eodisha summit 2014 - integrating service delivery... - prabhakar barad, deputy director,...
TRANSCRIPT
PRESENTATION
ON
Progress of NPR in ODISHA
Dt. 24th Jan 2014
By
DCO, Odisha
ABOUT NPRGeneration of Aadhaar number of each individual above 5
years is an important component of NPR Project.
NPR Project in the state is conducted as per the provision of
Citizenship Act 1955 and issue of Identity Cards Rule 2003.
Biographic data of each individual was collected during
7th April -22nd May, 2010 in the State.
After data entry the collection of Photo-Biometric Data is now in
progress.
So far out of the target population of 3.84 Crore, Biometric
enrollment is completed for population of 2.47 Crore (64.33%).
1st round collection of Photo-Biometric is completed for 19
districts.
The Biographic data along with Biometric-data are being
uploaded to UIDAI portal.
UIDAI is processing the data generating the Aadhaar number of
each individual and dispatching it directly to the person concerned
through post
PRESENT ENROLMENT STATUS
BME Present Status
24,679,466
13,686,418
BME done
BME leftover
TARGET POP-3,83,65,884
PLAN OF COMPLETION
First Round BME Completed
SI NO DISTRICTTarget
Population 2nd Round BME Status/ Expected
Date of Completion % age
Complete
1 Balangir 1,567,292 In-progress/Jan-2014 88
2 Cuttack 2,352,690 In-progress/Feb-2014 80
3 Khurda 2,059,185 In-progress/Feb-2014 65
4 PURI 1,555,409 In-progress/Feb-2014 83
5 Balasore 2,122,738 In-progress/Feb-2014 75
6 Bhadrak 1,415,040 To be started/Feb-2014 75
7 Jagatsinghpur 1,081,072 To be started/Feb-2014 82
8 Kendrapara 1,380,532 To be started/Feb-2014 79
9 Dhenkanal 1,071,144 To be started/Feb-2014 94
10 Angul 1,146,482 To be started/Feb-2014 78
11 Nayagarh 889,652 To be started/Feb-2014 79
12 Debagarh 282,473 To be started/Feb-2014 88
13 Nuapada 587,759 To be started/Feb-2014 69
14 Boudh 282,972 To be started/Feb-2014 73
15 Kendujhar 1,635,106 To be started/Mar-2014 64
16 Mayurbhanj 2,278,567 To be started/Feb-2014 83
17 Jajpur 1,706,337 To be started/Feb-2014 78
18 Subarnapur 572,826 In-progress/Feb-2014 76
19 Kandhamal 668,751 To be started/Mar-2014 63
Enrolment Operation in Progress
SI NO DISTRICTTarget
Population 1nd Round BME Status/
Expected Date of Completion 2nd Round BME Status/ Expected
Date of Completion % age
Complete
1 Sundargarh 1,872,493 In-progress/ Feb-2014 To be started/ Mar-2014 61
2Bargarh 1,340,163 In-progress/Jan-2014 To be started/ Mar-2014 65
3 Sambalpur 937,739 In-progress/ Feb-2014 To be started/ Mar-2014 50
4Koraput 1,231,755 In-progress/ Feb-2014 To be started/ Mar-2014 34
5 Ganjam 3,238,903 In-progress/ Feb-2014 To be started/ Mar-2014 43
6Gajapati 536,608 In-progress/Jan-2014 To be started/ Mar-2014 64
7 Nabarangpur 1,088,672 In-progress/Jan-2014 To be started/ Mar-2014 62
8Rayagada 866,259 In-progress/ Feb-2014 To be started/ Mar-2014 8
9 Kalahandi 1,424,083 In-progress/ Feb-2014 To be started/ Mar-2014 4
10Jharsuguda 518,616 In-progress/ Feb-2014 To be started/ Mar-2014
11 Malkangiri 540,011 In-progress/ Feb-2014 To be started/ Mar-2014
DBT/DBTL Odisha
Four districts viz. Balangir, Puri, Khordha & Cuttack
were selected for DBTL where the scheme is to be operated
from 1st Feb 2014.
Subarnapur district has been selected for DBT .
Further three more districts viz. Baleswar, Bhadrak &
Sundargarh have been selected for DBTL where the scheme is
to be operated from 1st April 2014.
As per Directive from ORGI, Special Camps were setup at all
distributer premises of Balangir district on pilot basis from
14-Dec-2013 to 22-Dec-2014 with extension upto 31-Dec-2013
and further extension upto 31-Jan-2014. (Total 47 days)
Operator Utilization as on 17-Jan-2014-At Balangir
Coverage Of NPR Left Out Population
Left out population in First Round is covered during
Second round of BME operation along with the new
entrants in the concerned Enumeration Block (EB).
Enumerators are inviting Enrollees by visiting door to
door in their EBs to ensure their presence at BME
camps.
If Capture percentage is still low, there will be
establishment of special centres for BME under
close supervision of Tahasil/Town/District
Administration.
Coverage of “Out of NPR” Population
To cover the persons who were not covered during NPR
survey or he/she is a new entrant after NPR, fresh NPR
schedules were filled up during First Round of BME
operation by the Enumerator under his/her jurisdiction.
For these persons Demographic Data entry were done at
Bulk Data Center.
Afterwards these population are being covered during
Second round of BME operation.
Coverage of DBT / DBTL Beneficiaries
2nd round BME operation in DBT districts to cover all left-out
including DBT/DBTL beneficiaries has been prioritized.
Deployment of Kit had been made as per the requirement of
of concerned DBT departments at Charge level camps.
Steps taken for collection of Photo-Biometric Data :
1. List of left-out whose BME is required is being prepared.
2. Arrangement has been made for filling-up NPR data in the
prescribed form.
3. Program for collection of Photo-Biometric data is now taken up.
4. Left-out beneficiaries are being called to the respective camps as
per program.
5. State Government has sanctioned a sum of Rs 53.64 lacs for
establishment Of Permanent Centres for four months to collect all
the left out persons in eight DBT districts.
Coverage of Rejected Enrolments
It is reported that BME packets of some persons are rejected due
to various reasons causing disappointment to the people who have
already gone through BME operation.
A sense of doubt is created among the people when they got the
message of rejection.
A huge number around 30 lakhs of BME have been reported
rejected due to data/process error.
Coverage of Rejected Enrolments….Contd
BME packets were successfully generated during enrolment
and same were accepted during uploading at CIDR server.
Total technology for generation of BME packets were provided
by highly technical team of UIDAI authority considering all
technical aspects and protocols.
UIDAI authority is requested to reconsider the rejected packets
for Generation of Aadhaar Number as these were not rejected
during enrolment.
Steps are being taken for installation of helpline by
UIDAI to sort out the rejected enrollments.
Setting-up of Permanent Enrollment Centres
And RGI policy for coverage of under 5 age group
The proposal for setting-up of permanent Enrolment centres at
districts/ sub-districts is now under active consideration. ECIL
is starting BME enrollment at Tahsil/ Block offices on 25th Jan
at Cuttack, Khurdha, Puri, Balangir, Balasore, Bhadrak .
There is no proposal for biometric coverage of under 5 age group,
however those who attain age group of 5 will be covered in the
permanent centres.