earned value analysis. making 'gravity
DESCRIPTION
TRANSCRIPT
M A K I N G ‘ G R A V I T Y ’
ALFONSO CUARÓN IS DIRECTING AN EPIC SCIENCE FICTION THRILLER (RIGHTS SOLD TO WARNER BROS.), TAKING HIM 11 MONTHS TO COMPLETE THE PRODUCTION, STARTING MARCH, 10, 2011
P L A N F I G U R E S
ACTIVITY START DURATION BUDGET DISTRIBUTIONDEVELOPMENT MARCH 2 2 1-1ART DIRECTION & PREVISUALIZATION MARCH 4 15 6-5-3-1FILM SETTING APRIL 2 2 1-1FILMING MAY 3 6 3-2-1EDITING (FINAL CUT) JULY 2 4 3-1SPECIAL (VISUAL) EFFECTS AUGUST 2 50 35-15STEREO RENDERING (3D CONVERTING) SEPTEMBER 2 2 1-1CONVERSION WORK SEPTEMBER 1 4 -POST-PRODUCTION NOVEMBER 2 12 7-5MUSIC NOVEMBER 1 1 -MARKETING DECEMBER 2 2 1-1
B U D G E T | $ 1 0 0 M I L L I O N
0 8 | 0 1 | 1 1
ACTIVITY EV ACDEVELOPMENT 2 2ART DIRECTION & PREVISUALIZATION 14 18
FILM SETTING 2 2FILMING 6 7EDITING (FINAL CUT) 2 3SPECIAL (VISUAL) EFFECTS 3 6STEREO RENDERING (3D CONVERTING) 0 0
CONVERSION WORK 0 0POST-PRODUCTION 0 0MUSIC 0 0MARKETING 0 0
G A N T T C H A R T
MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN
DEVELOPMENT 1 1PREVISUALIZATION 6 5 3 1FILM SETTING 1 1FILMING 3 2 1EDITING (FINAL CUT) 3 1SPECIAL (VISUAL) EFFECTS 35 15STEREO RENDERING 1 1CONVERSION WORK 4POST-PRODUCTION 7 5MUSIC 1MARKETING 1 1
| 2011 | 2012
C A L C U L A T I O N S
BAC=100 PV=28 EV=29 AC=38
SV=1,04 CV=-9 VAC=-31,03
SPI=1,04 CPI=0,76 TCPI=1,15
EACt=8,68 EAC=131,03 CR=0,79
B E L E N O V A A N A S T A S I A | L E O N T ’ E V D I M A