gauteng department of human settlements 17 march 2015
TRANSCRIPT
GAUTENG DEPARTMENT OF HUMAN SETTLEMENTS
17 MARCH 2015
CONTENT
1. Gauteng Department of Human Settlements Report
2. Reports for Metropolitan Municipalitiesa) Johannesburg metropolitan Municipalityb) Tshwane Metropolitan Municipalityc) Ekurhuleni Metropolitan Municipality
INTRODUCTION• The National Department of Human Settlements presented
Section 32 Reports to the Portfolio Committee on Human Settlements
• The Department and its Metropolitan Municipalities were found to be underperforming
• The Portfolio Committee invited the Department and its Metropolitan Municipalities to present the challenges relating to: – Delivery and expenditure on the Human Settlements Development
Grant (HSDG)– Delivery and expenditure on the Urban Settlements Development
Grant (USDG)– Performance on Social and Rental Housing– Performance Mining Towns– Delivery performance on rectification– Delivery performance on other milestones on the Operational
Expenditure Budget in support of the implementation of National and Provincial Housing Programmes (OPSCAP)
1. DELIVERY AND EXPENDITURE ON THE HSDG
Total Allocation 2014/15 R’000
HSDG 4 417 641
Total Expenditure as at 31 Dec 2014: Quarter 3 R’000
HSDG 4 417 641
EXPENDITURE 2 786 556
TOTAL BALANCE 1 631 085
Total Expenditure as at 12 Mar 2015 Jan 2015R’000
Feb 2015R’000
MarR’000
HSDG 4 417 641 4 417 641 4 417 641
EXPENDITURE 2 961 406 3 399 732 3 785 316
TOTAL BALANCE 1 456 235 1 017 909 632 325
DELIVERY AND EXPENDITURE ON HSDG [Cont.]
Annual Delivery Targets - Original Annual Delivery Targets - Revised Actual Performance as at 31 December 2014
% %
Sites Units/ Houses
Total Sites Units/ Houses
Total Sites Units/ Houses
Total Sites Units/ Houses
10 407 24 261 34 668 7 728 17 678 25 406 2 293 10 340 12 633 30% 71%
ACTUAL PERFORMANCE AS AT 12 MARCH 2015
Targets Achieved Work in Progress
Sites 7 728 2 534
Units/Houses 17 678 12 477
Completed Units awaiting Quality Assurance 1195
Wall plate/ Roof level 964
Foundation 680
CHALLENGES EXPERIENCED IN HSDG DELIVERY• Budget revision and revision of targets by 9262
housing opportunities due to expenditure on items that were not on the Business Plan like rectification of hailstorm damaged houses and asbestos assessment by R1,1 billion
• Regularization of expired and invalid contracts • For 2015/16 an allocation has been made for
emergencies and disasters will be referred to COGTA
• There will be no further assessment done for asbestos roofs
PERFORMANCE ON SOCIAL AND RENTAL HOUSING
•GPF is the delivery agent for the Department for affordable rental and Social housing •GPF was not included in the original approved departmental budget and got allocated during the budget revision process•For the new financial year provision has been made for GPF and allocation will be in terms of the approved 5 year strategic plan
Annual Delivery Targets - Original
Annual Delivery Targets - Revised
Actual Performance as at 31 Dec 2014
Actual Performance as at 12 March 2015
2 265 616 181 261
PERFORMANCE ON MINING TOWNS
PERFORMANCE ON MINING TOWNS
PERFORMANCE ON MINING TOWNS
PERFORMANCE ON MINING TOWNS
PERFORMANCE ON OTHER MILESTONES: OPSCAP
• OPSCAP used for shack fire disasters• Costs relating to rates and taxes• Security costs for completed houses and
hostels not yet handed over • Rental costs for regional offices• Legal costs incurred to prevent illegal
invasion, to obtain eviction orders• Lease costs for temporal residential units and
portable ablution facilities.
