Ganda ERP Project |

ERP Project Status Reportfor CFCFebruary 2014

Ganda ERP Project |

Current Progress and Achievements

2

• CG and SAG ERP go live on 01-Jan-2014 including Purchasing, Inventory, sales, Distribution & FG Warehouse, Production and Finance & Accounting.

• CG ERP Jan-2014 accounting period still in Month-End closing process, most of sub-ledger (AP, AR, NM, FA) and GL Accounts are balanced, now is doing Cost Related Voucher adjustment and final checking.

• SAG ERP Jan-2014 accounting period still in Month-End closing process, most of sub-ledger (AP, AR, NM, FA) and GL Accounts are balanced, now is doing cost value check and fine tune.

• All of CFC ERP Customization requirement have been collected and now is under Customization Spec Development and Programming

• All of MFG Modules customization spec have been confirmed and near 60% customization program (Total around 2200 Hrs, Finished around 1200 Hrs)have been complete and under internal testing.

• All of MFG Reports Requirement have been confirmed on Feb-2014 and those customization specs will be finished before 16-Mar-2014.

• All of FIN customization have been collected and confirmed, except Dual currency solution.

Ganda ERP Project |

ERP Implementation Schedule for Whole Group

3

2013 2014

Oct Nov Dec Jan Feb Mar April May June July

CG, SAG, GAMA

CFC

SIN

MM

ANP

Preparation For Go-Live

Preparation For Go-Live

Go-Live

Parallel Run Go-Live

Go-LivePreparation For Go-LiveTraining

Training

Training Customize

Customize

Preparation For Go-Live

Preparation For Go-Live

Prepare PUR & FIN Go-Live

Prepare PUR & FIN Go-Live

Customize

Ganda ERP Project |

Nov-2013 Dec-2013 Jan-2014 Feb-2014 Mar-2014 Apr-2014 May-2014 June-2014 July-2014 Aug-2014

Purchasing

Inventory

Sales

Distribution / FG Warehouse

Production

Maintenance

Finance & Accounting

Human Resouce

Customization Basic Data upload Test / Simulation End User Training Parallel Test Run

GO - LIVE

ERP Go Live

The Schedule to Go-Live for CFC

ERP Go Live

Sim

ulation Testing 10%

(15-Apr)

Sim

ulation Testing 50%

(12-May)

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Purchasing 1.PRProposalPOGR have been completed , except Proposal and related reports. 2. Purchasing Proposal have been confirmed by C.G on 03-Mar, and plan to delivery on Mar-2014.3. Proposal Customization spec have need developed but still wait CFC & CG final confirm4. GR weight-scale & belt-scale Integration will be put on Phase-I (Plan to delivery on May-2014)5. Purchasing Reports will be delivery on May-2014

1. Under Progress (Total :12 items , Complete : 9 items)2. Should be put into ERP before Mid of Mar-2014

p.s. please reference “CFC Basic Data List- Non Finance

Module.xls”

1. Middle Risk 2. Purchase Proposal

Customization. Will be release to programming on this week.

3. GR Weight-Scale and Belt-Scale will be set lower priority in this Phase.

Inventory 1. Almost the same with CG ERP go live Inventory function, just need to add some additional column for memo purpose.2. All of the customization have been completed.3. CFC need application for new Item No (using TIPTOP standard function to fulfilled ; program id : aimi150)

1.Under Process (Total : 5 items , Complete : 4 items)2.Should be put into

ERP before Mid of Mar-2014

p.s. please reference “CFC Basic Data List- Non Finance Module.xls

1. Low Risk

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Sales 1. B2B Web SO and Delivery Schedule have been completed and under internal testing, those function will be delivery before 07-Mar. ( MIS check )2. Quotation Contract SO DO operation functions almost same with CG, and related customization have been completed.3. Delivery Target Setting Requirements are not include in project scope, so will not be delivery in this Phase. (we plan to have discussed about those extend requirements in the Mid of Mar-2014)

1. Under Progress (Total :13 items , Complete : 9 items)2. Should be put into

ERP before Mid of Mar-2014

p.s. please reference “CFC Basic Data List- Non Finance Module.xls

1. Low Risk 2. All of the function

will be trained and tested when Consultant fly-in

on Mar-2014.3. Related Cust report will be delivery on May-2014.4. CFC want sales

target in phase-I, so need to discuss.

Distribution& F/G Warehouse

1. Main flow is same with CG, and most of customization have been completed. (> 90%) (DODSLNLCDN all complete)

2. Delivery Note need to add internal Invoice and Commercial Invoice function will be delivery on 16-Mar.

1.Under Process (Total :8 items , Complete : 6 items)

2. Should be put into ERP before Mid of Mar-2014

1. Low Risk2. Digiwin already put

high-priority for Delivery Note Cust. Requirement.

