Download - Robert Ioffrida - Lend Lease
NorthConnex Technical Presentation13th Australian Tunnelling Conference
Presented by Robert Ioffrida, Project Director
Project Overview
Who is delivering NorthConnex?
3
Project - Key Stakeholders
• Transurban, Canada Pension Plan and QIC
Client (Project Co.)
• Lendlease Bouygues JV (50/50)Contractor
• Aurecon SMEC JV (50/50)Designers
Lendlease Bouygues Joint Venture
Project - Key Dates
• 13 January 2015Project Approval
• 18 June 2015Start Construction
• 3rd Qtr 2015Start Tunnelling
• 4th Qtr 2019Completion
Lendlease Bouygues Joint Venture
5
Project – Expected Project Personnel
• 400 +LLBJV Staff
• 160+LLB/UGL Alliance
Staff
• 500+ 300+ Tunnelling and 200+ Civil Employees
LLBJV Direct Labour
• 800+ (including M&E)Contractor
Partners
Lendlease Bouygues Joint Venture
What is NorthConnex?
• NorthConnex will provide the vital
link between Hills M2 Motorway
and the M1 Pacific Motorway.
• Two key components – Tunnel and
M2 Integration Works
• Australia’s longest and deepest road
tunnel – longer than the Eastern
Distributor, M5 East and Cross City
tunnels combined
Lendlease Bouygues Joint Venture
7
Project scope
• Twin motorway tunnels - nine kilometres in
length / two lanes plus a breakdown lane in
each direction, and a speed limit of 80 km/h (or
90?)
• Each tunnel will be built with future capability to
provide three lanes in each direction at reduced
speed
• A northern interchange connecting with the M1,
the Pacific Highway & Pennant Hills Road
• A southern interchange connecting with the Hills
M2 Motorway and Pennant Hills Road
Lendlease Bouygues Joint Venture
8
• A motorway control centre and ancillary
buildings, southern and northern ventilation
outlets and water treatment plant near the
southern interchange
• Ancillary facilities for operation, such as
electronic tolling facilities, ventilation
facilities as well as fire and life safety
systems
• Two additional smoke exhaust shafts in the
event of an underground fire
• Modifications to service utilities and
associated work at surface roads near the
two interchanges
Lendlease Bouygues Joint Venture
9
Project scope cont.
Pioneer Avenue Construction Compound
M2 Integration Works
Project Map
Tunnelling – Basic schemeMain construction sites
Southern Interchange – M2 Portal
Wilson Road – Smoke Extraction Shaft
Trelawney Street – Smoke Extraction Shaft
Northern Interchange - M1 Portal
Southern InterchangeM2 Portal
WILSON SHAFT
TRELAWNEYSHAFT
M1 InterchangeNorth Portal
11
Tunnelling – major quantities
Scope Quantity
Tunnel length - mainline tunnel 16,313 m
Tunnel length - cross passage only 1,375 m
Tunnel length - on and off ramp 3,177 m
Tunnel length - Y Junctions 1,050 m
Quantity - cross passages 75 pc
Quantity - substation underground 2 pc
Quantity - low point sumps underground 1 pc
Quantity - shafts 4 pc
Excavation total 2,250,000 m3
Project Design Features
Standard Cross Section Main Carriageway
2 lane tunnel designed for future 3 lane use
Dynamic envelope = 10.5m x 5.3m
Tunnel Concept :
- Mechanized excavation using road headers / rock boltings and shotcrete
- Drained tunnel: 1l/s/km allowable water inflow limit.
