employee involvement using kaizen events · the kaizen approach in the proposals process total...

21
© 2016 Aker Solutions Employee Involvement Using Kaizen Events Continuous Improvement Seminar, 1 st December 2016 Gary Downs, VP Lean Deployment November 30, 2016 Slide 1

Upload: others

Post on 23-Sep-2019

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Employee Involvement Using Kaizen Events

Continuous Improvement Seminar, 1st December 2016

Gary Downs, VP Lean Deployment

November 30, 2016 Slide 1

Page 2: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Page 3: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Lean is 90% Attitude & Behaviours, 10% Tool Application

November 30, 2016 Slide 3

Tools &

Methods

Behaviours

Attitudes

Page 4: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Process for Kaizen Competency Build

Slide 4

Attend4 day

Kaizen training

Co-deliver Kaizen 110%

90% supported by

qualified Kaizen facilitator

Co-deliver

Lean & Kaizen

Training 1

Co-deliver Lean & Kaizen

Training 2

Co-deliver Kaizen 250%

50% supported by

qualified Kaizen facilitator

Co-deliver Kaizen 390%

10% supported by

qualified Kaizen facilitator

Kaizen facilitator

Kaizen Trainer

Senior Leaders

Attend3 day

Kaizen training

Senior Leaders

participate in

Kaizen Events

Senior Leaders

Sponsor

Kaizen Events

Senior Leaders

Page 5: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

The Kaizen ApproachKaizen is a vehicle to execute improvements quickly and help

build a culture of employee involvement

Pre-Event prep (1 day) 3 weeks before event

Identify and plan the agreed scoped event:

Define the problem with a clear problem statement

Measure the baseline and establish goal(s)

Plan the timing of execution of the event by team

Carry out a Value Stream Mapping session

Deliver any relevant training

Kaizen Event (3-5 days)

Engage the team to validate the problem:

Carry out Root Cause analysis

Check for any unintended consequences of proposed solutions.

Test and Implement do-now solutions during the Kaizen-implement a minimum of 90% during Kaizen

Report out daily for Management buy in

Event Follow up (21days)

Follow-up actions typically end 21 days following the Kaizen

November 30, 2016 Slide 5

Page 6: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Kaizen Change Readiness

November 30, 2016 Slide 6

1. Rate the new process (P) from 1 to 10

2. Rate the level of acceptance (A) from 1 to 10

3. Multiply the two numbers; e.g.

P9 X A2 Results = 18

P7 X A5 Results = 35

Conclusion

Trying to force a perfect process without buy-in, is less effective than a less-

than-perfect process, with buy-in from those who use it

Process (P) x Acceptance (A) = Results

Page 7: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Current State Process Map

November 30, 2016 Slide 7

Page 8: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Kaizen Implementation Center (KIC)

■ Used to control Kaizen Event

deliverables

■ All actions added to KIC

■ Daily review of open / closed actions

■ Actions closed during event:

■ Day 1: 8 - expanding on issues

■ Day 2: 10 - Providing solutions

■ Day 3: 13 - Delivering solutions,

implementing new layout,

updating procedures, flows etc

■ Day 4: 14 - Implementing new

layout, designing standard work

■ Day 5: 17 - Closing out

remaining actions

■ Grand total: 62

November 30, 2016 Slide 8

Page 9: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

PSV Workplace Organisation Kaizen

November 30, 2016 Slide 9

Page 10: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

PSV Workplace Organisation Kaizen | BEFORE

November 30, 2016 Slide 10

Page 11: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

PSV Workplace Organisation Kaizen | AFTER

November 30, 2016 Slide 11

Page 12: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Red Tagging and Waste Removal

■ 3 tonnes of metal waste

removed

■ 2.5 tonnes of Unserviceable

Electrical Equipment removed

■ 3 tonnes of paperwork

removed

■ Out of three unserviceable

extraction units, one repaired

and two removed from site

November 30, 2016 Slide 12

Page 13: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Standard Bay Before & After

■ With newly designed standard bays the

capacity for Welding, Fitting and or

Plating Bays has risen from 10 to 13

with, four more on the freed-up

Mezzanine deck, which represent 70%

increase in capacity

■ Tradesmen no longer have to provide

their own tools

November 30, 2016 Slide 13

Before

After

Page 14: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Shadow Boards and Bay Replication Complete

