Page 1: Mid-term Review Meeting - WP6

Project SLOPE1

WP 6 – System integration

Page 2: Mid-term Review Meeting - WP6

Project SLOPE

Mid-term Review2/Jul/2015

T6.1– Definition of the integration steps

Brussels, July 2nd, 2015

Page 3: Mid-term Review Meeting - WP6

Task Overview

Mid-term Review2/Jul/2015

• Status: Completed (100%)• Length: 7 Months (From M10 to M16)• 5 Involved Partners

• Leader: GraphiTech• Participants: COMPOLAB, MHG, FLY, ITENE

• Aim: Achieve a complete integration of the different components that are part of the SLOPE platform to be tested on pilot areas

• Output: • D.6.01 System integration and validation plan

Page 4: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Work Package key aspects

• Build a working system

• Ready for pilots and on-the-field testing

• 3 Main tasks:• First Integration - Forest Inventory & Harvesting

System • Second Integration - Forest Management• Third Integration – System Validation

• Technical and Economical Analysis • Overall solution costs• Social impacts• Environmental impacts

T.6.2

T.6.3

T.6.4

Page 5: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Process• Evaluate existing software development processes

• Definition of the integration strategy

• Enrich each integration task (6.2, 6.3, 6.4) with the chosen strategy

Page 6: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

SW Development processes evaluation

• Different processes studied and evaluated:• Heavyweight:

• Waterfall• Unified process• Spiral

• Lightweight (AGILE): • Extreme programming• Scrum

• Conclusions:• Best choice: AGILE (but not enough)• Too many development teams• Mix waterfall and Agile

Page 7: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Integration StrategyWaterfall + agile like approach• 3 major loops of integration and lab validation• 4 minor loops of iterative evolution• Bug fixing and integration at high frequency• Parallel support for real use case pilots

T.6.2

T.6.3

T.6.4

Page 8: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Integration Strategy

For each main integration step:• Definition of the involved components• Timeline with integration steps, milestones, telcos, days for testing• One testing scenario based on the use case• Recognize Involved actors • Definition of required HW and SW• Functional requirements

• defining a function• Non-functional requirements

• defining a criteria for an operation• Testing approach

Page 9: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) - Components

Page 10: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) - Timeline

• 4 agile-like integration sprints (bimonthly)• 2 sprint overlapping with step 2

• 1 monitoring meeting every 2 weeks• 1 Round of testing at the end of each sprint

• Incremental built of D.6.02.1 System Integration Report I• Incremental build of D.6.04.1 Techno-economic evaluation I

Page 11: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) – Integration

1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS3. Connection of cable crane and processor head enhanced HW with the FIS4. Connection of truck control units with the FIS5. Connection of planning and editing functionalities already available in the

3D modelling for harvesting planning system with the FIS

Page 12: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) – Actors, HW and SW

• Actors:• Forest Planner• Forest operator• On-field harvesting operator• Forestry expert• Cableway Operator

• Hardware:• RFID Handheld (Tablet / Smartphone)• GPS Sensor (integrated inside the handheld or

external)• Industrial PC installed inside the harvesting

machine• CompactRIO Custom system• Desktop Computer• Wifi/3G connectivity

• Software:• 3D Planning for Harvesting

software• Forest Information System

(Web Services and Database)• Web Mapping Service

(GeoServer)

Page 13: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) – Functional Requirements

3 Analytics3.1 Show satellite imagery HIGH3.2 Toggle aerial imagery visualization of the

standHIGH

3.3 Toggle NIR imagery visualization of the stand HIGH3.4 Toggle open data visualization MEDIUM3.5 Toggle digital surface model visualization HIGH3.6 Distance measurement HIGH3.7 Area measurement HIGH3.8 Terrain profiling HIGH3.9 Point of interest visualization MEDIUM4.0 Toggle roads visualization HIGH

