Transcript
Page 1: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

Nigeria Erosion and Watershed Management Project (NEWMAP)

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

FOR IYI-UDELE FLOOD SITE IN ABAKALIKI CAPITAL CITY

DRAFT FINAL REPORT

State Project Management Unit (SPMU) Abakaliki, Ebonyi State.

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

ii

TABLE OF CONTENTS

Content Page

Cover Page

Table of Contents ii

List of Tables vi

List of Figures vii

List of Plates viii

List of Abbreviations and Acronyms ix

Executive Summary xii

CHAPTER ONE: INTRODUCTION

1.1 Background of the Project 1

1.2. Description of the intervention 2

1.2.1 Likely impacts of the Project 4

1.3 Rationale and Objective of the project 4

1.4 Scope of the Project’s ESMP 5

CHAPTER TWO: INSTITUTIONAL AND LEGAL

FRAMEWORK FOR ENVIRONMENTAL MANAGEMENT

2.1 Background 7

2.2 Policy and Legal Framework 7

2.3 Administrative Framework 9

2.3.1 Federal MDAs 9

2.3.2 State MDAs 9

2.3.3 World Bank Safeguard Policies 9

2.4 International Treaties and Conventions on

Environment to which Nigeria is a party 10

Page 3: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

iii

CHAPTER THREE: BIOPHYSICAL ENVIRONMENT

3.1 Introduction 12

3.2 Description of the Project Site 12

3.2.1: Farming Activities in the Proposed Project Area 16

3.3. Specific Project Design and Alternative 17

3.4 Physical Environment 17

3.4.1 Geology and Hydrology of the Proposed Project Area 17

3.4.2 Physiography and Climate 17

3.5 Environment Quality Assessment 23

3.5.1 Analysis of Soil Samples 23

3.5.2 Physico-Chemical Characteristics of the Soils 23

3.5.3 Metal Content of the Soils 27

3.6 Physico-Chemical Analysis of Water Samples 28

3.7 Biological Environment 31

3.7.1 Ecosystem 31

3.7.2 Vegetation 31

3.7.3 Fauna and Wildlife Resources 34

3.8 Air Quality and Noise 36

CHAPTER FOUR: SOCIO-ECONOMIC CHARACTERISTICS

AND CONSULTATION

4.1 Introduction 39

4.2 Methodology 39

4.3 Population Estimation and Projection 40

4.4 Gender and Age of Respondents 40

4.5 Current Marital Status of Respondents 42

4.6 Educational Status of Respondents 42

4.7 Occupation of Respondents 43

4.8 Religion and Culture 44

4.9 Assessment of Health Status of Respondents 44

Page 4: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

iv

4.10 Method of Waste Disposal 44

4.11 Accessible Sources of Water 45

4.12 Project Activity Impact Evaluation 45

4.13 Stakeholders Consultation 46

CHAPTER FIVE: ASSESSMENT OF POTENTIAL IMPACTS

AND ANALYSIS OF ALTERNATIVES

5.1 Introduction 51

5.2 Impact Identification and Evaluation 51

5.3 Potential Impacts of the Projects 51

5.3.1 Potential Positive Impacts 51

5.3.2 Potential Negative Impacts 52

5.3.2.1 Negative Environmental Impacts 53

5.3.2.2 Negative Social Impacts 54

5.4 Analysis of Project Alternatives 57

5.4.1 No Action Option 58

5.4.2 Delayed Project Option 58

5.4.3 Go Ahead Option 58

CHAPTER SIX: ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN

6.1 Introduction 60

6.2 Mitigation Measures 60

6.3 Project Monitoring 74

6.4 Institutional Arrangements 83

6.5 Capacity Building and Training 84

6.6 ESMP Implementation Schedule 86

6.7 Summary ESMP Estimated Budget 87

Page 5: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

v

CHAPTER SEVEN: SUMMARY, RECOMMENDATIONS AND CONCLUSION 88

References 90

Appendix I 92

Appendix II 99

Appendix III 100

Appendix IV 106

Page 6: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

vi

LIST OF TABLES

Table 2.1: Relevant Federal/State Policies, Legislations, Regulations & Guidelines 7

Table 2.2: International Treaties and Conventions on Environment to which Nigeria is a Party 11

Table 3.1: Climate Data of Abakaliki, Ebonyi 20

Table 3.2: Physico-chemical and microbial results of soil samples from the study area 24

Table 3.3: Basic and heavy metal concentrations of the top soil (0–15 cm) 27

Table 3.4: Basic and heavy metal concentrations of the sub soil (15–30 cm) 28

Table 3.5: Result of Physicochemical Analysis of Water Samples 30

Table 3.6: Terrestrial Floral Species Recorded in the Study Area 33

Table 3.7: Terrestrial Fauna Species Recorded in the Study Area 34

Table3.8: Results of ambient air quality measurements at the proposed project area 36

Table 3.9: Ambient noise levels for the project area 38

Table 4.1: Details of the Sampling Methodology and the Questionnaires Administered 39

Table 5.1: Probability of Occurrence, Severity, Likelihood Ranking and Risk Matrix 52

Table 5.2: Potential positive and negative environmental and social impacts 56

Table 6.1: Environmental Management Plan 66

Table 6.2: Social Management Plan 71

Table 6.3: Mitigation measures and related monitoring activities( Environmental Section) 75

Table 6.4: Mitigation measures and related monitoring activities (Social Section) 81

Table 6.5: Institutional Roles and Responsibilities 83

Table 6.6: Proposed Training Programme for the Implementation of ESMP 85

Table 6.7: ESMP Implementation Schedule 86

Table 6.8: Details of ESMP Cost Estimation 87

Page 7: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

vii

LIST OF FIGURES

Figure 1.1: Iyi-udele River System and locations of Flood Hot Spots 2

Figure 1.2 Typical Cross Section of Channel Drain 3

Figure 1.3 Iyiudele Plan and Profile 3

Figure 3.1: Map of Ebonyi State depicting the LGA of the Proposed Project 13

Figure 3.2: Drainage Pattern of Abakaliki Capital City and the flood hotspot sites 14

Figure 3.3: Map of Ebonyi State Showing the Location of Iyi-Udele 15

Figure 3.4: Imagery of Iyi Udele River and its Flood Plain 16

Figure 3.5: Geology of Abakaliki 19

Figure 3.6: Rainfall Intensity in the Proposed Project Area 21

Figure 3.7: Rainfall Intensity Duration in Proposed Project Area 21

Figure 3.8: Wind Rose Diagram in the Proposed Project Area 22

Figure 3.9: Soil Sample Points 25

Figure 3.10: Water Sample Points 29

Figure 3.11: Spatial Distribution of Air Quality Sample Points 37

Figure 3.12: Ambient Noise Sampling Points 38

Figure 4.1: Projected Population for Abakiliki LGA from 2006-2015 40

Figure 4.2: Gender of Respondents 41

Figure 4.3: Age Range of Respondents 41

Figure 4.4: Marital Status of Respondents 42

Figure 4.5: Educational Status of Respondents 42

Figure 4.6: Occupation of Respondents 43

Figure 4.7: Religion of the Respondents 44

Figure 4.8: Refuse (Solid Waste) Disposal Method 45

Figure 4.9: Impact assessment by respondents 46

Page 8: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

viii

LIST OF PLATES

Plate 3.1: Iyi-Udele River channel downstream and upstream Ogbaga Road 13

Plate 3.2: Secondary Vegetal Cover at Perimeter fence erected well inside the channel 32

Plate 3.3: A cross-section of the vegetation type found in the area 33

Plate 4.1: Consultant and Community Members in the Town Hall Meeting 47

Plate 4.2: Consultant Interacting with the Youths During the FGD 47

Plate 4.3: Consultant Interacting with the Men during the FGD 48

Plate 4.4: Pictures of Consultant with the Women after the Meeting 48

Plate 4.5: Interactive Session with a String Women Politician Led by a Youth at Iyi-Udele Area 49

Plate 4.6: In-depth Interview with Assembly Church of God Member at Iyi-Udele Area 50

Page 9: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

ix

LIST OF ABBREVIATIONS AND ACRONYMS

BOD Biochemical Oxygen Demand

CBOs Community Based Organizations

DO Dissolved Oxygen

EA Environmental Assessment

EBSEPA Ebonyi State Environmental Protection Agency

EC Electrical Conductivity

EFCZM Erosion, Flood and Coastal Zone Management

EIA Environmental Impact Assessment

ESMF Environmental and Social Management Framework

ESMP Environmental and Social Management Plan

ESO Environmental Safeguard Office

FEPA Federal Environmental Protection Agency

FMEnv Federal Ministry of Environment

FMWR Federal Ministry of Water Resources

FRSC Federal Road Safety Corps

GEF Global Environmental Facility

HIV/AIDS Human Immunodeficiency Virus / Acquired Immunodeficiency Syndrome

HSE Health Safety and Environment

HUB Hydrocarbon utilizing bacteria

IUCN International Union for Conservation of Nature

LGA Local Government Area

Lmax Maximum Noise Levels

Lmin Minimum Noise Levels

MDAs Ministries Departments and Agencies

MEAs Multilateral Environmental Agreements

MFMP Multilateral Fund for the Implementation of Montreal Protocol

MSL Mean Sea Level

ND Not Detected

NESREA National Environmental Standards and Regulations Enforcement Agency

NEWMAP Nigeria Erosion and Watershed Management Project

NGOs Non-Governmental Organization

NIMET Nigeria Meteorological Agency (NIMET)

NIOSH National Institute for Occupational Safety and Health

NIWRMC Nigeria Integrated Water Resources Management Commission

NWRI National Water Resources Institute

PAPs Project Affected Persons

PC Project Coordinator

PAD Project Appraisal document

PIM Project Implementation Manual

PMU Project Management Unit

PPE Personal Protective Equipment

PVC Polyvinyl Chloride

RAM Risk Assessment Matrix

RAP Resettlement Action Plan

RPF Resettlement Policy Framework

Page 10: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

x

SCCF Special Climate Change Fund

Sp Species

SPM Suspended Particulate Matter

SPMU State Project Management Unit

STD Sexually Transmitted Disease

TOR Terms of Reference

THB Total heterotrophic bacteria

WHO World Health Organization

WMP Waste Management Plan

THC Total Hydrocarbons

HUB Hydrocarbon Utilizing Bacteria

HUF Hydrocarbon Utilizing Fungi

THF Total Heterotrophic Fungi

UNITS OF MEASUREMENT

% Percentage

µg Microgramme

µS/cm Microsiems/centimeter

cfu/gm Colony forming unit per gramme

Cm Centimeter

cmol/kg Centimoles per kilogram

dB Decibel

Hrs Hours oC Temperature in degrees Celsius oE Degree East oN Degree North

kg Kilogramme

km Kilometer

pH Hydrogen ion concentration

ppm Parts per million

mm Millimeters

m/s Meter per second

mg/kg Milligramme per Kilogramme

mg/l Milligram per liter

m Meter

ds/m Decisiemens per meter

kN/m Kilonewton per meter

km Kilometer

CHEMICAL ELEMENTS AND COMPOUNDS

Ca Calcium

CaCO3 Calcium Carbonate

Cl- Chloride

CO Carbon Monoxide

Cu Copper

Fe Iron

Page 11: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xi

H2S Hydrogen Sulphide

HCN Hydrogen Cyanide

Hg Mecury

K Potassium

Mg Magnesium

Mn Manganese

Na Sodium

NH3 Ammonia

NO3 Nitrate

NO3- Nitrate ion

NOx Nitrogen Oxides

Pb Lead

AV.P Average Phosphorus

PO43- Phosphate

SO2 Sulphur dioxide

SO42- Sulphates

TDS Total Dissolved Solids

THC Total Hydrocarbons

TSS Total Soluble Solids

Zn Zinc

Page 12: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xii

EXECUTIVE SUMMARY

Background of the Project

The Nigeria Erosion and Watershed Management Project (NEWMAP) is an intervention project

for the management of the erosion and watershed challenges in Nigeria more especially within the

South-East and South-South of the Country. It is assisted by World Bank, the Nigeria Government

and supported by Global Environmental Facility (GEF) and the Special Climate Change Fund

(SCCF). The project initially targeted seven states namely Anambra, Abia, Cross River, Edo,

Enugu, Ebonyi, and Imo. However six additional states including Plateau, Kogi, Kano, Delta, Oyo

and Gombe have recently joined the programme.

Iyi-udele flood site in Abakaliki capital city is one of the priority sites for intervention under the

Ebonyi State Nigeria Erosion and Watershed Management Project (EBONYI-NEWMAP). The

construction works proposed for this site will involve medium-sized civil works which are likely

to cause negative environmental and social impacts. In order to minimize these impacts an

Environmental and Social Management Plan (ESMP) has been prepared in this report. The

overarching objective of the ESMP is to ensure that the environmental and social impacts likely to

arise from the project activities are addressed and appropriate mitigation measures are integrated

into project implementation and operation in order to protect human and environmental health.

The objective of this project is to prepare an environmental and social management plan (ESMP)

for the Ebonyi State sub-projects in Iyi –Udele Flood intervention site. It is also to facilitate

effective decision-making and ensures that implementation processes during the execution of the

proposed projects activities are sustainable.

Project Location

The Iyi –Udele Flood Site is located in Abakaliki Capital City of Ebonyi State (see figure 3.1). It

lies between latitudes 6o20’17.04” and 6o19’08.88”N and Longitudes 8o06’22.20” and

8o07’26.22”E, (official co-ordinates of project sites). It cuts across Ebonyi and Abakaliki Local

Government Areas of Ebonyi State, South-East Nigeria.

Specific Project Description

The Iyi –Udele Flood Site is one of the three principal tributaries of Eastern Ebonyi River that

drain Abakaliki Capital City. The flooded area has elevation ranging between 49m and 57m Mean

Sea Level approximately. Its source is within the city and it flows south-eastwards into River

Ebonyi. It is mainly drained by the River (Iyi) Udele from vantage points at Ogbaga Road,

Udensi Street, Nna Street, Assembly Church of God and Aniekwena . Some lined service drains

empty into some segments of the river as in Ogbaga area. Its catchment area spreads over the

Abakaliki township with urbanization as the main land use practice. However, some part of this

catchment area is still underdeveloped but it is intensively exploited for agriculture. The degree of

anthropogenic encroachment varies along the stretch of the river causing severe constrictions along

the river course. There is considerable evidence of solid waste dumping along the river channel

as may be seen at Ogbaga road. Although the terrain is gently undulating as is typical of the area,

the combinations of intensive urbanization, agriculture, solid waste dumping overgrown river

course aggravates the flooding menace witnessed on the Iyi-Udele. This is compounded by the

intense rainfall whose average annual values are in excess of 2,000 mm, generating appreciably

high runoff.

Page 13: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xiii

Project Design and Alternative

There are various river engineering works that are used, either singly or in combination, to provide

flood protection and reduce flood damages along river reaches. Flood Control measures directly

related to the quantitative degree of design safety level against flood or the design flood frequency

comprises the following two categories: Increase of river flow capacity and Reduction/control of

the peak discharge of flood. The former category include the following; Dike/Levee, Widening of

waterway/river, Dredging/Excavation and/or combination of above while the latter category

comprises Dam, Retarding basin and Floodway.

The design adopted for this intervention project is channelization of the river within Abakaliki

metropolis, through the provision of line drainage channels of appropriate dimensions and training

of the channels of River Iyiudele. The content of the design, the model adopted together with the

likely impacts and the control measures are highlighted in chapter one as given in the engineering

design.

Other alternative designs are not feasible because in urbanized area, implementation may be

difficult due to land acquisition problem. Besides the consequences of dam failure is often very

catastrophic which makes the intervention meaningless. The same is applicable to retarding basin

considering the fact that the project is at the heart of the state capital where land is a scarce

commodity. Hence, the channelization method of control is better because of the nature of the area

of intervention as earlier mentioned.

Project Activities

The Environmental and Social Management Plan (ESMP) is a site-specific social and environment

assessment tool and it consists of a set of mitigation, monitoring, and institutional actions to be

taken during the phases of the project implementation. The major developmental objective of the

ESMP is to facilitate effective decision-making and to ensure that implementation processes

during the execution of the proposed project activities are sustainable. The intervention project

entails the channelization of the river within Abakaliki metropolis, through the provision of line

drainage channels of appropriate dimensions and training of the channels of River Iyiudele. The

channel is meant to collect the runoff water from the catchment of the River Iyiudele, conduct it

safely through the metropolis and discharge it effectively to the Ebonyi River. There should also

be construction of adequately sized culverts at all road crossings across Iyiudele River where none

is available or the existing culvert is not adequate among others. The scope of the consultancy

services covers the preparation of an ESMP for the project area, detailing the impacts and the

respective mitigation measures and to prepare a detailed ESMP cost analysis amongst others.

Safeguard Instruments and other Frameworks for Environmental Management

The relevant Federal/State Policies, Legislations, Regulations & Guidelines; the administrative

frameworks and the International Treaties and Conventions on Environment to which Nigeria is a

party are highlighted in chapter two of the report. The World Bank’s Environmental and Social

Safeguard Policies are cornerstones of its support for sustainable poverty diminution. The World

Bank safeguard policies contains ten (10) Environmental and Social Safeguard Policies which are

designed basically to enhance the adverse effects of development projects, and to improve decision

making. Specifically, the proposed project has triggered the following policies: OP/BP 4.01:

Environmental Assessment; OP/BP 4.12: Involuntary Resettlement and OP/BP 4.04: Natural

Habitat.

Page 14: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xiv

Biophysical Environment

The assessment of the biophysical environment of the study area covers general climate and

meteorology, air quality and noise level, topography, hydrology, water and soil quality, geology,

ecosystem, vegetation, plant physiognomy, inventory of economic crops, and fauna and wildlife

resources. Most parameters measured were in conformity with local and international standards.

Flooding is a seasonal event which occurs during rainy seasons. It is exacerbated by human

activities leading to further degradation of the environment. Essentially, to this end, the relevant

biophysical environmental baseline conditions were captured and described, as presented in

Chapter 3 of this ESMP. This provides the context upon which the proposed intervention activities

were related to the environment, to identify the impacts and develop the necessary mitigation

measures.

Socio-Economic Characteristics and Consultation

The Population for 2006 for the LGA indicating the males and females are given as males (72,518),

females (77,165), Total (149,683) according to National Bureau of Statistics (2010). The estimated

population for the area from 2006 to 2015 at the growth rate of 2.8% is projected to be Males

(92,979), Females (98,937), and Total (191,916). The survey covered a total of 102 (51%) male

and 98 (49) female respondents. The foremost respondents fall between 18 years and 45years

(54.0%). Majority of the respondents (86; 43%) have Senior Secondary School Certificate. A

preponderance of the respondents are civil servants (72; 36.0%) of the total respondents. 98% of

the respondents are Christians. The sickness mostly suffered from the respondents includes malaria

(52.0%), typhoid (15.5%). Open dumping is practiced by about 75.5% of the households. The

community depends primarily on tanked water as their source of domestic water supply for

drinking (65.5%). 91% of the respondents were of the opinion that the project is going to impact

on them positively.

Potential Impacts and Analysis of Alternatives

The project is envisaged to have a range of positive environmental and social impacts. It is

anticipated that the proposed intervention will reduce to the barest minimum the worrisome

experiences of the entire area occasioned by the flooding. However, the intervention is likely to

have some marginal environmental and social impact both to the community and in the

environment particularly during the pre-construction, construction and maintenance phases. These

impacts will be largely localized in spatial extent, short in duration, occurring within less sensitive

environmental areas and are manageable through the implementation of appropriate mitigation

measures. Almost all the respondents were of the opinion that the proposed project will enhance

safety of lives and properties, provide employment opportunities, securing public infrastructures,

minimize flooding and lead to improved accessibility and higher productivity.

For this intervention project, a number of viable options that were considered include; No action

option, Delayed action project and Go ahead option. Choosing the no project option implies a loss

of efforts made by all parties to ensure that flooding do not continue to pose risk to lives and the

environment and even loss of job opportunity to Nigerians. Delay option will mean the onset of

heavy rainfall which could trigger another flooding episode that will inflict more harm than it is

presently. Go ahead option is therefore considered the most viable and recommended for

implementation. This is an option that supports outright commencement of the project. It entails

Page 15: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xv

the channelization of the river within Abakaliki metropolis, through the provision of line drainage

channels of appropriate dimensions and training of the channels of River Iyi-udele.

Environmental and Social Management Plan

Environmental and social management objectives and actions are integrated into the project

planning and design based on identified impacts. The ESMP outlines the measures to be taken

during project implementation and operation to control adverse environmental and social impacts

and the actions needed. The ESMP components include recommended mitigation measures and

Implementation schedule, description of monitoring program; institutional arrangement including

capacity building; and Cost estimates.

Mitigation Measures

Measures to enhance beneficial impacts have been proposed. They are based on recommended

good practice, regulatory requirements and contributions received from relevant stakeholders.

Feasible, practical and cost effective measures to reduce the potentially significant adverse

environmental and social impacts to acceptable levels have been developed. These measures are

described in Table 6.1. and mainly relate to the adoption of best environmental practices in the

design, construction and operations of the project. Consequently the mitigation measures will be

included in the bid and contract documents for the successful enterprise to implement. Some of

the key mitigation measures proposed in the ESMP include; suppression of dust emissions, proper

maintenance of vehicles and machinery, fitting of exhaust mufflers/silencers, control of oil

spillages, proper management of spoils, selective land clearance and re-vegetation. Other measures

include adoption of best engineering practices, preparation and implementation of Waste

Management Plan (WMP) and site specific Health, Safety and Environment (HSE) Plan to address

occupational health issues.

Monitoring Program

An environmental performance monitoring program has been designed to provide specific

description and technical details of monitoring measures, including the parameters to be measured,

methods to be used, sampling locations, frequency of measurements, detection limits (where

appropriate), and definition of thresholds that will signal the need for corrective actions. It also

includes monitoring and reporting procedures to ensure early detection of conditions that

necessitate particular mitigation measures, and furnish information on the progress and results of

mitigation. Detailed proposed mitigation measures and related monitoring activities are provided

in the Monitoring Plan

Institutional Arrangements

The implementation of this ESMP requires the involvement of various institutions and

stakeholders fulfilling roles to ensure sound environmental management during the life cycle of

the project. The institutional arrangement as well as the roles and responsibilities of the various

institutions and persons that will be involved in the implementation, monitoring and review of the

ESMP are highlighted in Section 6.3. The Project Coordinator will be responsible for the overall

implementation of the ESMP and ensuring that the environmental and social requirements are

satisfied.

Page 16: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

xvi

Capacity Building and Training

Capacity building measures will be required to ensure that institutions involved in implementing

the various ESMP components have the necessary knowledge and skills to fulfill their roles. The

broad areas of capacity building and proposed training programme are presented in Table 6.4. The

cost for capacity building is estimated at ₦5,000,000.

