ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

CAIRO METRO

10/26/2014

Page 2: Essam selim   egypt

SPEAKER BIO

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

2

ESSAM SELIM Free Lancer Consultant for Railways, Metro 32 Years in Oil & Gas Fields (13 years in Abu Dhabi) 6 Years Egyptian Railways & Metro 3 Years Free Lancer Consultant E mail Address: [email protected]

Page 3: Essam selim   egypt

W ITH A POPULATION OF APPROXIMATELY

20 MILLION, CAIRO IS ONE OF THE MOST

DENSELY POPULATED CITIES IN AFRICA

CAIRO METRO TO ACCOMMODATE 80 % OF

CAIRO TRANSPORTATION NEEDS

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

3

CAIRO METRO OF SIX LINES TO ACCOMMODATE

THE EVER-GROWING POPULATION OF CAIRO

Page 4: Essam selim   egypt

CAIRO METRO

The first of only two full-fledged metro systems in Africa, and the Arab World. The system consists of three operational lines.

Egypt celebrated the 25th anniversary (Silver Jubilee) of operating the first line last year,

Operated by a Private Company fully owned by National Authority of Tunnel

Carrying daily an estimated three million passengers

The lines use standard gauge (1435 mm).

The ticket price is EGP 1.00 for each journey, about GBP 0.12, EUR 0.14, or USD 0.18 (expected to be raised shortly)

The middle two cars (4th and 5th) of each train are reserved for women (the 5th car becomes a mixed use after 21:00).

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO,

[email protected]

4

10/26/2014

Page 5: Essam selim   egypt

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

5

FUTURE LINES L i n e 4 : FROM NASR C ITY TO ABBASYA,

G IZA AND E L AHRAM L I N E 5 FROM NASR C ITY TO PORT

SAID STREET AND SHUBRA E L

KHEIMA C ) L I N E 6 : FROM SHUBRA E L KHEIMA VIA

E L AHRAM, TO MAADI

Page 6: Essam selim   egypt

CAIRO METRO

Line 1 (Helwan - El Marg), completed in 1987, 42.5km long with 33 stations. It covers the Egyptian capital from north to south.

Line 2, (Shobra El Kheima - El Mounib) constructed in two phases, first in 1997 and the other in 2004. It is 21km long and serves 20 stations from the north to the south-west, covering the district of Shubra and the pyramids of Giza.

Line 3 (Imbaba / Mohandiseen - Cairo Int'l Airport) will be 43km long with 34 stations, of which 28 will be underground. The line will connect Cairo Airport in the east to Imbaba and Mohandisseen in the west, crossing the downturn area and Heliopolis. The Mohandisseen area will be connected to the main line going to Imbaba.

Line 4 (October-Oasis Highway - the Police Academy) is expected to operate between Haram District in the east and New Cairo district in the west.

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

6

Page 7: Essam selim   egypt

LINE 3 PLAN & SPECIFICATIONS

Line 3 will be 43km long with 34 stations, of which 28 will be underground.

Construction began in 2007, with the first section opened on February 21, 2012.

Tunnel by bored tunnel & stations by cut & cover]

Plan to be fully operational by October 2019.

Expected to add 1.8 M passengers per day[

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO,

[email protected]

7

10/26/2014

Page 8: Essam selim   egypt

PROJECT CONSORTIUM

The contract was awarded to a consortium led by Vinci Construction Grand Projects, a French construction company, which holds a 28.5% stake in the consortium, was given the civil engineering package of the contract in January 2007. Other parties in the consortium include Arab Contractors (27.5%), Bouygues (26%) and local company Orascom Construction Industries (18%).

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

8

10/26/2014

Page 9: Essam selim   egypt

CAIRO METRO LINE 3

Extends from the northwest of Greater Cairo at Imbaba to the northeast of Heliopolis and Cairo International Airport.

It crosses River Nile twice at western branch Kit Kat & Zamalek & eastern branch Zamalek & downtown Cairo

The total length of the line is approximately 43 km, 28.1 km underground and the rest is on grade & planned in four phases.

The project includes a main workshop adjacent to the western terminal & light repair workshop at the middle at Abbasia

The line will use trains manufactured in Japan by Kinki Sharyo Co. and Toshiba Corp

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

9

10/26/2014

Page 10: Essam selim   egypt

LINE 3 MAP

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

10

10/26/2014

Page 11: Essam selim   egypt

ROUTE OF LINE 3

From Cairo International Airport, to Imbaba in the west, passing through Heliopolis, Abbasiya, Attaba and Zamalek. In addition a branch from Kit Kat Square to Mohandeseen.

The total length of Line 3 will be about 43.5 Km. It will have 34 Stations

28.1 km is an underground section and the rest is on grade and will be implemented in four phase

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

11

10/26/2014

Page 12: Essam selim   egypt

SIGNALING & COMMUNICATIONS

The signaling and telecommunications system will be provided by a consortium led by Alstom Equipment. The total value of the signaling and telecommunications contract is €29.8m.