CONCLUSION• Our delivery model is underpinned by the connection
between all elements of the human settlements: – Delivery of Gauteng Human Settlements Mega Projects– Refining the finance model to suit our new trajectory– Capacity of the Province to be improved - Industry
specific qualifications– Strengthening the capacity of the PMO and Regions– Service Delivery Model will change to a teamwork approach – Integrated Planning (Intergovernmental Relations
Strengthened) – Explore models to incentivise private sector investment in
mega project– Unqualified Audit outcome
CONCLUSION
• Programmes to improve our delivery model will include
• Infill sites• Fully serviced sites• Employer assisted housing • Revised rental housing model • Social Housing Accelerated • CRU Improved Approach - Hybrid• Private Sector Partnerships • Urban Renewal• Revitalisation of mining towns
CONCLUSION
END
USDG PRESENTATION FOR EKURHULENI METROPOLITAN
MUNICIPALITY
13.03.15
FINANCIAL PERFORMANCE: FINANCIAL PERFORMANCE: CAPITAL BUDGET BREAKDOWNCAPITAL BUDGET BREAKDOWN
• The Ekurhuleni Metropolitan Municipality’s USDG Budget for the 2014/15 financial is 1 985 130 282, which includes the R 31 566 282 roll-over amount for the Human Settlement USDG.
• The total USDG expenditure as on the 06th of March 2015 is R 640 686 572 .• The expenditure represents 32.27% of the total budget for the 2014/15• The total expenditure plus commitments was R 695 061 768 • The expenditure plus commitments represents 35.01% of the budget• The unspent funds as on the 09th of March 2015 is R 1 235 768 514.
17
FINANCIAL PERFORMANCE: PER SERVICE/DEPARTMENTFINANCIAL PERFORMANCE: PER SERVICE/DEPARTMENT
18
Department Budget
Actual Expenditure
to Date 09/03/2015
Not Updated (Invoices Captured
and not paid as yet)
Expenditure Commitment
s on Venus (Stores
Orders, etc.)
Total Actual Expenditure + Commitments
on Venus (Stores Orders, etc.)
Total % Actual
spent vs Budget
Total % spent (with
commitment)
Unspent Funds
09/03/2015
Disaster & Emergency Management Services
46,336,000
12,749,716 -
- 12,749,716 27.52% 27.52%
33,586,284
Economic Development
29,200,000
3,784,628 -
288,596 4,073,225 12.96% 13.95%
25,126,775
EMPD 10,916,066
5,428,545 -
- 5,428,545
5,487,521
Energy 272,750,000
68,383,210 732,100
11,963,494 81,078,804 25.07% 29.73%
191,671,196
Environmental Resources Management
1,500,000
125,710 -
371,228 496,938 8.38% 33.13%
1,003,062
Health & Social Development
56,750,000
27,768,914 -
1,553,469 29,322,382 48.93% 51.67%
27,427,618
Human Settlements 322,942,435
92,979,416 166,410
14,182,271 107,328,096 28.79% 33.23%
215,614,339
Real Estate 29,546,314
8,036,175 -
3,257,586 11,293,761 27.20% 38.22%
18,252,553
Roads and Stormwater 285,450,000
61,716,610 -
- 61,716,610 21.62% 21.62%
223,733,390
SRAC 32,476,084
9,039,565 -
179,498 9,219,063 27.83% 28.39%
23,257,021
Transport 257,901,244
77,946,081 -
- 77,946,081 30.22% 30.22%
179,955,163
Department Budget
Actual Expenditure
to Date 09/03/2015
Not Updated (Invoices Captured
and not paid as yet)
Expenditure Commitments
on Venus (Stores
Orders, etc.)
Total Actual Expenditure + Commitments
on Venus (Stores Orders, etc.)
