i-35e project, dallas to denton

2
TEXAS DEPARTMENT OF TRANSPORTATION Work with others to provide safe and reliable transportation solutions for Texas. INTERSTATE 35E • PROJECT TRACKER FALL • 2012 OVERVIEW Interstate 35E (I-35E) serves the rapidly growing areas of southern and central Denton County, as well as the major Dallas suburbs immediately north of I-635. This corridor functions as a major artery for hundreds of thousands of commuters, as well as a primary link to major universities in the city of Denton, including the fourth-largest university in the state, the University of North Texas (UNT). In addition, I-35E functions as an important truck corridor and accommodates more than 12,000 trucks daily, according to 2008 state vehicle counts. The interstate also handles almost 200,000 total vehicles daily near I-635, and 128,000 vehicles a day across Lewisville Lake. Because of the challenges of crossing the Lewisville Lake and the lack of I-35E frontage roads across the lake, viable north- south commuting alternatives to I-35E do not exist. This condition makes it imperative to provide motorists reliable alternatives with a combination of continuous frontage roads and managed lanes in the I-35E corridor. The $4.8 billion project, proposed to be constructed in phases, would rebuild the entire 28-mile corridor and provide managed lanes that feature dynamic pricing to keep trafc moving at 50 mph. Approximately $1.1 billion in funding has been identied for this project, with most coming from SH 121 regional toll revenue funds dedicated to Denton County. PROJECT HISTORY/TIMELINE I-35E constructed: 1950s and 1960s Major Investment Study for future expansion: Began 1998 Express Lane Demonstration Program Approval by Federal Highway Administration: Sept. 30, 2009 Phase 1A project procurement began Jan. 2012 ENVIRONMENTAL REVIEW STATUS Environmental Assessment public meetings: 2008 FHWA schematic approval for all three sections: Oct. 28, 2009 Environmental Assessment process: 2003-2012 (complete) Finding of No Signicant Impact by FHWA: Jan. 28, 2011 (middle section); Dec. 28, 2011 (south section); Jan. 31, 2012 (north section) All public hearings have been completed Finding of No Signicant Impact (FONSI) from FHWA received for all sections Phase 1A FHWA Environmental coordination ongoing PROJECT PROGRESS Legislative authority granted for public-private partnership during 2011 session. Authority has been granted through August 2015. An aesthetics master plan was developed with the help of local stakeholders. TxDOT’s request for qualications were due March 23. Five design-build teams submitted qualication statements, and four were short-listed. The Senate Bill (SB) 1420 Committee determined at its March 26, 2012 meeting that Phase 1A of the project should be delivered as a design-build project with public nancing and utilizing the Regional Transportation Council managed lane policy. To maintain exibility in the future, no determination has been made on the type of nancing or delivery method for con- struction, for the remainder of the project, known as Phase 1B. Request for Proposals (RFP) was issued on July 13, 2012. EARLY PROJECTS: Early right-of-way (ROW) acquisition, near FM 407, is underway The Texas Transportation Commission committed funding in late 2010 for the FM 407 intersection in late 2010 Pedestrian bridge to access new University of North Texas football stadium is estimated to be completed by mid- October 2012 PROJECT FACTS LENGTH North section (US 380 to FM 2181): 10.5 miles Middle section (FM 2181 to Pres. George Bush TP): 12.1 miles South section (Pres. George Bush TP to I-635): 5.5 miles COST Ultimate design and construction cost (2010 estimate): $3.4 billion Right-of-way (2010 estimate): $1.4 billion (ultimate) CONSTRUCTION DATES Anticipated start date: 2013 (Phase 1A) NEXT STEPS Final proposals due: Nov. 12, 2012 Anticipated conditional award: Dec. 13, 2012 Full contract award anticipated: Early Feb. 2013 ROW acquisition anticipated to begin: Spring 2013 Construction schedule expedited, planned start: Summer 2013 PROJECT TRACKER INTERSTATE 35E INTERSTATE 35E 0090_092712 Rendering of proposed I-35E in ultimate conguration from south of Sandy Lake Road to the President George Bush Turnpike. TxDOT photo archive

Upload: the-dallas-morning-news

Post on 28-Apr-2015

2.012 views

Category:

Documents


1 download

DESCRIPTION

Here's more project information on the I-35E overhaul from Dallas to Denton.

