  • City of Franklin

    Water Treatment Plant

    Modifications

  • Schedule

    May 28, 2015

    Franklin Municipal Planning Commission Approval

    June 1, 2015

    Sealed Drawings and Specifications Submitted to TDEC

    June 21, 2015

    Public Advertisement for Bids

    July 23, 2015

    Public Bid Opening

    August 2015

    Project Award / Notice to Proceed

    Early 2017

    Final Completion and Acceptance of Project

  • Presentation Format

    Finished Water

    GAC Contactors

    UV / Advanced Oxidation

    Membrane Filtration Outside

    Site Plan WTP Building

    Inside

  • Site Plan

  • Northeast Elevation (Front)

  • Southeast Elevation (Left)

  • Southwest Elevation (Back)

  • Southeast Elevation (Right)

  • Southeast Elevation (Right)

  • Perspective View

  • Perspective View

  • Inside Plan View

  • Inside Southwest Elevation (Back)

  • Inside Perspective Membrane Racks

  • Inside Perspective UV / AOP System

  • Inside Perspective GAC Contact Tanks

  • Questions