growing datacentres in ireland and possible implications · cloud computing artificial intelligence...
TRANSCRIPT
@ESRIDublin #ESRIevents#ESRIpublications www.esri.ie
Growing Datacentres in Ireland and Possible Implications
DATE17/05/2019
VENUEESRI, Dublin, Ireland
AUTHORSDesta Fitiwi
[email protected] LynchJohn Curtis
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie2
This work has emanated from research conducted with the financial support of Science Foundation Irelandunder the SFI Strategic Partnership Programme Grant Number SFI/15/SPP/E3125. The opinions, findings andconclusions or recommendations expressed in this material are those of the authors and do not necessarilyreflect the views of the Science Foundation Ireland. This work has also benefited from the valuable supportof EirGrid, the Transmission System Operator in the Republic of Ireland. Hence, we would like to greatlyacknowledge EirGrid’s contributions in providing data and insights for this work.
www.esipp.ie
Acknowledgments
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie3
Tsunami of Data
• “Always-on” digital boom.
• Data traffic doubling every 4 years (CISCO, 2018).
• A “tsunami of data” created at a pace never seen before.➢ 600 x 1021 bytes of data traffic by 2020 (CISCO, 2018).
➢ Yet, anticipated to soon hit the Yottabyte range (1024).
• Key drivers➢ Online video streaming
➢ Internet-of-Things (IoTs)
➢ Blockchain
➢ Cloud computing
➢ Artificial intelligence
Sou
rce:
htt
ps:
//w
ww
.fo
rsm
arth
ote
ls.c
om
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie4
Datacentre Investments and Hotspots
• Massive investments in datacentres required.
• Ireland one of the hotspots in the world. ➢ Poised to become the datacentre capital of Europe.
➢ €9 Billion investments in the coming three years (SEAI, 2017).
• Currently ~ 500 MVA of datacentre capacity in Ireland.➢ Enough to power up about 400,000 Irish homes.
• Yet, anticipated to reach 1500 MVA by 2025 (EirGrid, 2017).
• Projections for 2030 range between 350 and 1450 MVA increase (EirGrid, 2017).
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie5
Anticipated Datacentre Growth in IE
In 2016, Ireland’s housing stock had 2,003,645 houses and apartments (CSO, 2016)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2018 2020 2022 2024 2026 2028 2030
Ca
pa
city
(M
VA
)
= 715,000 Irish homes
= 1,638,000 Irish homes
(EirGrid, 2017)
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie
Modelling Approach
Input OutputTools and Methods
Electricity Network and Generation INvEstment
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie7
Data
• Irish transmission system data, provided by EirGrid.
• ≥ 110 kV voltage level (plus generator nodes).
• 676 transmission nodes
• 900 transmission lines and transformers,
• 174 generators, …
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie8
Key Assumptions (1/2)
• Decentralized RESdevelopment portfolio
• 211 possible connection nodes
• New thermal power plants in brown fields.
• Replacing existing older power generation units with more efficient CCGTs.
• Or, with carbon capture and storage as an option.
• 55% vRES integration target by 2030.
• System Non-Synchronous Penetration (SNSP) set to 75%.
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie9
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2018 2020 2022 2024 2026 2028 2030
Ca
pa
city
(M
VA
)
= 715,000 Irish homes
= 1,638,000 Irish homes
Key Assumptions (2/2)
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie10
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2018 2020 2022 2024 2026 2028 2030
Ca
pa
city
(M
VA
)
= 715,000 Irish homes
= 1,638,000 Irish homes
Key Assumptions (2/2)
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie11
Implications of Growing Datacentre (1/5)
0
2
4
6
8
10
12
14
2017 2020 2025 2030
Frozen DC
Inst
alle
d c
apac
ity
(MW
)
Onshore wind Solar PV New CCGT Offshore wind
Frozen Datacentres
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie12
Implications of Growing Datacentre (2/5)
0
2
4
6
8
10
12
14
2017 2020 2025 2030
Growing DC
Inst
alle
d c
apac
ity
(MW
)
Onshore wind Solar PV New CCGT Offshore wind
25%
Growing Datacentres
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie13
Implications of Growing Datacentre (3/5)
• Datacentres => Massive grid investment needs
Frozen DCs Growing DCs
Number of transmission lines 19 23
Number of transformers 4 6
Total length of new lines (km) 145 200
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie14
Implications of Growing Datacentre (3/5)
• Datacentres => Massive grid investment needs
Frozen DCs Growing DCs
Number of transmission lines 19 23
Number of transformers 4 6
Total length of new lines (km) 145 200
38%
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie15
Implications of Growing Datacentre (4/5)
• Datacentres => Massive grid investment needs
• But optimally allocating some new DCs along the fibre optics corridor and adopting a decentralized renewable development.
• Substantially reduce network reinforcement needs.
Frozen DCs Growing DCs Distributed DCs
Number of transmission lines 19 23 23
Number of transformers 4 6 6
Total length of new lines (km) 145 200 170
38%
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie16
Implications of Growing Datacentre (4/5)
• Datacentres => Massive grid investment needs
• But optimally allocating some new DCs along the fibre optics corridor and adopting a decentralized renewable development.
• Substantially reduce network reinforcement needs.
Frozen DCs Growing DCs Distributed DCs
Number of transmission lines 19 23 23
Number of transformers 4 6 6
Total length of new lines (km) 145 200 170
38%17%
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie17
Implications of Growing Datacentre (5/5)
• ~ 24% increase in the system-wide NPV cost.
• ~ 14% increase in expected carbon emissions.
• ~ 18% increase in expected energy not served.
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie18
Summary
• The anticipated growth of datacentres by 2030 could lead to:
• Significant infrastructural challenges (supply and grid perspectives)
• Considerable increase in costs, average GHG emissions, involuntary load shedding, and grid expansion needs
• But these impacts can be alleviated by:• Encouraging investments in onsite power generation and storage
technologies.
• Adopting energy efficiency measures.
• Optimally allocating some datacentres in regional places (other than in and around Dublin)
@ESRIDublin #ESRIevents #ESRIpublications www.esri.ie19
Thank you for your attention!
This work has emanated from research conducted with the financial support of Science Foundation Irelandunder the SFI Strategic Partnership Programme Grant Number SFI/15/SPP/E3125. The opinions, findings andconclusions or recommendations expressed in this material are those of the authors and do not necessarilyreflect the views of the Science Foundation Ireland. This work has also benefited from the valuable supportof EirGrid, the Transmission System Operator in the Republic of Ireland. Hence, we would like to greatlyacknowledge EirGrid’s contributions in providing data and insights for this work.
www.esipp.ie