hard rock hotel - pinnaclecad · based hard rock international, marks the latest signal that the...

1
ard Rock Hotel comprising of 350 rooms on 18 floors (1st Floor - H Ground Level, 2nd Floor - Retail, 2nd Floor - Mezzanine, 3rd Floor - Accessible Parking, 4th to 7th Floor - Parking, 8th to 13th Floor - Hotel, 14th Floor - Hotel & Pool Deck, 15th Floor - Condos, 16th & 17th Floor - Penthouse and 18th Floor - Rood Deck) is spread over 40,000 sq. ft. in New Orleans, Louisiana, USA at the site of the former Woolworth Department Store in the 1000 Block of Canal Street. The mixed-use development, led by Florida- based Hard Rock International, marks the latest signal that the mid-Canal Street corridor is gaining commercial traction with big-name brands and retailers, largely buoyed by an interest in Downtown Living and as New Orleans continues to thrive as a tourist destination. Copyright © 2018 Pinnacle Infotech, Inc. Global Leader in BIM Services www.pinnaclecad.com Hard Rock Hotel [Hotel] New Orleans, Louisiana, USA Scope of Work Our scope of work for the project included: 1. 3D Model Creation of Sheet Metal (Ducts, Associated Fittings & Equipment) & Mechanical Piping @ LOD 400 as per design document & project specification 2. BIM Coordination - Updating the model to resolve clashes, as suggested by the client, Reviewed Interdisciplinary Coordination, Floor to Floor Alignment & Continuation to other areas 3. Preparation of Detail Shop Drawings with annotation, dimension and tagging BIM Start Date: January, 2018 40,000 sq ft Project Area: Average Team Size: 5 Engineers BIM End Date: April, 2018 Challenges & Solutions A. Challenge - Design Mismatch - 1. Diffuser Inlet Size & Duct Size are not matching between design plan and mechanical schedule 2. Stair Pressurization riser duct size mismatch between 1st, 2nd Floor & 3rd Floor - In the 1st Floor duct size - 26x10, in the 2nd Floor duct size - 16x16 and in the 3rd Floor, duct size - 28x12 Solution - Requested client to review and suggest on the same B. Challenge - Coordination Problem - 1. As per FCU generic model extracted from Revit model, SA duct was coming from top outlet of FCU and clashing with SLAB due to space constrain Solution - Requested client to review the reference drawing and suggest on the samec. Challenge - Missing Information 1. In third floor plan, there was no water connection for FCUs 2. Moreover, routing for condensate drain pipe was not found Solution - Requested client to provide the missing information Trades Covered: Mechanical(Sheet Metal & MP) Software Used: Revit Fabrication Part 2017 LOD: 400 Architect: HARRY BAKER SMITH ARCHITECTS II A PROFESSIONAL LLC. 1. Using BIM, the Pinnacle team searched and selected alternatives that meet project requirements, discovering and solving issues at an early stage, saving time, eliminating rework, improving quality and allowing everyone on the project team to be successful 2. The effective application of BIM reaped benefits throughout the life cycle of the project 3. Pinnacle’s approach to virtual construction with BIM created the opportunity to identify problems earlier in the building process and facilitate BIM team to find better ways to communicate ideas, reducing errors and improving Pinnacle's Value Addition Consulting Engineers: HOWARD MOSES, P.E. MOSES ENGINEERS, LLC. MEP Sub Contractor: Regional Mechanical Services, LLC* Owner/Developer: Kailas Companies, LLC. Structural Engineer: James Heaslip and Walter Zehner productivity 4. Newforma was used to streamline project communication 5. BIM ensured that the information related to design and construction activities flow seamlessly among all stakeholders involved in the project through simple exchange of models and data, so that team members can ensure accurate and complete information. This delivered a range of benefits, including simplified product selection, robust design solutions, automatic clash avoidance and effective team work Architectural BIM Model Clash Coordination

