gapp final report doc

Click here to load reader

Upload: nathaniel-r-gant-eit

Post on 08-Jan-2017

77 views

Category:

Documents


0 download

TRANSCRIPT

MORGAN STATE UNIVERSITYNEW RESIDENTIAL FACILITY

May 11, 2016

Project Management PlanGAPPQuality Driven Professionals.

TO: Dr. Tridip K. Bardhan, PhD, CMfgE, CENG Facility PlannerMorgan State University1700 East Cold Spring LaneBaltimore, Maryland 21251

FROM: Nathaniel R. Gant, P.E., PMP

CC:Jamaal Allen, P.E.Krystal Payton, LEED AP, AIABashan Prah, P.E.

DATE:May 11, 2016

SUBJECT:Technical and Cost ProposalArchitectural and Engineering Services for the New Residence FacilityGAPP Job No.: 16-001

Dear Dr. Bardhan:

GAPP Construction is pleased to submit a detailed project management plan, including scope of work, man-hour breakdown and cost proposal, for Architectural and Engineering Services for a New Residence Facility at Morgan State University. The detailed scope of services and fee in the amount of $1,742,302.00 (excluding construction cost and crashing) are attached. GAPP projects Morgan State to have a positive cash flow of approximately $682,245.13 (non-crashed) at payback period of two years after construction; this simple projection excludes the cost of construction and schedule crashing for the project. GAPP assumes MSU will independently negotiate advertisement, bidding, and construction.

If you have any questions or require additional information, please do not hesitate to contact me at (410) 600-7071. We appreciate the opportunity to provide our services and to continue working with you.

Very Respectfully,

GAPP, INC.

Nathaniel R. Gant, P.E., PMPProject Manager, GAPP Table of Contents

COVER PAGE

PROPOSAL MEMO

TABLE OF CONTENTS (page iii)

PROJECT SUMMARY (page 1)

PROJECT MANAGEMENT PLAN OVERVIEW

Scope Management Plan (page 2)Schedule Management Plan (page 20)Cost Management Plan (page 22)Human Resources Plan (page 24)Communication Management Plan (page 25)Quality Management Plan (page 27)Risk Management Plan (page 28)

ATTACHMENTS

Attachment A Limits of Survey (page 29)

Attachment B Resources / Manpower Needed (page30)

Attachment C Labor Estimate (page 31)

Attachment D Fees (page 32)

Attachment E CPM Chart (page 34)

Attachment F Calcs & Misc. (page 35)

GAPPQuality Driven Professionals. Page40

729 South President StreetBaltimore, Maryland Office: (410) 600-7070www.gapp.comFax: (410) 600-9090

Project Summary

Project Need and Purpose: Design new residential facility at Morgan State University in order to increase the size of the campus, improve safety on campus, and influence better retention rates.

Project Description: Design residential facility at Morgan State University near the CEBIS to grow Morgans physical presence, while create a safer campus environment, boosting the campuses image in the community and nation, provide educational opportunities for students, and influencing beneficial retention rates.

Summary Schedule: Milestone schedule:

Schedule ItemDays Until FinishEstimate Date

Start/ Proposal Presentation0May 11, 2016

NTP30June 22, 2016

Kickoff Meeting 44July 11, 2016

30% Plan Submittal166December 28, 2017

30% Review Meeting180January 17, 2017

65% Plan Submittal194October 18, 2017

65% Review Meeting390November 7, 2017

100% Plan Submittal404August 8, 2018

100% Review Meeting*600August 28, 2018

End