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Production 1. Most of production requirements are the same with CG except Packing ,and all of the programs have been complete. 2. Packing Program for CFC current is under programming and the expected delivery date will be 15-Mar

CFC need to know the gaps and solution between Packing shift report & F/G real time report (Please reference Appendix I ) Can setting some Warehouse to allow negative Inventory to solve.

1.Complete (Total : 4 items Complete : 4 items)

1. Low Risk 2. Digiwin already put

high-priority for CFC Packing Process Cust. Requirement.3. Related Cust. report willl be delivery on May-2014.

Maintain 1. New Development Module for Ganda ERP Project, all of programs for this module have been complete on 27-Feb.2. MFG Consultant need to introduce Maintain Module functions to CFC user and do some fine tuning.3. Plan to training on Apr-2014 and align between delivered function with CFC requirement.

1. Wait Maintain Module Training

1. Middle Risk2. New Module will be

delivery on 30-Mar.3. Due to this module

is not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Electric Power

1. New Module for CFC and Spec have been confirmed on End of Jan-2014.2. All of customization of spec already been released, and under programming now. (around 100 hours)3. The expected delivery date will be 30-Mar-2014.

p.s. Electric Power Report will related to Cost Calculation so need on phase-I.

1. No Need 1. Low Risk 2. Independent module3. Due to this module is

not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.

QC Report 1. New Module for CFC and Spec have been confirmed on End of Jan-2014.2. All of customization of spec already been released, and under programming now. (around 150 hours)3. The expected delivery date will be 30-Mar-2014.

p.s. QC Report will related IQC, PQC so need on phase-I.

1. No Need 1. Low Risk2. Independent module3. Due to this module is

not on the Major Operation Flow, We suggest to put this module into simulation test on May-2014.

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Financial & Accounting

1. All of Customization Requirement have been collected & confirmed on Feb-2014 except dual currency solution.2. Most of CG Financial & Accounting function can fulfill CFC requirement or just need a little bit adjustment.3. Ms. Iris have provide final suggestion to CFC about dual currency solution on 26-Feb and waiting CFC’s reply.4. All of customization spec will be released before 05-Mar, and expected delivery date on 21-Mar, except dual currency and VAT output format.

1.Under Progress (currently only provide COA data, total have 56 items)2. Should be put

into ERP before Mid of Mar-2014

p.s. please reference “CFC-Financial data

check list V2.xls”

1. Middle Risk 2. Need decision

support on dual currency solution

3. If dual currency solution can’t be delivery before 30-Mar-2014, we will suggest to use one currency to do simulation testing on Apr-2014 first.

4. If not yet finished the dual currency customization, CFC can not do the test.

Need to discuss

Cost Accounting

1. How to solve the problem for the dual currency and separate the cost for 2 production line

Please Reference Appendix II

1. Under Progress 1.Middle Risk2. Will related with dual currency solution

Ganda ERP Project |

Current Status of CFC ERP ImplementationModule Customization Basic Data Status Comment

SMS 1. Digiwin already release PO to buy SMS Modem and related software license. (MIS trace )

2. The SMS Platform is under developing and plan to complete before 10-Mar.

3. We plan to do the fist SMS message test on 17-Mar-2014. (check point)4. Each SMS Message Program will take 3 days to development. And all of the SMS functions will be delivery on 30-

Mar.

1. No Need 1.Low Risk 2.We will delivery SMS

Module to CFC on end of Mar-2014.

3. Supplier still not confirm when can delivery SMS modem to Digiwin.

Customization Reports(50 reports)

1. CFC site review all the first priority reports on 3/3/2014 and already reduce the reports from 61 to 52. 2. MFG Consultants will provide those RPT specs for CFC confirm on Mar-20143. Digiwin will select 2 confirmed shift- related reports to develop and delivery before 30-Mar-2014, to ensure the shift-related report can be process well.4. All of 50 Customization Reports will be delivery before 30-May-2014.

1. Under Progress 1.Middle Risk2. Customization RPTs

will be partially delivery from Apr-2014 to May-2014.

Ganda ERP Project |

Current Status of CFC ERP Implementation

Module Customization Basic Data Status Comment

Human Resource

1. All of Customization Requirement have been collected & confirmed on Feb-2014.2. HR Consultant will delivery Cust. Spec to CFC for confirm before 07-Mar.3. Digiwin HRM Product Center will modify HRM Product to support CFC Date Format on UI (User Interface), and the new HRM will be released on 10-May.4. Due to some customization should be

based on new HRM released, so the expected delivery date will be 31-May

5. Overtime > Offset and P-Bonus customization solution will be provided before 28-Mar.

6. The other work contents progress, please

reference Appexdix-III

1. Under Progress

1. High Risk2. Due to Date Format

Issue, some customization will be delivery on 31-May.