Total % Actual
spent vs Budget
Total % spent (with
commitment)
Unspent Funds
09/03/2015
Waste Management 4,600,000
136,500 -
20,382 156,882 2.97% 3.41%
4,443,118
Water & Sanitation 314,344,991
130,414,547 341,568
288,808 131,044,923 41.49% 41.69%
183,300,068
Erwat - Wastewater treatment (1326202566030)
50,000,000
50,000,000 -
- 50,000,000 100.00% 100.00% -
Chemical Toilets (1326202566031)
184,550,866
80,938,555
3,576,293
17,453,495 101,968,342 43.86% 55.25%
82,582,524.12
Human Settlement USDG (1450202566037)
31,566,282
11,238,401 -
- 11,238,401 35.60% 35.60%
20,327,881.36
Human Settlement USDG (1450302566037)
54,300,000 - -
- - 0.00% 0.00%
54,300,000.00
Total 1,985,130,282
640,686,572
4,816,370
49,558,827
695,061,768 32.27% 35.01%
1,235,768,514
20
CHALLENGES & REMEDIAL MEASURESCHALLENGES & REMEDIAL MEASURESThe Municipality has experience challenges that resulted in poor expenditure including amongst others as follows: •Review of the City’s procurement processes and introduction of new committees which slowed down the finalization of bids•Loss of technical capacity, which includes engineers and project managers•The Institutional Review is in the process of being approved by Council, and this will result in the augmentation of the organisational structure with appropriate levels of technical skills
Remedial Measures•The EPMO set up for the Metro is complete with all top management positions filled. The set up of departmental PMO’s has commenced with more than 8 departmental PMO’s already operational.•EMM is working on implementing a project management system that will assist in planning and monitoring of projects•EMM has sourced external service provider to carry out an Implementing Agent Role for the substantial part of the Infrastructure Building Programme.
Non Financial Performance for Human Settlements - USDG funded projects
Project name Non financial progress
Acquisition of Land for New Human Settlements
16,200,000
The following specialist studies have been completed: Phase1 Geotechnical report, Traffic Impact Assessment based on 2500 dwelling units, EIA was submitted with GDARD: record of decision is available, Feasibility report for intermodal transport facility. The Private Property Acquisition Form was signed by the Human Settlements HOD on the 24 June 2014 and submitted to Real Estate Department. On the 05 August 2014, Transnet confirmed Board approval for the acquisition. The valuation of the property was completed on the 29 September 2014. The Deed of Sale has been commented upon by EMM Corporate Legal Services on the 5 of December 2014 and is ready to be signed. The Council Item has been prepared for Council approval. The budget was adjusted from R7 million to R16,2 million.
Ptn 32 Modderfontein76 IR, Alliance EXT 2
32,000,000
A guarantee has been issued in this respect and the spending is in the suspense account a journal entry is being prepared against this vote to close the matter
Acquisition of Portion 402 of the Farm Driefontein 85 IR, ERPM VILLAGE
77,030,000
Matter finalized. Property registered in favour of EMM
Project Name Budget Non financial progress report
Servicing of stands in Balmoral and alliance settlements
35,000,000 The two projects will be used as pilot projects of the Department in provision of the essential services in the creation of human settlements. The package will include provision of roads and storm water infrastructure, electrification, and water and sanitation networks for Balmoral and alliance settlements. The DBSA technical capacity will be utilized for the designs in the current financial year and implementation in 2015/16. The development project plans and issue of IPWs is currently being undertaken
Delville and fire station Social Housing Project installation of services and construction of buildings
54,000,000
Awaiting SLA’s to be signed with DBSA so that can proceed with design and construction project management.
Human Settlements, Pre Planning Fees
44,826,345
Milestones were not met due the capping of the contract value that has been allocated to the three Professional Service Providers. For pre-planning payments are made when certain milestones have been achieved and most the milestone will be achieved in the fourth quarter of the financial year. To expedite the approval processes HS dept. had number of meetings with City Planning and other relevant departments
Project name Budget Non financial progress report
Refurbishment of Rental Property
37,212,435
99% complete, ahead of target
Wattville-Actonville Urban Renewal Project
2,824,000
Milestones were not met due the capping of the contract value that has been allocated to the three Professional Service Providers. Awaiting SLA’s to be signed with DBSA so that the dept. can proceed with detailed planning and design
Katorus Urban Renewal Project
2,500,000
Milestones were not met due the capping of the contract value that has been allocated to the three Professional Service Providers. Awaiting SLA’s to be signed with DBSA so that the dept. can proceed with detailed planning and design
Leeupoort Development (Bulk Infrastructure)
80,000,000
Commencement of the project delayed. Public participation process and signing of service level agreements with services departments are underway to enable the city to meet the section 33 requirements and commence with installation of bulk
Grants alignment – 2011 to 2015Project Name Sites Units
Palm Ridge 6146 1299
Alra Park 290 600
Eden Park West and Ext 1 860 782
Etwatwa 34 1461 1423
Etwatwa 37 1395 2100
Mayfield 1 353 600
Kwa Thema 3 856 1247
Vlakfontein Ptn 36 1620 600
Payneville 1 115 600
Moleleki 1 & 2 75 280
24
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
EMM HSDG PROGRAMME OVERVIEW
25
Name of Project Total No.