Other parties in the consortium include the Thales Group and Orascom. For the stations, Alstom will provide URBALIS 200 integrated signaling and train-control information system. It will include a control system, switches and signaling equipment.

The Automatic Train Control and interlocking will be provided by Alstom Units in France, while the locally manufactured products, including the Automatic Train Supervision, will be provided by CASCO. ALSTOM Transport Service Shanghai will supply local services for the project

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

12

Page 13: Essam selim   egypt

PHASE 1 (ATTABA – ABASIA) (OPENED)

It consist of 5 underground Stations about 4.3 Km, an interchange with Line 2 at Attaba station, the construction took 4 years started in 2007 and opened in February 2012

The line was inaugurated less than six months behind the original planned opening date and in time for a revised target, after facing significant tunneling problems in 2009, as well as the political upheaval that began in 2011.

Technical challenges for contractors include waterlogged ground and cramped conditions for above-ground work

Stations are 150m long, located at a depth of 14m to 58m. The tunnel will have a diameter of 9.4m

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

13

10/26/2014

Page 14: Essam selim   egypt

PHASE 2 (ABASIA - AL-AHRAM) (OPENED)

This Phase consist of 4 underground Stations, 7.7 Km length, started in 2009 to be completed in 2013

It comprises different packages for civil, electromechanical and railway works. The contract for civil engineering works has been awarded to Vinci for $323m. Orascom Construction has been awarded contracts worth $140m for civil, electromechanical and railway works.

The cost per kilometer is approximately $ 100 Million

Construction of railway tracks in joint venture Orascom Eurovia Travaux Ferroviaires (ETF), for a contract valued at approximately $24m. This package includes supplying and laying 14km of track and power rail in the tunnel.

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

14

10/26/2014

Page 15: Essam selim   egypt

PHASE 3 (ATTABA- IMBABA -

CAIRO UNIVERSITY)

It extends between Attaba , the center of Rod El Farag on the north and Cairo University on south , with total length of 17.7 km and 16 stations. This phase consists of 3 parts: 1 - Attaba - Kit Kat (two river Nile crossings) 2 - Kit Kat - Rod El Farag passing through the Imbaba 3 - Kit Kat - Cairo University passing through B. Dakrur the opposing conversions facilities for part 1 (Attaba- Kit Kat), planed to start in October 2013 not yet

Budget of this phase in LE 12 Billion using French loan of €900 Million Decision lately to postpone this phase after phase 4

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

15

10/26/2014

Page 16: Essam selim   egypt

PHASE 4(AL-AHRAM - CAIRO

AIRPORT)

It extends between Al-Ahram and Cairo Airport, with total length of 18 km, 10 stations, where 12 km is underground & 6 km is on grad . Decided to start with phase 4 to save mobilization cost of TBM

It is expected to be completed in four years, construction to start in 2014 & completed by 2018.

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

16

10/26/2014

Page 17: Essam selim   egypt

UPDATE OF PHASES 3 & 4

Zamalak citizens opposed the Line 3 rout through their island from their own environmental prospective

NTA announced that an agreement is reached to dig tunnel deeper but the location of the station seems to be not yet agreed

TBM finished phase 2 where it is the start of phase 4,

to mobilize machine as per schedule to start 3, high cost

Decision made not to mobilize TBM and continuously to start phase 4

Phase 4 extended 6 km to Al Salam suburban

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

17

10/26/2014

Page 18: Essam selim   egypt

LINE GEOGRAPHIC

the lines will have both at-grade and viaduct sections. After the underground El-Sudan station, the northern branch will rise on to a viaduct and run within the existing rail corridor on its way to Imbaba station, This sharing of Egyptian National Railways (ENR) land will avoid the problem of finding additional space in the crowded city. The line will stay on a viaduct until it has crossed the city ring road using an elevated, suspended bridge. After this, it will drop to grade level.

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

18

10/26/2014

Page 19: Essam selim   egypt

TECHNICAL & POLITICAL CHALLENGES

line 3 was inaugurated less than six months behind the original planned opening date and in time for a revised target, after facing significant tunneling problems in 2009, as well as the political upheaval that began in 2011

The popular uprising in Egypt had limited impact, that continued almost uninterrupted throughout the occupation of Tahrir Square & other unrest beyond Cairo.

The French lead contractor, confirms that work stopped for just a few weeks in February 2011 before restarting with additional site security in early March.

Phase 2 opened in May 2014 about one year late

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

19

10/26/2014

Page 20: Essam selim   egypt

EXAMPLES OF FACED

TECHNICAL OBSTACLES

The underground utilities in Cairo is so complicated and causes too many delays to the project plan

Press Release by National Authority of Tunneling that Boring of 3rd line second phase ceased because dispute between Electrical Authority on estimated cost of redirecting their cables away of the metro route

The negotiation between the two authorities started 3 months ago Electrical authority exaggerated the cost as per the National Authority of Tunneling

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

20

Page 21: Essam selim   egypt

FINANCE STATUS

The political instability is expected to have more of an effect on the financing of ongoing work and, particularly, the later phases of the line. These are currently being redesigned to save costs by using more above-ground running section

France provided a 280 million dollar loan for the second phase of the project to French companies involved in the project

France approved Loan of Euro 900 Million to finance phase three

Egypt seek LE 12 Billion to complete line 3

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

21

10/26/2014

Page 22: Essam selim   egypt

EGYPT’S FOREIGN RESERVES

DECLINES

Egypt's central bank says foreign currency reserves stood at $13.4 billion last month. That's a less than 1 percent decline from February, but the nation's reserves have fallen sharply from $36 billion since the popular uprising in 2011. The Egyptian government currently is in talks with the International Monetary Fund to secure a $4.8 billion loan to bolster the country's battered economy...