3. HRM Consultant will discuss with CFC to find out any chance to do simulation test on June-2014.

Ganda ERP Project |

Major Activities of CFC on Mar-2014

12

• Customization Report Spec Confirmation

• Customization Program Training & Testing

• SOP Integration Testing for Major Business Flow

• Basic Data and Simulated Opening Data Preparation

• Operation Simulation Environment Setup

• End User Training

Ganda ERP Project |

Suggestion about CFC Operation Simulation Test

13

• Operation Simulation Test Scope on Apr-2014

• Modules : Purchasing, Inventory, Sales & B2B, Distribution & Warehouse,

Production, Finance & Accounting, SMS

• Locations : TKP plant only (or TKP & HPGP two plants)

• Testing Data Volume : 5% ~ 10% of daily transactions

• Major Target : (1) Ensure ERP Major process can running well and do

some fine turning

(2) Let user have more real practice chance

• Remark & Notes

• Maintain, Elec. Power, QC Report, Customization Reports & HRM modules can be put on 2nd round Operation Simulation Test (May-2014)

• The Other CFC Branch Offices can be include in 2nd round Simulation Test

• Testing Data Volume can be enlarge to 50% ~ 100% of daily operation in 2nd round Simulation Test .

Ganda ERP Project |

Month-end Closing1.Check Up2.Reconciliation & Reporting

Apr May AugJune July OctSep

20/2

Jan Feb Mar

Phase 2 development1. Survey & Diagnosis2. Application Training3. Operation Training 4. S.O.P. Modeling5. Gap Analysis &

Customization6. HRM Application Training

/Gap Analysis

Nov Dec

ERP Project Milestone 2014

RMC & Transport1.Design & Development2.Basic data preparation3.UAT4.Training5.Launch

B I1.Workshop2.Design & Development3.UAT4.Launch

Easy flow 1.Design & Development2.UAT3.Launch

AASTAR1.Application Training2.Basic data preparation3.UAT4.Training5.Launch

HR1.Payroll2.ESS

15/3 10/4 10/5 05/6 05/7 20/8 15/8 05/8

RMC – Motive MuliaKick off 11/3/2014 – Go-Live July 2014

Transport - ANPKick off 01/4/2014 – Go-Live July 2014

AASTARKick off 07/4/2014 – Go-Live July 2014

Business IntelligenceKick off 18/3/2014 – Go-Live July 2014

Easyflow / Online approvalKick off 01/4/2014 – Go-Live July 2014

Payroll Kick off 05/2/2014 – Go-Live April 2014ESS (Employee Self ServiceKick Off 24/3/2014 – Go-Live July 2014

Ganda ERP Project |

THANK YOU

Ganda ERP Project |

Appendix IShift Report Solution

Ganda ERP Project |

17

CFC Shift Report Solution

TIPTOP ERP Shift Control

Ganda ERP Project |

18

CFC Shift Report Issue

• All production process already contain shift control column.

• To fulfill CFC Shift Report Issue, some Inventory transaction list below still need adding shift control column but need confirm with CG(Need about 24HR additional customization hour):

• Purchase Stock-in

• Purchase Return

• Sales Return

• WH MISC Material Issue

• WH MISC Material Stock-in

• WH transfer

Ganda ERP Project |

Appendix IICost Accounting Solution

Ganda ERP Project |

20

CFC Dual Currency Cost Accounting

AR(VND) AP(VND)Expense

Allocation(VND)

GLBook1(VND)

Cost AccountingBook1(VND)Calculation

ARBook2(USD)(Auto Gen.)

AP Book2(USD)(Auto Gen.)

Expense Allocation

Book2(USD)(Auto Gen.)

GLBook2(USD)

Cost Accounting

Book2 (USD)Calculation

TransactionBatch Copy and

Convert to USD Amt(by date EX Rate)

GL Voucher Batch Copy and Convert

to USD Amt(by date EX Rate)

WillNot copy

Cost Accounting

Voucher

Ganda ERP Project |

Appendix IIIHRM Work Content Progress

Ganda ERP Project |

22

HRM Work Contents Progress

No Items Progress or Reply Remark

01 Recruitment, training, performance : postponed to June or July

1. Only Training module will go live on 1st of the July.

2. Recruitment module, we suggest postponed to phase 2. And after discussion with CFC HR Department, actually they’re still using the formal way to recruit new comers, such as bulletin board or newspapers. So we suggest that we could postponed this module and discuss in the future days.