Cost Estimate

The total cost to implement the ESMP is estimated at ₦13,250,000. The breakdown is as shown

below: S/N Items Estimated Cost ($)

@₦ 217

Estimated Cost (₦)

1. Mitigation Measures 14,977 3,250,000

2. Monitoring 23,041 5,200,000

3. Training 23,041 5,000,000

Grand Total 61,059 13,450,000

SUMMARY, RECOMMENDATIONS AND CONCLUSION

The development of the Environmental and Social management plan of Iyi-udele flood site in

Abakaliki capital city for the Nigeria Erosion and Watershed Management Project (NEWMAP) is

crucial for the sustainable actualization of the proposed intervention which is aimed at proffering

solutions to the perennial flooding experienced within Abakaliki metropolis. It is anticipated that

the proposed intervention will reduce to the barest minimum the worrisome experiences of the

entire area occasioned by the flooding. Measures to enhance beneficial impacts which are based

on recommended good practice, regulatory requirements and contributions received from relevant

stakeholders have also been proposed. Very importantly, it was observed in the course of the study

that the community where this intervention project is sited is very happy to have it. They cannot

wait to see the commencement of the project. Conclusively, the study has shown that the proposed

project will not severely impact negatively on the existing environmental, social and health status

of the people

Page 17: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

1

CHAPTER ONE

INTRODUCTION

1.1 Background of the Project

The Nigeria Erosion and Watershed Management Project (NEWMAP) is an intervention project

for the management of the erosion and watershed challenges in Nigeria more especially within the

South-East and South-South of the Country. It is assisted by World Bank, the Nigeria Government

and supported by Global Environmental Facility (GEF) and the Special Climate Change Fund

(SCCF).

This report is for the Environmental and Social Management Plan (ESMP) of Iyi-udele flood site

in Abakaliki capital city for the Nigeria Erosion and Watershed Management Project (NEWMAP).

This project is commissioned jointly by World Bank and Ebonyi State Government. The proposed

project is generally aimed at rehabilitating the degraded lands and reducing erosion and flooding

disaster by the preparation of Environmental and Social Management Plan of the aforementioned

flood site.

The Environmental and Social Management Plan (ESMP) is a site-specific social and environment

assessment tool and it consists of a set of mitigation, monitoring, and institutional actions to be

taken during the phases of the project implementation. The major developmental objective of the

ESMP is to facilitate effective decision-making and to ensure that implementation processes

during the execution of the proposed project activities are sustainable. The intervention project

entails the channelization of the river within Abakaliki metropolis, through the provision of line

drainage channels of appropriate dimensions and training of the channels of River Iyiudele. The

channel is meant to collect the runoff water from the catchment of the River Iyiudele, conduct it

safely through the metropolis and discharge it effectively to the Ebonyi River. There should also

be construction of adequately sized culverts at all road crossings across Iyiudele River where none

is available or the existing culvert is not adequate among others. The scope of the consultancy

services covers the preparation of an ESMP for the project area, detailing the impacts and the

respective mitigation measures and to prepare a detailed ESMP cost analysis amongst others.

Page 18: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

2

1.2 Description of the intervention

The proposed engineering works for the remediation of the flood menace for the Iyi-Udele site

involve but not limited to the channelization of the river through the provision of line drainage

channels and training of the channels of the river as shown in figure (1.1). The proposed 7.5km

reinforced concrete channel will run from Ogbaga road through Udensi Street, Nna Street,

Assemblies of God Church road downstream to the confluence with the Ebonyi River (see figure

1.2). The channel sizes varies from 10m width by 2.5m depth to 14m width by 3.5m depth. A three

(3) metres setback floodway is proposed on both sides of the reinforced concrete channel with

gabion protection on sides slopes (3m) above the concrete channel to prevent erosion, provide

aesthetic view along the channel and particularly takes care of the maximum freeboard of 1.94m

obtained for the Iyiudele River See Figure (channel drain). A two metre vertical clay core be placed

interlocked between the river side and land sides slopes of the gabion, arranged stepwise .This will

provide additional flood flow storage raising the capacity of the entire waterways to 100yr flood

flow of 109.99m /sec for Iyiudele River. Furthermore, there shall be construction of 5nos. 20m

bridges and adequately sized culverts at all road crossings across Iyiudele River for the passage of

flood water below the road crossings. It is proposed that there shall be provision of 5m length side

drains to collect runoff from both sides of road crossings where they are not available and also

provide upstream 1.5m x 1.5m lined channel to drain along the gabion to collect overland flows

and discharge into the river at culvert positions.

Figure 1.1 Iyiudele River System and locations of Flood Hot Spots

Page 19: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

3

Figure1.2: Typical Cross Section of Channel Drain

Figure 1.3: Iyi-udele Plan and Profile

Page 20: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

4

1.2.1 Likely Impacts of the project

Likely Positive Impacts of may include

1. Removal of the menace of Flooding and Flooding Disasters –

2. Reduced Risks of flooding and flooding disasters

3. Improvement in the Planning controls which will result in the regulation of

building locations as well as creating awareness in the control of urban

agriculture on marginal lands and dumping of refuse into drainage channels.

4. Improved Drainage of the City and the Landscape Quality

The likely Adverse Impacts will include among others the following:

1. Involuntary Displacement

2. Indebtedness whereby the State has to acquire a loan to undertake the

project thus becoming financially indebted due to the project.

3. Increased Challenges on Refuse/Solid Waste Management

1.3 Rationale and Objective of the Project

The proposed rehabilitation works at the Iyi-Udele flood site is classified as a Category B project

according to the World Bank’s Operational Policy on Environmental Assessment OP 4.01. The

categorization is justified on the basis of the potential negative impacts of the project on the

biophysical and social environment. The OP 4.01 when triggered requires that an ESMP be

prepared that will ensure environmental and social sustainability of the project, hence the need to

develop site specific, measurable and monitorable actions as contained in this Environmental and

Social Management Plan (ESMP). The ESMP consist of mainly the mitigation, monitoring, and

institutional measures to be undertaken during the implementation and maintenance of the

intervention work in order to eliminate adverse environmental and social impacts, offset them or

reduce them to acceptable levels.

The objective of the project is to prepare an environmental and social management plan (ESMP)

for Iyi-udele NEWMAP flood intervention site in Abakaliki capital city. It is also to facilitate

effective decision-making and ensure that implementation processes of the proposed project

activities are sustainable.

Page 21: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

5

1.4 Scope of the Project’s ESMP

The ESMP is site-specific and consists of a well-documented set of mitigation, monitoring, and

institutional actions to be taken before and during project implementation to eliminate adverse

environmental and social impacts, and to offset them, or reduce them to acceptable levels. It also

includes the measures needed to implement these actions, addressing the adequacy of the

monitoring and institutional arrangements for the upper and lower watersheds in the intervention

site.

In line with the terms of reference, the tasks include the following:

a) Describe the existing status of the sub-watershed and the flood;

b) Identify the environmental and social issues/risks associated with the existing conditions;

c) Select and measure appropriate baseline indicators (for example, m3/sec of runoff collected

in the sub-watershed during a heavy hour-long rainfall);

d) Develop a plan for mitigating environmental and social risks associated with construction

and operation in the gully in consultation with the relevant public and government

agencies; Identify feasible and cost-effective measures that may reduce potentially

significant adverse environmental and social impacts to acceptable levels;

e) Develop a time-bound plan for mitigating environmental and social risks associated with

sub-watershed management in consultation with the relevant public and government

agencies; Identify feasible and cost-effective measures that may reduce potentially

significant adverse environmental and social impacts to acceptable levels;

f) Identify monitoring objectives and specifies the type of monitoring, with linkages to the

impacts assessed and the mitigation measures described above(in a-e);

g) Provide a specific description of institutional arrangements: the agencies responsible for

carrying out the mitigation and monitoring measures (e.g., for operation, supervision,

enforcement, monitoring of implementation, remedial action, financing, reporting, and

staff training) and the contractual arrangements for assuring the performance of each

implementing agency;

h) Define technical assistance programs that could strengthen environmental management

capability in the agencies responsible for implementation;

Page 22: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

6

i) Provide an implementation schedule for measures that must be carried out as part of the

project, showing phasing and coordination with overall project implementation plans; and

j) Provide the expected capital and recurrent cost estimates and sources of funds for

implementing the ESMP and inform accordingly the design consultants so that these costs

are duly taken into consideration in the designs.

The following socio-economic issues were addressed in the ESMP:

A summary of the impacted communities for the project: location, access, population

(number, demographic and social characteristics (Education & Health)); economy

(employment rate, income distribution); services (types, capacity, and adequacy) and

housing. Concern is the ability to provide work force, service new development and absorb

and adjust to growth (worker/family).

A summary of the views of the population including vulnerable groups, determined through

thoroughly documented discussions with local communities. These meetings and

discussions must be documented and should show how issues and problems raised are or

will be resolved (note that a Resettlement Action Plan (RAP) could be developed for the

Site, and this is covered under separate TORs).

Cultural: Summarize the possible effects of the project on historical/archaeological sites,

heritage/artifacts, native religious or harvest sites of the affected communities and

identification or development of mechanisms for handling chance findings.

Information will be gathered from field surveys and secondary data sources (interviews,

structured questionnaires, in-depth interviews and focus group discussions).

Other Tasks:

The consultant shall, if the need arises, assist the SPMU to: (i) Register the ESMP with the

environmental assessment (EA) departments at Federal and State levels; and (ii) Disclose

the finalized ESMP at National, State, LGA and Community levels.

Page 23: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

7

CHAPTER TWO

INSTITUTIONAL AND LEGAL FRAMEWORK FOR ENVIRONMENTAL

MANAGEMENT

2.1 Background

A number of national and international environmental guidelines are applicable to the operations

of the NEWMAP. The national and international environmental guidelines applicable to the

operation of the NEWMAP have already been discussed in ESMF prepared for the overall project.

In this chapter relevant Federal/State Policies, Legislations, Regulations & Guidelines, the

administrative framework and International Treaties and Conventions on Environment to which

Nigeria is a party are highlighted.

2.2 Policy and Legal Framework

The act establishing the Ministry of Environment places on it the responsibility of ensuring that

all developments and industrial activities, operations and emissions are within the limits prescribed

in the National Guidelines and Standards, and comply with relevant regulations for environmental

pollution management in Nigeria as may be released by the Ministry. Environmental management

in Nigeria is based on the National Policy on the Environment and various environmental

legislations, regulations and guidelines. The relevant policy and regulatory instruments are

summarized in Table 2.1 below.

Page 24: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

8

Table 2.1: Relevant Federal/State Policies, Legislations, Regulations & Guidelines

S/N Policy Instrument Year Provisions

1 National Policy on the Environment 1989

revised

1991

Describes the conceptual framework and strategies for

achieving the overall goal of sustainable development in

Nigeria.

2. National Erosion and Flood Control

Policy

2005 Addresses the need to combat erosion in the country utilizing

the procedures outlined in the National Action Plan for Flood

and Erosion Control and Technical Guidelines, developed by

the WIC Environmental Committee which was set up to plan

an operational platform for these issues.

Legal/Regulatory Instrument

3. Environmental Impact Assessment

(EIA) Act No. 86

1992 Provide guidelines for activities of developmental projects for

which EIA is mandatory in Nigeria. The Act also stipulates the

minimum content of an EIA as well as a schedule of projects,

which require mandatory EIAs.

4. Land Use Act 1978

modified

1990

The Act vests all land comprised in the territory of each state in

the Federation in the Governor of the state and requires that

such land shall be held in trust and administered for the use and

common benefit of all Nigerians in accordance with the

provisions of the Act.

5. Forestry Act 1994 Provides for the preservation of forests and the setting up of

forest reserves.

6. Endangered Species Act 1985 Provides for the conservation and management of Nigeria’s

wildlife and the protection of some of her endangered species

in danger of extinction as a result of over-exploitation

7. FEPA/FMEnv EIA Procedural

Guidelines

1995 The Procedural Guidelines indicate the steps to be followed in

the EIA process from project conception to commissioning in

order to ensure that the project is implemented with maximum

consideration for the environment.

8. National Guideline and Standard for

Environmental

Pollution Control

1991 Provide guidelines for management of pollution control

measures

9. S.I.8 National Environmental

Protection (Effluent

Limitation) Regulations

1991 The regulation makes it mandatory for industrial facilities to

install anti-pollution equipment, makes provision for effluent

treatment and prescribes a maximum limit of effluent

parameters allowed.

10 S.I.9 National Environmental

Protection (Pollution

and Abatement in Industries in

Facilities Producing

Waste Regulations)

1991 Imposes restrictions on the release of toxic substances and

stipulates requirements for monitoring of pollution. It also

makes it mandatory for existing industries and facilities to

conduct periodic environmental audits.

11 S.I.15 National Environmental

Protection (Management of Solid and

Hazardous Wastes)

Regulations

1991 Regulates the legal framework for the effective control of the

disposal of toxic and hazardous waste into any environment

within the confines of Nigeria.

12 Urban and Regional Planning Decree

No. 88

1993 Planned development of urban areas (to include and manage

waste sites).

13 Workmen Compensation Act 1987

reviewed

2010

Occupational Health and Safety

14 Ebonyi State Environmental Sanitation

Edicts, Laws and Enforcement

Agencies

- Making and enforcing environmental and health polices and

laws

Page 25: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

9

2.3 Administrative Framework

2.3.1 Federal MDAs

The federal MDAs responsible for regulating and monitoring environmental issues at the federal

level include the Federal Ministry of Environment (FMEnv) and the National Environmental

Standards and Regulations Enforcement Agency (NESREA). Other federal MDAs relevant to the

project include the Federal Ministry of Water Resources (FMWR) and its agencies such as River

Basin development Authorities (RBDAs), National Water Resources Institute (NWRI), Nigeria

Integrated Water Resources Management Commission (NIWRMC) and the Nigeria Hydrological

Services Agency (NIHSA). Their respective roles have been highlighted in the ESMF.

2.3.2 State MDAs

Ebonyi State Ministry of Environment and Health

The Ministry is responsible for the health of the State & the attainment of environmental

sustainability (MDG 7). With regard to environment, the Key priorities include: Wastes to wealth,

Refuse to resources and Trash to cash and Re-enforcement of environmental sustainability.

Ebonyi State Environmental Protection Agency

The major functions of the agency are to

To carry out activities that would uplift the environmental status of the state

To prosecute sanitation offenders

To ensure house collection of wastes among others

2.3.3 World Bank Safeguard Policies

The World Bank’s Environmental and Social Safeguard Policies are cornerstones of its support

for sustainable poverty diminution. It has, thus, ensured that Environmental and Social issues are

assessed in decision making so as to reduce and manage any proposed developmental

project/programme risk. The process inherently gives mechanisms for Consultations and

Disclosure of Information to the public and related stakeholders.

The NEWMAP intervention project activities at Iyi-Udele flood site in Abakaliki have triggered

the World Bank Policy OP 4.01, which is Environmental Assessment (EA). ESMF and RPF are

the instruments used to address the triggered policies by the NEWMAP proposed intervention

project. This is applicable to the project due to the civil works with site-specific impacts. The

Page 26: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

10

project addresses the policy requirement by ESMF prepared for NEWMAP and site specific

mitigation measures developed in this ESMP.

The World Bank safeguard policies contains ten (10) Environmental and Social Safeguard Policies

which are designed basically to enhance the adverse effects of development projects, and to

improve decision making. The policies are:

OP/BP 4.01: Environmental Assessment;

OP/BP 4.04: Natural Habitats;

OP 4.09: Pest Management;

OP/BP 4.12: Involuntary Resettlement;

OPN 4.11: Physical Cultural Resources;

OP 4.36: Forests;

OP/BP 4.37: Safety of Dams;

OP/BP 7.50: Projects on International Waters; and

OP/BP 7.60: Projects in Disputed Areas.

Specifically, the proposed project has triggered the following policies:

i. OP/BP 4.01: Environmental Assessment

ii. OP/BP 4.12: Involuntary Resettlement

iii. OP/BP 4.04: Natural Habitat

2.4 International Treaties and Conventions on Environment to which Nigeria is a party

Some of the international Treaties and Conventions on environment to which Nigeria is a party

are summarized in Table 2.2 below.

Page 27: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

11

Table 2.2: International Treaties and Conventions on Environment to which Nigeria is a Party

S/N Treaties and Conventions Year Agreement

1. The United Nations Environmental

Guidance Principles

1972 Provide guidelines for protecting the integrity

of the global environment and the

development system

2. Montreal Protocol on Substances that

deplete the Ozone Layer

1987 An international treaty to eliminate Ozone

depleting chemical production and

consumption.

3. United Nations Convention on

Biological Diversity

1992 Places general obligations on countries to

observe sustainable use and equitably share

the plants and animals of the earth

4. United Nations Framework Convention

on Climate Change

1994 It calls on developed countries and economies

to limit her emissions of the greenhouse gases

which cause global warming

5. Convention on International Trade in

Endangered Species of Wild Fauna and

Flora

1973 Restricts the trade of fauna and flora species

termed as endangered Species

6. Convention on Conservation of

Migratory species of Wild animals

(Bonn Convention)

1979 Stipulates actions for the conservation and

management of migratory

species including habitat conservation

7. Vienna Convention for the Protection of

the Ozone Layer

1985 Places general obligation on countries to

make appropriate measures to protect human

health and the environment against adverse

effects

resulting from human activities which tend to

modify the ozone layer

Page 28: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

12

CHAPTER THREE

BIOPHYSICAL ENVIRONMENT

3.1 Introduction

The baseline biophysical environment of the proposed intervention project at Iyi-Udele flood site

in Abakaliki, Ebonyi State is discussed in this section. Fundamentally, the chapter captures

physical characteristics of the proposed project area, which includes description of the project area,

climate, air quality, hydrology, vegetation; wildlife and biodiversity, land use categories and land

acquisition and tenure system.

3.2 Description of the Project Site

The proposed project is located in Abakaliki capital city of Ebonyi state (see Figure 3.1 and 3.3).

This is a flooding site, which lies between latitudes 6o20’17.04” and 6o19’08.88”N and Longitudes

8o06’22.20” and 8o07’26.22”E (official co-ordinates of project sites). Approximately, the flooded

area has elevation ranging between 49m and 57m Mean Sea Level (MSL). It is mainly drained by

the River (Iyi) Udele. From vantage points at Ogbaga Road, Udensi Street, Nna Street, Assembly

Church of God and Aniekwena.

River Iyi-Udele is observed to be one of the main drainage rivers of Abakaliki Township. Its

source is within the city and it flows southeastwards into River Ebonyi. Some lined service drains

empty into some segments of the river as in Ogbaga area. Its catchment area spreads over the

Abakaliki township, with urbanization as the main land use practice. However, some part of this

catchment area is still underdeveloped but it is intensively exploited for agriculture. The degree of

anthropogenic encroachment varies along the stretch of the river causing severe constrictions along

the river course. There is considerable evidence of solid waste dumping along the river channel

as may be seen at Ogbaga road (Plate 3.1). Although the terrain is gently undulating as is typical

of the area, the combinations of intensive urbanization, agriculture, solid waste dumping at the

overgrown river course aggravate the flooding menace witnessed on the Iyi-Udele. This is

compounded by the intense rainfall whose average annual values are in excess of 2,000 mm,

generating appreciably high runoff. Like the Iyi-Okwu which is the other main tributary of the

River Ebonyi, this drainage system is typically dendritic, receiving flows from tributaries that drain

the entire catchment on which Abakaliki is situated.

Page 29: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

13

Figure 3.1: Map of Ebonyi State depicting the LGA of the Proposed Project

Plate 3.1: Iyi-Udele River channel downstream and upstream Ogbaga Road

Page 30: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

14

The tributaries of Iyi-Udele watershed have stream flows that are characteristically recognized as

either flash flow, or seasonal flow or are of perennial flow. Some sections of the Iyi-Udele,

upstream of Ogbaga road had been channelized with the construction of reinforced rectangular

concrete channel under the Federal Ecological Fund supported programme (Figure 3.2).

Figure 3.2: Drainage Pattern of Abakaliki Capital City and the flood hotspot sites

The population is typically Ibo, although some minorities like Ibibios are also present. The three

main clans of the Ibo ethnic grouping (Ezza Ezekuna, Izzi and Ikwo ) are visibly represented

among the population of Abakaliki town. There is evidence of migrants among the populace

including indigenous and migrant populations from within and outside the state as the city of

Abakaliki continues to grow as result of being the state capital. The main occupation of the

population is farming due to the abundant rich fertile soil available in the area. Common crops

grown are swamp rice (in most of the flood plains) and yams among the indigenous population

while the migrant farmers concentrate on growing rice and cassava. The popularity of the

Page 31: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

15

Abakaliki rice has long been known as far back as the Second World War when importation of

rice was banned in Nigeria. It has long established as the ‘food basket’ of the South East

geopolitical zone as a result of its agricultural potentials and exploitation. To date, Abakaliki rice

is well known nationally and regionally in many parts of West and Central Africa. A major

perennial tree crop found in the area is Oil palm (Elaeis guineensis).

Figure 3.3: Map of Ebonyi State Showing the Location of Iyi-Udele

BENUE STATE

ISHIELU

OHAUKWU

EBONYI

IZZI

ONICHA

EZZA SOUTH

ABAKALIKI

EZZA NORTH

IVO

AFIKPO SOUTHAFIKPO NORTH

IKWO

OHAOZARA

CROSS RIVER

STATE

ENUGU

STATE

ABIA STATE

SCALE

10 0 10 20

Local Govt. Boundary

State Boundary

Km.

SCALE

10 0 10 20 Project Location

Local Govt. Boundary

State Boundary

State Capital Federal Highways

Minor Federal Roads

Major State Roads

Km. Minor State Roads

To Enugu

To Iyahe

To Okigwe

To Obubra

To Itigidi

To Nkanu

To Abiriba

To Erei

To Oboloafor

Abakaliki

o

Iyi-Udele

Page 32: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

16

According to Ogbodo (2011), the soils of the Iyi-Udele floodplains are averagely clayey loam with

proportion of sand slightly higher than the Iyi-Okwu samples with 36.4% sand and a lower clay

content of 26.8%. He further reported that the soils have average porosity of 54.5% and bulk

density of 1.2mg/m3 and are less acidic with average pH values of 6.15 in water. This lends

credence to the high agricultural use of the land resource in the area (see Figure 3.4).