Units Per
Project
Units
Delivered
2013/14
Balance
of Project
No. Units
Budgeted as per
GP DHS APP
2014/15
Budgeted Units
GP DHS APP
2014/15 as %
of Balance of
ProjectMagagula Heights 313 12 301 0 0%Moleleki Ext 1 & 2 746 0 746 0 0%Alra Park Ext 3 674 100 574 100 17%Etwatwa Ext 35 334 0 334 75 22%Eden Park West & Ext 1 693 0 693 130 19%
TOTAL 2 760 112 2 648 305 12%
The table above, illustrates that only a budget of 12% of active projects were considered by the GP DoHS. The funds (approximately 305 x R102, 000 per unit = R31.1 million) are yet to be made available to the EMM, despite the first quarter of the current financial year gone.
2 455 unfunded units that can be delivered – only 305 are funded
The listed projects are being serviced by the EMM Water & Sanitation Department and can be made available for construction, subject to funding availability:
26
Project Number of Stands
Payneville Ext 1
1 115
Etwatwa Ext 18
762
Etwatwa Ext 19 320
Langaville Ext 10 1 561
Masechaba View Ext 4 252
Cool breeze 50
TOTAL 4 060
Should funding be made available, the EMM would be able to expand its performance beyond the five (5) projects that are currently active.
EMM HSDG PROGRAMME OVERVIEW
END
USDG Progress Report for Quarter 2USDG Progress Report for Quarter 2CITY OF TSHWANECITY OF TSHWANE
FINANCIAL PERFORMANCE
Budget Allocation
Allocation : R 1 469 450 000.00 Expenditure as at 31/12/2014 : R 528 021 782.00
35.9 % overall spent as at 31 December 2014
USDG 2014/15
30
Strategic Departments Approved Budget 2014/15
Roll over from 2013/14
Total per department
% of allocatio
nHousing and Human Settlement
837 804 764 23 853 359 861 658 123 56.90%
Electricity 260 000 000 260 000 000 17.17%
Water and Sanitation 248 046 236 4 580 788 252 627 024 16.68%
Transport 123 599 000 123 599 000 8.16%
Cemeteries in Tshwane North Region
16 395 610 16 395 610 1.08%
Total USDG 2014/15 1 469 450 000 44 829 757 1 514 279 757
USDG 2014/15
31
FINANCIAL PERFORMANCE: HOUSING AND HUMAN SETTLEMENTS
Project Name Project Budget 2014/15 Expenditure % of expenditure
Roads & Storm water - Low Cost Housing 120 759 904.51 - 0%
Sewerage - Low Cost Housing 318 649 957.33 70 728 064.81 22%
Project Linked Housing - Water Provision 289 047 863.25 40 215 619.39 14%
Acquisition of land 109 847 039.00 29 952 000.00 28%
TOTAL HOUSING 837 804 764.00 140 895 684.20 17%
32
FINANCIAL PERFORMANCE: WATER AND SANITATION
33
Project Name Budget 2014/15 expenditure % of expenditure
Replacement, Upgrade and Construct Waste Water Treatment Works Facilities
44 000 000.00 40 425 322.80 92%
Refurbishment of Water Networks and Backlog Eradication
177 546 236.00
91 186 548.27 51%
Bulk Sewer Supply- Franspoort 1 500 000.00 -0%
Total USDG Service Infrastructure
223 046 236.00 131 611 871.07 59%
FINANCIAL PERFORMANCE: ELECTRICITY
34
Project Name Project number
Budget 2014/15 expenditure % of expenditure
Electricity for All 710178 260 000 000.00 159 886 887.65 61%
Tshwane Public Lighting Program
710556 25 000 000.00 5 003 031.56 20%
Total USDG Electricity
285 000 000.00 164 889 919.21 58%
FINANCIAL PERFORMANCE: TRANSPORT
35
Project Name Budget 2014/15 expenditure % of expenditure
Internal Roads: Northern Areas 97 599 000.00 65 272 303.58 67%
Flooding Backlogs: Sosh & Winterveldt Area
26 000 000.00 25 352 003.82 98%
Total USDG Transport
123 599 000.00 90 624 307.40 73%
FINANCIAL PERFORMANCE: FINANCIAL PERFORMANCE: 28 February 201528 February 2015
36
Allocation R1,469,450,000.00
Expenditure to date R630,973,302.00
Which is 43% of 14/15 USDG allocation as at 28.02.2015
FINANCIAL PERFORMANCE: FINANCIAL PERFORMANCE: PER DEPARTMENT AS AT 28 FEBRUARY 2015PER DEPARTMENT AS AT 28 FEBRUARY 2015
Department Approved Budget 2014/15