November 30, 2016 Slide 14

Material laydown areas marked and bin allocated to

each bay to reduce motion waste, increasing tool time

Page 15: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

HSE

■ Safe working throughout

kaizen event

■ Ergonomics - height adjustable

benches

■ Repainting of hazard lines

■ Shadow board frames

designed to incorporate hooks

to safely store wiring reducing

trip hazards

■ Removal of expired first aid

materials (e.g eyewash 2010)

■ New actions raised – fire risk

assessment, laser, extraction/

ventilation

November 30, 2016 Slide 15

Page 16: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Benefits

■ Reduction in motion waste (approx

73% for the most frequent job

type)

■ 8.5 tonnes removed – electrical,

paperwork, scrap metal

■ Additional space created for 4

bays on mezzanine deck for

Exotics welding pending HSE

approval

■ 230m2 space freed-up for potential

production bays

■ 70% increase in production with

introduction of new bays

■ Cost avoidance - removing need

for additional facility for Mariner

workload

November 30, 2016 Slide 16

Page 17: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

DCV Change Out Process Proposal

November 30, 2016 Slide 17

Page 18: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

DCV Change Out Process – As Was

■ Current process cycle time best case = 219 hours; worst case = 256

hours

■ SCM is constantly transported from one work area to another; ■ Potential for damage to module (cables, pipework, components) – Defects

■ Increased HSE risk (movement around people) – Defects, Waiting, Safety

■ Delays for other jobs to progress (use of crane, use of clean room) – Waiting

■ Current process requires complete removal of top cover and cutting

of all attached wiring and base plate Tronics

■ This process must be followed in order to allow installation within the

clean room

■ Module is contaminated in comparison to clean room

It is impossible to clean a fully populated module prior to

introducing it into the clean room, which increases the chance of

contaminating the clean room and other modules currently in situ.

November 30, 2016 Slide 18

Page 19: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Opportunity / Benefit of DCV Swap Out

■ Reduce overall cycle time by

74.5% (56 hours down from 219)

■ Module transportation reduced

from■ 5 crane movements 1 crane

movement – 80% improvement

■ 18 other crane activities 6 other

crane activities – 67%

improvement

■ Reduced risk of HSE incidents

■ Creating opportunity to progress

other jobs quicker

■ Reduced opportunity for damage

to module components

■ Contamination potential

unchanged■ No data available to suggest

November 30, 2016 Slide 19

Page 20: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

The Kaizen Approach in the Proposals Process

■ Total duration 22 days; only 4 days spent full time on the project

■ Benefits: Visual Management to show any delays

■ During the first 10 weeks after the Kaizen, the team submitted:■ Four tenders

■ Three requests for information

■ Three supplier questionnaires

■ Two contract negotiations

■ One estimate

■ Successes include:■ Study award for the FES team

■ A new customer for PSV

■ Three tenders submitted ahead of schedule – one delivered 8 days early!

■ Signed contract extension for a three year term

November 30, 2016 Slide 20

22nd May

Discussion with

Sponsor

24th May

A3 written; team

& dates agreed

29th May

VSM session

carried out

13th June

Kaizen

complete

Page 21: Employee Involvement Using Kaizen Events · The Kaizen Approach in the Proposals Process Total duration 22 days ; only 4 days spent full time on the project Benefits: Visual Management

© 2016 Aker Solutions

Copyright and Disclaimer

CopyrightCopyright of all published material including photographs, drawings and images in this document remains vested in Aker Solutions and

third party contributors as appropriate. Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor

used in any manner without express prior permission and applicable acknowledgements. No trademark, copyright or other notice shall

be altered or removed from any reproduction.

DisclaimerThis Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and

uncertainties that could cause actual results to differ. These statements and this Presentation are based on current expectations,

estimates and projections about global economic conditions, the economic conditions of the regions and industries that are major

markets for Aker Solutions ASA and Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations,

estimates and projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar

expressions. Important factors that could cause actual results to differ materially from those expectations include, among others,

economic and market conditions in the geographic areas and industries that are or will be major markets for Aker Solutions’ businesses,

oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency

exchange rates and such other factors as may be discussed from time to time in the Presentation. Although Aker Solutions ASA believes

that its expectations and the Presentation are based upon reasonable assumptions, it can give no assurance that those expectations will

be achieved or that the actual results will be as set out in the Presentation. Aker Solutions ASA is making no representation or warranty,

expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Aker Solutions ASA nor any of its

directors, officers or employees will have any liability to you or any other persons resulting from your use.

Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the

common brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when

we refer to Aker Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions

company.

November 30, 2016 Slide 21