Figure 3.4: Imagery of Iyi Udele River and its Flood Plain

3.2.1 Farming Activities in the Proposed Project Area

There are two types of oil palm production in the region. By far, the most important at present is

the harvesting and processing of oil palm fruits from wild palm that occur naturally in the forests

and are preserved, when land is cleared for farming. Although the wild palm oil is an important

source of cooking oil for consumption and sale, the pericarp is thin and produces little oil in

Page 33: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

17

comparison with the cultivated varieties. Raphia palm (Raphia spp.) occurs wild and is cultivated

in low-lying marshy area. It can be an important source of additional income for the farmers skilled

in tapping for palm wine. Vegetables grown are mainly indigenous vegetables and include okra,

peppers, tomatoes, eggplant, and green leafy vegetables. These are not grown purposely for sale

but rather are staples for the gardeners, and cultivated for personal consumption, although

surpluses are sold in local market. In the area, household and peri-urban cultivators have mostly

grown food crops like maize, plantain, cassava, and cocoyam, rice, yam and cassava. Likewise,

fruits such as pineapples, mangoes, pawpaw, orange, coconut, and palm oil are grown by

householders and for commercial basis by peri-urban cultivators.

3.3 Specific Project Design and Alternative

There are various river engineering works that could be used, either singly or in combination,

to provide flood protection and reduce flood damages. The types may include increase of river

flow capacity which entails: Dike/Levee, Widening of waterway/river, Dredging/Excavation and

combination of the above. The alternative design that could be used is Reduction/control of the

peak discharge of flood which entails Dam, Retarding basin and Floodway.

The design adopted for this intervention project is channelization of the river within Abakaliki

metropolis, through the provision of line drainage channels of appropriate dimensions and training

of the channels of River Iyi-udele. On the other hand, the alternative design that could have been

used includes Dam, Retarding basin and floodway but they are not feasible because in urbanized

area, implementation may be difficult due to land acquisition problem. Besides the consequences

of dam failure is often very catastrophic and might make the intervention meaningless. The same

is applicable to retarding basin considering the fact that the project is at the heart of the state capital

where land is a scarce commodity. Hence, the channelization method of control is better because

of the nature of the area of intervention as earlier mentioned.

3.4 Physical Environment

3.4.1 Geology and Hydrology of the Proposed Project Area

The first marine transgression of the Benue trough is generally believed to have started in the mid-

Albian period with the deposition of the Asu River Group. Figure 3.5 shows the distribution of the

Asu River Group and other lithologic units in the lower (or southern) Benue trough, Southeastern

Page 34: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

18

Nigeria. The rocks consist of profile bluish grey shales, sandy shales, fine grained micaceous and

calcareous sandstones and limestone. The Asu River group sediments are predominantly shales,

commonly referred to as the ‘Abakaliki shale formation’ in and around the Abakaliki metropolis

(about 452 sq.km), and localized occurrences of sandstone, siltstone and limestone intercalations

(Ofoegbu and Amajor, 1987). Emplaced in these Asu River group sediments are intermediates to

basic intrusive, extrusives and Pyroclastics. The group has average thickness of about 2000 m and

rests unconformably on the Precambrian Basement. The Abakaliki shale formation, which has an

average thickness of about 500 m, is dominantly shale, dark grey in colour, blocky, and non-

micaceous in most locations. It is calcareous (calcite-cemented) and deeply weathered to brownish

clay in the greater part of the formation (Okogbue et. al, 2010)As the river flows southeastwards,

it drains territories of the basement complexes (Pre-cambian), through cretaceous to sedimentary

beds. The major river that drains the area is the Ebonyi River and its tributaries; Udene and Iyiokwu

Rivers. Both tributaries are perennial and usually overflow their banks at the peak of the rains.

Stunted trees and pockets of derelict woodland exist where the lithology has undergone high

degree of laterization. Elsewhere, typical of the tropical rain forest are displayed; multitude of

evergreen trees, climbing plants, parasitic plants that live on the other plants, and creepers.

Page 35: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

19

Figure 3.5: Geology of Abakaliki

Source: Okogbue and Aghamelu, 2010

Page 36: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

20

3.4.2 Physiography and Climate

The relief of the area is generally undulating and no location exceeds 400 m above-sea-level. A

major relief structure is hills formed by the pyroclastic bodies. No trend has been established by

previous research (Ofoegbu and Amajor, 1987) of these conical shaped hills and other residual

hills that spread sporadically within the area. The predominant shale has favoured the low

erodability of the lithology, resulting in absence or near absence of deep cut valleys and erosion

channels.

Table 3.1: Climate Data of Abakaliki, Ebonyi

Month Mean Max

Temp 0C

Mean

Rainfall

(mm)

Relative

Humidity (%)

Sunshine

(Hrs)

Jan 26 25 45 6.5

Feb 28 50 35 7.1

Mar 28 125 45 6.2

Apr 28 200 66 6.2

May 27 200 65 6.2

Jun 26 200 68 5.1

Jul 26 200 68 3.8

Aug 26 200 68 3.3

Sep 26 325 75 3.5

Oct 26 325 68 5.5

Nov 27 50 58 6.5

Dec 26 20 49 7.1

Source: NIMET, 2015

As shown in Table 3.1, two main seasons exist in the Abakaliki area, the dry season which lasts

from November to early March and the rainy season which begins in April and ends in October

with a short period of reduced rains in August commonly referred to as “August break”.

Temperature in the dry season ranges from 20 to 38°C, and results in high evapotranspiration,

while during the rainy season temperature ranges from 16 to 28°C, with generally lower

evapotranspiration. The average monthly rainfall ranges from 20 mm in December to 325 mm in

each of month of September and October, with the dry season experiencing much reduced volume

of rainfall unlike the rainy season, which has high volume of rainfall. Average annual rainfall

varies from 1,500 to 1,650 mm (see Figures 3.6 and 3.7). These climatic conditions are responsible

for the development of thick lateritic soils in the area.

Page 37: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

21

Figure 3.6: Rainfall Intensity in the Proposed Project Area

Figure 3.7: Rainfall Intensity Duration in Proposed Project Area

Page 38: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

22

The project area is dominated by two seasonal reverse winds, the dry tropical wind or the north-

easterly winds from January to March and the tropical maritime wind or the south-westerly winds

From April to December. The prevailing wind direction in the area is southwest at an average

speed of 1.4 m/s. The dominant wind direction places the major communities upwind relative to

potential emission sources from the project (Figure 3.8). Relative humidity is high, usually

between 60% and 80% in the peak of rainy season. It is highest between June and October (Table

3.1).

Figure 3.8: Wind Rose Diagram in the Proposed Project Area

Page 39: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

23

3.5 Environment Quality Assessment

3.5.1 Analysis of Soil Samples

The type and nature of bedrock to a large extent influence the soil which developed upon it. This

is reminiscent of the geology and the topographic nature of the land. In the project area, there are

generic soil classified according to international soil classification system based on textural

classes.

3.5.2 Physico-Chemical Characteristics of the Soils

The results of the physico-chemical analysis of the soils in the project area are presented in Table

3.2 for the two essential soil layers viz. topsoil and subsoil respectively. Figure 3.9 and Table 3.2

show the geographic coordinates and the spatial distribution of the sample points for soil analysis.

The pH of the soil samples from the project area ranged between 5.1 (slightly acidic) and 8.3

(alkaline) while the electrical conductivity of the soil samples ranged between 50.51mg/kg to

60.02mg/kg suggesting moderately dissolved ions content. The electrical conductivity of soil

expresses its total ionic strength (both cations and anions). Low total ionic strength indicates low

dissolved salt content and vice versa.

The concentrations of Mg, Ca, Na, and K recorded in soils from the study area fall within the

natural occurrence levels for tropical soils. Sodium ranged from 75.34mg/kg to 95.26mg/kg,

calcium ranged from 62.04mg/kg to 92.09, potassium ranged from 51.36mg/kg to 66.17mg/kg

while magnesium ranged from 41.02mg/kg to 50.10mg/kg. Among the anions, nitrate and sulphate

ions were the most prominent while phosphate recorded the least concentrations. Nitrate

concentrations in the soil samples from the area ranged from 31.05mg/kg to 35.01mg/kg, sulphate

ranged between 37.07mg/kg to 50.36mg/kg, chloride ranged from 24.16mg/kg to 28.22mg/kg

while phosphate ranged between 16.40mg/kg and 20.05mg/kg. This is detailed in Table 3.2 below.

Page 40: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

24

Table 3.2: Physico-chemical and microbial results of soil samples from the study area

Parameters PS1 PS2 PS3 PS Control 1 PS Control 2

Top Soil Sub Soil Top Soil Sub Soil Top Soil Sub Soil Top Soil Sub Soil Top Soil Sub Soil

Physico-chemical

Ph 6.52 5.1 5.3 6.9 6.5 6.4 7.7 7.4 8.2 8.3

Electrical

Conductivity (µS/cm)

53.59 60.02 57.34 56.14 50.51 58.13 59.12 58.29 56.65 58.14

Moisture content (%) 7.3 8.5 9.4 9.8 10.5 7.5 7.4 9.6 11.2 10.5

Total Nitrogen (mg/kg) 20.50 20.10 22.07 24.07 20.13 20.76 24.43 23.54 25.26 21.21

Sulphate (mg/kg) 41.13 41.21 50.36 43.26 48.26 44.02 40.03 37.07 47.02 43.01

Phosphate (mg/kg) 16.40 17.30 15.32 19.15 19.08 17.95 16.63 18.25 20.05 19.24

Chloride (mg/kg) 24.16 26.45 25.85 26.77 27.72 27.19 28.20 25.44 28.22 26.30

Nitrate (mg/kg) 31.05 33.23 33.93 33.26 33.45 33.95 32.15 35.01 33.14 33.55

Sodium (mg/kg) 75.34 85.46 85.13 93.24 75.24 95.26 82.36 83.95 87.88 91.58

Potassium (mg/kg) 58.34 54.21 56.99 54.68 53.19 53.18 65.39 57.11 51.11 50.59

Calcium (mg/kg) 63.28 67.29 66.64 69.12 70.12 68.19 64.27 65.54 68.89 63.26

Magnesium (mg/kg) 40.12 44.12 44.29 45.29 41.28 49.12 45.11 46.96 42.33 44.46

Copper(mg/kg) 10.21 15.53 16.35 14.26 12.13 13.85 19.20 17.67 18.14 16.25

Zinc (mg/kg) 40.20 44.65 43.95 42.86 47.75 49.65 36.66 49.52 49.22 40.25

Iron (mg/kg) 558.2 556.5 659.2 665.5 698.34 514.0 505.43 504.65 512.28 516.17

Cadmium (mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Lead (mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Chromium (mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Nickel (mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Mercury (mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

Arsenic(mg/kg) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001

THC(mg/kg) (mg/kg) 1.63 2.30 <0.001 0.9 0.82 0.45 0.29 2.03 0.27 0.35

Microbiology (cfu/gm)

Total Heterotrophic

Bacteria

31 x 105 35 x 105 47 x 105 55 x 105 67 x 105 62 x 105 48 x 105 53 x 105 45 x 105 56 x 105

Total Heterotrophic Fungi 4.3 x 103

4.1 x 103

5.1 x 103

6.2 x 103

4.5x 103

5.6 x 103

6.7 x 103

9.1 x 103

5.1 x 103

7.5 x 103

Hydrocarbon Utilizing

Bacteria

7.0 x 102

3.0 x 102

3.0 x 102

8.0 x 102

7.0 x 102

5.0 x 102

5.0 x 102

3.0 x 102

6.0 x 102

3.0 x 102

Hydrocarbon Utilizing

Fungi

1.55 x 101

1.15 x 101

1.23 x 101

1.39 x 101

1.20 x 101

1.35 x 101

1.39 x 101

1.58 x 101

1.65 x 101

2.35 x 101

Field Survey 2015

Page 41: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

25

Figure 3.9: Soil Sample Points

As shown from findings, bulk density values for the floodplains and the river basin were

significantly lower than that of the upland, whereas the soil densities of the floodplains were

statistically comparable with the river basin soil. The soil total porosity of the Iyiokwu and Iyiudele

flood plains and the Ebonyi river basin were correspondingly higher than the soil total porosity of

the upland, owing to the lower soil density of the areas. It was also observed that the soil water

retention capacity was higher with the floodplains and the Ebonyi river basin than the upland. The

soils of the Iyi-Udele flood plain had high moisture retention capacity (Table 3.2)..

Heavy metals concentrations were generally low at all the sampling stations. Iron (Fe) was the

most abundant with a range of 504.65mg/kg to 698.34mg/kg followed by Zinc, then Copper. Zinc

ranged between 36.66mg/kg and 49.65mg/kg while Copper ranged between 10.21mg/kg and

19.20mg/kg. Mercury, Arsenic, Lead, Cadmium, and Vanadium concentrations in the soil samples

Page 42: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

26

were below the detection limit of 0.001mg/kg. The concentration of heavy metals recorded in the

soil samples suggest that the soil environment of the study area is not polluted. The heavy metals

profile of the soil samples is within the naturally occurring heavy metals concentrations in soil

(Cu, 50-100mg/kg; Zinc 10-100mg/kg; Cd, 0.03-0.3mg/kg; Ni, 5-50mg/kg; Pb, 2-20mg/kg)

The concentrations of measured Total Hydrocarbons THC in soil samples from the project sites

ranged between<0.001mg/kg and 2.30mg/kg, which falls within the limit 50mg/kg for mineral oil

in soil. The total heterotrophic bacteria (THB) recorded in the soil samples ranged between 31 x

105cfu/g and 67 x 108cfu/g while total heterotrophic fungi (THF) ranged between 4.1 x 103cfu/g

and 9.1 x 104cfu/g. The population of hydrocarbon utilizing bacteria (HUB) and hydrocarbon

utilizing fungi (HUF) in the soil samples were low compared to the THB counts. HUB ranged

from 1.0 x 102cfu/g to 2.4 x 102cfu/g while HUF ranged between 1.15 x 101cfu/g and 2.40 x

101cfu/g.

Soil pH: The pH values recorded for soils in the study area ranged between 5.1 and 5.2 with a

mean of 5.15 for the topsoils and 5.2 to 5.7 with an average of 5.21 for the subsoils. The soil pH

is moderately acidic.

Total Nitrogen: Soils in the study area have total nitrogen ranging between 0.74 and 0.77mg/kg

with an average of 0.97mg/kg for the topsoils; and 0.65– 0.94mg/kg (mean, 0.76mg/kg) in the

subsoils. Surface soils had a higher total nitrogen content compared to subsurface soils.

Available Phosphorus: Surface soils in the study area have available-phosphorus values ranging

between 6.2 and 7.7 mg/kg (mean of 8.7mg/kg) and subsoils have 6.4 to 6.8 mg/kg (average of

6.71mg/kg).

Sulphate: The top soils of the study area have sulphate content between of 3.0 and 5.0mg/kg, with

an average of 4.0mg/kg, and the sub soils have sulphate content of between 3.0 and 4.0mg/kg, with

an average of 3.67mg/kg. The sulphate contents of the soils are considerably lower than 500mg/kg.

Page 43: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

27

3.5.3 Metal Content of the Soils

Data obtained from the proposed intervention project area for the basic and heavy metal

concentrations in the acquired soil samples are presented in Tables 3.3 and 3.4, for the topsoils and

sub-soils, respectively.

Table 3.3: Basic and heavy metal concentrations of the top soil (0–15 cm)

*ND- Not Detected (Source: Fieldwork, October 2015)

Basic Metals: The basic metals (K+, Na+, Ca2+, Mg2+) with the exception of Na are important plant

nutrients. It was observed that the basic metals were dominated by Na+, Ca2+, K+ and Mg2+. Mg2+

had a mean concentration of 3.51mg/kg for the topsoil and 2.95mg/kg for the subsoil; Na+ had a

mean concentration of 10.7mg/kg for the topsoil and 8.83mg/kg for the subsoil; K+ had an average

of 4.75mg/kg for top soil and 4.31mg/kg for subsoil. The mean concentration of Ca2+ for the topsoil

was 11.2mg/kg and 10.12mg/kg for the subsoil.

Heavy Metals: Concentrations of the heavy metals investigated in the study area are presented in

Tables 2.3 and 2.4. The most prominent metal detected in the soils collected from the study area

was Zn, with a mean concentration of 24.17mg/kg for the top soil and 25.33mg/kg for the subsoil.

Other heavy metals detected were Fe and Cu. The mean concentration of Fe was 0.04mg/kg for

the top soil and 0.05mg/kg for the subsoil. Cu had a mean concentration of 2.65mg/kg for the

topsoil and 2.40mg/kg for the subsoil. Ba, Pb, V, Ni, Hg were not detected. The values obtained

for heavy metal concentrations were within the limits described as the normal range in unpolluted

soils by Allen et al. (1974) and Alloway (1991).

Sample

Points

Heavy Metals (mg/kg) Basic Metals (mg/kg)

Cr Cu Cd Fe Ba Hg Ni Pb V Zn Ca2+ K+ Mg2+ Na+

S1 ND* 3.3 ND* 0.08 ND* ND* ND* ND* ND* 25.13 12.7 5.2 4.4 8.4

S2 ND* 2.8 ND* 0.04 ND* ND* ND* ND* ND* 24.04 11.4 5.3 3.6 11.1

S3 ND* 2.7 ND* 0.02 ND* ND* ND* ND* ND* 23.78 10.7 4.0 3.2 12.0

Min. 0 2.8 0 0.02 0 0 0 0 0 23.78 10.7 4.2 3.4 8.0

Max. 0 3.3 0 0.08 0 0 0 0 0 25.57 12.5 5.2 4.0 12.0

Mean 0.0 2.65 0 0.02 0.0 0.0 0.0 0.0 0.0 24.39 11.2 4.75 3.51 10.5

Page 44: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

28

Table 3.4: Basic and heavy metal concentrations of the sub soil (15–30 cm)

*ND- Not Detected (Source: Fieldwork, October 2015)

3.6 Physico-Chemical Analysis of Water Samples

Table 3.5 gives the result of a physico-chemical investigation conducted in the proposed

intervention project area. The Table shows the results of analysis based on the parameters

measured. Average pH values for both hand dug wells and boreholes were almost equal. Mean pH

for all the tested water samples, however, showed neutrality (6.9 on the pH scale). A comparison

of the concentrations of the tested water samples with normal concentrations of elements in

unpolluted fresh water showed the tested water samples had high values of ions, with HCO-3 and

NO-3 being exceptionally high (above normal range). Probable source of the ions in the water

included dissolution of calcite and other rock salts, as well as mica and organic matters within the

proposed project area. Occurrences of siltstone, sandstone and limestone beds have also been noted

in the Abakaliki shale (Reyment, 1965). NO-3 source might also be anthropogenic, that is, due to

activities of human beings in the area.

A borehole in near the upper course of the watershed recorded highest enrichment of Ca2+, HCO-

3 and carbonate hardness. This may be either due to the fact that the borehole tapped deeper shaley

bed that have secondary enrichment due to effects of leaching or that static that is (steady) and

deeper water table in boreholes aided more dissolution. Usually, most hand dug wells, and even

Sample

Points

Heavy Metals (mg/kg) Basic Metals (mg/kg)

Cr Cu Cd Fe Ba Hg Ni Pb V Zn Ca2+ K+ Mg2+ Na+

S1 ND* 2.3 ND 0.07 ND* ND* ND* ND* ND* 25.34 10.7 5.3 3.4 8.7

S2 ND* 2.8 ND 0.02 ND* ND* ND* ND* ND* 22.78 8.8 4.1 2.8 10.

4

S3 ND* 2.7 ND 0.07 ND* ND* ND* ND* ND* 28.48 11.4 3.8 2.7 7.6

Min. 0 2.3 0 0.02 0 0 0 0 0 22.78 8.8 3.6 2.7 7.8

Max. 0 2.8 0 0.07 0 0 0 0 0 28.48 11.4 5.3 3.4 10.

4

Mean 0 2.22 0 0.07 0 0 0 0 0 25.13 10.32 4.11 2.55 8.6

5

Page 45: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

29

some boreholes, in the Abakaliki area dry up in the middle of dry season leaving the town with

acute shortage of portable water (Aghamelu, et. al., 2010). Figure 3.10 shows the locations of water

samples. In the proposed intervention project area, ground water generally exists in the following

ways:

i. Fractured zones within the Asu River group.

ii. Sandstone and limestone layers or members.

iii. Weathered zones

iv. Bedrock interfaces with the shale group.

Usually, the yields are poor. According to Ismael (1990), the fractured and weathered zone shale-

aquifer systems have specific yields values as follows; range 1.26 × 10-3 to 1.60 × 10-3 litre per

second (l/s) and 1.22 × 10-3 to 1.81 × 10-3 l/s, with average values of 1.48 × 10-3 l/s and 1.59 ×

10-3 l/s, respectively. Both shale-aquifer systems have only served for the establishment of hand-

pump boreholes and hand-dug wells.

Figure 3.10: Water Sample Points

Page 46: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

30

Table 3.5: Result of Physicochemical Analysis of Water Samples

Sample Borehole Water Hand Dug Wells Stream water FMENV

LIMIT

Colour Clear Clear Clear Colourless

Odour Odourless Odourless Odourless Odourless

pH 6.7 6.9 6.2 6.5-8.5

Conductivity (µS/cm) 29 52 63 NS

Acidity 27 29 16 200

Alkalinity (mgCaCO3/L) 4.6 13.4 13.4 200

Cl- (mgCl/L) 14 16 16 250

Salinity (ppt) 0.04 0.04 0.04 0.5

Hardness (mg CaCO3/L) 26 29 34 250

Oil and grease (g/l) ND ND ND 10

DO (mgO2/L) 6.4 5.8 5.6 >7.5

COD (mgO2/L) 364 345 362 NS

TDS (mg/L) 20 40 40 500

TS (mg/L) 20 40 50 2000

TSS (mg/L) ND ND 10 30

Nitrates (mg/L) 1.3 1.0 1.7 20

Phosphates (mg/l) ND 0.03 0.1 < 5

Sulphate (mg/l) 0.27 4.1 6.5 250

Pb (mg/l) ND ND 0.3 0.1

Cu (mg/l) ND ND ND 3.0

Cr (mg/l) ND ND ND 0.1

Zn (mg/l) 0.1 0.1 0.2 0.1

Fe (mg/l) 0.4 0.2 1.1 0.3

Cd (mg/l) ND ND ND 0.01

K (mg/l) 0.9 2.0 1.9

ND= Not detected; NS = Not specified

As shown in Table 3.5, all the water sources recorded considerable amounts of Total Dissolved

Solids (TDS) and appreciable hardness. Hardness in water is caused by the presence of any

polyvalent metallic cations (Kiely, 1997) but principally Ca2+, Mg2+ and, less so, Fe2+ and

Mn2+. Kiely (1997) notes that total hardness is usually computed based on the concentration of

Ca2+ and Mg2+ and is usually expressed in mg/l as CaCO3. Details on the softening processes

Page 47: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

31

and other physical, chemical and microbiological techniques that can be utilized to achieve

acceptable standard for the groundwater in the Abakaliki area are presented in American Water

Works Association (AWWA) (1990), Thomas and King (1991) and Kiely (1997).

The concentrations obtained for the physico-chemical parameters, the cations and anions and

heavy metals are presented in Tables 3.5. Figure 3.10 shows the spatial distribution of the sample

locations.