Projected expenditure
at Q2
Expenditure at 28 Feb 2015
% of expenditure
Housing and Human Settlements
837 804 764 292 645 447 220 972 206 27%
Electricity 285 000 000 142 499 994 205 972 206 72%
Water and Sanitation
223 046 236 127 923 114 151 899 664 68%
Transport 123 599 000 123 599 000 120 403 759 97%
Total USDG 1 469 450 000 686 667 555 630 973 302 43%
37
38
CHALLENGES
• Issues with Land Claims and re-opening of land claims process
• Delays with finalization of LAAs
• Land invasion
• Disruptions on site by local labourers & Political interference
• Huge boulders underground requiring blasting
39
MITIGATION PLAN
• Regular Meetings with Land Claims Commissioner, Province and land claimants
• Final LAA’s submitted to the City in February 2015
• Eviction of people illegally occupying land
• Political Intervention
• Increase resources on site
40
END
CITY OF JOHANNESBURGCITY OF JOHANNESBURG
13 March 201513 March 2015
2014/15 QUARTER 2
FINANCIAL PERFORMANCE & FORECAST TO JUNE’15FINANCIAL PERFORMANCE & FORECAST TO JUNE’15
Department / Budget YTDCommit
-Total % Quarter
Quarter
Total % of
Entity 2014/15 Exp ments Exp Spent 3 4 CostBudge
t R'000 R'000 R'000 R'000 R'000 R'000 R'000 Community Development
23 300 1 523 20 168 21 691 93% 1 609 - 23 300
100%
Health 60 000 422 - 422 1% 24 700 34 878 60 000
100%
Housing 792 862 92 961 9 680 102 641 13% 251 670 438 551 792 862
100%
City Power 90 000 25 403 5 760 31 163 35% 33 534 25 303 90 000
100%
Johannesburg Water
222 411 71 822 - 71 822 32% 75 072 75 517 222 411
100%
Pikitup 14 000 437 - 437 3% 3 563 10 000 14 000
100%
Jhb Roads Agency
349 027 57 366 4 558 61 924 18% 143 115 143 988 349 027
100%
Jhb City Parks and Zoo
54 000 15 129 24 254 39 383 73% 14 617 - 54 000
100%
Jhb Development Agency
69 589 18 706 - 18 706 27% 20 860 30 023 69 589
100%
JOSHCO 20 000 2 699 - 2 699 13% 4 000 13 301 20 000
100%
Total USDG: 1 695 189 286 469 64 420 350 888 21% 572 740 771 561 1 695 189
100%
42
43
FINANCIAL PERFORMANCE PER SERVICE DELIVERY AREAFINANCIAL PERFORMANCE PER SERVICE DELIVERY AREA
Service Delivery Area
BudgetActual
Expenditure
Commitments
Total Expenditure
Percentage Spent
R'000 R'000 R'000 R'000
Land Acquisition 40
000
– 9 680 9 680 24%
Housing Internal Services
835 362
114 366
– 114 366 14%
Roads and Stormwater
349 727
57 366
4 558 61 924 18%
Water 89
367
901 – 901 1%
Sanitation 133
044 70
921 – 70 921 53%
Electricity 90
000 25
403 5 760 31 163 35%
Waste Management
14 229
437
– 437 3%
Social Amenities 143
460 17
074 44 422 61 496 43%
TOTAL: 1 695
189 286
469 64 420 350 888 21%
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000LAND ACQUISITION
Land Purchases
N/APurchase Univille land and Rabie Ridge Land
To date CoJ has settled with 23 farmers( Lufhereng ), with
13 settlements still in dispute/ unresolved. CoJ
Housing and Group Legal aim to finalise all matters by 01
April 2015. CoJ is in process of negotiations with the
owner of Unaville land and Rabie Ridge land. offer to
purchase (done )
40 000 9 680
44
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000HOUSING: INTERNAL SERVICES
Devland Ext 1,27,30,31&33 Region D
Construction of 7,2km of surfaced roads and 0.84km stormwate drainage system, installation of water and sewer to 252 stands and construction of 15ml bulk reservoir
Construction of roads and stormwater in Ext 1/30/31 is at 100% completion because the works was carried over from 2013/14 fin year, Construction of JAN de Nicker is at 90% completion also carried over from 2013/14 fin year, Internal water, sewer and reservoir for Lindelani commenced in Nov 2014. The budget for this project will be increased by R38.3 m in the adjustment budget, to accelerate this project.
