ganda erp project | cfc erp project bi-weekly meeting (28/03/2014)

13
Ganda ERP Project | CFC ERP Project bi-weekly meeting (28/03/2014)

Upload: blaise-ralph-singleton

Post on 01-Jan-2016

224 views

Category:

Documents


4 download

TRANSCRIPT

Ganda ERP Project |

CFC ERP Project bi-weekly meeting (28/03/2014)

Ganda ERP Project |

Nov-2013 Dec-2013 Jan-2014 Feb-2014 Mar-2014 Apr-2014 May-2014 June-2014 July-2014 Aug-2014

Purchasing

Inventory

Sales

Distribution / FG Warehouse

Production

Maintenance

Finance & Accounting

Human Resouce

Customization Basic Data upload Test / Simulation End User Training Parallel Test Run

GO - LIVE

ERP Go Live

The Schedule to Go-Live for CFC

ERP Go Live

Sim

ulation Testing 10%

(15-Apr)

Sim

ulation Testing 50%

(12-May)

2

Ganda ERP Project |

CFC Operation Simulation Test

3

• Operation Simulation Test Scope on Apr-2014

• Modules : Purchasing, Inventory, Sales & B2B, Distribution & Warehouse,

Production, Finance & Accounting, SMS

• Locations : TKP & HPGP two plants ( MPLS can be finished on 12/4 )

• Testing Data Volume : 5% ~ 10% of daily transactions

• Major Target : (1) Ensure ERP Major process can running well and do

some fine turning

(2) Let user have more real practice chance

• Remark & Notes

• Maintain, Elec. Power, QC Report, Customization Reports & HRM modules can be put on 2nd round Operation Simulation Test (May-2014)

• The Other CFC Branch Offices can be include in 2nd round Simulation Test

• Testing Data Volume can be enlarge to 50% ~ 100% of daily operation in 2nd round Simulation Test .

Ganda ERP Project | 4

CFC KM/KU Examination• http://tkcfc.dyndns.org/erp/Tiptop/Examination/

• Sales & B2B & F/G & Logistic

• Materials: Sent: Mon 24/03/2014 5:59 PM

• Participate: Marketing + G/A + F/G + Logistic

• Schedule: ???

• Purchasing

• Materials: Sent: Wed 26/03/2014 7:25 AM

• Participate: Purchasing + G/A + W/H

• Schedule: ???

• Financial & Accounting

• Materials: Sent: Wed 26/03/2014 7:42 AM

• Participate: Financial + Accounting

• Schedule: ???

• Inventory

• Materials: Sent: Thu 27/03/2014 11:30 PM

• Participate: Warehouse + G/A

• Schedule: ???

Ganda ERP Project |

Progress update

Finance & Accounting

Progress Update Next Plan

Sales & F/G & Logistic

Module / Function

5

1. Digiwin Project Team have provided a new solution for CFC Dual Currency

2. Regarding to how many Operation Center (DB) should be configured in CFC ERP system. Due to the VAT output

1. Overall conclusion, CFC agree to adopt two operation database for dual currency, but need to provide reliable program to make two account consist, but because it’s possible to have some adjust, so accounting department need to manually contra two account.

2. For the overall consideration except Financial Accounting, already final to separate two Operation Database CFC-TKP ; CFC-HPGP

Due to CFC daily logistic operation process requirement, the “Delivery Target Setting” function on have to put on Phase-I

Only make one report that F/G need (Loading Report of Zone). 

B2B interface should have Vietnamese ( MIS will try to replace Simplify

Chinese to Vietnamese )B2B date time format should be

change to dd/mm/yyyy. ( Done )

Area Database name Branches

North, Central VN CFC-TKP TK, HP, HN, DN

South VN CFC-HPGP HCM, HPGP

Ganda ERP Project |

Progress update

Branch Warehouse

Progress Update Next action PlanModule / Function

Production

6

Distribution / Logistic

Due to CFC user still have no chance to see the full distribution operation flow demonstration on CFC ERP (DO DS LN LC DN), so users are worry about those function really can run or not.

Sales and Delivery Module Simulation Demonstration (March-17) and material please referance “CFC Sales Function Demo v1.docx”

Due to branch office warehouse size not big as TK plant, and transaction not so many like factory, so maybe can have easier process for delivery

Since outside warehouse process usually done by branch office logistic, it’s not real time operation, so to maintain program and process consistency, still follow standard deliver process same as TK plant.