As shown above, the pH of all the water samples falls within the FMenv/WHO (Federal Ministry

of Environment/ World Health Organisation) limits for drinking water. The conductivities, total

hardness, chloride, phosphate, dissolved oxygen (DO) , nitrates, dissolved solids, total suspended

solids, total solids and sulphates also all fall within the FMenv/WHO limits.

The water samples were observed to have very low inorganics, as most of the metals determined

were below the limits, with the exception of lead and zinc in the stream water samples. The

concentrations of these metals could be due to human activities which take place in streams as all

sorts of containers are usually used to collect water samples from the stream. The chemical oxygen

demand (COD) was observed to be quite high. COD is a measure of the amount of oxygen needed

to oxidize both the organics and inorganics in a water sample. Since the amount of inorganics

appears to be low, the high COD value could be as a result of the organics in the samples.

3.7 Biological Environment

3.7.1 Ecosystem

Overall, the observed ecology of the project area suggests a suburb landscape with nascent

structures built along strands of farmlands and natural ecology. The farm plots located further

down suggests families’ dependence on the farm output for survival.

3.7.2 Vegetation

The vegetation is mainly savannah, with the intense anthropogenic through urbanization and

agricultural interference rapidly modifying the emergence of stable forest species. Vegetation is

an integral part of the terrestrial environment. It performs several functions that are crucial to the

sustenance of the environment. Some of these functions include:

i. Protection of the fragile soils from the erosive impacts of rains and wind;

ii. Maintenance of soil fertility through continuous nutrient recycling;

Page 48: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

32

iii. Conservation of water resources through shading;

iv. Preservation of water sheds;

v. Regulation of air and soil temperatures;

vi. Moisture balance;

vii. Provision of habitat for countless terrestrial flora and fauna; and

viii. Purification of the environment through the carbon dioxide during photosynthesis and the

release of oxygen for human and animal respiration.

Three (3) vegetation types exist in the study area namely; freshwater swamp forest, lowland rain

forest and open herbaceous re-growth (secondary grassland). The vegetation of the area has been

greatly disturbed as most parts were cultivated farmland. The vegetation cover is two-storey with

very few emergent trees (uppermost storey) that are sparsely scattered throughout the entire study

area and a second layer dominated by herbaceous plant species as shown in Plate 3.1, Plate 3.3

and Table 3.6.

Plate 3.2: Secondary Vegetal Cover at Perimeter fence erected well inside the channel

Page 49: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

33

Plate 3.3: A cross-section of the vegetation type found in the area

Common plant species in all parts of the study area are presented in the table below.

Table 3.6: Terrestrial Floral Species Recorded in the Study Area

S/N Common/Commercial

Names

Scientific Names

1 Christmas bush Alchornea cordifolia

2 Poison devil’s pepper Rauvolfia vomitora

3 Twisted ginger Costus afer

4 Dragon’s blood tree Harungana madagascariensis

5 Cassava Manihot esculata

6 Banana Musa sapientum

7 Cocoyam Colocasia esculata

8 Plantain Musa paradisiaca

9 Pineapple Ananas sativa

Page 50: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

34

10 Yam Discorea spp

11 Oil palm tree Elaeis guinensis

12 Avocado pear Persea americana

13 Local pear Dacryodes edulis

14 Mango Mangifera indica

15 Kola nut Cola acuminata

16 Orange Citrus spp

17 Rice Oryza sativa

The secondary grassland is made up of mainly the forbs, grasses and sedges. However, none of

the plant species recorded is in the vulnerable category of the IUCN.

3.7.3 Fauna and Wildlife Resources

The terrestrial fauna recorded in the study area is presented in Table 3.7 below. Faunas in the study

area are not IUCN threat status classified. The wildlife in the area is subjugated by birds, reptiles

and mammals. Direct observations in the field and interviews showed that main birds are doves,

crow and weaver birds, while the reptilians are chiefly diverse types of snakes. The mammals

rarely encountered include monkey, squirrels, grass cutters, and antelopes.

Table 3.7: Terrestrial Fauna Species Recorded in the Study Area

S/N Major Taxa/Species Common Names

A

MYRIAPODA:

Diplopoda: Harbrodesmos; Oxydesmus, spirostreptus Millipedes

B ARACHNIDA: Araneae Spiders

C INSECTA

1 Coleoptera Beetles

2 Carabidae: Anthia sp. Ground beetles

3 Chrysomelidae

4 Dictyoptera

5 Mantidae: Sphodromantis sp. Praying mantis

6 Diptera Flies

7 Bomdyliidae Boefly

8 Calliphoridae Blowfly

9 Glossinidae: Glossina Tsetse fly

10 Sacrophagidae Flash fly

11 Ephemeroptera: Coenagrion sp. Damsel fly

Page 51: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

35

12 Hemiptera Bugs

13 Pentatomidae: Nzera viridula Sting bug

14 Reduvidae: Nulanda sp. Assassin bug

15 Hymenoptera

16 Apidae: Apis sp. Bees

17 Formicidae: Formica, Monomorium, Oecophylla Ants

18 Vespidae&Sphecidae: Polistes sp. Wasps

19 Lepidoptera Butterflies and Moths

20 Acracidae: Acraca sp., Hypoglycaena sp.

21 Orthoptera

22 Acrididae Grasshopper

23 Gryllidae: Gryllussp. Cricket

24 Gryllatalpidae: Gryllotaps Africana Mole-cricket

25 Tettigonidae: Bush cricket

D MOLLUSCA: GASTROPODA

1 Achatinidae: Archachatinamarginata Giant snail

2 Limicolariaflammea Garden snail

E AMPHIBIA

1 Bufonidae: Buforegularis Toads

2 Rhacophoridae: Hyperolius sp. Tree frog

3 H. picturatus Tree frog

4 Xenopustropicalis Clawed frog

F REPTILIA

1 Kinixys erosa Common tortoise

2 Varanidae: Varanus niloticus Monitor lizard

G AVES

1 Falconidae: Milvus migrans

2 Alcedinidae: Isipidina picta Black kite

5 Chadriformes: Actophilornis Africana African cormorant

6 Strixwoodfordi Wood owl

7 Bucerotidae: Lophocerossemifasciatus Allied hornbill

8 Columbidae: Vinagroaustralis Green fruit pigeon

9 Turturafer Dove

10 Columba guinea Dove

11 Nectariniidae: Nectariniaolivacea Sunbird

12 Anthreptescollaris Sunbird

13 Apodidae: Apusaffiris Little swift

14 Accipiter badius Shikra

H MAMMALIA

1 Felicidae: Viverra civetta: Genetta maculata African civetus

2 Hystricidae: Hystrix cristata Porcupine

3 Sciieridae: Protoxerus sp. Nerus erythropus Squirrels

4 Thryonomyyidae: Thryonomysswinderrianus Grass cutter

5 Muridae: Cricetomysgambians Giant rat

6 Eidolonhelvum Fruit bat

7 Epomopsfrangueti Fruit bat

Page 52: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

36

8 Ratusratus Common rat

9 Rattusmorio Bush rat

10 Xeruserythropus Red-legged ground squirrel

11 Heliosciuruspunctatus Sun squirrel

12 Protoxerusstrangeri Giant squirrel

13 Perodicticuspotto Bosman'spotto

3.8 Air Quality and Noise

Ambient Air Quality

Ambient air quality was measured through the use of digitalized air quality equipment for NH3,

SOx, CO2 and NOx. Concentrations of Volatile Organic Compounds (VOC) were determined

using photo-ionization detector. Concentrations of Suspended Particulate Matter (SPM) in the

ambient air were determined using digitalized handheld air monitor (Microdust Pro).

The SPM values measured based on 8-hour daily measurements were low with an average of

0.018µg/m3 – 0.043µg/m3. The concentrations of noxious gases were equally low and in most

cases below the detection level of the equipment as shown in Table 3.8. The values estimated

showed that the air quality is within the Federal Ministry of Environment (FMEnv) limits. The

concentrations recorded for SO2, H2S and NH3 were all less than 1 ppm while volatile organic

carbon VOC had an estimated value range of 0.01 to 0.02 ppm. CO had a range of 0.16 to 0.32

ppm and a mean value of 0.223 ppm while NO2 had a range of 0.01 and 0.025 ppm. A detail result

is shown in Table 3.8

Table3.8: Results of ambient air quality measurements at the proposed project area

S/N Sampling Code SPM

(μg/m3)

CO2

(%)

NO2

(ppm)

SO2

(ppm)

VOC

(ppm)

H2S

(ppm)

CO

(ppm)

NH3

(ppm)

1 A1 0.022 0.02 0.02 <0.01 <0.01 <0.01 0.15 <0.01

2 A2 0.020 0.07 0.025 <0.01 <0.01 <0.01 0.21 <0.01

3 A3 0.027 0.05 0.011 <0.01 0.02 <0.01 0.2 <0.01

4 A4 0.042 0.02 0.010 <0.01 <0.01 <0.01 0.25 <0.01

5 A5 0.017 0.06 0.01 <0.01 0.03 <0.01 0.3 <0.01

Min. 0.017 0.02 0.01 0 0.01 - 0.15 -

Max. 0.042 0.07 0.025 0 0.02 - 0.31 -

Mean 0.0265 0.035 0.0177 0 0 0 0.222 0

FMENV Limit 0.25 NS 0.04-

0.06

0.1 NS NS 10 NS

Field Survey 2015 NS= Not Specified

Page 53: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

37

In addition, all the observed reading for SPM, NO2, NH3 and VOC were lower than the FMEnv

regulatory limit of 0.25 for SPM, 0.10 for SO2, and 004-0.06 ppm for NO2 as shown in Table 3.8

The spatial distribution of the air quality sample points is shown in Figure 3.11

Figure 3.11: Spatial Distribution of Air Quality Sample Points

Ambient Noise Levels

Ambient noise levels recorded in the proposed project area ranged from 35 to 52.1 dB(A) with a

mean value of 42.22 dB(A). The values measured were extremely below the FMEnv recommended

standard of 90 dB(A) for 8 hours exposure (see Table 3.9). Thus, the measured ambient noise

levels show that the proposed project area is devoid of noisome activities that are detrimental to

human and environmental health. Spatial distribution of noise sample points is shown in Figure

3.12.

Page 54: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

38

Table 3.9: Ambient noise levels for the project area

S/N Sampling Code Noise Level dB(A)

1 A1 40.1

2 A2 42.3

3 A3 52.1

4 A4 39.0

5 A5 35.0

Mean 42.22

FMEnv Limits 90

(Source: Fieldwork, October, 2015)

Figure 3.12: Ambient Noise Sampling Points

Page 55: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

39

CHAPTER FOUR

SOCIO-ECONOMIC CHARACTERISTICS AND STAKEHOLDER’S

CONSULTATION

4.1 Introduction

This chapter focuses on the socio-economic characteristics and impacts of the proposed

intervention project on the livelihood of the project affected people. The socio-demographic

characteristics covered include amongst others; age, gender, education, income, occupation,

residential and health status and standard of living rating.

This assessment also provides an avenue for the perceptions and views of project affected persons

and communities at large to be incorporated into the project planning.

4.2 Methodology

Structured questionnaires were administered to elicit information from 200 randomly selected

respondents across the affected communities within the project intervention area. The categories

of the stake holders sampled are shown in table 4.1 below. The questionnaire contained five

sections of structured questions covering the required information on household socio-

demographic information, health status, standard of living, cultural property and impacts of

proposed intervention. Also, Key Informant Interviews and focus group discussions were carried

out.

Table 4.1: Details of the Sampling Methodology and the Questionnaires Administered

Categories of Stakeholders

Sampled

Questionnaire

Administered

Questionnaire

Returned

FGD IDI Town Hall

Meeting

Direct Project Affected

Persons (PAPs)

80 80 2 2 1

Key Stakeholders 20 20

Other members of the

community

100 100

Total 200 200 2 2 1

Page 56: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

40

4.3 Population Estimation and Projection

This proposed intervention project at Iyi-Udele site falls within Abakiliki Local Government Areas

in Ebonyi State. The Population for 2006 for the LGA indicating the males and females are given

as males (72,518), females (77165), Total (149,683) according to National Bureau of Statistics

(2010). The estimated population for the proposed project LGA from 2006 to 2015 at the growth

rate of 2.8% are presented in Figure 4.1. Hence, the population estimates for Abakiliki LGA of

Ebonyi for 2015 is projected to be Males (92,979), Females (98,937), Total (191,916)

Figure 4.1: Projected Population for Abakiliki LGA from 2006-2015

4.4 Gender and Age of Respondents

Gender characteristics give comparative proportion of males and females in the sample frame

while age distribution provides a reflection of age structure of the in-scope individuals and

households of the project affected persons. The survey covered a total of 102 (51%) male and 98

(49%) female respondents as shown in figure 4.2. The foremost respondents fall between 18 years

and 45years of age (54.0%) and this was followed by those between 46 and 65 years of age, which

account for 40% of the sampled frame. The least responses (1.5%) are below 18 years of age but

not less than 15 years of age. The responses above 65 years of age who are mainly retirees account

for 5.0% (10 individuals) as shown in figure 4.3

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015

Male 72518 74549 76636 78782 80988 83255 85586 87983 90446 92979

Female 77165 79326 81547 83830 86177 88590 91071 93621 96242 98937

Total 1E+052E+052E+052E+052E+052E+052E+052E+052E+052E+05

0

50000

100000

150000

200000

250000

Male Female Total

Page 57: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

41

Figure 4.2: Gender of Respondents

Source: Field Survey, 2015

Figure 4.3: Age Range of Respondents

Source: Field Survey, 2015

51%

49%

Below 18 years, 3

18 -45 years , 108

46 - 65 years, 79

Above 66 years , 10

Page 58: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

42

4.5 Current Marital Status of Respondents

Figure 4.4 depicts the marital status of respondents as at the time of the survey. Of all the responses

from the sampled frame, 27 (13.5%) indicated that they had never been married, 153 (76.5%) were

married, 4 (2.0%) were divorced or separated and 16 (8%) were widowed.

Figure 4.4: Marital Status of Respondents

Source: Field Survey, 2015

4.6 Educational Status of Respondents

The distribution of educational status of the respondents is shown in Figure 4.5 below. Majority

of the respondents (86; 43%) have Senior Secondary School Certificate.

Figure 4.5: Educational Status of Respondents

Source: Field Survey, 2015

Single MarriedDivorced/Seperated

Widowed

Marital Status 27 153 4 16

27

153

4 160

20

40

60

80

100

120

140

160

180

Page 59: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

43

4.7 Occupation of Respondents

An assessment of employment status of the sampled population illustrates that the preponderance

of the respondents are civil servants 72 (36.0%) of the total respondents. This was next to self-

employed with 32 (16.0%) of the respondents. The unemployed portion of the respondents

accounted for 15.5% of the total 200. Respondents who engaged in trading and shop keeping had

an estimated proportion of 11.5%. Others include farmers, daily labourers, artisans and people on

social support who had estimated figures of 12.5%, 5.0%, 3.5% and 0.0% respectively (see Figure

4.6).

Figure 4.6: Occupation of Respondents

Source: Field Survey, 2015

Farmer , 12.50% Daily Labourer, 5.00%

Trading and Shop Keeping, 11.50%

Artisans, 3.50%

Employed (Salary), 36.00%

Self Employed, 16.00%

Social Support, 0.00%Unemployed, 15.50%

Farmer Daily Labourer Trading and Shop Keeping Artisans

Employed (Salary) Self Employed Social Support Unemployed

Page 60: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

44

4.8 Religion and Culture

The project community is made up of mainly Christian worshippers (98%) with only about 2% of

the respondents who claimed to be traditional worshippers as shown in figure 4.7. There was no

Islam respondent.

Figure 4.7: Religion of the Respondents

4.9 Assessment of Health Status of Respondents

Analysis of health status was carried out using information derived from respondents to structured

questionnaire on health status. The data show that the health conditions of the residents in the

proposed project area are affected by the high incidence of disease vectors such as mosquito. The

ailment/sickness mostly suffered from by the residence in the communities in the proposed

intervention project area includes malaria (52.0%), typhoid (15.5%). Rheumatism (2%) is

predominant among the aged as noted in the area. Other ailments among the communities in the

area include pile (5%), Rashes (14%), Eczema (12.5%), hypertension (9%), eye pains (5.5%),

Cataract (4%), Ringworm (2%), Glaucoma (2%), and whooping cough (1.5%),

4.10 Method of Waste Disposal

Open dumping is practiced by about 75.5% of the households followed by people that dump at

their backyard (19%) as shown in table 4.8 below. 4% dump in water body while 1.5% burns

theirs, as shown in Fig. 4.8 below. The poor nature of waste disposal may not be unconnected with

the breeding of mosquitoes which results in high level of malaria sickness noted in the community.

Islam, 0.00%

Christianity, 98.00%

Traditional, 2.00%

0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00%

Islam

Christianity

Traditional

Islam

Christianity

Traditional

Page 61: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

45

Figure 4.8: Refuse (Solid Waste) Disposal Method

Source: Field Survey, 2015

4.11 Accessible Sources of Water.

The communities depend primarily on tank water as their source of domestic water supply for

drinking (65.5%), while they relied on well water for cooking (47.0%), and bathing & washing

(67.5%). Community tap was identified as of no effect as it was unavailable (0.00%). Borehole

water was however used interchangeably with others for drinking (14.0%), cooking (33.0%) and

bathing and washing (22.5%). Rain harvest can only be available in the rainy season between April

and October annually although was not used by the respondents.

4.12 Project Activity Impact Evaluation.

The community members are actually excited about the project intervention. 91% of the

respondents were of the opinion that the project is going to impact on them positively while 9%

said that the project would not benefit them as shown in figure 4.9 below.

0.00%20.00%40.00%60.00%80.00%

19.00%4.00%

75.50%

1.50%0%

Page 62: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

46

Figure 4.9: Impact assessment by respondents

4.13 Stakeholders Consultation

Stakeholder’s consultation is crucial in project intervention of this sort for assuring social inclusion

and sustainable development. It is a requirement by both World Bank and the Federal Ministry of

Environment for development project of this magnitude. During this assignment, public

consultation was helpful not only in the identification and participation of the relevant stakeholders

and community but also in ensuring that they assume ownership and drive the smooth conduct of

the ESMP preparation by making suggestions and volunteering information on the relevant aspect

of the job including nature of social/community organization and women participation, perceptions

about the project, envisaged impacts and mitigations, expectations from the project, community

needs, stakeholder and community commitment and responsibilities towards project successful

implementation.

This intervention project falls within Abakaliki metropolis which is made up of cosmopolitan

population, hence there are no traditional ruler, Community leaders in the area. This reflected in

the town hall meeting where Professors, Ex and current Honorable members of the House,

business men and women, Civil servants, Farmers, Artisans and Students attended.

Town Hall meeting was held at Udoka Hall where all stakeholders in the community ranging from

men, women and youths were present as shown in plate 4.1. The focal group discussions were held

as shown in plates 4.2, 4.3 and 4.4 for the youths, men and women respectively. The attendance

for the meeting is attached (see appendix 4)

91%

9%

0% 20% 40% 60% 80% 100%

1 No

Yes

Page 63: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

47

Plate 4.1: Consultant and Community Members in the Town Hall Meeting

Plate 4.2: Consultant Interacting with Youths during the FGD

Page 64: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

48

Plate 4.3: Consultant interacting with the men during FGD

Plate 4.4: Picture of the Consultant with the women after the meeting

Page 65: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

49

Perception of Impact of Flooding in the Project Area

The impacts enumerated by members of the community attributed to flooding include:

Threat to live and property

Devastation of community farm land and cultivated crops

Leaching of soil nutrients and low productivity of crops

Depletion of land and alteration of land use;

Community’s Expectations from the Project

Community members expressed their expectations from the project as follows:

Supply of some raw materials and other locally available items to the contractor;

Employment/empowerment of youths and women in the area.

Proper measurement of properties affected for proper evaluation

Adequate compensation to people whose properties will be lost due to the intervention

The responses to the proposed project were highly positive with respondents optimistic about the

economic boost that the community will benefit from the proposed intervention. The sampled

individuals and households were optimistic see Plates 4.5 and 4.6 . They promised adequate

security / protection of lives, properties and equipment during construction and total cooperation

with all concerned stakeholders

Plate 4.5: Interactive session with a strong woman politician led by a youth at Iyi-Udele area

Page 66: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

50

Plate 4.6: In-depth Interview with Assemblies of God Church member at Iyi-Udele area

Page 67: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

51

CHAPTER FIVE

ASSESSMENT OF POTENTIAL IMPACTS AND ANALYSIS OF ALTERNATIVES

5.1 Introduction

This chapter describes the positive and negative impacts that are likely to result due to the proposed

intervention. The methods and techniques used in assessing and analyzing the environmental and

social impacts of the projects were highlighted. A comparison of the “No Action” alternative and

the proposed works is equally shown.

5.2 Impact Identification and Evaluation

The existing baseline description of the project environment and the key project activities were

used to develop a checklist of potential impacts of the project on the biophysical and social

environment. The risk of the impacts occurring was analyzed by determining the

consequences/severity of the impacts and the probability of occurrence. The severity of the

consequences was determined using a Consequence Severity Table and the probability of an

impact resulting from a pathway was determined with a Likelihood Ranking Table. The Risk

Assessment Matrix in Table 5.1 was then used to determine the level of risk and the significances

or otherwise of the impacts.

5.3 Potential Impacts of the Projects

5.3.1 Potential Positive Impacts

The project is envisaged to have a range of positive environmental and social impacts. It is

anticipated that the proposed intervention will reduce to the barest minimum the worrisome

experiences of the entire area occasioned by the flooding. The positive impacts may include:-

Reduced risk of flood due to proper channelization

Reduced loss of infrastructure including roads, houses, etc

Safety of lives and Improvement in the Sanitation and Health of the Populace

Reduced siltation in rivers

Employment opportunities and skill acquisition

Improved Drainage of the City and the Landscape Quality

Improvement in the city Planning controls

Page 68: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

52

Table 5.1: Probability of Occurrence, Consequence Severity, Likelihood Ranking and Risk Matrix

Probability Attributes

Certain Impacts that can reasonably be expected to occur during the project

Likely Impacts that are likely to occur during the project

Possible Impacts that might occur sometime during the project

Unlikely Impacts that can reasonably be expected NOT to occur during the project

Rare Impacts that are unlikely to occur except in exceptional circumstances

Severity Attributes Negligible No detectable environmental and socio-economic impact

Marginal

Minimum environmental and socio-economic impact. Localized reversible habitat

loss or minimal long term effects on habitat species or media/ public health and safety

Critical

Significant environmental and socio-economic harm. Significant widespread and

persistent changes in species, habitat and media (e.g. widespread habitat

degradation/public health and safety)

Catastrophic

Detrimental environmental and socio-economic impact. Loss of a significant portion

of a valued species or effective ecosystem function on a landscape scale/ injury and

death is possible

Severity

Probability Negligible Marginal Critical Catastrophic

Certain Likely Possible Unlikely Rare

Low

medium

High

Extreme

Impact Rating

plans will be needed for these risks.

response planning for these risks.

treme Risk: Significant additional action and high priority management attention will be required

to control risk. There is need for an in-depth response plans for these risks

5.3.2 Potential Negative Impacts

The intervention is likely to have some marginal environmental and social impact both to the

community and in the environment particularly during the pre-construction, construction and

maintenance phases. These impacts will largely be localized in spatial extent, short in duration,

occurring within less sensitive environmental areas and are manageable through the

Page 69: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

53

implementation of appropriate mitigation measures. Most of these negative impacts can be avoided

by sound design, good construction practices, effective maintenance and adequate supervision and

enforcement during construction and operational phases of the project.