130 000 10 647
Diepsloot Redevelopment Renewal RDP Flats DIEPSLOOT WES
Region A
Complete Roads & stormwater , Link Water and sewer including the internal services for phase 1.
Water, Sewer, roads and stormwater for Ph1 is 98% complete. The sewer pump station upgrade is at construction phase and will be completed in March 2015.
50 000 23 191
45
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
HOUSING: INTERNAL SERVICES (CONT.)
Elias Motsoaledi Region D Construction of Bulk and Internal Roads Including Curlver Bridge New Bulk
The site camp has been established. The first batch of material was delivered in November. The contractor has started clearing on site. The tender for construction of a bridge was advertised in December. The budget will be fully spent by June 2015.
20 000 287
Fleurhof Mixed Development (Bulk and internal infrastructure) New Bulk Infrastructure FLEURHOF
Region C Electricity Sub-Station including 4 Km of road
Construction of Electricity Sub-Station is continuing from 2013/14 fin year, progress at 50%. Electrification of additional 1000 Houses is underway. Construction of remainder of Fleurhof Drive, to Meadowlands, as well as bulk and internal services, bulk sewer outfall and stormwater canal to Ext. 18 - 21 all commenced in August 2014 and are due for completion March - June 2015. The budget for this project will be increased by R76 m in the adjustment budget to accelerate this project.
6 500( USDG)83 500 (COJ) 8 688
Klipspruit/Kliptown Ext 11 Bulk Services New Bulk Infrastructure KLIPSPRUIT EXT.11
Region D Construction of Bulk and Internal Roads
Construction of bulk stormwater and access road commenced in September 2014 and construction is at an advanced stage. The tender document for construction of roads and stormwater at Klipspruit Ext 11 and Klipspruit Ext7 are ready for advertisement. Construction is planned to commence beginning of the 3rd quarter. The total budget for the project will be adjusted by R20 m due to delayed start.
50 000 4 193
HOUSING: INTERNAL SERVICES (CONT.)Lehae Ext 1 Bulk Water Line New Bulk Infrastructure LEHAE EXT.1
RegionG 88/11KV Substation and electrification of 1518 houses
This project is at construction phase and is well on track to fully spend the budget by June 2015.
114 027 18 755
Lufhereng Mixed Development (Bulk Infrastructure Roads, Stormwater Management Systems, Sewer & Water for 24 000 houses) New Bulk Infrastructure DOORNKOP EXT.1 C Regional
Region D Construction of various bulk, link and internal services
CoJ appointed a Turnkey Developer for installation of water, sewer, roads and stormwater services for Lufhereng Ext 5. Overall progress for this project is 28%. The construction of electrical sub-station will start in February 2015. This project requires an additional R45 m, which cannot be granted due to financial constraints.
156 000 15 108
HOUSING: INTERNAL SERVICES (CONT.)
Nancefield Station Precinct Development New Precinct Redevelopment KLIPSPRUIT
Klipspruit 100% Completion roads & stormwater
Construction of Phase 2 is progressing well and is 60% complete. The designs for Phase 3 were approved in October 2014, currently planning for the project is underway. The project is on schedule to fully spend the budget by June 2015.
60 000 10 671
Project Name
Areas &No of
Households benefitting
Annual Target
outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000
WATERBasic Water Service New Basic Water and Sewer Services ORANGE FARM EXT.8 G Regional
Lawley Ext 2, Lawley station, Tshepisong West, Randleases,
N/AProject in construction phase and is on track with the construction programme.