Due to CFC user still have no chance to see the full operation flow demonstration on CFC ERP (Quarry RM Kiln CM Packing ), so users are worry about those function really can run or not.

We would like to invite Digiwin also provide a whole production operation flow demonstration when MFG consultant next coming trip. ( Apr ???)

Ganda ERP Project |

Progress update

Cost Accounting

Progress Update Next action Plan

Budget

Module / Function

7

TIPTOP ERP Budget Functions are designed in GL Module, the main focus of TIPTOP Budget function are Budget Data Setting, Actual/Budget Comparison and Purchasing Budget Control. There are not supporting function for Budget Planning and Budget Simulation on standard TIPTOP Package.

Mr. Ted Reply Tue 18/03/2014 10:37 AM

Regarding to CFC Budgeting Function requirement, I will suggest CFC to keep using current manual process

(due to there is no times and no budget to deal with it in this project) and let us focusing on CFC ERP Go-live activities first,

because of there are still lots of thing need both of our teams to do and to ensure we can achieve the target.

Currently customization when packing process finished, the stock in Item No. is merged both Line 1 and Line 2 cement . CFC request when finished packing, stock-in finish goods item no should still separated into Line 1 and Line 2. And required one more process to merge the Line 1 and Line 2 into the merged item No.

Digiwin explain that, because of this additional level process is a visual process so means need to auto generate related transaction from system, this will cause additional customization 88 hours not existing in the confirmed customization scope. So they need extra charge for this.

Ganda ERP Project |

Progress update

Progress Update Next action PlanModule / Function

8

Customization Reports

Digiwin will provide the RPT Specs to CFC for confirmation on Mar-2014 QUA+KILN+WH+DN

All of Customization Reports will be delivery before 30-May-2014.

Purchasing

SMS

The SMS Module customizations are CFC Phase-I Must-Have functions, Digiwin will provide the progress to CFC continually..

Mr. Ted provided the spec. on Sat 15/03/2014 11:27 AM

MIS need to confirm with consultant for more details.

Due to CFC process control requirement, the “weight-scale & belt-scale integration function” on GR (Good Receiving) have to put on Phase-I (01-July-2014 Go-Live Must-Have function)

1. Before 28/3 related dept. need to input the new Item-No. & Vendor code to the LiGu basic data by excel file and reply to MIS Mr. Tuan.

2. Before 31/3 MIS Mr. Tuan will reset all the LiGu Basic data based on the excel file. And lock the user rights for input the new data to LiGu system.

3. Purchasing Dept. Mr. Hung will design the application form for the new Item-No. and vendor code. Before the end of March.

Due to LiGu Database Structure can not fulfill with our existing Coding. So we proposed asks LiGu upgrade:

1. Open DB for Basic Data2. Add LN No + BARGE ID 3. Windows 7 Version4. Transaction export by each trip

Ganda ERP Project |

Progress update

Equipment Maintain

Progress Update Next action PlanModule / Function

9

Electric Power

Q.C Reports

Due to Maintain Module is a whole new customization module, Digiwin Project Team plan to provide Maintain Module Training and collect the gaps between delivered functions and CFC requirements on Apr-2014.

10/03/2014 For the Basic Data, Mr. Thanh suggest to use real case: One desktop computer found shutdown / overheated and suspected need to check or replace CPU or CPU fan, what is basic data we need to provide into TIPTOP system so as let thing done.

Mr. Nick have explain the basic data on 19/3

Digiwin will deliver those customization function progressively from May-2014.

Digiwin will deliver those customization function progressively from May-2014

Spec. confirmed on Wed 19/02/2014 3:23 PM

Waiting for the Customization training

Spec. confirmed on Mon 10/03/2014 10:40 AM

Waiting for the Customization training

Basic data done in 28/3/2014

Ganda ERP Project |

Progress update

Progress Update Next action PlanModule / Function

10

HR & ESS

Mr. Andrew sent on Fri 21/03/2014 12:06 PM

1. Provide the spec of P/S Bonus

2. Provide the spec of Daily shift arrangement.

3. Provide the spec of reports.

4. Testing the salary formula.

1. Finished the spec of Annual leave parameters and Annual Leave Planning .

2. We classified the class of report, please help us to confirm it.

3. Seniority Subsidize had tested in HRM system and It can be calculate from Payroll Management

4. We had confirmed the details of P/S bonus again.

5. We can use the basic function of overtime parameters, so there's no need to customize the OT parameters. I had tested in HRM system, and it work to fulfill the requirement from CFC, but we still have to customize in Offset leave Setting. 6. Confirm the Vietnam's social Insurances, medical insurance, jobless insurance and personal income tax details

Ganda ERP Project | 11

HPGP & Branch Office

Inquire for VDC / FPT / VIETTEL4/03/2014 Alex sent Acceptance Test Condition for vendor.