4 Operation4.1 Cableway planning HIGH4.1.1 Add/Remove pillars HIGH

4.1.2 Show harvesting area HIGH

4.1.3 Show cable information (angles, height from terrain, length)

HIGH

4.1.4 Show cable line profile MEDIUM

4.2 Working area setup4.2.1 Draw working area HIGH

4.2.2 Place harvesting machines HIGH

4.2.3 Place other resources HIGH

4.2.4 Plan routes MEDIUM

4.3 Track felling activities MEDIUM4.4 Toggle building and terminals visualization MEDIUM4.5 Track logistics MEDIUM4.5.1 Show truck movements MEDIUM

4.5.2 Track wood storage areas MEDIUM

4.5.3 Track sawmills MEDIUM

4.5.4 Show logs inventory MEDIUM

4.6 Track harvesting progress HIGH4.6.1 Real-time updates and statistics MEDIUM

4.7 Show weather conditions and forecast HIGH

5 Forest 5.1 Toggle stand visualization HIGH5.2 Toggle simple tree models visualization (from UAV) HIGH5.3 Toggle complex tree models visualization (from TLS) HIGH5.4 Single tree selection and inspection HIGH5.5 Single tree virtual marking HIGH5.5.1 Issue a report MEDIUM5.5.2 Update tree properties (Quality indices, status, etc.) HIGH5.6 Retrieve forest area information MEDIUM

Page 14: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.02) – Non-Functional Requirements

Forest Information System (FIS)1 User friendliness HIGH2 Compatibility with all the desktop browsers HIGH3 Compatibility with mobile browsers MEDIUM4 Cross platform HIGH5 Dynamic interface MEDIUM

Mobile scenario6 Easy identification of virtually marked trees on the field HIGH7 GPS signal should work in the forest MEDIUM8 Offline fault tolerance MEDIUM

In-vehicle scenario8 Offline fault tolerance MEDIUM

Page 15: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 1 (T6.03) – Testing

• One validation every 2 months• 2-3 days of work• Test of each requirement in laboratory conditions

• Based on functional test case• Incremental document • Threshold to be reached 70%

Test N° Test case DescriptionExpected

resultObtained

ResultAnomaly Performed Passed

1 … … … … YES/NO YES/NO1

Page 16: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) - Components

Page 17: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) - Timeline

• 4 agile-like integration sprints (bimonthly)• 2 sprint overlapping with step 3

• 1 Virtual meeting every 2 weeks• 1 Round of testing at the end of each sprint

• Incremental built of D.6.02.2 System Integration Report II• Incremental build of D.6.04.2 Techno-economic evaluation II

Page 18: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) – Integration

1. Refinement of already existing Web services to access the FIS2. Development of new Web Services functions to cope with online

purchasing/invoicing, real-time operation control and logistic optimization3. Connection of purchasing/invoicing system with the FIS4. Connection of real-time operation control system with the FIS

Page 19: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) – Actors, HW and SW

• Actors:• Forest Planner• Forestry expert• Truck Operator

• Hardware:• In-vehicle GPS System

• Software:• Real-time enterprise resource

planning system• Online selling and auction system• MHG Mobile app

Page 20: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) – Functional Requirements

4 Operation4.8 Schedule operations and give work orders MEDIUM

7 Purchasing7.1 Online auction MEDIUM7.2 Direct selling MEDIUM

8 Business Analytics8.1 Harvesting cost estimation HIGH8.2 Income estimation HIGH

9 Resource inspection9.1 Staff monitoring MEDIUM9.1.2 Update human resource usage MEDIUM9.2 Machinery monitoring MEDIUM9.2.1 Update machine status MEDIUM9.3 Terminals monitoring MEDIUM9.3.1 Update terminal status MEDIUM9.3.2 Documentation with mobile app MEDIUM9.3.3 Biomass quality monitoring MEDIUM9.3.4 Road side storage monitoring MEDIUM9.3.5 Transport monitoring & reports (delivery notes) MEDIUM