30 000 –
Ennerdale: Lenasia high level Reservoir New Reserviors LENASIA EXT.1
Lenasia Ext 1 Increase water capacity
Project in design phase. The budget will be adjusted by R3.5 m in the adjustment to accommodate the revised programme.
10 000 –
Ennerdale: Orange Farm high level reservior New Reserviors ORANGE FARM
Orange Farm Increase water capacity
Project in design phase. The budget will be reduced by R11.5 m to accommodate the revised programme.
20 000 854
Roodepoort/Diepsloot: Diepsloot Reservoir New Reserviors DIEPSLOOT WES
Diepsloot Land acquisition
The budget for this project will be adjusted by R16.9 m in the adjustment budget to accommodate only the planning for this project.
25 411 –
49
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000SANITATION
Bushkoppies Works: Replacement of Aerotion System Renewal Bulk Waste Water DEVLAND
Soweto Increase treatment capacity
Project in construction phase and is on track with the construction programme, progress at 55%. This project will be increased by R7.2 m in the adjustment budget.
24 091 16
Driefontein Works: Extension New Bulk Waste Water COSMO CITY EXT.2 C Regional
Roodepoort Build reators, balancing tank and head of works
Project in construction phase and is on track with the construction programme, progress at 87%. This project will be increased by R14.8 m in the adjustment budget.
26 000 23 370
50
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
SANITATION (CONT.)
Northern Works: desludge Dam 01 and 02 Renewal Bulk Waste Water DIEPSLOOT WES EXT.5 A Regional
Diepsloot To reduce the rate of future sludge ingress
Project in construction phase and is on track with the construction programme, progress at 6%. This project will be increased by R10.8 m in the adjustment budget.
20 000 958
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress Budget Expenditur
e
ROADS & STORMWATER
BRID 05 - Naledi/Protea Bridge (Between Wards 20 and 14). New Bridges (Pedestrian and Vehicles) NALEDI
Areas surrounding the Naledi Train Station
100%(60% of bridge)
Total expenditure to date is R 15 698 948.81 against a budget of R20 million (79.8%). Additional funds have been requested in the adjusted budget. Expected expenditure R38million by the end of June 2015.
20 000 16 181
52
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
ROADS & STORMWATER (CONT.)MISCL - Emergency, Critical and Urgent Depot Stormwater Improvements. New Stormwater Management Projects JOHANNESBURCity Wide
Various % of Project completed as per project plan
Projects are at various stages:ten projects at consultant procurement stagesixteen at contractor procurement stage, three projects at construction stage.
40 000 8 220
MISCL - Gravel Roads: Bram Fischerville. New Roads: Construction and Upgrades BRAM FISCHERVILLE
Bram Fischerville
% of Project completed as per project plan
New contractor has been appointed and the old contractor is proceeding with work.Consultant's tender for phase 2 has been advertised and will be fast tracked.
35 000 5 346
53
DETAILED PROJECT DETAILED PROJECT PROGESSPROGESS
ROADS & STORMWATER (CONT.)MISCL - Gravel Roads: Diepsloot. New Roads: Construction and Upgrades DIEPSLOOT WEST EXT.3
Diepsloot% of Project completed as per project plan
The new contractor has been appoint ans site establishment is complete, the old contractor is proceeding with work. Consultant's tender for phase 2 tenders closed on 18 December 2014.
46 060 5 794
MISCL - Gravel Roads: Doornkop/Thulani. New Roads: Construction and Upgrades DOORNKOP
Doornkop / Thulani
% of Project completed as per project plan
Appointment of contractor is at evaluation stage and process will be fast tracked.Consultant's tender Bid specification was approved and the tender will be re-advertised in January 2015.It is anticipated that the expenditure to end of June 2015 will be R9.5 million. The budget has been adjusted accordingly.
16 100 4 458
54
DETAILED PROJECT DETAILED PROJECT PROGESSPROGESS
ROADS & STORMWATER (CONT.)
MISCL - Tarring of Gravel Roads: Orange Farm and Surrounding Areas.
