Electrical Activities Weekly Progress Report
From : 10/8/2015 To : ###
Substation # : 9029Substation Name : INSTALLATION OF TRANSFORMERS AT BURAYDAH 9029Report # : 7Site Engineer : SANEESH S S
document.xlsx
SITE REPORT
A. Construction Activities
S.N Activity Manpower Current Progress % Planned (Forecast) start date Actual start date Planned (Forecast) finish date Actual finish date Remarks
1 Earthing
1.1 Grid Earthing 3 90% 22-Oct-15
1.2 Re-inforcement Earthing 3 100% 9/15/2015
1.3 Equipment Earthing 2 45% 11/30/2015
2 Equipment Erection
2.1
2.2 132/33 KV Power Transformer Erection 10/19/2015 24-Oct-15
2.3 GT1
10
100%
oil filling under progress2.4 GT2 100%
2.5 GT3 100%
2.6 33 kV Panel erection 11/10/2015 awaiting 33 kV switchgear
2.7
2.8 33 KV GROUNDING TRANSFORMER erection
2.9
2.10 120 KV Surge Arrester
2.11 33 /0.4 KV Auxiliary Transformer
2.12 33 KV Capacitor Bank Erection
2.13 33 kV LBFS LBFS delivered at site
2.14 ACDB erection Nov-15
2.15 DCDB ERECTION Nov-15
2.16 Control and relay Panel erection Nov-15
2.17 Battery Erection Nov-15
2.18 Battery charger erection Nov-15
2.19 SAS Nov-15
2.20 communication system Nov-15
2.21 AMI system Dec-15
2.22 DSM system Nov-15 Awaitng delivery on October 2015
3 LIGHTING INSTALLATION WORKS
3.1 Electrical Lighting erection switchgear ground floor
3.1.1 Conduit(Piping work) with JB and accessories 30-Oct-15
3.1.2 Over head cable tray and accessories erection
3.1.3 AWG Wiring and termination 15-Nov-15
3.1.4 Light fixtures fixing Dec-15
3.1.5 Power Outlet and switches Nov-15
3.2 Electrical Lighting erection switchgear Basement
3.2.1 Conduit(Piping work) with JB and accessories3
20%
3.2.2 Over head cable tray and accessories erection 90%
3.2.3 AWG Wiring and termination
3.2.4 Light fixtures fixing
3.2.5 Power Outlet and switches
3.3 Electrical Lighting erection control room buildings
3.3.1 Conduit(Piping work) with JB and accessories Marking under progress 30-Oct-15
0% ( waiting for civil readiness)
0% (waiting for civil readiness)
Awaitng delivery on November 2015
0% (waiting for civil readiness)
materials reached site on 25 august 2015
LBFS RECIEIVED. WAITING FOR CIVIL FOUNDATION READINESS
0% ( control room civil in progress)
Awaitng delivery on November 2015
0% ( control room civil in progress)
DCDB delivered to site on 26 August 2015
0% ( control room civil in progress)
Awaitng delivery on November 2015
0% ( control room civil in progress)
Awaitng delivery on November 2015
0% ( control room civil in progress)
Awaitng delivery on November 2015
0% ( control room civil in progress)
Awaitng delivery on November 2015
Awaitng delivery on November 2015
Awaitng delivery on November 2015
Awaitng delivery on November 2015
PECE contractor manpower not available
AWAITING ANGULAR SUPPORT
marking under progress at basement
RGS CONDUITS AND ACCESSORIES DELIVERED TO SITE
document.xlsx
SITE REPORT
3.3.2 Over head cable tray and accessories erection
3.3.3 AWG Wiring and termination 15-Nov-15
3.3.4 Light fixtures fixing Dec-15
3.3.5 Power Outlet and switches Nov-15
3.5 HV,MV and LV duct bank work
3.5.1 132 kV duct bank work 100%
3.5.2 33 kV duct bank work 100%
3.5.3 LV and Control piping 85% 30-Oct-15
3.5.4 Equipment earthing pipes sleeves 100%
3.6 OUTDOOR LIGHTING AND POWER SOCKECT INSTALLATION
3.6.1 Conduit(Piping work) with JB and accessories Dec-15
3.6.2 AWG Wiring and termination
3.6.3 Light fixtures fixing
3.6.4 Power Outlet and switches
4 Cable tray and cable Laying works
4.1 Cable Tray and Support Erection 8/5/2015 30-Oct-15
Switchgear basement area
LV AND CONTROL CABLE LADDER/TRAY
15
85%
MV AND CAPACITOR CABLE LADDDER 75%
Control room and Telecom room 75%
overhead cable tray
4.2 33 KV cable Laying
4.3 132 KV cable Laying Dec-15
4.4 33 KV Cable Termination
4.5 13.8 KV Cable Termination
4.6 LV cable Laying Nov-15 Awaitng delivery on october 2015
4.7 LV cable termination
4.8 Control cable laying and termination
4.9 Communication and FO cable Laying and termination
5 Flat Earthing
6 Lightning works (Shielding) and lightning pole erection Dec-15
7 Indoor and Outdoor Lighting Panels Nov-15
8 ACSR Conductor along with clamps and connectors
PANEL SUPPORT WORKS 3 60%
B. Issues/Concerns which require Action:
1
RGS CONDUITS AND ACCESSORIES DELIVERED TO SITE
Awaitng delivery on November/December 2015
50 X 6 bare copper flat delivered to site
Awaitng delivery on November 2015
Bending machine and ladder accessories needed for ladder installation work and flat bar earthing work
100 MVA TRANSFORMER OIL FILTERATION AND FILLING UNDER PROGRESS
TELECOM ROOM CABLE LADDER/TRAY WORK IN FINISHING STAGE
BASEMENT OUTGOING FEEDER CABLE LADDER WORK
BASEMENT 2 X 28 WATTS LIGHT FIXTURES MARKING
CONTROL ROOM PANEL SUPPORT WORKS