5.3.2.1 Negative Environmental Impacts

Impact on Air Quality

Air Quality Deterioration

During pre-construction and construction periods, deterioration of local ambient air quality can

arise as a result of dust emissions from activities such as site clearing, excavation, filling and

concrete works as well as gaseous emissions from vehicles and operating machinery.

Noise and Vibration

Noise and vibrations is inevitable nuisance to the public during a project of this nature. During

preconstruction and construction activities, noise and vibration will arise mostly from equipment

used for site clearing and civil engineering works. The noise will have an impact mostly on

construction workers and residents living within 100 meters from the construction sites.

Impact on Water

Surface and Ground Water Contamination

Contamination of surface water can arise from sediment runoffs from exposed soil and

spoils/stockpile during clearing and excavation as well as from waste water during concrete works.

These discharges into the surface water body in the project area can have adverse attendant effects

on water quality and aquatic life. This impact is however likely to be more pronounced if the

project is implemented during the rainy season. Contamination of ground water can also occur

from spillages and leakages of fuel and oils from project activities during the construction.

Impact on Flora and Fauna

Vegetation Loss

Loss of vegetation will inevitably arise from site clearing during the preconstruction phase.

Vegetation will be cleared to allow for mobilization of equipment and machinery to site as well as

installation of camp offices and workshops. Loss of vegetation will occur in areas around the

channel where excavation activities will take place.

Page 70: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

54

Ecosystem Disturbance & Displacement/Destruction of Fauna

Site clearing activities will alter the flora and fauna species of the project site. The clearing of trees

and related flora will reduce the protection and shelter they afford to the fauna including the

wildlife of the area. This will lead to the displacement of fauna away from the site and as well

increase their exploitation tendencies through hunting.

Impact on Soil

Soil Contamination

Fuel spills and leakages from vehicles, machinery and storage facilities on site may lead to soil

contamination.

Waste Generation

Waste generation is inevitable throughout the preconstruction and construction phases of the

project. The largest amount of waste is expected to come from the clearance of vegetation cover

and will include grasses, tree trunks and branches. Other wastes will be generated from

construction activities and operations of the site offices. These will comprise construction wastes

such as equipment casings, electrical wastes, metal scraps, waste oils as well as sewer and sewage

from base camps. These wastes if not properly managed could lead to significant deterioration of

soil quality and possible contamination.

5.3.2.2 Negative Social Impacts

Traffic Congestion

Increased traffic congestion may arise from road obstructions and diversion as well as from

movement of workers and materials to and from site.

Disruption of Public Utility Services

Damage to existing public utility poles, cables and pipes that traverse the corridor of the project

during excavation works could disrupt power and privately owned water supply in the project area.

This may constitute economic and social difficulty to the members of the public.

Page 71: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

55

Public Health and Safety

Respiratory problems such as respiratory tract infection, cough and other related diseases may

occur as a result of exposure to dust particulates from site clearing and excavation activities during

preconstruction and construction phases of the project. Vehicular exhaust emission might also be

a source of air pollution capable of triggering respiratory conditions. Construction workers are

however more at risk of exposure to air pollutants.

Interactions amongst recruited male and female staff and the community members may lead to

unprotected sex that could result to sexual infections such as HIV/AIDS and other STDs.

The health and safety of the general public may also be threatened from accidental discharges of

construction materials such as stone and sand during transportation.

The significant potential positive and negative environmental and social impacts of the project

during the different phases are summarized in Table 5.2.

Page 72: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

56

Activities Potential Impacts Impact Level

Low Medium High Extreme

A Pre-Construction Phase

1. Mobilization of equipment

and other materials to site

Air quality deterioration from

release of dusts and emissions from

vehicles transporting equipment to

site

X

Noise and vibration from movement

of heavy duty vehicles

X

Traffic congestion and increased

risk of road traffic accidents and

injuries as a result of movement of

heavy equipment

X

B Construction Stage

1 Site Clearing and land

acquisition for right of way

Removal of flora and fauna X

Air quality deterioration from

release of dusts and gaseous

emissions from exposed soil

surfaces and vehicles

X

Employment of local labour for

construction activities resulting in

improved livelihood and welfare

X

Noise and vibration from the use of

machineries and motorized

equipment

X

Generation of vegetal wastes from

site clearing activities

X

2. Installation of Equipment

and Structures (Site

offices,

Utilities, Workshops, etc.)

Generation of construction wastes X

Noise and vibration from the use of

machineries and motorized

equipment during

construction of site structures

X

Air quality deterioration from

release of cement dusts, and toxic

fumes from equipment and

machineries used during building

and welding of site structures

X

3. Earthworks - Excavation,

grading, and compaction

Noise and vibration from the use of

machineries and vehicles during

excavation, burrowing, backfilling

and compaction activities

X

Air Quality deterioration from dusts

generated during excavation ,

burrowing, filling, backfilling and

compaction activities

Disruption of public utility services

from damage to existing

underground public utility

cables and pipes during excavation

works

X

Risk of occupational accidents and

injuries from the use of equipment

X

Table 5.2: Potential positive and negative environmental and social impacts

Page 73: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

57

S/N Activities Potential Impacts

Impact Level

Low medium High Extreme

4. All Civil Engineering

Works

Noise and vibration from the use of

machineries and motorized

equipment

X

Contamination of surface and

underground water from waste

water and spillages of oil and other

petroleum products through

leakages and/improper handling.

X

Waste generation from cement and

concrete works such as cement bags

and metal scraps

X

Deterioration of air quality from

release of cement dusts and toxic

fumes during construction of

concrete structures

X

Employment of local labour for

construction activities resulting in

improved livelihood and welfare

X

Occupational accidents and injuries

from the use of machineries and

equipment

X

C Operation and Maintenance Phase

1 Maintenance and operation Creation of employment by training

locals as maintenance officers

X

Waste generation from de-silting

and other maintenance works

X

Occupational accidents and injuries

as a result of falling and tripping

during routine maintenance

X

Reduced mortality/morbidity from

water related diseases

X

5.4 Analysis of Project Alternatives

Analysis of project alternatives in this ESMP context refers to the performance of the natural and

socio-economic resources with or without the project or with or without the implementation of the

measures of this ESMP and/or other safeguard instrument considered appropriate. For this

intervention project, a number of viable options that can be considered include;

No action option

Delayed action project

Go ahead option

Page 74: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

58

5.4.1 No Action Option

The no project option implies that the intervention work shall not be executed; hence there is no

need to carry out this study. This option is not environmentally friendly because this situation will

worsen and put the activities of man and the environment into further jeopardy since the area is

already exposed to the flooding. The intervention work is designed to stop these forces and mitigate

any negative impacts that may arise.

Hence, choosing the no project option will mean a loss of efforts made by all parties to ensure the

flooding do not continue to pose risk to lives and the environment and even loss of job opportunity

to Nigerians. The ‘no project option’ is therefore not considered a viable option.

5.4.2 Delayed Project Option

This delayed option implies that the planned intervention be delayed until a much later date due to

one reason or the other. Such option is usually taken when conditions are unfavourable to project

implementation such as in heavy rainfall, war situation, or where the host community is deeply

resentful to it. Also, if the prevailing economic climate is not quite favourable, then delayed option

may be feasible.

None of these conditions is applicable at present because the fund has been made available, there

is no sign of war and the host community would want the commencement of the intervention

soonest. Further delay will mean the onset of heavy rainfall which could trigger another flooding

episode that will inflict more harm than it is presently. Thus, that is not favourable for the proposed

treatment method. Therefore, the implication of delayed project option will mean that all the

preliminary work and associated efforts/ costs incurred would be futile. Also, because of

inflationary trends, such a delay may result in unanticipated increase in project costs, which may

affect the final target from the project. These, and other related problems make adopting the

delayed option a wrong alternative.

5.4.3 Go Ahead Option

This is an option that supports outright commencement of the project. It entails the channelization

of the river within Abakaliki metropolis, through the provision of line drainage channels of

Page 75: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

59

appropriate dimensions and training of the channels of River Iyi-Udele. It implies incorporating

professional advice on the most practicable option such as are spelt out in this ESMP and other

relevant safeguard instruments and/or best practices relating to the execution of the intervention.

This approach will ensure that relevant components of the natural and human environment such as

soil, public infrastructure, social and community infrastructures and facilities are taken into

account, improved and redeveloped in the affected areas concerned. The option would help in

proffering solutions to the perennial flooding experienced within Abakaliki metropolis. The

rehabilitation of the degraded environment together with remediation of the biological life forms

will guide to improvement of life. Properties will be protected, lives being saved, resources being

recovered, transportation facilities enhanced and general restoration of livelihood. It will benefit

the communities’ residents.

On the other hand, the alternative design that could have been used include Dam, Retarding basin

and floodway but they are not feasible because in urbanized area, implementation may be difficult

due to land acquisition problem. Besides the consequences of dam failure is often very catastrophic

which makes the intervention meaningless. The same is applicable to retarding basin considering

the fact that the project is at the heart of the state capital where land is a scarce commodity. Hence,

the channelization method of control is better because of the nature of the area of intervention as

earlier mentioned and is therefore considered the most viable and recommended for

implementation.

Page 76: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

60

CHAPTER SIX

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN

6.1 Introduction

The Environmental and Social Management Plan (ESMP) of the project is fully illustrated in this

chapter. Here the environmental and social management objectives and actions are integrated into

the project planning and design based on identified impacts. It provides specific description of the

potential impacts identified, mitigation measures designed as well as the institutional

responsibilities. The financial implications of all the identified mitigation measures are also given

as appropriate.

6.2 Mitigation Measures

The mitigation measures are activities aimed at reducing the severity, avoiding or controlling

project impacts and where possible enhance environmental quality through the designed

alternatives, scheduling or other means. Measures to enhance potential beneficial impacts have

also been proposed. They are based on recommended good practices, regulatory requirements and

contributions received from relevant stakeholders. The measures may be in various forms ranging

from avoidance, prevention, minimization and compensation. The potential impacts of the

projects, their mitigation and enhancement measures and the cost implication for environmental

and social components are indicated in Table 6.1 and 6.2 respectively.

Measures for Mitigation of Impacts of the Environmental Components of ESMP

There are three segments in the Environmental management plan which comprise of the Pre-

construction segment, Construction Segment and the Operation and Maintenance Segment. The

impact and their mitigation measures are hereby highlighted according to the segment.

Pre-construction segment

Here, there shall be primarily movement of equipment and other materials to site which is

expected to have some negative impacts which may include:

1. Air quality deterioration from release of dusts and emissions from vehicles

transporting equipment to site. The mitigation measures are highlighted below:

Page 77: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

61

Suppression of dust emissions by appropriate methods such as spraying water on

soil.

Employ fuel efficient and well-maintained haulage trucks with proper exhaust

system to minimize emissions.

All parked vehicles on the site shall have their engines turned off;

Service vehicles as at when due and stick to manufacturers’ specifications in use.

2. It is expected that there will be noise and vibration emanating from movement of

heavy duty vehicles. The mitigation measures are hereby given below

Maintain equipment and machineries adequately to reduce their noise levels

Fit machineries and motorized equipment with exhaust mufflers/silencers to

minimize noise generation.

Avoid unnecessary idling of internal combustion engines.

Provide ear plugs/muffs and anti-vibration hand gloves to workers and enforce

usage

Construction Segment

In this segment, there shall be site clearing and land acquisition for right of way. There shall also

be installation of equipment and structures (site offices, utilities, workshops, etc.); earthworks -

excavation, grading, and compaction; and all other Civil Engineering works. All these activities

have their impacts on the environment which are hereby highlighted with their mitigation measures

accordingly.

Site Clearing and Land Acquisition

There shall be removal of flora and fauna which is going to impact negatively on the

environment. These shall be mitigated using the following strategies:

Adherence to the RAP for compensation of affected persons.

Identification of any specie of special scientific interest

Ensure that affected flora species are transferred and raised in available nurseries.

Re-vegetate areas likely to be impacted with indigenous plant species immediately.

There shall also be air quality deterioration from release of dusts and gaseous emissions

from exposed soil surfaces and vehicles which shall be mitigated thus:

Suppression of dust emissions by appropriate methods such as spraying water on soil.

Employ fuel efficient and well-maintained haulage trucks with proper exhaust system to

minimize emissions.

All parked vehicles on the site shall have their engines turned off;

Service vehicles as at when due and stick to manufacturers’ specifications in use.

Noise and vibration from the use of machineries and motorized equipment. These shall be

mitigated thus:

Maintain equipment and machineries adequately to reduce their noise levels

Page 78: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

62

Fit machineries and motorized equipment with exhaust mufflers/silencers to minimize

noise generation

Avoid unnecessary idling of internal combustion engines.

Generation of vegetal wastes from site clearing activities. The impacts are mitigated by

adopting the following strategies:

Prepare and implement a Waste Management Plan (WMP)

Ensure submission of WMP is a condition in the procurement document for the contractor.

Ensure prompt evacuation

Workers could have accidents and sustain injuries in the course of the work and this could

thus be mitigated by doing the following:

Prepare and implement site specific HSE plan for workers

Ensure that workers are provided with health and safety equipment such as High visibility

vest, safety helmets, earplugs, safety glasses, and safety boots and, stress on the need to

use them always.

Ensure that proper signs and barriers are put up within the project location sites.

Provision of First Aid onsite.

Ensure daily supervision of PPEs.

Installation of Equipment and Structures

1. Wastes shall be generated as these activities are going on and it could be mitigated by

ensuring that the below are put in place;

Provide details of requirements for handling, stockpiling, disposal of construction

wastes (especially contaminated soil or water, concrete, demolition materials, oils,

grease, lubricants, sanitary wastes, metals, etc.).

Ensure prompt and efficient evacuation

2. It is expected that there would be noise and vibration emanating from the use of

machineries and motorized equipment during construction of site structures. These

could be mitigated with the underlisted strategies;

Maintain equipment and machineries adequately to reduce their noise levels

Fit machineries and motorized equipment with exhaust mufflers/silencers to minimize

noise generation.

Avoid unnecessary idling of internal combustion engines.

3. Air quality deterioration from release of cement dusts, and toxic fumes from equipment

and machineries used during building and welding of site structures. The mitigation

measures are;

Prepare and implement site specific HSE plan for workers.

Ensure use of nose mask specifically meant for toxic fumes and dust.

Ensure consistent monitoring of these PPEs

Page 79: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

63

Earthworks - Excavation, grading, and compaction

1. There shall be noise and vibration from the use of machineries and vehicles during

excavation, burrowing, and compaction activities. The mitigation strategies are:

Maintain equipment and machineries adequately to reduce their noise levels

Fit machineries and motorized equipment with exhaust mufflers/silencers to minimize

noise generation.

Avoid unnecessary idling of internal combustion engines.

Provide ear plugs/muffs and anti-vibration hand gloves to workers and enforce usage.

2. Air Quality deterioration from dusts generated during excavation, burrowing, filling,

backfilling and compaction activities. The mitigation measures are:

Prepare and implement site specific HSE plan for workers.

Ensure use of nose mask

Ensure consistent monitoring of these PPEs

All Civil Engineering Works

1. Noise and vibration is expected during the activities from the use of machineries and

motorized equipment. The mitigation measures are:

Maintain equipment and machineries adequately to reduce their noise levels

Fit machineries and motorized equipment with exhaust mufflers/silencers to minimize

noise generation.

Avoid unnecessary idling of internal combustion engines.

Provide ear plugs/muffs and anti-vibration hand gloves to workers and staff.

2. Contamination of surface and underground water from waste water and spillages of oil

and other petroleum products through leakages and/improper handling during civil

works. The mitigation measures include;

Implement measures to control oil spillages that will be included in construction

contracts including guidelines for the proper storage and siting of hazardous materials

such as oil, grease, fuel.

Refueling, maintenance as well as storage of diesel and oil should conform to best

practices to ensure there are no spillages or leakages. Specifically;

Fuel storage tanks should be leak-proof and checked daily. The tanks should be

installed in a bounded area and should be replaced in cases of leakage;

Procedures for storage, handling of hazardous wastes and raw materials (e.g. batteries,

chemicals, fuels) should be prepared as part of the Contractors Waste Management

Plan;

Oils should be stored in their original drums and kept on top of an impermeable surface

preferably in the contractors store room.

3. Waste generation from cement and concrete works such as cement bags and metal

scraps. The mitigation measures include:

Page 80: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

64

Implement the Waste Management Plan (WMP), using the waste minimization

hierarchy principles of avoid-reduce- reuse -recycle- dispose

The Plan will Identify requirements for waste avoidance; reduction; reuse and

recycling;

Provide details of requirements for handling, stockpiling, disposal of wastes

4. Deterioration of air quality from release of cement dusts and toxic fumes during

construction of concrete structures. The mitigation measures include:

Prepare and implement site specific HSE plan for workers.

Ensure use of nose mask

Ensure consistent monitoring of these PPEs

Operation and Maintenance Segment

There are at this stage some positive and negative impacts which shall be highlighted below.

1. There shall be highly reduced vulnerability to flooding and loss of agricultural land and

productivity due to the intervention

2. Waste shall be generated from de-silting of the channel and other maintenance works.

This could be mitigated by prompt and efficient evacuation of the drainages and the

channels as often as possible

Mitigation Measures of Impacts for the Social Components of the ESMP

There are also three segments in the Environmental management plan for the social component

which comprise of the Pre-construction segment, Construction Segment and the Operation and

Maintenance Segment. The impact and their mitigation measures are hereby highlighted

according to the segment.

Pre-construction Segment

Here, there shall be primarily movement of equipment and other materials to site which is

expected to have some social negative impacts.

1. There shall be traffic congestion and increased risk of road traffic accidents and injuries

as a result of movement of heavy equipment. The mitigation measures for this include to:

Develop and implement a Traffic Management Plan (TMP).

Ensure compliance and strict enforcement of speed limits, use of appropriate road safety

signages and signalers.

Minimize movement at peak hours of the day.

Train drivers on haulage safety and pedestrian safety.

Ensure submission of TMP as a condition in the procurement document for the contractor.

Construction Segment

Page 81: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

65

In this segment, there shall be site clearing and land acquisition for right-of-way. There shall also

be installation of equipment and structures (site offices, utilities, workshops, etc.); earthworks -

excavation, grading, and compaction; and all other Civil Engineering works. All these activities

have their impacts on the environment which are hereby highlighted with their mitigation measures

accordingly.

Site Clearing and Land Acquisition This will have positive social impact as there would be employment of local labour for site clearing.

Earthworks - Excavation, Grading, and Compaction There is likely going to be disruption of public utility services as a result of damage to existing underground

public utility cables and pipes during excavation works. This could be mitigated by adopting the following

strategies:

Use utility survey maps to identify existing underground facilities before excavation works to

prevent damages and disruption of services.

Where a need for shut down of service is necessary, it should be as temporal as possible to avoid

significant adverse effect on the people.

HIV/AIDS and other STDs

Sexual interactions amongst the workforce and the host Community could lead to dissemination

of HIV/AIDs and other STDs. The mitigation measures are:

Provide education, guidance and counseling on HIV/AIDS and other STDs for workers.

Provide condoms to construction staff

All Civil Engineering Works

There is a positive impact that will result by employment of local labour for construction activities.

This would result in improved livelihood and welfare of the community people. Employment of

local labour could be maximized by ensuring the submission of statement of intent to employ local

labour as a condition in the procurement document for the contractor. This stage could however

have a negative social impact as there could be occupational accidents and injuries from the use of

machineries and equipment during the civil engineering works. This could be mitigated by the

following strategies;

Prepare and implement site specific HSE plan for workers.

Ensure consistent use of PPEs

Regular briefing on safety and good work ethics

Page 82: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

66

Table 6.1: Environmental Management Plan

S/N Project Activity Potential Impacts

( Positive/Negative)

Mitigation Measures Monitoring Institutional

Responsibility

Estimated

Cost(N)

Indicators frequency Monitori

ng:

Implement

ation

A Pre-construction segment

1. Mobilization of

equipment and

other materials to

site

Negative Impacts

Air quality deterioration from

release of dusts and emissions

from vehicles transporting

equipment to site

1. Suppress dust emissions by

appropriate methods such as spraying

water on soil.

2. Employ fuel efficient and well-

maintained haulage trucks with proper

exhaust system to minimize emissions.

3. All parked vehicles on the site shall

have their engines turned off;

4. Service vehicles as at when due and

stick to manufacturers’ specifications in

use.

Dust and

vehicular

emissions

Regular

checks for

levels

consistent

with the

allowable

limits.

SPMU

Ebonyi,

Ministry

of

Environ

ment.

Contractor Should have

been

accommodat

ed in

Contract

sum.

Negative Impacts

Noise and vibration from

movement of heavy duty

vehicles

1. Maintain equipment and machineries

adequately to reduce their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of internal

combustion engines.

4. Provide ear plugs/muffs and anti-

vibration hand gloves to workers and

enforce usage.

Levels in

relation to

regulatory

limits or

absence of

public

complaints

Regular

checks for

levels

consistent

with the

allowable

limits.

SPMU

Ebonyi

and

Ministry

of

Environ

ment

Contractor

Page 83: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

67

S/N Project Activity Potential Impacts Mitigation Measures Monitoring Institutional Responsibility Estimated

Cost(₦) Indicator Frequency Monitoring: Implementation

B. Construction Segment

1. Site Clearing and

land acquisition

for right of way

Negative Impacts

Removal of flora and

fauna

1. Adhere to the RAP for

compensation of affected persons

2. Identify any specie of special

scientific interest

3. Ensure that affected flora species

are transferred and raised in

available nurseries.

4. Re vegetate areas likely to be

impacted with indigenous plant

species immediately.

1.Absence of

complaints

from PAP and

communities

2 .Absence of

avoidable

vegetation

clearance.

All through

the clearing

SPMU

Ebonyi,

Ministry of

Agric and

Environment

Contractor 200,000

Negative Impacts

Air quality deterioration

from release of dusts and

gaseous emissions from

exposed soil surfaces and

vehicles

1. Suppress dust emissions by

appropriate methods such as

spraying water on soil.