Orange Farm% of Project completed as per project plan
The contractor has been appointed and site establishment is complete, the old contractor is executing work Consultant's tender for phase 2 is at adjudication and evaluation stage. It is anticipated that with two contractors on site simultaneously the expenditure by the end of June 2015 will be R39.34 millon. The budget has been adjusted accordingly.
47 340 4 916
55
DETAILED PROJECT DETAILED PROJECT PROGESSPROGESS
ROADS & STORMWATER (CONT.)
MISCL - Gravel Roads: Tshepisong. New Roads: Construction and Upgrades TSHEPISONG
Tshepisong% of Project completed as per project plan
The new contractor has been appointed and site establishment is arranged for January 2015, the old contractor is proceeding with work. Consultant's tender for phase 2 - Bid spec document has been approved. It is anticipated that with two contractors on site simultaneously that the expenditure by the end of June 2015 will be R28 million. The budget will be adjusted acordingly.
20 000 8 840
RNP003_Westlake Road Extension New Roads: Construction and Upgrades RAND LEASES EXT.1
Various% of Project completed as per project plan
City of Johannesburg (Housing) is implementiing the project on behalf of JRA.This project is jointly funded by USDG ans CoJ. CoJ funding will only be utilised this financial year. The expencted expenditure is R0.00 and the budget has been adjusted accordingly.
10 000 –
56
DETAILED PROJECT DETAILED PROJECT PROGESSPROGESS
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000
ELECTRICITY
Lufhereng Substation. Establish new 88/11 kV sub station. New Bulk Infrastructure LUFHERENG
Lufhereng Development
Substation Yard,Switching Station, Power Transformer, auxilary equipments
Construction material has been ordered. Project is under construction and is a continuation from last financial year. This project is on track to fully utilise the budget by June 2015.
60 000 12 968
57
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
Project Name
Areas &No of
Households benefitting
Annual Target outputs
Non-Financial Actual Progress
Budget
R’000
Expendi-ture
R’000
WASTE MANAGEMENT
5 Composting Organic Waste New Plant and Equipment ORANGE FARM EXT.8 City Wide
Citywide Complete 5 composting plants
The whole budget will be re-allocated in the adjustment budget because composting plants are no longer a strategic goal for Pikitup. The funds will be re-directed to Garden Sites, Kya Sands Landfill Site and Upgrading of Facilities.
13 500 –
58
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
59
CHALLENGES & REMEDIAL MEASURESCHALLENGES & REMEDIAL MEASURES
KEY CHALLENGES REMEDIAL MEASURES Procurement delays. Use of budget adjustment period to
reallocate funds to over-performing projects.
Lengthy land acquisition processes. Improvements sought from Dept. / Entities in respect of capital planning.
Capital planning. Concerted effort by Dept. / Entities to plan projects over the medium term to eliminate the hockey stick spending pattern.
Name of Informal
Settlement
Service provided
No of Househol
ds to benefit
Annual Target
2014/15
Actual Progress1 April
2014 to 31 December
2014
Budget Expenditure
INFORMAL SETTLEMENT UPGRADING
60
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
Project NameAnnual Target
2014/15
Number of title deeds
issued1 June 2014 to 31 December
2014
Budget Expenditure
TITLE DEEDS ISSUED
3750 791 ( Houses delivered 1800) - -
61
DETAILED PROJECT PROGESSDETAILED PROJECT PROGESS
USDG – Housing Internal Services: Project Name
2014/2015R 000
HSDG – Top Structure: Project Name
2014/2015
Lehae 114 027 Lehae 40 300
Fleurhof 90 000 Fleurhof 70 000
Lufhereng 156 000 Lufhereng 23 000
Diepsloot Riverside Development 50 000Diepsloot Riverside Development
18 000
Elias Motsoaledi 20 000 Elias Motsoaledi46 000
Greater Kliptown 50 000 Greater Kliptown 56 000
South Hill 56 335 South Hill 22 000
Devland Ext 130 000 Devland Ext 50 300
62
LINK BETWEEN USDG & HSDGLINK BETWEEN USDG & HSDG
Sustainability
• The 2014/15 Repairs and Maintenance provision represents more than 9% of the total expenditure.
• The following Table is a Consolidation of all Expenditure Associated with Repairs & Maintenance.
63
Sustainability
64