TRANSCRIPT

Page 1: I-35E Project, Dallas to Denton

TEXAS DEPARTMENT OF TRANSPORTATION Work with others to provide safe and reliable transportation solutions for Texas.

INTERSTATE 35E • PROJECT TRACKER FALL • 2012

OVERVIEW

Interstate 35E (I-35E) serves the rapidly growing areas of southern and central Denton County, as well as the major Dallas suburbs immediately north of I-635. This corridor functions as a major artery for hundreds of thousands of commuters, as well as a primary link to major universities in the city of Denton, including the fourth-largest university in the state, the University of North Texas (UNT). In addition, I-35E functions as an important truck corridor and accommodates more than 12,000 trucks daily, according to 2008 state vehicle counts. The interstate also handles almost 200,000 total vehicles daily near I-635, and 128,000 vehicles a day across Lewisville Lake. Because of the challenges of crossing the Lewisville Lake and the lack of I-35E frontage roads across the lake, viable north-south commuting alternatives to I-35E do not exist. This condition makes it imperative to provide motorists reliable alternatives with a combination of continuous frontage roads and managed lanes in the I-35E corridor. The $4.8 billion project, proposed to be constructed in phases, would rebuild the entire 28-mile corridor and provide managed lanes that feature dynamic pricing to keep traffi c moving at 50 mph. Approximately $1.1 billion in funding has been identifi ed for this project, with most coming from SH 121 regional toll revenue funds dedicated to Denton County.

PROJECT HISTORY/TIMELINE

■ I-35E constructed: 1950s and 1960s ■ Major Investment Study for future expansion: Began 1998 ■ Express Lane Demonstration Program Approval by Federal Highway Administration: Sept. 30, 2009

■ Phase 1A project procurement began Jan. 2012

ENVIRONMENTAL REVIEW STATUS

■ Environmental Assessment public meetings: 2008 ■ FHWA schematic approval for all three sections: Oct. 28, 2009 ■ Environmental Assessment process: 2003-2012 (complete) ■ Finding of No Signifi cant Impact by FHWA: Jan. 28, 2011 (middle section); Dec. 28, 2011 (south section); Jan. 31, 2012 (north section)

■ All public hearings have been completed ■ Finding of No Signifi cant Impact (FONSI) from FHWA received for all sections

■ Phase 1A FHWA Environmental coordination ongoing

PROJECT PROGRESS

■ Legislative authority granted for public-private partnership during 2011 session. Authority has been granted through August 2015.

■ An aesthetics master plan was developed with the help of local stakeholders.

■ TxDOT’s request for qualifi cations were due March 23. Five design-build teams submitted qualifi cation statements, and four were short-listed.

■ The Senate Bill (SB) 1420 Committee determined at its March 26, 2012 meeting that Phase 1A of the project should be delivered as a design-build project with public fi nancing and utilizing the Regional Transportation Council managed lane policy.

■ To maintain fl exibility in the future, no determination has been made on the type of fi nancing or delivery method for con-struction, for the remainder of the project, known as Phase 1B.

■ Request for Proposals (RFP) was issued on July 13, 2012.

EARLY PROJECTS:

▪ Early right-of-way (ROW) acquisition, near FM 407, is underway

▪ The Texas Transportation Commission committed funding in late 2010 for the FM 407 intersection in late 2010

▪ Pedestrian bridge to access new University of North Texas football stadium is estimated to be completed by mid-October 2012

PROJECT FACTSLENGTH

▪North section (US 380 to FM 2181): 10.5 miles

▪Middle section (FM 2181 to Pres. George Bush TP): 12.1 miles

▪ South section (Pres. George Bush TP to I-635): 5.5 milesCOST

▪Ultimate design and construction cost (2010 estimate): $3.4 billion

▪ Right-of-way (2010 estimate): $1.4 billion (ultimate) CONSTRUCTION DATES

▪Anticipated start date: 2013 (Phase 1A)