2. Employ fuel efficient and well-

maintained haulage trucks with

proper exhaust system to minimize

emissions.

3. All parked vehicles on the site

shall have their engines turned off;

4. Service vehicles as at when due

and stick to manufacturers’

specifications in use.

Dust and

vehicular

emissions

Regular

checks for

levels

consistent

with the

allowable

limits.

SPMU

Ebonyi

Contractor 200,000

Negative Impacts

Noise and vibration from

the use of machineries

and motorized equipment

1.Maintain equipment and

machineries adequately to reduce

their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of

internal combustion engines.

Absence of

complaints

from PAP and

communities

Regular

checks for

levels

consistent

with the

allowable

limits.

SPMU

Ebonyi and

Ministry of

Environment

Contractor 100,000

Negative Impacts Generation of vegetal wastes

from site clearing activities

Prepare and implement a Waste Management Plan (WMP)

Ensure submission of WMP is a

condition in the procurement document

Cleanliness of site

Consistent monitoring

for prompt

and efficient evacuation

Monitoring: EBSEPA,

SPMU Ebonyi

Contractor 600,000

Page 84: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

68

for the contractor. Ensure prompt

evacuation

S/N

Project

Activity

Potential Impacts Mitigation Measures Monitoring Institutional

Responsibility

Estimated

Cost(₦) Indicator Frequency

Monitoring:

Implementatio

n

Negative Impact

Workers could have

accidents and sustain

injuries in the course of the

work

1. Prepare and implement site specific HSE

plan for workers

2. Ensure that workers are provided with

health and safety equipment such as High

visibility vest, safety helmets, earplugs,

safety glasses, and safety boots and, stress on

the need to use them always.

3. Ensure that proper signs and barriers are

put up within the project location sites.

4. Provision of First Aid onsite.

5. Ensure daily supervision of PPEs

Absence of

injury and

casualties.

All through the

work

SPMU

Ebonyi

Contractor Should

have been

accommod

ated in

Contract

sum.

2. Installation of

Equipment

and Structures

(Site offices,

Utilities,

Workshops,

etc.)

Negative Impact

Generation of

construction wastes

1. Provide details of requirements for

handling, stockpiling, disposal of

construction wastes (especially

contaminated soil or water, concrete,

demolition materials, oils, grease,

lubricants, sanitary wastes, metals, etc.).

2. Ensure prompt and efficient

evacuation to designated dump sites

Cleanliness of

site.

Periodic

evacuation

EBSEPA,

SPMU

Ebonyi

Contractor 600,000

Negative Impact

Noise and vibration

from the use of

machineries and

motorized equipment

during

construction of site

structures

1.Maintain equipment and machineries

adequately to reduce their noise levels

2. Fit machineries and motorized equipment

with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of internal

combustion engines.

Absence of

complaints

from PAP and

communities

All through the

work SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor 100,000

Page 85: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

69

Negative Impact

Air quality deterioration

from release of cement

dusts, and toxic fumes

from equipment and

machineries used during

building and welding of

site structures

1. Prepare and implement site specific

HSE plan for workers.

2. Ensure use of nose mask specifically

meant for toxic fumes and dust.

3. Ensure consistent monitoring of these

PPEs

Reduced sick

workers and

less reports of

respiratory

diseases

All through the

work

SPMU

Ebonyi

and

Ministry

of Health

Contractor

150,000

S/N Project

Activity

Potential Impacts Mitigation Measures Monitoring Institutional

Responsibility

Estimated

Cost(N) Indicator Frequency

Monitoring: Implementation

3. Earthworks -

Excavation,

grading, and

compaction

Negative Impacts: Noise

and vibration from the

use of machineries and

vehicles during

excavation, burrowing,

and compaction

activities

.Maintain equipment and machineries

adequately to reduce their noise levels

2. Fit machineries and motorized equipment

with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of internal

combustion engines.

4. Provide ear plugs/muffs and anti-vibration

hand gloves to workers and enforce usage.

Absence of

complaints from

PAP and

communities

All through

the activity

SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor

150,000

Negative Impact

Air Quality deterioration

from dusts generated

during excavation ,

burrowing, filling,

backfilling and

compaction activities

1. Prepare and implement site specific HSE

plan for workers.

2. Ensure use of nose mask

3. Ensure consistent monitoring of these

PPEs

Absence of

complaints from

PAP and

communities

Less sick leave as a

result of

respiratory related

illness

All through

the activity

SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor

100,000

4. All Civil

Engineering

Works

Negative Impact

Noise and vibration from

the use of machineries and

motorized equipment

1. Maintain equipment and machineries

adequately to reduce their noise levels

2. Fit machineries and motorized equipment

with exhaust mufflers/silencers to minimize

noise generation.

3. Avoid unnecessary idling of internal

combustion engines.

4. Provide ear plugs/muffs and anti-vibration

hand gloves to workers.

Absence of

complaints from

PAP and

communities

All through

the activity

SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor

Page 86: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

70

Negative Impact

Contamination of surface

and underground water

from waste water and

spillages of oil and other

petroleum products

through leakages

and/improper handling.

1. Implement measures to control oil

spillages that will be included in construction

contracts including guidelines for the proper

storage and siting of hazardous materials

such as oil, grease, fuel.

2. Refueling, maintenance as well as storage

of diesel and oil should conform to

international best practices to ensure there are

no spillages or leakages. Specifically;

3. Fuel storage tanks should be leak-proof

and checked daily. The tanks should be

installed in a bounded area and should be

replaced in cases of leakage;

4. Procedures for storage, handling of

hazardous wastes and raw materials (e.g.

batteries, chemicals, fuels) should be

prepared as part of the Contractors Waste

Management Plan;

6. Oils should be stored in their original

drums and kept on top of an impermeable

surface preferably in the contractors store

room.

Absence of

complaints from

PAP and

communities

All through

the activity

SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor

100,000

Negative Impact

Waste generation from

cement and concrete

works such as cement

bags and metal scraps

Implement the Waste Management Plan

(WMP), using the waste minimization

hierarchy principles of avoid-reduce-

reuserecycle- disposal. The Plan will:

- Identify requirements for waste avoidance;

reduction; reuse and recycling;

- Provide details of requirements for

handling, stockpiling, disposal of wastes

Cleanliness of

site.

Periodic

evacuation

all through

the activity

SPMU

Ebonyi

and

EBSEPA

Contractor 200,000

Negative Impact

Deterioration of air

quality from release of

cement dusts and toxic

fumes during

construction of concrete

structures

1. Prepare and implement site specific HSE

plan for workers.

2. Ensure use of nose mask

3. Ensure consistent monitoring of these

PPEs

Less complaints

from communities

and

Less sick leave

Periodic

evacuation

SPMU

Ebonyi

and

Ministry

of

Environm

ent

Contractor 50,000

Page 87: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

71

C Operation and Maintenance Segment

1 Maintenance

and

operation

Negative Impact

Waste generation from de-

silting and other maintenance

works

Immediate evacuation of all the

wastes

Free flow and

Total cleanliness

of the storm water

channels

Periodically

(bi-

monthly)

SPMU

Ministry of

Environme

nt and

EBSEPA

400,000

Sub- total 2,950,000

Table 6.2: Social Management Plan

S/N Project Activity Potential Impacts

(Positive/Negative)

Mitigation Measures Monitoring Institutional

Responsibility

Estimated

Cost(N) Indicators

Frequency

Monitoring: Implementation

A Pre-construction segment

1. Mobilization of

equipment and

other materials

to site

Negative Impacts

Traffic congestion and increased

risk of road traffic accidents and

injuries as a result of movement

of heavy equipment

Emission of carbon monoxide

from heavy duty trucks

1. Develop and implement a Traffic

Management Plan (TMP).

2. Ensure compliance and strict

enforcement of speed limits, use of

appropriate road safety signages and

signalers.

3. Minimization of movement at peak

hours of the day.

4. Training of drivers on haulage safety

and pedestrian safety.

5. Ensure submission of TMP as a

condition in the procurement document

for the contractor.

Number or

absence of

public

complaints

and accidents

Daily SPMU

Ebonyi,

Ministry

responsibl

e for

transport

in the state

Contractor

and

Ministry of

Transport

Should have

been

accommodate

d in Contract

sum.

Page 88: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

72

B. Construction Segment

1. Site Clearing

and land

acquisition for

right of way

Positive Impact:

Employment of local labour for

site clearing

Absence of

complaints from

PAP and

communities

All

through

the

stage

SPMU

Ebonyi,

Contractor Should have

been

accommodate

d in Contract

sum

2. Earthworks -

Excavation,

grading, and

compaction

Negative Impact

Disruption of public utility

services from damage to existing

underground public utility cables

and pipes during excavation

works

1. Use utility survey maps to identify existing

underground facilities before excavation works to prevent damages and disruption

of services.

2. Where there is a need for shut down of service is necessary, it should be as temporal as

possible to avoid significant adverse effect on

the people.

Absence of

complaints from

PAP and

communities

All

through

the

stage

SPMU

Ebonyi and

Ministry of

Public

utilities

Contractor 100,000

Negative Impact

HIV/AIDS and other STDs

arising from the

interactions amongst the

workforce and the host

Community.

1. Provide education, guidance and counseling on HIV/AIDS and other STDs for workers.

2. Provide condoms to construction staff.

Low cases or

absence of STDs

project

All

through

the

stage

SPMU

Ebonyi and

Ministry of

Health

Contractor 100,000

3 All Civil

Engineering

Works

Positive Impact

Employment of local labour

for construction activities

resulting in improved

livelihood and welfare

Maximize employment of local labour by

ensuring the submission of statement of

intent to employ local labour as a

condition in the procurement document

for the contractor.

No employment

complaint from

community

All

through

the

project

SPMU

Ebonyi and

NGO

Contractor Should have

been

accommodate

d in Contract

sum

Negative Impact

Occupational accidents and

injuries from the use of

machineries and equipment

Prepare and implement site specific HSE

plan for workers.

Ensure consistent use of PPEs

Regular briefing on safety and good work

ethics

Very low or

absence of cases

of accident and

injuries

All

through

the

project

SPMU

Ebonyi and

Ministry of

Health

Contractor Should have

been

accommodate

d in Contract

sum

Page 89: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

73

C Operation and Maintenance Segment

1 Maintenance

and operation

Positive Impact

Creation of employment by

training locals as maintenance

officers

Maximize employment of local labour

by ensuring the submission of statement

of intent to employ local labour as a

condition in the procurement document

for the contractor.

Employment of

sufficient

indigenes

Proper

maintenance of

intervention

At the

inceptio

n of the

project

and

whenev

er

necessa

ry

SPMU

Ebonyi

Contracto

r

Negative Impact

Occupational accidents and

injuries as a result of falling and

tripping during routine

maintenance

Prepare and implement site specific

HSE plan for workers.

Ensure consistent use of PPEs

Regular briefing on safety and good

work ethics

Very low or

absence of cases

of accident and

injuries

As long

as the

mainte

nance

lasts

SPMU

Ebonyi

Ministry

of Health

100,000

Sub- total 300,000

Page 90: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

74

6.3 Project Monitoring

Monitoring is a tool to ensure adherence to agreed actions, to assess compliance, and to provide

enhanced data for refined risk management purposes. Environmental monitoring during project

implementation provides information about key environmental aspects of the project and the

effectiveness of mitigation measures, which enables proper evaluation of the success of the

mitigation and allows for any additional corrective action to be taken when needed. The

Environmental monitoring activities shall be based on direct or indirect indicators of emissions,

effluents, and resource use applicable to the intervention works. Monitoring frequency shall be

sufficient to provide representative data for the parameter being monitored. Monitoring shall be

conducted for trained individuals who can carry out the monitoring and record-keeping effectively

using properly calibrated and maintained equipment.

In order to effectively and efficiently implement this ESMP, an environmental performance

monitoring program has been designed to provide specific description and technical details of

monitoring measures, including the parameters to be measured, methods to be used, sampling

locations, frequency of measurements, detection limits (where appropriate), and definition of

thresholds that will signal the need for corrective actions. It also includes monitoring and reporting

procedures to ensure early detection of conditions that necessitate particular mitigation measures,

and furnish information on the progress and results of mitigation. Detailed proposed mitigation

measures and related monitoring activities are provided in the Monitoring Plan in Table 6.3 and

6.4 for the environmental and social components respectively.

Page 91: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

75

Table 6.3: Mitigation measures and related monitoring activities ( Environmental section)

S/N Potential Impacts

(Positive/Negative

Impacts)

Mitigation Measures Indicators/Parameter Sampling

location

Method of

Measurement

Frequency Responsibility Cost (₦)

A Pre-construction Segment

Mobilization of equipment and other materials to site

1. Air quality deterioration

from release of dusts and

emissions from vehicles

transporting equipment to

site

1. Suppress dust emissions by appropriate

methods such as spraying water on soil.

2. Employ fuel efficient and well-

maintained haulage trucks with proper

exhaust system to minimize emissions.

3. All parked vehicles on the site shall have

their engines turned off;

4. Service vehicles as at when due and stick

to manufacturers’ specifications in use.

1.Records of

maintenance

for all machineries

and equipment

2. Values of TSP,

SO2, NOx, CO,

Project

Site and

surroundin

g

In situ Monthly SPMU

Ebonyi,

Ministry of

environment,

and

Construction

contractor

600,000

2 Noise and vibration from

movement of heavy duty

vehicles

1. Maintain equipment and machineries

adequately to reduce their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of internal

combustion engines.

4. Provide ear plugs/muffs and anti-

vibration hand gloves to workers and

enforce usage.

1.Noise Levels

(Not to exceed

90dB(A)

2.No of

Complaints

Records of

Equipment

Maintenance

1.Construct

ion Site

2.

Transport

corridor

1.In-Situ

Measureme

nt

2.Sighting

3.Complain

t

Register

Daily SPMU

Ebonyi,

Ministry of

environment,

Monitoring

and

Evaluation

contractor

100,000

Page 92: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

76

S/N Potential Impacts Mitigation Measures Indicators/Parameter Sampling

location

Method of

Measurement

Frequency Responsibility Cost (₦)

B. Construction Segment

Site Clearing and land acquisition for right of way

1 Removal of flora and

fauna

1. Adhere to the RAP for

compensation of affected persons

2. Identify any specie of special

scientific interest

3. Ensure that affected flora species

are transferred and raised in available

nurseries.

4. Re vegetate areas likely to be

impacted with indigenous plant

species immediately.

Clearly Defined

Boundaries

Density

Loss/Vegetal cover

Diversity of

indigenous

and exotic plant

species

All through the

channelization

corridor

1.Visual

Observation

2.Visual

Estimate

of Cover

Daily Construction

Contractor,

SPMU

Ebonyi, Site

committee

50,000

2 Air quality

deterioration from

release of dusts and

gaseous emissions

from exposed soil

surfaces and vehicles

1. Suppress dust emissions by

appropriate methods such as spraying

water on soil.

2. Employ fuel efficient and well-

maintained haulage trucks with

proper exhaust system to minimize

emissions.

3. All parked vehicles on the site shall

have their engines turned off;

4. Service vehicles as at when due

and stick to manufacturers’

specifications in use.

1.Records of

maintenance

for all machineries and

equipment

2. Values of TSP, SO2,

NOx, CO,

Project

Site and

surrounding

In situ Monthly SPMU

Ebonyi,

Ministry of

environment,

Construction

contractor

600,000

3 Noise and vibration

from the use of

machineries and

motorized equipment

1.Maintain equipment and

machineries adequately to reduce

their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/ silencers to minimize

noise generation.

3. Avoid unnecessary idling of

internal combustion engines.

1.Noise Levels (Not

to exceed 90dB(A)

2.No of Complaints

Records of

Equipment

Maintenance

1.Construction

Site

2. Transport

corridor

1.In-Situ

Measurement

2.Sighting

3.Complaint

Register

Daily SPMU

Ebonyi,

Ministry of

environment,

Construction

contractor

100,000

Page 93: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

77

S/N Potential Impacts Mitigation Measures Indicators/Parameter Sampling

location

Method of

Measurement

Frequency Responsibility Cost (₦)

4 Generation of vegetal

wastes from site

clearing activities

Prepare and implement a Waste

Management Plan (WMP)

Ensure submission of WMP is a

condition in the procurement

document for the contractor. Ensure

prompt evacuation

1.Reference to Waste

Mgt plan

2.Contractor’s

Compliance to WMP

3.Waste Handling and

Disposal of Wastes

Construction

Site

1. Sighting

2.Visual

Observation

3. Waste

Tracking

Report

Weekly Monitoring &

Control

Contractor/

Firm

5. Exposure of soil/land

to

erosion

1.Avoid removal of vegetation and

trees to the extent possible

2. Protect all vegetation not required

to be removed against damage

3. Re vegetate exposed soil quickly

1.% of Vegetal Loss

2. Natural/Cultivated

vegetation Cover

Construction

Site

Visual Estimate

As long

as the

clearing

lasts

Contractor,

SPMU

Ebonyi,

Ministry of

environment

Accommodated

in the contract

sum

Installation of Equipment and Structures (Site offices,

Utilities, Workshops, etc.)

1 Generation of

construction wastes

1. Provide details of requirements for

handling, stockpiling, disposal of

construction wastes (especially

contaminated soil or water, concrete,

demolition materials, oils, grease,

lubricants, sanitary wastes, metals,

etc.).

2. Ensure prompt and efficient

evacuation

1. Contractors

Compliance

to WMP

2. Waste Handling and

Disposal

Construction

Site

1.Visual

Observation

2.Waste

Tracking

Report

Daily Construction

contractor,

EBSEPA

500,000

2 Noise and vibration

from the use of

machineries and

motorized

equipment during

construction of site

structures

1.Maintain equipment and

machineries adequately to reduce

their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/ silencers to minimize noise

generation.

3. Avoid unnecessary idling of

internal combustion engines.

1.Noise Levels (Not

to exceed 90 dB(A)

2.No of Complaints

Records of

Equipment

Maintenance

1.Construction

Site

2. Transport

corridor

1.In-Situ

Measurement

2.Sighting

3.Complaint

Register

Daily SPMU

Ebonyi,

Ministry of

environment,

Construction

contractor

100,000

Page 94: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

78

S/N Potential Impacts Mitigation Measures Indicators/Parameter Sampling

location

Method of

Measurement

Frequency Responsibility Cost (₦)

3 Air quality deterioration from release of cement

dusts, and toxic fumes

from equipment and machineries used during

building and welding of

site structures

1. Prepare and implement site specific HSE plan for workers.

2. Ensure use of nose mask specifically

meant for toxic fumes and dust. 3. Ensure consistent monitoring of these

PPEs

Measured Values of

TSP, SO2, NOx, CO,

Project

Site and

surrounding

In situ Monthly SPMU

Ebonyi,

Ministry of

environment,

Construction

contractor

50,000

Earthworks - Excavation, grading, and compaction

1 Noise and vibration

from the use of

machineries and

vehicles during

excavation,

burrowing, and

compaction

activities

.Maintain equipment and machineries

adequately to reduce their noise

levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/silencers to minimize noise

generation.

3. Avoid unnecessary idling of

internal combustion engines.

4. Provide ear plugs/muffs and anti-

vibration hand gloves to workers and

enforce usage.

1.Noise Levels (Not

to exceed 90dB(A)

2.No of Complaints

Records of

Equipment

Maintenance

1.Construction

Site

2. Transport

corridor

1.In-Situ

Measurement

2.Sighting

3.Complaint

Register

Daily SPMU

Ebonyi, State

Ministry of

environment,

Construction

contractor

100,000

2 Air Quality

deterioration from

dusts generated

during excavation ,

burrowing, filling,

backfilling and

compaction

activities

1. Prepare and implement site

specific HSE plan for workers.

2. Ensure use of nose mask

3. Ensure consistent monitoring of

these PPEs

Measured Values of

TSP, SO2, NOx, CO,

Project

Site and

surrounding

In situ Monthly SPMU

Ebonyi, state

Ministry of

environment,

Construction

contractor

600,000

All Civil Engineering Works

1. Noise and vibration

from the use of

machineries and

motorized equipment

1. Maintain equipment and

machineries adequately to reduce

their noise levels

2. Fit machineries and motorized

equipment with exhaust

mufflers/silencers to minimize noise

generation.

1.Noise Levels (Not

to exceed 90dB(A)

2.No of Complaints

Records of Equipment

Maintenance

1.Construction

Site

2. Transport

corridor

1.In-Situ

Measurement

2.Sighting

3.Complaint

Register

Daily SPMU

Ebonyi,

Ministry of

environment,

contractor

100,000

Page 95: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

79

3. Avoid unnecessary idling of

internal combustion engines.

4. Provide ear plugs/muffs and anti-

vibration hand gloves to workers and

2. Contamination of

surface and

underground water

from waste water and

spillages of oil and

other petroleum

products through

leakages

and/improper

handling.

1. Implement measures to control oil

spillages that will be included in

construction contracts including

guidelines for the proper storage and

siting of hazardous materials such as

oil, grease, fuel.

2. Refueling, maintenance as well as

storage of diesel and oil should

conform to best practices to ensure

there are no spillages or leakages.

Specifically;

3. Fuel storage tanks should be leak-

proof and checked daily. The tanks

should be installed in a bounded area

and should be replaced in cases of

leakage;

4. Procedures for storage, handling of

hazardous wastes and raw materials

(e.g. batteries, chemicals, fuels)

should be prepared as part of the

Contractors Waste Management

Plan;

6. Oils should be stored in their

original drums and kept on top of an

impermeable surface preferably in

the contractors store

room.

Evidence of

leakages

of oil and fuels

3. Contractor’s

Compliance

1.Construction

Site

1. Soil Quality

Test

2.Visual

Observation

3. Spot check

Bi-

monthly

SPMU

Ebonyi,

Ministry of

environment,

contractor

200,000

3. Waste generation

from cement and

concrete works such

as cement bags and

metal scraps

Implement the Waste Management

Plan (WMP), using the waste

minimization hierarchy principles of

avoid-reduce- reuserecycle- disposal.

The Plan will:

- Identify requirements for waste

avoidance; reduction; reuse and

recycling;

- Provide details of requirements for

handling, stockpiling, disposal of

wastes

1. Contractors

Compliance

to WMP

2. Waste Handling and

Disposal

Construction

Site

1.Visual

Observation

2.Waste

Tracking

Report

Daily Contractor,

EBSEPA

400,000

Page 96: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

80

4. Deterioration of air

quality from release

of cement dusts and

toxic fumes during

construction of

concrete structures

1. Prepare and implement site

specific HSE plan for workers.