Page 21: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 2 (T6.03) – Testing

• One validation every 2 months• 2-3 days of work• Test of each requirement in laboratory conditions

• Based on functional test case• Incremental document • Threshold to be reached 80%

Test N° Test case DescriptionExpected

resultObtained

ResultAnomaly Performed Passed

1 … … … … YES/NO YES/NO1

Page 22: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 3 (T6.04) - Components

Page 23: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Step 3 (T6.04) - Timeline

• 4 agile-like integration sprints (bimonthly) • 1 Virtual meeting every 2 weeks• 1 Round of testing at the end of each sprint

• Incremental built of D.6.023• Actors, requirements and test case as union of the first two steps• Threshold to be reached 90%

Page 24: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Conclusions

• Guidelines for efficient and continuous integration• 4 sprints with validation and reporting per task

• Regular monitoring meetings

• Incremental testing phase

• Ready for changing requirements• Partners• Forestry Actors

Page 25: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Contact info

Daniele Magliocchetti: [email protected]

Thank you for your attention

Page 26: Mid-term Review Meeting - WP6

Project SLOPE

Mid-term Review2/Jul/2015

T6.2– First Integration

Forest Inventory & Harvesting System

Brussels, July 2nd, 2015

Page 27: Mid-term Review Meeting - WP6

Task Overview

Mid-term Review2/Jul/2015

• Status: In progress (20%)• Length: 14 Months (From M14 to M27)• 8 Involved Partners

• Leader: GraphiTech• Participants: COMPOLAB, MHG, FLY, GRE, TRE, ITENE, CNR

• Aim: • Integration of forest information system (FIS) with harvesting

measurement systems and software components

• Output: • D.6.21 System integration report I• D.6.41 SLOPE System Techno-Economic Evaluation Report I

Page 28: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Task Overview

1. Connection of the 3D modelling for harvesting planning (T.2.4) with the FIS

2. Connection of handheld devices (e.g. RFID UHF readers) with the FIS

3. Connection of cable crane and processor head enhanced HW with the FIS

4. Connection of truck control units with the FIS

5. Connection of planning and editing functionalities already available in the3D modelling for harvesting planning system with the FIS

Page 29: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Task Overview• Currently at M18• Major effort spent on:

• Interface improvements• Alpha 1.0• Alpha 1.1• Alpha 1.2 Early Access Preview

• DB and Webservices improvements• Connection of viewer with DB and Webservices

• First Integration and validation planned after review

Page 30: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Alpha 1.0 • Focused on functions• Features:

• Measurements• Stem readings• Cable crane placement• Forest visualization• 3D moving objects• DSM visualization• WMS support

Page 31: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Alpha 1.1 • New Interface

• Menu bar• Floating panels

• Improved Features:• Pilot specific layers and

functions• Distance and Measurements• Weather forecast• Pickable objects• Terrain analysis• Cable crane placement• Forest visualization

Page 32: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Demo

Page 33: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Alpha 1.2 early access preview

• Features:• Cable crane placement, profiling and animation• Multilanguage support• 3D moving objects along a path

• Focused on refinements and FIS connection

Page 34: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Alpha 1.2 Upcoming

• Features:• New languages• New WMS data for Austrian pilot• Point cloud visualization• Point of interest (sawmills, storage areas, etc.)• Project saving

Page 35: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Conclusions and Future Work

• Web platform in a good shape • Many functionalities not connected with the FIS

• Mobile devices• Cable crane• Truck control units

Next Steps:• First validation• Connect missing components to the FIS• Fill the database with real-time data• Expose all the available data throught the 3D Viewer

Page 36: Mid-term Review Meeting - WP6

Mid-term Review 2/Jul/15

Contact info

Daniele Magliocchetti: [email protected] Andreolli: [email protected] Devigili: [email protected]

Thank you for your attention