- Waterproof membrane to divert water away from tunnel crown
14
Mechanical and Electrical Design
Electrical Systems• High voltage reticulation
• Low voltage reticulation
• Tunnel lighting
• Street lighting
• Emergency exit lighting
• Fire detection
Control Systems• Control room & video wall
• Plant management & control system
• Traffic management & control system
• Closed circuit television / Video incident detection
• Electronic signage
Mechanical Systems
• Tunnel ventilation
• Drainage
• Mechanical ventilation & air conditioning
• Tunnel air monitoring include air dispersion
• Fire and life safety strategy
• Fire suppression and tunnel fire doors Lendlease Bouygues Joint Venture
Communication systems
• Phones
• Public address
• Radio rebroadcast
• Mobile phone rebroadcast
Additional site investigation
Geology
16
Geology
Competent geology / with localized features
Largely in Hawkesbury sandstone with some Ashfield shale
17
Soil and extremely weathered
rock
Ashfield shale
Mittagong
Formation
Hawkesbury
sandstone
Permanent Lining - Cast in situ
Typical Cross Section – Shale only
Volume Kicker = 1.6m3/m
Volume Vault = 7.16m3/m
Perimeter = 22.7m
18
Permanent Lining – Sprayed Shotcrete
Typical Cross Section – Hawkesbury Sandstone
Volume Vault = 2.72m3/m
Perimeter = 16.6m
19
Tunnel Construction
Southern Portal and Ramps - Sequence of Excavation
21
Typical Tunnel Sections
22
Environmental Layout - Wilson Shaft
23
Shaft depth
Shaft Depth (collar to invert)
Southern Interchange 12/30m
Wilson Road 81.3m
Trelawney 56.6m
M1 Interchange 43.7m
24
Excavation Sequence – Wilson Shaft
25
Typical Noise Shed arrangement / Conveyor
26
Shaft access to tunnel
Lendlease Bouygues Joint Venture
Shaft access to tunnel
Lendlease Bouygues Joint Venture
Excavation Sequence – Shafts
Excavation Sequence – Tunnel Level
30
Excavation Sequence – Tunnel Level
31
Excavation Sequence – Tunnel Level
32
Excavation Sequence Tunnel - Cut
33
Different Excavation Activities in the tunnel
34
Shotcrete Trials
35
Plant (Shaft Jumbo)
36
Tunnel Procurement - Plant
(Roadheader Fabrication in Japan)
37
Tunnel Procurement - Plant (Road header Fabrication in
Austria)
38
Tunnel Excavation
Lendlease Bouygues Joint Venture
Tunnel Procurement - Plant (Shotcrete Machines)
40
Tunnel Procurement - Plant (Mobile Agitator and Bolter)
41
Ventilation Fan
– Ventilation: Forced Overlap system chosen with 35and 50 M3/s de-Dusters
42
Program of Works
Tunnelling – Basic scheme
General sequence of excavation:
1- RH excavation 1- XP Excavation 2- Benching 3- Lining / waterproofing
(1 activity in the program)
4- Drainage/Cable pit 5- Paving (no fine, asphalt, CRCP)
excavation ducts install backfill
Access to M&E Blue: Civil Activities
7- Cable Pulling Red: M&E Activities
7- M&E 1st Fix (cable trays, fans, cables)
6- Traffic Barriers fundation 7- Cladding frame support 8- Install Traffic Barriers
Access to M&E 11- Commissioning
9- Infill Concrete 10- M&E 2nd Fix (cable termination) 11- Cladding installation
11- Low noise diamond grind, pavement, line mark
together
Benching starts once excavation for full length of regular section is
completed by Road header
Enlarged section will be excavated once full length of regular section
is completed by road header
1- RH excavation 1- XP Excavation 2- Benching 3- Lining / waterproofing
(1 activity in the program)
4- Drainage/Cable pit 5- Paving (no fine, asphalt, CRCP)
excavation ducts install backfill
Access to M&E Blue: Civil Activities
7- Cable Pulling Red: M&E Activities
7- M&E 1st Fix (cable trays, fans, cables)
6- Traffic Barriers fundation 7- Cladding frame support 8- Install Traffic Barriers
Access to M&E 11- Commissioning
9- Infill Concrete 10- M&E 2nd Fix (cable termination) 11- Cladding installation
11- Low noise diamond grind, pavement, line mark
together
Benching starts once excavation for full length of regular section is
completed by Road header
Enlarged section will be excavated once full length of regular section
is completed by road header
M2 WILSON TRELAWNEY M1
NB Entry Ramp (M1C0)M1C0N1 M1C0N2
M2 ACCESS SHAFT FOR M110 & M120 S110N OUT M1C0N2 OUT T110N OUT T110N OUT
NB (M110) S110N M1C0N2 W110S W110N T110S T110N N110S N110N
M2W110S OUT T110S OUT N110S OUT
M1S120N OUT M1C0N1 OUT W120N OUT T120N OUT
SB (M120) M1D0N S120N M1C0N1 W120S W120N T120S T120N N120S N120NM1D0N OUT W120S OUT T120S OUT N120S OUT
N110N NB EXIT RAMP (M1P0)
SB Exit Ramp (M1D0) M1C0N1 M1D0N
N110N OUT
N120N SB ENTRY RAMP (M1Q0)N120N OUT
TEMPORARY
ACCESS TO SB &
M1D0 (XP13)
XP83 ACCESS
FOR ROAD
HEADER TO
M1DO
M1
C0
N1
44
Community Benefits
Hornsby Quarry (before)
Lendlease Bouygues Joint Venture
Hornsby Quarry (after)
Lendlease Bouygues Joint Venture
Local Engagement
Lendlease Bouygues Joint Venture
• Promote opportunities for local businesses
• Promote opportunities for local employees