2. Ensure use of nose mask

3. Ensure consistent monitoring of

these PPEs

Measured Values of

TSP, SO2, NOx, CO,

Project

Site and

surrounding

In situ Monthly SPMU

Ebonyi,

Ministry of

environment,

contractor

600,000

C Operation and Maintenance Segment

1. Waste generation

from de-silting and

other maintenance

works

Immediate evacuation of all the

wastes

1. Contractors

Compliance

to WMP

2. Waste Handling and

Disposal

Construction

Site

1.Visual

Observation

2.Waste

Tracking

Report

Daily Contractor,

EBSEPA

400,000

Sub-total = ₦4,500,000

Page 97: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

81

Table 6.4: Mitigation measures and related monitoring activities ( Social Impact)

S/

N

Potential Impacts

(Positive/Negative)

Enhancement/Mitigation Measures Indicators/Paramet

er

Sampling

location

Method of

Measurement

Frequenc

y

Responsibility Cost (₦)

A Pre-construction Segment

Mobilization of equipment and

other materials to site

1 Negative Impact

Traffic congestion and

increased risk of road

traffic accidents and

injuries as a result of

movement of heavy

equipment

1. Develop and implement a Traffic

Management Plan (TMP).

2. Ensure compliance and strict

enforcement of speed limits, use of

appropriate road safety signages and

signalers.

3. Minimization of movement at peak hours

of the day.

4. Training of drivers on haulage safety and

pedestrian safety.

5. Ensure submission of TMP as a condition

in the procurement document for the

contractor.

1.Traffic flow

2.Safety signages

& signalers

installed at

strategic locations

3.No of

Complaints from

residents and other

road users

4.No of Road

Traffic Accidents

Transport

corridor 1.Visual

Observation

Complaint

Register

Police/FRSC

Report

Daily Federal Road

Safety

Corps (FRSC)

SPMU Ebonyi

200,000

B. Construction Segment

Site Clearing and land

acquisition for right of way

1 Positive Impact:

Employment of local

labour for site clearing

Maximize employment of local labour by

ensuring the submission of statement of

intent to employ local labour as a

condition in the procurement document for

the contractor.

Absence of

complaints from

PAP and

communities

In the

Project area

Complaints

Register Wheneve

r

necessar

y

Contractor,

Earthworks - Excavation,

grading, and compaction

1 Negative Impact

Disruption of public

utility services from

damage to existing

underground public

utility cables and pipes

during excavation works

1. Use utility survey maps to identify existing

underground facilities before excavation works

to prevent damages and disruption

of services.

2. Where a need for shut down of service is necessary, it should be as temporal as possible to

avoid significant adverse effect on the people.

Complaints to

Utility

Service Providers

Constructio

n

Site

(excavated

areas)

1.Complain

ts Register

2.Visual

Observatio

n

All

through

Excavati

on period

Contractor

100,000

Page 98: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

82

2 Negative Impact

HIV/AIDS and other

STDs arising from the

interactions amongst the

workforce and the host

Community.

1. Provide education, guidance and counseling

on HIV/AIDS and other STDs for workers. 2. Provide condoms to construction staff.

3. Medical examination targeted at STD and

screening for HIV/AIDs 4. Treatment and counseling should follow.

Low cases or

absence of STDs

Amongst

the

workers.

Interview

and medical

test

Bi-

monthly

SPMU

Ebonyi,

Ministry of

Health,

400,000

All Civil Engineering Works

1 Negative Impact

Occupational

accidents and injuries

as a result of falling

and tripping during

routine maintenance

Prepare and implement site specific HSE

plan for workers.

Ensure consistent use of PPEs

Regular briefing on safety and good work

ethics.

First aid equipment present on site

HSE statistics

Contractors

Compliance

Training

Records

Workers using

PPE

5. First Aid Kit

Constructio

n

Site

1.Sighting

HSE

Reports

Routine

Inspection

Monthly SPMU

Ebonyi,

Ministry of

Health,

contractor

Accommodated

in the budget

C Operation and Maintenance Segment

1. Positive Impact

Creation of

employment by

training locals as

maintenance officers

Maximize employment of local labour by

ensuring the submission of statement of

intent to employ local labour as a condition

in the procurement document for the

contractor.

1.Contractors

compliance to

employment of

indigenes

Community 1.No of Complaints

from

community.

2. % No of

workers

employed

Periodica

lly

SPMU

Ebonyi,

contractor

Accommodated

in the budget

2. Negative Impact

Occupational

accidents and injuries

as a result of falling

and tripping during

routine maintenance

Prepare and implement site specific HSE

plan for workers.

Ensure consistent use of PPEs

Regular briefing on safety and good work

ethics

Presence of First Aid Equipment on site

HSE statistics

Contractors

Compliance

Training

Records

Workers using

PPE

5. First Aid Kitt

Constructio

n

Site

1.Sighting

HSE

Reports

Routine

Inspection

Monthly SPMU

Ebonyi,

Ministry of

Health,

contractor

Accommodated

in the budget

Sub-total= ₦700,000

Page 99: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

83

6.4 Institutional Arrangements

Institutional arrangements are essential to the effective implementation of the environmental and

social management plan. The roles and responsibility of the institutions in the implementation are

outlined in Table 6.5.

Table 6.5: Institutional Roles and Responsibilities

S/N Category Roles and Responsibilities

1. World Bank Assess implementation

Recommend additional measures for strengthening the management

framework and implementation performance.

Responsible for the final review and clearance of the ESMP;

Ensures that environmental safeguards are taken care of during World Bank

supervision mission.

2. FMEnv play the role of lead environmental regulator, overseeing compliance

requirements, granting consent and also monitoring

providing supervisory oversight for the project in conjunction with other

MDAs under its supervision

3. SPMU Ensure the smooth and efficient implementation of the project’s various

technical programmes

Maintain and manage all funds effectively and efficiently for the projects

Liaise with the FMEnv and World Bank with respect to the preparation and

implementation of the ESMP;

Ensure the integration of the required environmental and social measures and

obligations in the tender documents and contracts;

Monitor implementation of these measures and take adequate steps in case of

non-compliance;

Compile and prepare periodic environmental reports for submission to the

World Bank.

Ensures that the World Bank Safeguard policies including the

OP4.01 is strictly adhered to.

Liaise with the Contractor on implementation of the ESMP / ARAP.

Liaise with various Central and State Government agencies on environmental,

resettlement and other regulatory matters.

Engagement of core and support staff and submits same to the WB for no

objection

Sourcing of counterpart fund from the state government.

4. State Ministry of

works Site assessment and monitoring of works and engineering activities

5. State Ministry of

Environment and

EBSEPA

Lead role to ensure adherence to this ESMP and applicable standards,

environmental and social liability investigations, Monitoring and evaluation

process and criteria

Appoint an Environmental Officer, Site Engineer or Independent Consultant

that will be responsible for onsite implementation of the ESMP and

coordination of the activities of the contractor

Ensure Prompt and efficient waste evacuation

6. State Ministry of

Lands Overseer matters of Land Acquisition and compensation and other resettlement

issues

Page 100: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

84

7. State Ministry of

Health Ensures that all health and allied issues are properly addressed and supervised

8. Local

Government Support in monitoring project execution within their domains to ensure

compliance with this ESMP and other relevant requirements

9. Local

Community

Promote environmental awareness

Assist and Liaise with other stakeholders to ensure proper siting and provision

of approval for such sites

Support with provision of necessary infrastructures and engage/ encourage

carrying out comprehensive and practical awareness campaign for the

proposed projects, amongst the various relevant grass roots interest groups.

10. Other MDAs Come in as and when relevant areas or resources under their jurisdiction or

management are likely to be affected by or implicated projects such as utility.

11 Contractor Compliance to Bill of Quantity specification in procurement of material and

construction and adherence to the ESMP and good practice

to provide sufficient training to his workforce in order to ensure they are fully

aware of the relevant aspects of the ESMP and are able to fulfill their roles and

functions.

Ensures full compliance to World Bank principles and ESMP

6.5 Capacity Building and Training

Capacity building of all and sundry involved in the implementation of the ESMP is crucial to

enhance the performance of the individuals in their roles and for collaboration of relevant

stakeholders. The Contractor will be required to provide sufficient training to his workforce in

order to ensure they are fully aware of the relevant aspects of the ESMP and are able to fulfill their

roles and functions. This training will be a requirement of contract for the construction Contractor.

Specific training should be provided for workers that have specific tasks associated with the

implementation of the ESMP. Training should include:

Training on General Environmental Awareness to foster the implementation of

environmentally sound practices.

Induction Courses

Refresher Courses

Daily Tool Box Talks.

Page 101: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

85

Table 6.6: Proposed Training Programme for the Implementation of ESMP Capacity Building

Activity

Proposed Topics Target Audience Duration Estimated

Budget

Module 1:

Training on

Environmental and

Social Management

Plan

Implementation

1.Overview of Environmental and

Social Impact Assessment Process

2. Overview of Anticipated Impacts of

Project

3.Environmental Pollution & Control

4.Environmental and Social

Management Plan

5.Environmental Performance

Monitoring – Monitoring

6. Environmental Reporting

7.Mitigation Measures in ESMP

Officers of

SPMU, relevant

MDAs, LGA

departments,

NGOs,

CBOs.

1week ₦2,500,000

Module 2:

Training on

Construction HSE

1.Introduction to Construction HSE

2. Overview of Health and Safety

3. Hazards in Construction

4. Incidents: Causation, Investigation &

Reporting

5.Excavation Safety

6. Construction Site Inspection

7. Use of Personal Protective

Equipment

Relevant staff of

SPMU, other

relevant MDAs,

LGA

departments,

NGOs,CBOs.

1week ₦2,500,000

Total 2weeks ₦5,000,000

Page 102: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

86

6.6 ESMP Implementation Schedule

Most of the environmental and social management actions have to be observed throughout the construction

activities. The tentative schedule for the intervention project is shown in Table 6.7

Table 6.7: ESMP Implementation Schedule (in months)

S/N Activity Responsibility Pre-

Construction

Construction

Operation &

Maintenance

1 2 3 4 5 6 7 8 9 10 11 12

1. Disclosure of ESMP

Report

PMU

2. Allocating Budget

for ESMP

PMU

3. Appointing Support

Staff for ESMP

PMU

4. Review and Approval

of Contractor’s ESMP

PMU

5. Finalizing Site

Layout Plan of

Construction

PMU/Contractor

6. Implementation of

Mitigation

Measures

PMU/Contractor

7. Supervising ESMP

Implementation

PMU/Contractor

8. Environmental

Auditing

PMU/FMENV/MoE/

Environmental

Consultant

9. Monitoring &

Reporting on ESMP

Implementation

PMU /Contractor

10 Environmental

Training and

supervision

Contractor/HSE

Consultant

Page 103: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

87

6.7 Summary of Estimated ESMP Budget

The cost of implementing the mitigation and monitoring measures recommended in this ESMP

have been estimated and included in the ESMP. The estimated costs include the cost of capacity

building, cost of environmental monitoring and cost of mitigation by the Contractor .The details

of cost estimations are given in Table 6.8

Table 6.8: Details of ESMP Cost Estimation

S/N Items Estimated Cost ($)

@₦ 217

Estimated Cost (₦)

1. Mitigation Measures 14,977 3,250,000

2. Monitoring 23,041 5,200,000

3. Training 23,041 5,000,000

Grand Total 61,059 13,450,000

Page 104: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

88

CHAPTER SEVEN

SUMMARY, RECOMMENDATIONS AND CONCLUSION

The development of the Environmental and Social management plan of Iyi-udele flood site in

Abakaliki capital city for the Nigeria Erosion and Watershed Management Project (NEWMAP) is

crucial for the sustainable actualization of the proposed intervention which is aimed at proffering

solutions to the perennial flooding experienced within Abakaliki metropolis. The project is

envisaged to have a range of positive environmental and social impacts. It is anticipated that the

proposed intervention will reduce to the barest minimum the worrisome experiences of the entire

area occasioned by the flooding. Moreover some negative impacts are inevitable also. All these

are highlighted in chapter 5 of this report.

Measures to enhance beneficial impacts which are based on recommended good practice,

regulatory requirements and contributions received from relevant stakeholders have also been

proposed. The measures may be in various forms ranging from avoidance, prevention,

minimization and compensation

In the ESMP:

● It is observed that the proposed intervention work is most desirable because of the obvious

environmental, health and socio-economic benefits.

● Of all the viable options that were considered namely, No action option, Delayed action

project and Go ahead option, the latter was considered because the benefits far out-weigh

the negative impacts that could arise in the course of implementation.

● The design adopted for this intervention project is channelization of the river within

Abakaliki metropolis, through the provision of line drainage channels of appropriate

dimensions and training of the channels of River Iyiudele

● Mitigation measures and management plans have been suggested and developed for the

negative impacts.

● Appropriate strategy for environmental monitoring during project implementation which

provides information about key environmental aspects of the project and the effectiveness

of mitigation measures are developed

Page 105: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

89

● Responsibilities were assigned to various Institutions and Authorities for the

implementation of the mitigation measures and the environmental and social management

plan and monitoring programmes.

● The baseline biophysical data were acquired and the results were shown in chapter three.

● Very importantly, it was observed in the course of the study that the community where this

intervention project is sited is very happy to have it. They cannot wait to see the

commencement of the project.

It is recommended that a qualified contractor that is not only very competent but also conscious of

the World Bank standard should be deployed to embark on this timely and crucial intervention

project so that the ESMP would be followed to the letter for the sustainable actualization of the

project.

Conclusively, the study has shown that the proposed project will not severely impact negatively

on the existing environmental, social and health status of the people. Aside from the

environmental benefits to the community and people affected directly, the intervention would

offer the following social benefits:

Reduced mortality and morbidity from water related diseases

Diversification of livelihood and increased productivity offered to most of project

affected person and

Creation of employment

Page 106: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

90

References

Aghamelu, O. P., Nnabo P. N. and Ezeh H. N. (2010). Geotechnical and environmental

problems related to shales in the Abakaliki area, Southeastern Nigeria. African

Journal of Environmental Science and Technology, Vol. 5(2), pp. 80-88

Alloway BJ, Jackson AP. (1991). The behavior of heavy metals in sewage sludge-amended

soils. Science of the Total Environment, Vol. 100, pp. 151–176.

Allen, S.E., Grimshaw, H.M., Parkinson, J.A. & Quarmby, C. (1974). Chemical analysis

of ecological materials.Oxford: Blackwell Scientific.

American Water Works Association (AWWA) (1990). Water quality and treatment,

McGraw-Hill, New York.

FEPA (1991): National Environmental Protection (effluent Limitation) Regulations.

Federal Environmental Protection Agency, Nigeria.

Fetter CN (1990). Applied hydrogeology. CBS, New Delhi, p. 567

Freeze A, Cheery JA (1979). Groundwater. Prentice-Hall Inc., Eagle Wood Cliffs, New

Jersey, p. 491.

Global Environment Facility (GEF) 2012, Investing In Our Planet for Nigeria Erosion and

Watershed Management Project: World Bank Document

IITA (1979): Methods of Soils and Plant Tissue Analysis (International Institute for

Tropical Agriculture (IITA), Ibadan, 1979).

Ismael AMO (1990). Water resources of Abakaliki, Ishielu and Ohaozara areas of SE

Nigeria. M.Sc Thesis, Nnamdi Azikiwe University, Awka, Nigeria.

Kiely G (1997). Environmental engineering. McGraw-Hill, New York, p. 946.

Lochner, P. (2005): Guideline for Environmental Management Plans. CSIR Report No

ENV-S-C 2005-053 H. Republic of South Africa, Provincial Government of the

Western Cape, Department of Environmental Affairs & Development Planning,

Cape Town.

NEWMAP, 2012: Environmental and Social Management Framework (ESMF) for Nigeria

Erosion and Watershed Management Project: World Bank Document

NEWMAP, 2012: Resettlement Policy Framework (RPF) for Nigeria Erosion and

Watershed Management Project: World Bank Document

Page 107: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

91

Nwafor J.C. (2006) Environmental Impact Assessment for Sustainable Development: The

Nigerian Perspective. EDPCA Publications, EL’DEMAK Publishers, Enugu.

Ofoegbu CO, Amajor LC (1987). A geochemical comparison of the pyroclastic rocks from

Abakaliki and Ezillo, southeastern Benue Trough. J. Min. Geol., 23(1 - 2): 45-51.

Okogbue CO, Aghamelu OP (2010a). The Impact of the Geotechnical Properties of the

Abakaliki Shale on the Incessant Road Failures in the Abakaliki Area,

southeastern Nigeria. Paper presented at the 1st International Workshop on

Landslides and Other Natural Disasters, University of Nigeria, Nsukka, Nigeria.

22-26th March 2010.

Okogbue CO, Aghamelu OP (2010b). Comparison of the geotechnical properties of

crushed shales from Southeastern Nigeria. Bull. Eng. Geol. Environ., 69(4): 587-

597.

Reyment RA (1965). Aspects of Geology of Nigeria. Ibadan University, Ibadan, pp 145.

Sawyer CN, McCarty PL (1967). Chemistry for Sanitary Engineers. Second edition,

McGraw-Hill, New York, p. 58.

Thomas G, King R (1991). Advances in water treatment and environmental management.

Elsevier Appl. Sci., Oxford..

World Bank (1999 ): Environmental Management Plan , OP 4.01 - Annex C

Page 108: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

92

Appendix I

Questionnaire

Environmental and Social Management Plan (ESMP) for Iyi-Udele Flood Site in

Abakaliki Capital City, Ebonyi State

Dear Respondent,

Thank you for taking the time to complete the following survey! The purpose of this survey is to gain valuable insight

from the Project Affected Persons (PAPs) on the ESMP of proposed project for Iyi-Udele flood site in Abakaliki

Capital City, Ebonyi State. This is your chance to tell us what you think!

NOTE:

Please read each question carefully. Your answers are completely confidential and will be included only in summaries

where individual answers cannot be identified. Unless otherwise instructed, please tick appropriate answer category

that best describes your opinion. It will take approximately 20 minutes to complete this questionnaire.

Settlement/Community: ………………………… State/L.G.A: …….……………………

Name of Interviewer: ……..…………….…………… Date: ...……………..……………

Coordinates: Northing ………………………… Easting …………………………………

Survey Location: (a) Major Urban (b) Other Urban (c) Rural

SECTION A: Household data

1. Gender of Respondent: (a) Male (b) Female

2. Age: (a) Below 18 yrs (b) 18-45 yrs (c) 46-65 yrs (d) Above 66 yrs

3. Marital Status: (a) Single (b) Married (d) Divorced/Separated (e) Widowed

4. Residential Status: (a) Permanent Resident (b) Back Home (Returnee) (c) Non Resident, Visiting

5. Ethnic Group: (a) Ezza (b) Ezekuna (c) Izzi (d) Ikwo (d) Other, specify…………

6. Religion: (a) Islam (b) Christianity (c) Traditional

7. Education: (a) None (b) Primary School (c) Secondary School (d) Tertiary (Excluding University)

(e) University Graduate (f) University Post Graduate

8. Relationship to HH: (a) Self (b) Spouse (c) Child (d) Parent (e) Other, specify

9. Type of HH (a) Normal (Father) (b) Woman (c) Child

10. Size of the HH ……………………………

No. of Adults (Above 18) Men Women

No. of Children (below 18) Boys Girls

11. Are you affected by the flood development? (a) yes (b) no

12. If question 11 is yes, how (a) loss of Agric/farmland (b) loss of building (c) loss of landed property (d) others

specify……………..

13. Occupation: (a) Famer (b) Daily Labourer (c) Trading & Shop Keeping (d) Artisans (e) Employed

(salary) (f) Self Employed (g) Social Support (h) unemployed (i) Others specify………………………

14. How long have you been living in this area? (a) 0-2 yrs (b) 3-5 yrs (c) 6-9 yrs (d) 10 yrs and Above

Page 109: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

93

15. If non-resident, please state your actual location: ……………. (Location/LGA/State)

Education

1.1 Does anyone in your household

currently attend school (If no, skip to 2)

A Yes b No

1.2. Where do the children go to school?

(Place name)

School Category Number

a Primary b Junior High

c Senior High/ Tech/ Voc d Post-Secondary

1.3. How long does it take to get to

school?

(Note response to each school accessed)

a <5 mins b 5-15 mins

c 15-30 mins d 30-60 mins

e 60+ mins

1.4. What method of transport is used to

get to school?

(Note response to each school accessed)

a Foot b Bicycle

c Mini bus d Taxi

e Private Car f Okada

g Tri-cycle

SECTION B: HEALTH STATUS

1. Is your present state of health affected in any way by the flood activity? (a) Yes (b) No

2. If yes, in what way? (a) Skin diseases (b) Cough (c) Catarrh (d) Malaria

(e)Water-borne diseases (f) Other, Specify……………………

3. How do you manage your health conditions when sick? (a) Attend hospital/clinic (b) Buys drugs from

nearby chemist (c) Traditional medicine (d) None (e) Others Specify………………………….

4. If you do attend hospital/clinic, when last did you visit one? (a) last six months (b) last one year (c)

last five years (d) more than five years ago (e) Never visited one.

