted to MPS
Before
March 2015
In March 2015 In April 2015 Total
Ministry of Agriculture & Fisheries 4 0 0 4
Ministry of Public Works 0 0 0 0
Ministry of Transport &
Communication
0 0 0 0
Ministry of Education 0 0 0 0
Ministry of Justice 0 0 4 4
Ministry of Commerce, Industry &
Environment
0 11 0 11
Ministry of State Administration 0 9 0 9
Ministry of Finance 0 0 0 0
Ministry of Security & Defence 0 0 0 0
Ministry of Petroleum & Mineral
Resources
0 0 0 0
Ministry of Health 0 0 0 0
Ministry of Tourism 0 0 0 0
Ministry of Social Solidarity 0 0 0 0
Secretary of State for Promotion &
Equality
0 0 0 0
Secretary of State for Private
Enterprise
0 0 0 0
Secretary of State for Media 0 0 0 0
Secretary of State for Youth & Sports 0 0 0 0
National Development Agency 0 0 0 0
Total 4 19 4 28
% 15% 70% 15%
% Cumulative 15% 85% 100%
26.2 REVIEW OF PROJECT BRIEFS
28 Project Briefs have been received by MPS from four ministries (see Table 26.1). Of these,
three of the four submitted by Ministry of Agriculture and Fisheries are for projects already
151 | P a g e
in the IF portfolio and the fourth may also be considered to be an extension of an on-going IF
funded project7.
The Ministry of Commerce, Industry and Environment has submitted ten (10) Project
Briefs. All are for projects for which Concept Designs appear yet to require preparation. The
project costs for each strongly suggest that IF funds for Concept design and Detailed
Engineering Design (DED) only are being sought at this time. At this stage full appraisals
cannot be carried out but the overall programme of the ministry requires clarification in order
to assist them in preparing a time-based rational action plan for procurement and completion
of the Concept Designs and DEDs, including feasibility, environmental and social impact
studies.
From the Ministry of State Administration nine (9) Project Briefs have been received. All
proposals reportedly have Geotechnical Studies and Concept Designs completed. This needs
to be confirmed and the locations and land acquisition situations confirmed. Many other data
are required and Project Implementation Plans defined. These will require extensive meetings
with the ministry and possible a limited number of site visits.
Four (4) Project Briefs have been received from the Ministry of Justice (MoJ). One, Supply
and Installation of Components for the new main MoJ office, is valued at below the minimum
threshold for IF financing and should be referred to CAFI for a decision on whether or not to
consider the proposal as an extension of the civil works programme. No information on
project preparation status has been submitted for two projects, 1) Construction of Office for
the Criminal Scientific Investigation Department and 2) Construction of Office for the STJ,
TSAFC and CSM). The fourth project, Construction of Juvenile Detention Centre, reportedly
has Concept Design, DED and Bill of Quantities (BoQ) and is relatively well supported by
back-up documentation
26.3 CANCELATION OF NEW PROJECT FOR FISCAL YEAR OF 2016
The extra-ordinary CAFI meeting on June 17, 2015 has decided that no new project will be
proposed to be included in the fiscal year of 2016 and only focusing in the existing projects.
This also includes pending in the contruction of new office building at various government
agencies that are under the preparation and design stage.
With the above decision, the project appraisal of the new project will not be completed;
instead each line ministry will be informed to provide more information regarding the
proposed projects for better project appraisal in the fiscal yeat 2016 to be included in the fiscal
year of 2017.
7 Continuation of Dam and Reservoir Studies
152 | P a g e
27 CAFI MEETING
As presented earier that CAFI as the government executive body that is responsible for the
implementation of the IF funded project, condutcs various meeting throughout any given
fiscal year. The objective of the meeting is to provide an update of the progress made of each
IF funded project, discuss and reolve various issues that occur during the project
implementation.
During the second quarter of fiscal year of 2015, five CAFI meetings were conducted which
inline with the above mentioned objective. Two ordinary and 3 extraordinary CAFI meetings
were conducted between April and June 2015 that resulted in various decisions and resolution
that affect positively to the IF project implementation. The following table presented the
summary of the each CAFI meeting conducted during the reporting period.
Table 27. 1 Summary of CAFI Meeting during the Reporting Period
Date of Meeting Type of Meeting
Monday, April 13, 2015 Ordinary
Friday, April 24, 2015 Ordinary
Thursday, May 21, 2015 Extra-Ordinary
Tuesday, June 9, 2015 Extra-Ordinary
Wednesday, June 17, 2015 Extra-Ordinary
The detail information of each CAFI meeting during the reporting period, including the
agenda, decision, and attendance can be found in the annex 1.
153 | P a g e
28 DATABASE & IT UNIT
As of end-2014, Database & Reporting Unit carried out the regular task of maintaining all the
electronic records of Infrastructure Fund Payments through compiling of incoming documents
received each day. In the fiscal year of 2015, SGP take the full benefit of the database and
information tracking systems to well manage the IF funded project. The result of the first
quarter of 2015 can be seen from the following figure.
Figure 28.1 Example of the Information provided in the IT and Database system
154 | P a g e
29 CHALLENGES
In general, the challenges confronted by most implementing agencies and private companies
were lack of capacity for conducting proper project planning, lack of experienced and
dedicated staffs as well as skilled labourers to perform the work and services according to
agreed procedures, specifications and technical requirements.
There also appears to be a general lack of discipline in the conduct of works of the contractors.
Many projects commenced prior to the issuance of Notice-to-Proceed (NTP) and/or without
adequate works preparation, and proper planning and procurement leading to slow progress of
project implementation. Completion of as-staked plans and drawings before working on site is
one of the vital obligations of contractors which oftentimes are not complied with.
Slow implementation progress is attributable to a number of reasons.
Contract Agreement preparation inclusive of conditions of contract should be done in
full coordination and consultation with relevant government institutions like Tax
agency, Legal agency in order to make sure that the contracts are in compliance with
the laws being imposed in the country. Otherwise the impact will be on delay of
payment process and accumulated to the physical work and implementation and time
frame as well as quality of product to be delivered.
Amendment of contracts should comply with procurement law, financial law or
international law acceptable in this country to avoid irregularities.
Limited knowledge on legal procedures and unavailability of legal advisers in place is
challenging the overall process of project management and budget execution.
Inadequate or no pre-construction works planning and scheduling, relevant
government agencies and supervision consultants should insist on pre-mobilisation
meetings for each project to ensure that the contractor has prepared adequate plans and
schedules to complete the works according to the contract.
Inadequate provision of capable technical staff by the contractors to undertake
verification and construction surveys (short term temporary deployment of surveyors is
common practice but insufficient to maintain good works progress and quality).
Lack of coordination among relevant agencies, program linkages and sequencing at
sector, program and project level: for instance, how best to sequence the drainage
Master Plan and preparation of the Dili Urban Plan.
Equally important is to ensure that monitoring works must always be performed by
capable engineers to ensure that the materials and works carried out are in accordance
with the specifications stipulated in the contract and design standards.
These short comings bear the risk of low quality of works and performance and completion
schedule. Measures need to be taken to mitigate such risks and improve quality and work
performance. This include assurances of the client/Government to employ suitably qualified
staff and consultants for project supervision in support of line ministries, until internal
capacity is available to ensure that projects are being constructed in accordance with
155 | P a g e
specifications prior to the approval of fund release. Similar action also needs to be taken by
the private companies.
156 | P a g e
ANNEX 1. MINUTES OF CAFI MEETINGS, END- 2015
157 | P a g e
ANNEX 2. FREE BALANCE REPORT - END- 2015