3. Performance module: Mr. Andrew will create a blank field in employee master data to let them upload the performance index over there, so we could give up the performance module.

02 Items in Employee basic data : Blood type, Identification Code

Those items we already maintain in HRM system, by the way, CFC have to provide the identification code of Vietnam

Ganda ERP Project |

23

HRM Work Contents Progress

No Items Progress or Reply Remark

03 Seniority Subsidize (automatically calculated from 1st Jan. each year)

Seniority Subsidize will be calculate in payroll module and I will set up the parameters and formula to let them automatically calculated from 1st of Jan on each year.

04 P&S bonus This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

05 Tax balance This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

06 Shift arrangement This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

07 Overtime, Offset Leave This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

08 All kinds of Report This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

Ganda ERP Project |

24

HRM Work Contents Progress

No Items Progress or Reply Remark

09 Annual Budget We have a final decision of annual budget , isn’t it? Your currently process are still using paperwork and in our main system, we don’t have any module of function to record this, so please remain your own process.

10 Annual leave : the new commer can take annual leave after 11 months of service

This will be customization item. Solution Spec under Develop and will provide to CFC before 28-Mar

11 Fingerprint system, E-card : connect to HR system

Mr. Andrew already set up the format of fingerprint in HRM system. And the E-card system, if you want to use it , It also can be set up in HRM system

12 Date formating : DD-MM-YYYY

Under process, HRM Product will modify to support DD-MM-YYY format when user thru UI view and edit data .

Ganda ERP Project |

25

HRM Work Contents Progress

No Items Progress or Reply Remark

13 Employee no need to pay Social Insurance, Medical Insurance in month; employee can not get P&S bonus in month

This will be set up in payroll module, and I already show you the way if the people they no need to pay social insurance or medical insurance in each month. You have to prepare a list of excel( need to pay is 1; no need to pay is 0), so please prepare this excel file and upload to system, then the system will follow your rule to calculate insurance or p/s bonus .

14 Check the order of the item; use standard English in all system

Work in process

Ganda ERP Project |

Appendix IVDual Currency Solution

Ganda ERP Project |

Dual Currency Solution Digiwin Proposed

PurchasingSales &

Distribution

Good Receiving

ShippingTransaction

Inventory

Production

AccountPayable(VND)

AccountReceivable

(VND)

Cash & NoteManagement

(VND)

Fixed Asset(VND)

General Ledger(VND)

VN

D

FIN

for M

ajor C

urren

cy S

OB

AccountPayable(USD)

AccountReceivable

(USD)

Cash & NoteManagement

(USD)

Fixed Asset(USD)

General Ledger(USD)

FIN

for S

econ

d C

urren

cy SO

B

MF

G M

od

ules

Transfer into 1st set of Accounting Transactions

Sub-LedgerData Transfer(AP, AR , NM, FA)

Transfer into 2nd set of Accounting Transactions

US

D

(synonmy)

Ganda ERP Project |

Account Payable System StructureAccount Payable System Structure

Receipt

AP

offset

Payment Process

Post Voucherto GL

Foreign Purchase

Foreign PurchaseReceipt

LC Application

Misc. APAdvance Payment

PurchaseReturn

PO

Temporary AP

To-offsetAccount

Cost Apportionment

AP Revaluation

APMonth End

Ganda ERP Project |

Sales Order

Sales Return

Incoming Payment

Notes Receivable

Cash Transactions

DepositConfirmation

Incoming Payment

ARMoth End

AR Balance of Payment

Deposit Misc. AR

Credit Memo

Misc. to-offset

Depositto-offset

Over Receipt

Delivery Note

AccountReceivable

Issue VAT Invoice

LC Management

AR Revaluation

Account Receivable System StructureAccount Receivable System Structure

Ganda ERP Project | 30

Dual Solution ComparisonDual Solution Comparison No Solution Description Advantage Disadvantage Remark

01 All of front-end accounting transaction data maintain screen need to put 3 kind of currency like current CFC system

• Can fulfill current CFC process needs.

• User can view & adjust dual currency data in one screen.

(more efficiency)

• Customization hours are 2,619 hrs. (time & cost)

• Due to Impact current ERP design structure will need longer time for testing and hard to maintain.

CFC prefer one.

02 Base on TIPTOP System Structure and create two Set of Books (two full set of sub-ledger) to fulfill DualCurrency Needs

• Can fulfill ACC and auditing need.

• Base on current ERP structure can leverage most of ERP standard reports and easy maintain.

• Customization cost under original budgets (600 hrs)

• Although most of 2nd accounting data can be auto-create by ERP, but still need ACC Dept. to confirm and do some adjustment if needed.

• Different with current process, user have longer learning curve.

Digiwin Suggested