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

22

Page 23: Essam selim   egypt

BY 2025, CAIRO METRO CARRIES 6.5

MILLION PASSENGERS A DAY.”

Construction of Line 4 is yet to begin, The route will begin at El-Malek El Saleh station on Line 1 and end at October-Oasis Highway station.

It is expected to add two more lines. Line 5 will be 20km connecting Nasr city to Port Said Street. It will be a half-circular line connecting to the other lines. Line 6 will extend from north south Shubra to Maadi, and will be 19km long.

ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

23

10/26/2014

Page 24: Essam selim   egypt

LINE 4 PLAN

Extends from the interactive station next to the workshop near Ring Road, north of Dream Land on the border province of October 6 Station via the Grand Egyptian Museum and then the Rmaia square, then EL-Haram Street, Giza Station of line 2 to ended at El-Malak El- Saleh station of line 1

JICA has recommended the execution of phase 1 in the distance between Remaya square up to El-Malek El-Saleh station of line no.1 while line4 will meet the route of line2 in Giza station for the service exchange between the two lines

Length of this phase is 19 km compose of 17 stations

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

24

Page 25: Essam selim   egypt

PHASE 1 OF LINE 4 :

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

25

Page 26: Essam selim   egypt

LINE 3

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

26

Page 27: Essam selim   egypt

CAIRO METRO ACCOMMODATES 80% OF TRANSPORTATION NEEDS

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, [email protected]

27

Page 28: Essam selim   egypt

Alexandria Metro future project

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

28

Page 29: Essam selim   egypt

ALEXANDRIA METRO

Alexandria Metro Line shall extend from Abou-Qier (at the east) to K.P. 21 Matrouh Road (at the west) with a length of about 43 km. The Project phases shall be as follows.

* Phase 1:

from Abou-Qier Railway Station to Misr Station 21.5 km long. 18 Stations , 9 at-grade, 6 over track and 3 viaduct, with a maintenance workshop and rolling stock depot

* Phase 2:

*from Misr Station to Al-Max Station 8 km long, 6 underground stations

Phase 3:

from Al-Max Station to K.P. 21 Matrouh Road (at the west) 13.5 km long, 9 stations, 3 viaduct and 6 under-ground

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

29

Page 30: Essam selim   egypt

LINE 5

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

30

Page 31: Essam selim   egypt

LINE 5

The fifth Line of the Greater Cairo Metro " Nasr City - Heliopolis - El Sawah -Rod El Farag":

this line with a length of about 20 km , the total number of stations will be about 17 underground station.

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

31

Page 32: Essam selim   egypt

LINE 6

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

32

Page 33: Essam selim   egypt

LINE 6

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

33

This line starts from El Khosous , the East of Shubra Al Khiemah, El Sawah Square, then Port Said St. to cross above Line 1 at Ghamrah Station Until El-Sayeda Zeinab Square, to El Fustat Park to intersect with Line 4 , the New Maadi area next to the Satellite area with a length 30 km , 10 km of them on viaduct and about 20 km underground. The sixth line will include 24 Stations, , 4 elevated and 20 underground stations.

Page 34: Essam selim   egypt

EXTENSION OF LINE 2 TO

QALYOUB

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

34

The studies for this line will cost about 25 Million EGP, whereas the construction cost will be around 3 Billion EGP.

• Extension of Line 2 (El Mounib- Shubra Al Khiema) to Qalyoub. • The Route, within the Right of Way of (Cairo – Alexandria Railways Line) so

as to minimize the lands expropriation in the region. • from Shubra Al Khiema station till the city of Qalyoub, The length of this

Part is about 7 km. • The extension will continue with an additional distance of about 1.8 km

to reach the intermodal station, the total length of this extension will be 8.8 km.

• The studies for this line will cost about 25 Million EGP, whereas the construction cost will be around 3 Billion EGP

Page 35: Essam selim   egypt

EXTENSION OF LINE 2 TO

QALYOUB

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

35

Page 36: Essam selim   egypt

PORT SAID ROAD AND

RAILWAY TUNNELS

This project consists of three tunnels two of them are road and the last for railway with an inner diameter of 10,8 meters and its outer diameter is 11,8 meter ,the maximum height is 5.5 meters

10/26/2014 ESSAM SELIM, CONSULTANT OF RAILWAYS & METRO, EASELIM@ IBISEGYPT.COM

36