NEXT STEPS

■ Final proposals due: Nov. 12, 2012 ■ Anticipated conditional award: Dec. 13, 2012 ■ Full contract award anticipated: Early Feb. 2013 ■ ROW acquisition anticipated to begin: Spring 2013 ■ Construction schedule expedited, planned start: Summer 2013

PROJECT TRACKERINTERSTATE 35EINTERSTATE 35E

0090_092712

Rendering of proposed I-35E in ultimate confi guration from south of Sandy Lake Road to the President George Bush Turnpike.

TxDOT photo archive

Page 2: I-35E Project, Dallas to Denton

FALL • 2012

INTERSTATE 35E CONTACTSINTERSTATE 35E CONTACTS

INTERSTATE 35E • PROJECT TRACKER FALL • 2012

INTERSTATE 35E • PROJECT TRACKER

Project website: www.keepitmovingdallas.com“IH 35E” linkTexas Department of Transportation

4777 East Highway 80Mesquite, TX 75150214-320-6100

Tony Hartzel TxDOT DFW Strategic ProjectsPublic Information4777 E Highway 80Mesquite, TX 75150214-320-4481

NO

TE: H

ighl

ight

ed a

reas

are

not

to sc

ale.

DENTON

Grapevine Lake

Ray RobertsLake

121

121

288

288

455

428

428

428

428

423

423

455

455

156

407

380380

35W

35

35

380

377

377

377

377

LewisvilleLake

26

26

77

Sanger

PilotPoint

Aubrey

Krugerville

Lincoln Park

Prosper

Frisco

Coppell

Grapevine

Carrollton

Farmers Branch

OakPoint

Hackberry

The Colony

Hebron

Addison

Lewisville

Copper Canyon

Hickory Creek

Shady Shores

Argyle

FlowerMound

2499

11711171

1830

3163

2164 2153

1385

1385

407

2931

114

TrophyClub

114

635

Westlake

Southlake 97

DFWInt’l. Airport

N

5 miles

CO

LLIN

CO

.

DEN

TON

CO

.

TARRANT CO.

DENTON CO.DALLAS CO.

DENTON CO.

35E

Corinth

77

35E

77

35E2

- 3*

23

2 - 3

*2

3

2 - 3

1 - 2

2

4 4 3

South

:I-6

35 to

Pre

siden

t Geo

rge

Bush

Tur

npik

e

Mid

dle

:

Pre

siden

t Geo

rge

Bush

Tur

npik

e to

FM

218

1

Nort

h:

FM 2

181

to U

.S. 3

80

2 - 3

2 - 3

2 - 3

1 0 0

Road

way

and

Lim

its

Exist

ing

front

age

road

lane

s(E

ach

dir.

)

Exist

ing

mai

nla

nes

(Eac

h d

ir.)

Prop

osed

fro

ntag

ero

ad la

nes

(Eac

h d

ir., 2

030)

Exist

ing

HOV

lane

s(E

ach

dir.

)

Prop

osed

ge

nera

lpu

rpos

e la

nes

(Eac

h d

ir., 2

030)

Prop

osed

m

anag

edla

nes

(Eac

h d

ir., 2

030)

* D

iscon

tinuo

us.

** L

oop

288

to F

M 2

181.

***

Inte

rim c

onfig

urat

ion

relie

s prim

arily

on

use

of e

xistin

g pa

vem

ent f

or e

xpan

sion.

Fin

al c

onfig

urat

ion

invo

lves

reco

nstru

ctio

n of

rem

aind

er o

f the

cor

ridor

.Tx

DO

T gr

aphi

c

2 2 2**

4 4 3

2 - 3

2 - 3

2 - 3

Inte

rim**

*fro

ntag

ero

ad la

nes

(Eac

h d

ir., 2

017)

Inte

rim**

*ge

nera

lpu

rpos

e la

nes

(Eac

h d

ir., 2

017)

Inte

rim**

*re

vers

ible

man

aged

lane

s (2

017)

35E