Upload: others

Post on 26-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hard Rock Hotel - pinnaclecad · based Hard Rock International, marks the latest signal that the mid-Canal Street corridor is gaining commercial traction with big-name brands and

ard Rock Hotel comprising of 350 rooms on 18 floors (1st Floor - HGround Level, 2nd Floor - Retail, 2nd Floor - Mezzanine, 3rd Floor - Accessible Parking, 4th to 7th Floor - Parking, 8th to 13th Floor - Hotel,

14th Floor - Hotel & Pool Deck, 15th Floor - Condos, 16th & 17th Floor - Penthouse and 18th Floor - Rood Deck) is spread over 40,000 sq. ft. in New Orleans, Louisiana, USA at the site of the former Woolworth Department Store in the 1000 Block of Canal Street. The mixed-use development, led by Florida-based Hard Rock International, marks the latest signal that the mid-Canal Street corridor is gaining commercial traction with big-name brands and retailers, largely buoyed by an interest in Downtown Living and as New Orleans continues to thrive as a tourist destination.

Copyright © 2018 Pinnacle Infotech, Inc.

Global Leader in BIM Serviceswww.pinnaclecad.com

Hard Rock Hotel

[Hotel]

New Orleans,Louisiana, USA

Scope of Work

Our scope of work for the project included: 1. 3D Model Creation of Sheet Metal (Ducts, Associated Fittings & Equipment) & Mechanical Piping @ LOD 400 as per design document & project specification2. BIM Coordination - Updating the model to resolve clashes, as suggested by the client, Reviewed Interdisciplinary Coordination, Floor to Floor Alignment & Continuation to other areas3. Preparation of Detail Shop Drawings with annotation, dimension and tagging

BIM Start Date: January, 2018

40,000 sq ftProject Area:

Average Team Size: 5 Engineers

BIM End Date: April, 2018

Challenges & Solutions

A. Challenge - Design Mismatch - 1. Diffuser Inlet Size & Duct Size are not matching between design plan and mechanical schedule2. Stair Pressurization riser duct size mismatch between 1st, 2nd Floor & 3rd Floor - In the 1st Floor duct size - 26x10, in the 2nd Floor duct size - 16x16 and in the 3rd Floor, duct size - 28x12 Solution - Requested client to review and suggest on the sameB. Challenge - Coordination Problem - 1. As per FCU generic model extracted from Revit model, SA duct was coming from top outlet of FCU and clashing with SLAB due to space constrain Solution - Requested client to review the reference drawing and suggest on the samec. Challenge - Missing Information1. In third floor plan, there was no water connection for FCUs2. Moreover, routing for condensate drain pipe was not found Solution - Requested client to provide the missing information

Trades Covered: Mechanical(Sheet Metal & MP)

Software Used: Revit Fabrication Part 2017

LOD: 400

Architect: HARRY BAKER SMITH ARCHITECTS II A PROFESSIONAL LLC.

1. Using BIM, the Pinnacle team searched and selected alternatives that meet project requirements, discovering and solving issues at an early stage, saving time, eliminating rework, improving quality and allowing everyone on the project team to be successful2. The effective application of BIM reaped benefits throughout the life cycle of the project 3. Pinnacle’s approach to virtual construction with BIM created the opportunity to identify problems earlier in the building process and facilitate BIM team to find better ways to communicate ideas, reducing errors and improving

Pinnacle's Value Addition

Consulting Engineers: HOWARD MOSES, P.E.MOSES ENGINEERS, LLC.

MEP Sub Contractor: Regional Mechanical Services, LLC*

Owner/Developer: Kailas Companies, LLC.

Structural Engineer: James Heaslip and Walter Zehner

productivity4. Newforma was used to streamline project communication5. BIM ensured that the information related to design and construction activities flow seamlessly among all stakeholders involved in the project through simple exchange of models and data, so that team members can ensure accurate and complete information. This delivered a range of benefits, including simplified product selection, robust design solutions, automatic clash avoidance and effective team work

Architectural BIM Model

Clash Coordination