PROJECT AREA HOLI – II Small Hydro Project (07 MW)

Upload: zorro7

Post on 05-Dec-2014

2.735 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Holi project presentation

PROJECT AREAHOLI – II Small Hydro Project (07 MW)

Page 2: Holi project presentation

HOLI – II HEP – 7 MWDistrict – Chamba, Himachal Pradesh

Page 3: Holi project presentation

HOLI – II HEP – 7 MWDistrict – Chamba, Himachal Pradesh

Page 4: Holi project presentation

PROJECT SUMMERY • Project Name Holi-II Small Hydro Project• Capacity 07 MW• Total Project Land 4.1595 Hect. (Forest Land)• Type of Scheme Run of River• MOU signed on 17th July 2007• DPR Prepared by AHEC, IIT, Roorkee • Major Component Weir, Water Conductor system,

Power House, Muck Disposal Sites, Switch Yard

• Grid Connectivity Holi-I 33Kv Sub-Station• Project Cost Rs. 54.06 Crores• LADA Money 1st Installment Paid• Implementation Agreement Signed on 8th Oct, 2010

Page 5: Holi project presentation

Joint Inspection of Project Held on 5th May, 2010

• District Administration– ADM Bharmour/Tehsildar/Patwari

• Gram Panchayat– Gram Pradhan/ Panchayat Member

• Project Administration – Director, Om Energy Generation P. Ltd.

• Pollution Control Board– Asst. Environment Engineer, Chamba

• Forest Department– ACF Bharmour

• IPH Department– Asst. Engineer, Bharmour

• PWD Department– Asst. Engineer, Garola Sub Division

• Mining Department – Mining Inspector, Chamba

Page 6: Holi project presentation

Joint Inspection of Project Held on 5th May, 2010

Page 7: Holi project presentation

NO OBJECTION CERTIFICATE’S

• Gram Panchayat Received• Wildlife Received• Fisheries Received• I&PH Received• PWD Received• PCB Received • Forest Land Received

Page 8: Holi project presentation

CDM Registration for Project

Consultant:

Agrinergy Consultancy Pvt. Ltd.

1st Floor, Mathuradas Mills Compound,

N M Joshi Marg, Lower Parel (w),

Mumbai – 400013 (India)

Website: www.agrinergy.com

Present StatusPre-Consideration Process Completed

with UNFCCC

Website: www.cdm.unfccc.int

Page 9: Holi project presentation

PROJECT ADVANTAGES

• Socio Economic Development

• Displacement of CO2 Emissions

• Environmentally Benign source of Energy

• Zero Submergence and No R&R Issue

• Improves Stability and Reliability of Grid System

Page 10: Holi project presentation

DEVELOPMENT CONSIDERATION

Om Energy Generation Believes Hydro Power Development

Channels Multi-Region &

Bipartisan Support

Than any other “Clean Energy Technology”

Page 11: Holi project presentation

Developed By:Dalip Dua & Sanjay Saklani

M/s Om Energy Generation Pvt. Ltd.

THANK YOU