Transcript

Managing Power Distribution

Losses in the Zambian

Electricity Industry - Reducing

Losses from 25% to below 14%:

ZESCO’s Experience

Presented by: Patrick Wakalila Simwinga Manager Product Security - Zesco E-mail: [email protected] Cell: +260 977758766

PRESENTATION OUTLINE

1.0 Introduction

2.0 Background to the ZESCO Distribution Loss Problem

3.0 Main drivers to the high Distribution Losses

4.0 Major challenges in Distribution Loss Management

5.0 How did ZESCO manage to reduce its Distribution

Losses?

6.0 Major achievements

7.0 Factors that influenced DL management

8.0 Conclusion

•ZESCO

INTRODUCTION

• Ownership

• Primary Business

• Gen. capacity: 2,216 MW

• Transmission & Distr.

Capacity: 39,000 km &

5,000 MVA

• Customer base: 662,526

•ZESCO

Customer

BACKGROUND TO THE ZESCO

DISTRIBUTION LOSS PROBLEM

23 23.1

17.2

13 14

12.7 13.6 14 14 14 14 14 14 14

2007/08 2008/09 2009/10 2010/2011 2011/12 2012/13 2013/14

Annual Corporate Distribution Loss Performance Trend (%)

Actual % Loss ERB % Target

2007/8 2008/9 2009/10 2010/11 2011/12 2012/13 2013/14 Distribution Loss (%) 23 23.1 17.2 13 14 12.7 13.6 Energy Loss (GWh) 1,094 1,098 854 632 756 718 798

“The only way

to discover the

limits of the

possible

is to go beyond

them into the

impossible ” -Arthur C. Clarke-

1. Technical Losses

2. Non-technical losses

WHAT WERE THE

MAIN DRIVERS OF

HIGH

DISTRIBUTION

LOSSES IN

ZESCO?

Reasons for High Technical Losses: • Long power distribution

lines • Long power distribution

lines

• Overloaded distribution

networks

• Ageing distribution

infrastructure.

• Loose connections on

distribution lines

Planning

New Installation/

Construction

Metering

Meter Reading

Billing

Debt Control

Customer Service

Reasons for High Non-Technical Losses:

Commercial cycle processes

Product Security

High Distribution

losses • Poorly

managed

Commercial

cycle

processes

• Theft

• Removal of voltage links

• Shorting of CT’s

• Mismatching CT ratios

• Tripping meter voltage

MCB’s

• Swapping of phases

• Meter bypass

voltage link removed

Shorted CT’s

voltage MCBs

Most common ways in which Electricity was

being stolen

• Illegal connections

• Illegal reconnections

• Fake meter readings

• Willful burning of

meters

• System frauds

Most common ways in which Electricity

was being stolen Cont’d

Other causes of Distribution

losses

Aged electromechanical metering technology.

Aged electromechanical meters

Defective metering units

Unmetered services

Non-payment of bills

Diesel power stations

Uncaptured customers (CIS – BIS)

Delays in enrolling new customers

What were the major challenges in

Distribution Loss Management?

• Non compliance to system procedures

• High number of Unmetered services and BSP’s

• Meter Reading and Billing challenges

• Low Inspector-to-Customer ratio

• Corruption - energy theft – street level decisions

• Load shedding

• Introduction of prepayment metering system

• Weak legal framework

• Incorrect customer data base

• Impersonators

• Resistance by customers

• Poor reticulation

• Difficulties locating premises

• Socio-economic problems

• Difficulties collecting revenue

Major

challenges in

Distribution

Loss

Management Cont’d

Strategy Formulation

How did ZESCO manage to reduce its Distribution

Losses?

Strategies to reduce Non-technical losses

1: Identified the greatest distribution loss potential areas

2: Improved meter reading and billing

3: Metered all BSP’s & customers

4: Intensified community sensitization campaigns

5: Introduced penalties for offenders & rewards syst.

6: Restructured revenue protection department

7: Documented all revenue protection processes

8: Strictly monitored the commercial cycle processes

9: Introduced the Integrity department

Strategies to reduce Technical Losses

1: Identified weakest areas in the DS (DERP/IAES)

2: Built new substations & upgraded old substations

3: Reinforced overloaded transformers

4: Uprated conductor sizes for HT and MV lines

5: Balanced loads between phases on feeders

6: Eliminated loose connections at jointing points

7: Installed shunt capacitors - power factor

Major Achievements

23 23.1

17.2

13 14

12.7 13.6 14 14 14 14 14 14 14 14 14

Actual % Loss ERB % Target

• Reduction in Distribution

Losses

• Reduction in Revenue

Losses

0

50

100

150

200

250

300

350

Revenue Loss (ZMK' Million)

30%

70%

Customer base composition as at March 2010

UNMETERED

METERED

97%

3%

Customer base composition as at

31 December 2014

Prepaid

Post paid

Unmetered

Major Achievements Cont’d 100% Customers metered - Total customer base of

662,526 as at December 2014

Successfully:

• Reinforced and

upgraded existing

substations and

associated overhead

lines.

• Constructed new

substations and

overhead lines.

Major Achievements Cont’d

Factors that influenced the Successful

Distribution Loss Management

• Clear road map

• Top Management support

• ERB set DL KPI of 14% in 2010

Nelson Mandela

Long Walk to Freedom “I have walked that long road to

freedom. I have tried not to falter; I have made missteps along the way. But I have discovered the

secret that after climbing a great hill, one only finds that there are many more hills to climb. I have taken a moment here to rest, to steal a view of the glorious vista that surrounds me, to look back

on the distance I have come. But I

can rest only for a moment, and I dare not linger, for my long walk is

not yet ended.

CONCLUSION

• This performance was achieved by understanding the

distribution loss problems at hand and then choosing the right

strategies

• Each utility (including consumer’s attitudes and behavior) has

its own unique qualities and only by knowing the system and the

problem can effective solutions be designed and implemented.

• Utilities should consider DL management as a critical function.

No business can

afford the risk!

THANK YOU FOR YOUR ATTENTION

Patrick Wakalila Simwinga

Manager Product Security

ZESCO LIMITED

[email protected]:

Questions ?


Top Related