evaluation and reporting entc 4060 project scheduling

22
Evaluation and Reporting ENTC 4060 Project Scheduling

Upload: philippa-maud-mcdonald

Post on 16-Dec-2015

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Evaluation and Reporting ENTC 4060 Project Scheduling

Evaluationand

Reporting

ENTC 4060Project Scheduling

Page 2: Evaluation and Reporting ENTC 4060 Project Scheduling

Why Track a Project?

Keep the following on target: Cost — Expenditures Time — Schedules Scope — Technical performance

Page 3: Evaluation and Reporting ENTC 4060 Project Scheduling

Project Manager’s Duties

Oversees work Coordinates corrective action as

required Evaluates status Initiates communication

Up and down chain of command

Page 4: Evaluation and Reporting ENTC 4060 Project Scheduling

Purpose of Evaluation

Assess performance Reveal areas of deviation from

original scope &/or goals Snoop out potential problem areas Keep stakeholders informed

Page 5: Evaluation and Reporting ENTC 4060 Project Scheduling

Two Types of Evaluation

Formative evaluation Throughout project lifecycle Provide information for corrective action “What’s happening?” & “How’s progress?”

Summary evaluation After project completed AKA “Lessons Learned” “What happened and what resulted?”

Page 6: Evaluation and Reporting ENTC 4060 Project Scheduling

Formative Evaluation

Complex relationships among cost, time, & scope

CT&S are always interrelated and draw from the same limited resource pool

Cannot just look at one criteria

Page 7: Evaluation and Reporting ENTC 4060 Project Scheduling

Goals of Evaluation

Reveals problem areas Alerts personnel to potential problem

areas Identifies opportunities to increase

customer satisfaction by reducing costs, accelerating work, or enhancing project outcomes

Page 8: Evaluation and Reporting ENTC 4060 Project Scheduling

Project Reporting

Four Methods of Reporting Graphics (charts & tables) Reports (oral & written) Observations (MBW) Review meetings

Page 9: Evaluation and Reporting ENTC 4060 Project Scheduling

Graphical Methods—Pros

Most efficient Consolidate large amounts of data

into easily understood information Clarify project progress,

performance, & projections Distribute &/or display

Page 10: Evaluation and Reporting ENTC 4060 Project Scheduling

Graphical Methods—Cons

Hide or obscure information Especially at work package level

May lead to erroneous conclusions Don’t reveal causes or solutions Potentially time consuming

Use computer-based tools

Page 11: Evaluation and Reporting ENTC 4060 Project Scheduling

Reports — Oral

Quick & easy to obtain Quality depends upon communication

skills of presenter Both interpretative and verbal

Subject to loss of information if not followed up by other, more permanent, methods

Page 12: Evaluation and Reporting ENTC 4060 Project Scheduling

Reports — Written

Valuable but quality and usefulness varies Summary format is best

Incorporate graphics & ratios (percentages) Time consuming to prepare During planning phase, schedule key

reports as milestones and allow for preparation

Page 13: Evaluation and Reporting ENTC 4060 Project Scheduling

Direct Observation

“Management By Walking” Get out of the office & do it often!

Limit distortion and filtering due to natural “spin” from senders to receivers

Maintain worker’s importance and ownership in project

Page 14: Evaluation and Reporting ENTC 4060 Project Scheduling

Project Review Meetings

Goal is to identify (a) project plan deviations & (b) corrective actions

Focus on Current & anticipated CS&T problems Potential methods of resolution Improvement opportunities

Formal vs. Informal Reviews

Page 15: Evaluation and Reporting ENTC 4060 Project Scheduling

Formal Reviews

Formal review meetings Must be planned and scheduled for particular

project phases(critical stages & project milestones)

Project team accumulates & formats data May require considerable preparation and

outside experts &/or scrutiny Review period may last for days or weeks

Page 16: Evaluation and Reporting ENTC 4060 Project Scheduling

Formal Review Meetings

Four common Preliminary Design Review Critical Design Review Functional Readiness Deliverable Readiness & Fitness

Page 17: Evaluation and Reporting ENTC 4060 Project Scheduling

Informal Meetings

“Peer Reviews” Often just project team members, critical

vendors and customer reps.

Hold frequently and regularly Limit size to involved phase participants Update status and prepare presentations

Page 18: Evaluation and Reporting ENTC 4060 Project Scheduling

Informal Meetings

Goals:1. Uncover problems & emerging issues2. Suggest corrective action

Expect problems Avoid “finger pointing” and assigning blame

PM functions as group facilitator and encourages honesty & candor

Page 19: Evaluation and Reporting ENTC 4060 Project Scheduling

POA Pow-Wows

POA work sheet POA—Planned, Organized, Actual

Simple Work Package level, matrix-type tracking tool Task description Person(s) Responsible Dates planned, organized, and actually

delivered

Page 20: Evaluation and Reporting ENTC 4060 Project Scheduling

Monthly Progress Reports

Brief project status summary “Red Flag” items & corrective action Accomplishments, changes, &

projections Minor problem areas & corrective

action Cost & manpower situation

Page 21: Evaluation and Reporting ENTC 4060 Project Scheduling

Reports to Project Manager

Work completed to date Forecasts:

Costs at completion Schedule expectations

Financial status Incurred costs Planned vs. actual

Page 22: Evaluation and Reporting ENTC 4060 Project Scheduling

Reports to Customer

Work completion status & projections Changes (by requests &/or events)

Impacts on cost/time/scope PM should bear responsibility

Honest & frequent Avoid “Surprises”