5. Please tick one or more of the under-mentioned ailment/sickness, you suffer from most accordingly?

Degree Ailment Always Sparingly Seldom Never

Degree

Ailment Always Sparingly Seldom Never

Whooping

Cough Rheumatism

Tuberculosis Rashes

Asthma Eczema

Dysentery Ringworm

Diarrhoea Eye pains

Cholera Cataract

Pile Glaucoma

Hypertension Typhoid

fever

Congestive

health problem Malaria

Pneumonia Sickle cell

anaemia

Sexually

transmitted

diseases

Epilepsy

6. Do you think your ailment will be affected by the proposed intervention? (a) Yes (b) No

7. If yes, how? (a) Contamination of ground water (b) Contamination of surface water (c) Provide breading site

for disease vectors (d) Noise/air pollution (e) Others, specify:……………………………………

Page 110: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

94

SECTION C. STANDARD OF LIVING / SOCIO-ECONOMIC ACTIVITIES

1. Assets

1.1 Do you have any of the following items

Item Quantity Item Quantity

a.radio / tape recorder

k. beds

b. television

l. furniture set

c. DVD player

m. fan

d. telephone (land line)

n. computer

e. mobile phone o. generator

f. stove

p. mosquito nets

g. fridge

q. insect screens

h. hunting trap r. other (specify)

1.2 What sort of transport does your family own

Item Quantity Item Quantity

a. bicycle

f. car

b. motorcycle/okada

g. truck

c. canoe

h. taxi

d. boat i. bus

e. tri-cycle j. other (specify)

1.3 What mode of transport do you frequently use

Item Quantity Item Quantity

a. bicycle

f. car

b. motorcycle/okada

g. truck

c. canoe

h. taxi

d. boat i. bus

e. tri-cycle j. other (specify)

Page 111: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

95

1.4 What sort of housing does your household live in?

a. Construction material - Walls

Plastered mud c. Number of rooms

1-2

Cement blocks 3-4

Other (specify) Other

(specify) b. Construction material - roofing

Corrugated roofing d. Other structures on

plot

Animal

Pen Aluminium Granary

Asbestors Shops

Tile

Kiosks

Other (specify) Other

(specify) e. Construction material - floor

Earthen

Concretes

Tiles

Other (specify)

f. Toilet Facility Pit latrine

Water closet

Toilet facility outside dwelling

Pier latrine

Other (specify)

None

g. Tenure of housing Owned

Rented

Occupied rent free

Other

h. Tenure of land Owned

Rented

Occupied rent free

Lease hold

Others specify

2. Indicate household refuse disposal for solid waste? (Multiple options) (a) Depositing refuse at backyard of the

house (b) Dumping in water body (c) Dumping in community refuse/garbage pit/dumpsite (d) Burning after

gathering together (e) Waste collector (f) Other specify………

Page 112: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

96

2.0 Household Services

2.1 Rank in order of availability and usability the source(s) of lighting for the household? (please use 1, 2,...in

hierarchical order with 1 indicating the most available and used source)

(a)

PHCN

(b)

Generator

(c)

Lantern

(d)

Candle

(e) Palm

Oil

Lamp

(f)

Torchlight

Battery

(g)

Wood

(h)

Kerosene

(i) Gas

2.2 Using the method in 2.1, indicate major source of energy for cooking?

(a) Fire

Wood

(b) Coal (c)

Kerosene

(d)

Electricity

(e) Animal

dropping

(f) Gas (g) Crop

Residue/saw dust

Others

3.0 Sources of Water

for drinking for cooking for bathing and washing

a. Well

Yes No Yes No Yes No

b. Borehole

Yes No Yes No Yes No

c. Water pump Yes No Yes No Yes No

d. Community tap Yes No Yes No Yes No

e. Piped water outside

dwelling

Yes No Yes No Yes No

f. River Yes No Yes No Yes No

h. Rain harvesting Yes No Yes No Yes No

i. Water vendor Yes No Yes No Yes No

j. Tanked water Yes No Yes No Yes No

k. Other (specify)

Yes No Yes No Yes No

4.0 Income

State your main income per month N

4.1 Remittances

1. Does anyone in the family who lives elsewhere send money to you? 1 Yes 2 No

2. If yes, how much (per month) N

5.0 Other Income

1. Do you have other income streams Yes

Yes

No

No 2. If yes, please specify the amount? N

6. Total Income

1 What is the total household monthly income (all activities)? N

7. In your opinion, how has the standard of living of your household changed over the previous three years?

(a) Same (b) Better (c) Worse

8. Is the option in 7 propelled by the flooding problem (a) Yes (b) No

9. If 8 is yes, do you think the proposed intervention will improve the situation? (a) Yes (b) No

Page 113: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

97

10. If 9 is yes specify how the project will improve the situation ………………………

11. How do you ensure gender equity in the community? (a) Women are elected in public office (b) Females are

given equal opportunity and access to education and employment (c) Quotas on genders are ensured in

leadership of community based organizations (d) Others specify…………………………………………...

SECTION D: RESOURCES/ CULTURAL PROPERTY

1. Please indicate the environmental problems which your settlement/community experiences and whose cause

can be linked to flooding? (a) Soil infertility (b) Poor drainage system (c) Bad road (d) Bad lands (e)

environmental degradation (f) Degraded land (i) Destruction of infrastructures (j) Others (specify)

…………………………..

2. Please indicate the environmental problems which your settlement/community would likely experience and

whose cause can be linked to the proposed intervention project during construction? (a) Soil infertility

(b) Poor drainage system (c) Bad road (d) Low visibility (e) Erosion Problems (f) Flooding

(g) Environmental degradation (g) Destruction of infrastructures (h) encroachment of land properties

(i) Pollution (air, surface water, ground water, noise) (j) Others (specify) ………………………….

3. Please indicate the environmental problems which your settlement/community would likely experience and

whose cause can be linked to the proposed intervention project during operation? (a) Soil infertility

(b) Poor drainage system (c) Bad road (d) Low visibility (e) Erosion Problems (f) Flooding

(g) Environmental degradation (h) Destruction of infrastructures (i) encroachment of land properties

(j) Pollution (air, surface water, ground water, noise) (k) Others (specify) …………………………..

4. Do you think the proposed intervention project will affect any valued resource/cultural/archaeological

property in your area? (a) Yes (b) No

5. If yes mention the name(s) of the valued resource/cultural/archaeological property …………………………

6. How will valued resource/cultural/archaeological property be affected? (a) Displacement of such valued

cultural properties (b) Vandalisation of sacred items/locations (c) Possible theft of sacred/archaeological

items (d) Others, specify: ……………………………

SECTION E: Intervention Project Activities Impact Evaluation

1. Are you aware of the proposed intervention by NEWMAP (a) Yes (b) No

2. If yes, from which source (a) Community meetings (b) Media (TV, Radio, Newspaper, Internet)

(c) Others specify…………………………….

3. Do you think the project can cause restiveness in your community? (a) Yes (b) No

4. If 3 is yes how will the proposed intervention result in restiveness? (a) Disrespect of norms and culture by

contractors (b) loss of farmland / Property (c) Possible theft of sacred/archaeological items

(d) local people not employed during construction (e) Others, specify: ……………………………

5. How will the proposed intervention project impact on your livelihood and environment?

Page 114: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

98

Positive impacts Negative impacts

(a) (b) (c) (d) (e) (f)

6. Can you name some of the animals and other habitat at the flood site that may be affected by the proposed

intervention project? …………………………………………………………………………………………

7. What do you expect from the activities of NEWMAP intervention? (a) employment of Locals during

construction (b) compensation for those whose properties will be affected (c) capacity building for

maintenance during implementation (d) community input into final engineering design (e) Others please

specify……………………..

8. Are there any other issue(s) of concern as regards the intervention project in your area, please state clearly?

……………………...…………………………………………………………………………………

Page 115: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

99

Appendix II

Nigerian Ambient Air Quality Standards (NAAQS)

Pollutants Time of Average Limits

Particulates Daily average of daily values

1hour

250µg/m3

600 µg/m3

Sulphuroxide

(Sulphurdioxide)

Daily average of hourly

values 1 hour

0.01ppm

0.1ppm

Non-methanehydrocarbon Daily average of 3-

hourly values

160µg/m3

Carbonmonoxide Daily average of hourly

values 8-hour average

10ppm

20ppm

Nitrogen oxides

(Nitrogen dioxide)

Daily average of hourly values

(range)

0.04- 0.06ppm

Photochemical Oxidant Hourly values 0.06ppm

Source: Guidelines and Standards for Environmental Pollution Control in Nigeria (FEPA, 1991)

Noise Exposure Limits for Nigeria

Duration per Day, Hour Permissible Exposure Limit dB(A)

8 90

6 92

4 95

3 97

2 100

1.5 102

1 105

0.5 110

0.25 115

Source: Guidelines and Standards for Environmental Pollution

Page 116: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

100

Appendix III

GENERAL ENVIRONMENTAL MANAGEMENT CONDITIONS FOR CONSTRUCTION

CONTRACTS

General

1. In addition to these general conditions, the Contractor shall comply with any specific Environmental

Management Plan (EMP) or Environmental and Social Management Plan (ESMP) for the works he is

responsible for. The Contractor shall inform himself about such an EMP, and prepare his work strategy and

plan to fully take into account relevant provisions of that EMP. If the Contractor fails to implement the

approved EMP after written instruction by the Supervising Engineer (SE) to fulfill his obligation within the

requested time, the Owner reserves the right to arrange through the SE for execution of the missing action

by a third party on account of the Contractor.

2. Notwithstanding the Contractor’s obligation under the above clause, the Contractor shall implement all

measures necessary to avoid undesirable adverse environmental and social impacts wherever possible,

restore work sites to acceptable standards, and abide by any environmental performance requirements

specified in an EMP. In general these measures shall include but not be limited to:

(a) Minimize the effect of dust on the surrounding environment resulting from earth mixing sites, vibrating

equipment, temporary access roads, etc. to ensure safety, health and the protection of workers and

communities living in the vicinity dust producing activities.

(b) Ensure that noise levels emanating from machinery, vehicles and noisy construction activities (e.g.

excavation, blasting) are kept at a minimum for the safety, health and protection of workers within the

vicinity of high noise levels and nearby communities.

(c) Ensure that existing water flow regimes in rivers, streams and other natural or irrigation channels is

maintained and/or re-established where they are disrupted due to works being carried out.

(d) Prevent oils, lubricants and waste water used or produced during the execution of works from entering

into rivers, streams, irrigation channels and other natural water bodies/reservoirs, and also ensure that

stagnant water in uncovered borrow pits is treated in the best way to avoid creating possible breeding

grounds for mosquitoes.

(e) Prevent and minimize the impacts of quarrying, earth borrowing, piling and building of temporary

construction camps and access roads on the biophysical environment including protected areas and arable

lands; local communities and their settlements. In as much as possible restore/rehabilitate all sites to

acceptable standards.

(f) Upon discovery of ancient heritage, relics or anything that might or believed to be of archeological or

historical importance during the execution of works, immediately report such findings to the SE so that the

appropriate authorities may be expeditiously contacted for fulfillment of the measures aimed at protecting

such historical or archaeological resources.

(g) Discourage construction workers from engaging in the exploitation of natural resources such as hunting,

fishing, and collection of forest products or any other activity that might have a negative impact on the

social and economic welfare of the local communities.

(h) Implement soil erosion control measures in order to avoid surface run off and prevents

siltation, etc.

(i) Ensure that garbage, sanitation and drinking water facilities are provided in construction workers camps.

(j) Ensure that, in as much as possible, local materials are used to avoid importation of foreign material and

long distance transportation.

(k) Ensure public safety, and meet traffic safety requirements for the operation of work to avoid accidents.

Page 117: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

101

3. The Contractor shall indicate the period within which he/she shall maintain status on site after completion

of civil works to ensure that significant adverse impacts arising from such works have been appropriately

addressed.

4. The Contractor shall adhere to the proposed activity implementation schedule and the monitoring plan /

strategy to ensure effective feedback of monitoring information to project management so that impact

management can be implemented properly, and if necessary, adapt to changing and unforeseen conditions.

5. Besides the regular inspection of the sites by the SE for adherence to the contract conditions and

specifications, the Owner may appoint an Inspector to oversee the compliance with these environmental

conditions and any proposed mitigation measures. State environmental authorities may carry out similar

inspection duties. In all cases, as directed by the SE, the Contractor shall comply with directives from such

inspectors to implement measures required to ensure the adequacy rehabilitation measures carried out on

the bio-physical environment and compensation for socio-economic disruption resulting from

implementation of any works.

Worksite/Campsite Waste Management

6. All vessels (drums, containers, bags, etc.) containing oil/fuel/construction materials and other hazardous

chemicals shall be bunded in order to contain spillage. All waste containers, litter and any other waste

generated during the construction shall be collected and disposed off at designated disposal sites in line

with applicable government waste management regulations.

7. All drainage and effluent from storage areas, workshops and camp sites shall be captured and treated

before being discharged into the drainage system in line with applicable government water pollution control

regulations.

8. Used oil from maintenance shall be collected and disposed off appropriately at designated sites or be re-

used or sold for re-use locally.

9. Entry of runoff to the site shall be restricted by constructing diversion channels or holding structures such

as banks, drains, dams, etc. to reduce the potential of soil erosion and water pollution.

10. Construction waste shall not be left in stockpiles along the road, but removed and reused or disposed of

on a daily basis.

11. If disposal sites for clean spoil are necessary, they shall be located in areas, approved by the SE, of low

land use value and where they will not result in material being easily washed into drainage channels.

Whenever possible, spoil materials should be placed in low-lying areas and should be compacted and

planted with species indigenous to the locality.

Material Excavation and Deposit

12. The Contractor shall obtain appropriate licenses/permits from relevant authorities to operate quarries or

borrow areas.

13. The location of quarries and borrow areas shall be subject to approval by relevant local and national

authorities, including traditional authorities if the land on which the quarry or borrow areas fall in traditional

land.

14. New extraction sites:

a) Shall not be located in the vicinity of settlement areas, cultural sites, wetlands or any other valued

ecosystem component, or on high or steep ground or in areas of high scenic value, and shall not be located

less than 1km from such areas.

b) Shall not be located adjacent to stream channels wherever possible to avoid siltation of river channels.

Where they are located near water sources, borrow pits and perimeter drains shall surround quarry sites.

c) Shall not be located in archaeological areas. Excavations in the vicinity of such areas shall proceed with

great care and shall be done in the presence of government authorities having a mandate for their protection.

d) Shall not be located in forest reserves. However, where there are no other alternatives, permission shall

be obtained from the appropriate authorities and an environmental impact study shall be conducted.

Page 118: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

102

e) Shall be easily rehabilitated. Areas with minimal vegetation cover such as flat and bare ground, or areas

covered with grass only or covered with shrubs less than 1.5m in height, are preferred.

f) Shall have clearly demarcated and marked boundaries to minimize vegetation clearing.

15. Vegetation clearing shall be restricted to the area required for safe operation of construction work.

Vegetation clearing shall not be done more than two months in advance of operations.

16. Stockpile areas shall be located in areas where trees can act as buffers to prevent dust pollution.

Perimeter drains shall be built around stockpile areas. Sediment and other pollutant traps shall be located

at drainage exits from workings.

17. The Contractor shall deposit any excess material in accordance with the principles of these general

conditions, and any applicable EMP, in areas approved by local authorities and/or the SE.

18. Areas for depositing hazardous materials such as contaminated liquid and solid materials shall be

approved by the SE and appropriate local and/or national authorities before the commencement of work.

Use of existing, approved sites shall be preferred over the establishment of new sites.

Rehabilitation and Soil Erosion Prevention

19. To the extent practicable, the Contractor shall rehabilitate the site progressively so that the rate of

rehabilitation is similar to the rate of construction.

20. Always remove and retain topsoil for subsequent rehabilitation. Soils shall not be stripped when they

are wet as this can lead to soil compaction and loss of structure.

21. Topsoil shall not be stored in large heaps. Low mounds of no more than 1 to 2m high are recommended.

22. Re-vegetate stockpiles to protect the soil from erosion, discourage weeds and maintain an

active population of beneficial soil microbes.

23. Locate stockpiles where they will not be disturbed by future construction activities.

24. To the extent practicable, reinstate natural drainage patterns where they have been altered or

impaired.

25. Remove toxic materials and dispose of them in designated sites. Backfill excavated areas with soils or

overburden that is free of foreign material that could pollute groundwater and soil.

26. Identify potentially toxic overburden and screen with suitable material to prevent mobilization of toxins.

27. Ensure reshaped land is formed so as to be inherently stable, adequately drained and suitable for the

desired long-term land use, and allow natural regeneration of vegetation.

28. Minimize the long-term visual impact by creating landforms that are compatible with the adjacent

landscape.

29. Minimize erosion by wind and water both during and after the process of reinstatement.

30. Compacted surfaces shall be deep ripped to relieve compaction unless subsurface conditions dictate

otherwise.

31. Revegetate with plant species that will control erosion, provide vegetative diversity and, through

succession, contribute to a resilient ecosystem. The choice of plant species for rehabilitation shall be done

in consultation with local research institutions, forest department and the local people.

Water Resources Management

32. The Contractor shall at all costs avoid conflicting with water demands of local communities.

33. Abstraction of both surface and underground water shall only be done with the consultation of the local

community and after obtaining a permit from the relevant Water Authority.

34. Abstraction of water from wetlands shall be avoided. Where necessary, authority has to be obtained

from relevant authorities.

35. Temporary damming of streams and rivers shall be done in such a way avoids disrupting water supplies

to communities downstream, and maintains the ecological balance of the river system.

36. No construction water containing spoils or site effluent, especially cement and oil, shall be allowed to

flow into natural water drainage courses.

37. Wash water from washing out of equipment shall not be discharged into water courses or road drains.

Page 119: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

103

38. Site spoils and temporary stockpiles shall be located away from the drainage system, and surface run

off shall be directed away from stockpiles to prevent erosion.

Traffic Management

39. Location of access roads/detours shall be done in consultation with the local community especially in

important or sensitive environments. Access roads shall not traverse wetland areas.

40. Upon the completion of civil works, all access roads shall be ripped and rehabilitated.

41. Access roads shall be sprinkled with water at least five times a day in settled areas, and three times in

unsettled areas, to suppress dust emissions.

Blasting

42. Blasting activities shall not take place less than 2km from settlement areas, cultural sites, or wetlands

without the permission of the SE.

43. Blasting activities shall be done during working hours, and local communities shall be consulted on the

proposed blasting times.

44. Noise levels reaching the communities from blasting activities shall not exceed 90 decibels.

Disposal of Unusable Elements

45. Unusable materials and construction elements such as electro-mechanical equipment, pipes, accessories

and demolished structures will be disposed of in a manner approved by the SE.

The Contractor has to agree with the SE which elements are to be surrendered to the Client’s premises,

which will be recycled or reused, and which will be disposed of at approved landfill sites.

46. As far as possible, abandoned pipelines shall remain in place. Where for any reason no alternative

alignment for the new pipeline is possible, the old pipes shall be safely removed and stored at a safe place

to be agreed upon with the SE and the local authorities concerned. AC-pipes as well as broken parts thereof

have to be treated as hazardous material and disposed of as specified above.

48. Unsuitable and demolished elements shall be dismantled to a size fitting on ordinary trucks for transport.

Health and Safety

49. In advance of the construction work, the Contractor shall mount an awareness and hygiene campaign.

Workers and local residents shall be sensitized on health risks particularly of AIDS.

50. Adequate road signs to warn pedestrians and motorists of construction activities, diversions, etc. shall

be provided at appropriate points.

51. Construction vehicles shall not exceed maximum speed limit of 40km per hour.

Repair of Private Property

52. Should the Contractor, deliberately or accidentally, damage private property, he shall repair the property

to the owner’s satisfaction and at his own cost. For each repair, the Contractor shall obtain from the owner

a certificate that the damage has been made good satisfactorily in order to indemnify the Client from

subsequent claims.

53. In cases where compensation for inconveniences, damage of assets etc. are claimed by the owner, the

Client has to be informed by the Contractor through the SE. This compensation is in general settled under

the responsibility of the Client before signing the Contract. In unforeseeable cases, the respective

administrative entities of the Client will take care of compensation.

Contractor’s Health, Safety and Environment Management Plan (HSE-MP)

54. Within 6 weeks of signing the Contract, the Contractor shall prepare an EHS-MP to ensure the adequate

management of the health, safety, environmental and social aspects of the works, including implementation

of the requirements of these general conditions and any specific requirements of an EMP for the works.

The Contractor’s EHS-MP will serve two main purposes:

Page 120: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

104

• For the Contractor, for internal purposes, to ensure that all measures are in place for adequate HSE

management, and as an operational manual for his staff.

• For the Client, supported where necessary by a SE, to ensure that the Contractor is fully prepared for the

adequate management of the HSE aspects of the project, and as a basis for monitoring of the Contractor’s

HSE performance.

55. The Contractor’s EHS-MP shall provide at least:

• a description of procedures and methods for complying with these general environmental management

conditions, and any specific conditions specified in an EMP;

• a description of specific mitigation measures that will be implemented in order to minimize adverse

impacts;

• a description of all planned monitoring activities (e.g. sediment discharges from borrow areas) and the

reporting thereof; and

• the internal organizational, management and reporting mechanisms put in place for such.

56. The Contractor’s EHS-MP will be reviewed and approved by the Client before start of the works. This

review should demonstrate if the Contractor’s EHS-MP covers all of the identified impacts, and has defined

appropriate measures to counteract any potential impacts.

HSE Reporting

57. The Contractor shall prepare bi-weekly progress reports to the SE on compliance with these general

conditions, the project EMP if any, and his own EHS-MP. An example format for a Contractor HSE report

is given below. It is expected that the Contractor’s reports will include information on:

• HSE management actions/measures taken, including approvals sought from local or national authorities;

• Problems encountered in relation to HSE aspects (incidents, including delays, cost consequences, etc. as

a result thereof);

• Lack of compliance with contract requirements on the part of the Contractor;

• Changes of assumptions, conditions, measures, designs and actual works in relation to HSE aspects; and

• Observations, concerns raised and/or decisions taken with regard to HSE management during site

meetings.

58. It is advisable that reporting of significant HSE incidents be done “as soon as practicable”.Such incident

reporting shall therefore be done individually. Also, it is advisable that the Contractor keeps his own records

on health, safety and welfare of persons, and damage to property. It is advisable to include such records, as

well as copies of incident reports, as appendixes to the bi-weekly reports. Example formats for an incident

notification and detailed report are given below. Details of HSE performance will be reported to the Client

through the SE’s reports to the Client.

Training of Contractor’s Personnel

59. The Contractor shall provide sufficient training to his own personnel to ensure that they are all

aware of the relevant aspects of these general conditions, any project EMP, and his own EHSMP,

and are able to fulfill their expected roles and functions. Specific training should be provided to those

employees that have particular responsibilities associated with the implementation of the EHS-MP. General

topics should be:

• HSE in general (working procedures);

• emergency procedures; and

• social and cultural aspects (awareness raising on social issues).

Cost of Compliance

60. It is expected that compliance with these conditions is already part of standard good workmanship and

state of art as generally required under this Contract. The item “Compliance with Environmental

Page 121: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

105

Management Conditions” in the Bill of Quantities covers these costs. No other payments will be made to

the Contractor for compliance with any request to avoid and/or mitigate an avoidable HSE impact.

Example Format: HSE Report

Contract:

Period of reporting:

HSE management actions/measures:

Summarize HSE management actions/measures taken during period of reporting, including planning and

management activities (e.g. risk and impact assessments), HSE training, specific design and work measures

taken, etc.

HSE incidents:

Report on any problems encountered in relation to HSE aspects, including its consequences (delays, costs)

and corrective measures taken. Include relevant incident reports.

HSE compliance:

Report on compliance with Contract HSE conditions, including any cases of noncompliance.

Changes:

Report on any changes of assumptions, conditions, measures, designs and actual works in relation

to HSE aspects.

Concerns and observations:

Report on any observations, concerns raised and/or decisions taken with regard to HSE management during

site meetings and visits.

Signature (Name, Title Date):

Contractor Representative

Example Format: HSE Incident Notification

Provide within 24 hrs to the Supervising Engineer

Originators Reference No:

Date of Incident: Time:

Location of incident:

Name of Person(s) involved:

Employing Company:

Type of Incident:

Description of Incident:

Where, when, what, how, who, operation in progress at the time (only factual)

Immediate Action:

Immediate remedial action and actions taken to prevent reoccurrence or escalation

Signature (Name, Title, Date):

Contractor Representative

Page 122: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

106

Appendix IV

Page 123: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

107

Page 124: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

108

Page 125: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

109

Page 126: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

110

Page 127: Nigeria Erosion and Watershed Management Project (NEWMAP)documents.worldbank.org/curated/en/... · Nigeria Erosion and Watershed Management Project (NEWMAP) ENVIRONMENTAL AND SOCIAL

111


Top Related