ı eight industrial painters - central arizona project board meeting/… · four industrial...

41

Upload: lamthuan

Post on 16-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

õ Eight Industrial Paintersô Six are assigned to Protective Coatings traveling

crewô Two are assigned to the Paint Shop and Blast

Booth at Headquartersõ Three Maintenance Workers

Presenter
Presentation Notes
The Protective Coatings crew also consists of three Maintenance Workers One is assigned to the Paint shop and Blast booth Two are assigned to the traveling crew

õ CAP is a state certified apprenticeship program

õ Partner with National Association Of Corrosion Engineers (NACE)

õ Partner with Steel Structure Painting Council (SSPC)

õ 600 hours of classroom trainingõ 6000 hours of On the Job Learning

Presenter
Presentation Notes
CAP Industrial Painters are unique because: the equipment they work on safety requirements - hearing conservation, respiratory protection environment requirements – proper handling and disposal of hazardous waste types of coatings used precision needed for the finished products Confined spaces – pipes 24” to 144”, pump volutes, 21’ siphons NACE is a world wide recognized organization Currently there are 30,000 NACE inspectors world wide State of AZ there are 12 – 15 NACE inspectors OJL used to be OJT

õ Registered with the AZ Commerce Authority, Dept. of Apprenticeship Services

õ U.S. Dept. of Labor, Bureau of Apprenticeship and Training

õ Four Industrial Painters are certified Level 3 NACE Coating Inspectors

õ Four Industrial Painters are certified Level 2 NACE Coating Technicians

Presenter
Presentation Notes
Certification to become an inspector requires 3 weeks of classroom and hands on training with a 200 question test at the end of each week. Level 3 Inspector is the highest level of Coating Inspector. With this level of certification a person has demonstrated experience in practical environments to a panel of peers when faced with coatings related scenarios.

õ Four Industrial Painters are certified Concrete Coating Inspectors

õ Four Industrial Painters are certified Concrete Coating Technicians

Presenter
Presentation Notes
Concrete Coating Inspectors are required to pass an intense week-long training which involves a 200 question test plus hands on testing. The concrete coating inspector program was started six years ago.

õ Typical equipment used by the Industrial Painters

Presenter
Presentation Notes
The following slides show equipment used by Industrial Painters to perform their daily tasks.
Presenter
Presentation Notes
The Blast Booth uses steel grit that is recycled 50 to 60 times during the blasting process. The Blast Booth and Paint Shop were designed to handle a radial gate which measure approximately 17 ft x 17 ft. The Blast Booth has a Hepa air filtration system which filters down to 5 microns.
Presenter
Presentation Notes
The Paintbooth is heated and cooled. The epoxy coatings used need a minimum of 60 degrees and a maximum of 100 degrees to cure Rails run between the paint and blast booth for easy movement of large parts The construction of the new Blastbooth and Paintbooth was completed in 2008
Presenter
Presentation Notes
These cabinets are used for abrasive blasting of small parts and equipment Completely self contained, recycled abrasive material, filters that remove all dust down to 5 microns
Presenter
Presentation Notes
Trailer mounted with a half cubic yard sized hopper for vacuuming spent abrasive from job sites
Presenter
Presentation Notes
This compressor is used for abrasive blasting and breathable air The air coming out of the machine is instrument quality air (does not need to be filtered)
Presenter
Presentation Notes
Working pressure 40,000 psi at 6 gallons per minute Noise level is 115 decibels which is equal to the sound of a jet at take off at 10 meters Operating limits are one hour per employee per day because of the noise level
Presenter
Presentation Notes
56 – 1 means for every 1 psi there are 56 psi at the spray nozzle. 100 psi equals 5,600 psi. These are used to spray epoxy coatings The higher pressure is needed because of the thickness of the coatings being used
Presenter
Presentation Notes
The pressure washer is used to clean areas before painting
Presenter
Presentation Notes
Abrasive blast pots operate at 90 to 100 psi Blasting produces decibels up to 115 limiting blasters to one hour per day
Presenter
Presentation Notes
Uses an asphalt based material heated to 350 degrees F Material is used to seal joints and cracks on the canal lining to prevent leakage
Presenter
Presentation Notes
Mark Wilmer Unit 4 overhaul 3/1/2010 Material being applied by Jaime Servin is a polymer composite
Presenter
Presentation Notes
Finished product Blue material is the same material used on rudders and props of large ships
Presenter
Presentation Notes
One of the steps in an overhaul
Presenter
Presentation Notes
3/1/2010 Suction tube being recoated with an epoxy coating

Before After

Presenter
Presentation Notes
3/1/2010 With the coating being used now and with minimum maintenance the unit should look like the picture on the right for 10 to 15 years

Before After

Presenter
Presentation Notes
Paint on the walls and equipment helps to lighten the area in the plant for maintenance personnel

Before After

Presenter
Presentation Notes
Brightening of the plant

Before After

Presenter
Presentation Notes
5/3/2011
Presenter
Presentation Notes
Workers in the discharge line at Pima Lateral Turnout
Presenter
Presentation Notes
Workers in discharge line at Pima Lateral
Presenter
Presentation Notes
Ken Brunk water jetting in the discharge line at Roosevelt Turnout
Presenter
Presentation Notes
Note all of the PPE (personal protective equipment) Gloves Respirator Headlamp Tyvek suit A jet lance is being used when water jetting with a two stage trigger for safety, working pressure 40,000 psi, noise level 115 decibels, working time one hour
Presenter
Presentation Notes
Siphon is 21 ft diameter and 1.5 miles long Scaffold is Safeway Scaffold on a rolling platform engineered and constructed at CAP
Presenter
Presentation Notes
Office area at Twin Peaks Pumping Plant The floor had been shot blasted and Industrial Coaters are in the process of applying an epoxy coating to the floor
Presenter
Presentation Notes
Discharge valve was removed and transported to 7th street for rebuilding Jake Pickard is doing touch up as needed on the discharge line
Presenter
Presentation Notes
11/20/2010 Replacement grate coated inside the Paintbooth
Presenter
Presentation Notes
Recoating the roof at Bouse Hills Pumping Plant Approximately 300,000 sq. ft. All of the pumping plants roofs are foam roofs and the protective elastomeric coating needs to be reapplied every 7 to 10 years
Presenter
Presentation Notes
The gates weigh approximately 17,000 lbs with the arms attached and are approximately 17 ft x 17 ft in size This gate has been water jetted with the next process to be abrasive blasting before recoating
Presenter
Presentation Notes
Water jetting at a pipe overchute There are approximately 260 pipe overchutes
Presenter
Presentation Notes
Finished product of pipe overchute. These overchutes carry drainage water from one side of the canal to the other. Most are above the water but some are submerged Pipes are approximately 60 inches in diameter and 100 ft long The work is performed working off of barges designed and built at CAP
Presenter
Presentation Notes
9/15/2010 All parking canopies at CAP were pressure washed and recoated Beginning in June the painting of Building 1 will begin
Presenter
Presentation Notes
Protective Coatings constructed this mockup of Buckskin Mountain (Mark Wilmer) demonstrating the pumping of the water uphill from the plant and the gravity flow of the water down to the different turnouts etc. along the way.

õPainting/coating is very easy when you don’t know how, but

very difficult when you do.

Presenter
Presentation Notes
This is the Protective Coatings motto