Viettel Demonstration 25/03/2014 15:00

MIS based on the instruction of Viettel and already make ERP server combine with our existing LAN on 25/03/2014.

We will sign the testing contract before 12/4/2014. TKP with HPGP

Progress update

Progress Update Next action PlanModule / Function

Need to make sure the sub-mask will not Interfere with TKP & HPGP

Ganda ERP Project | 12

1.      Customization Report Spec. confirm ( Mr. Nick providing for us to confirm via email and should be finished before 28/3 ) -> CFC RPTs Spec Release Schedule (52 RPTs) : 28/3 : 25 RPTs ; 5/4 : 10 RPTs; 11/4 : 8 RPTs ; 18/4 : 5 RPTs ; 25/4 : 4 RPTs 

2.      CFC Internal bi-weekly meeting 28/3 ( review all the progress and outstanding issues )

3.      PRD + PUR + Maintain + ELEC + QC Customization Training ( Suggest for Mr. Nick come to CFC 31/3 ~ 4/4 ) -> Due to schedule conflict, Mr. Nick can not come to CFC 31/3 ~ 4/4 ; Mr. Nick will plan to delivery PRD + PUR customization training on the next trip (7/4 ~ 18/4) Mr. Nick will try to put Maintain Module training on the next trip if the schedule is not fully assigned (7/4 ~ 18/4) ELEC + QC Customization training will be postpone to May-2014.

4.      Key User Training ( Suggest for Mr. Nick + Ms. Iris come to CFC and starting from 7/4 ~ 18/4, We all asks related dept. KM/KU overtime on 9/4 ) -> Confirmed !  (I will provide detail daily activities and air-ticket itinerary to CFC before 28/3)

5.      CFC Internal bi-weekly meeting 11/4 ( review all the progress and outstanding issues + Key User training evaluation )

6.      Whole Module Simulation Testing 5 ~ 10% real data ( Starting from 15/4 ) -> Confirmed !

7.      Invited Mr. Ted come for the ERP monthly reporting. ( Suggest 23/4 ~ 24/4 ) -> Ted have schedule on 22/4 at Taiwan, So ted will flight-to HAN on 23/4 and start meeting on 23/4 afternoon !

8.      CFC Internal bi-weekly meeting 25/4 ( review all the progress and outstanding issues ) 

Major Activities on Apr-2014

Ganda ERP Project |

Dear Mr. Ryan Sent: Wed 26/03/2014 7:30 PM         Thanks for your reminding. I will update to our bi-weekly meeting.         1. For simulate 100% transaction data is the target goal of Mr. Chinh F/G dept. and very difficult to reach. And for the open balance in the end of June, not only for F/G also have a lot of W/H we need to know the physical inventory ending balance. ( Accounting dept. also worry about how to cut off the outstanding data and switch to ERP )          2. If Digiwin need to discuss the extra contract, we need Digiwin provide us the compare table first, for we can know the detailed of the time allocate.          3. B2B date format already done. We will try to use the Simplify Chinese replace to Vietnamese based on your instruction. Thanks with Best Regards, Dear Mr. Alex

        Some remind from me as below:1.      If you can simulate 100% transaction, so means in June already have all transaction and don’t need to do open balance in end of June, open balance strategy would be different.2.      Today discuss with our Top management, about extra charge things is there any possibility we make additional contract (consider all possibility at least this year), not just 88 hrs?3.      About B2B web site, date format Mr. Sean will check it, Vietnamese language part now system can have multi-lingual setting, but because now system only have 3 language(0. Traditional Chinese 01. Simply Chinese 2. English), maybe you can try to put Vietnamese description in Simplify Chinese part (program ID: p_weblang).

13