Welcome to
Audit
KAIZEN®/ Lean Assessment
June 24-27, 2013, Abuja
2KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Agenda
1. Management Priorities2. Highlights3. Some Metrics4. Way Forward5. Potential Benefits6. Q & A
3KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Top Management Direction: OE Imperatives for BE
1. Improve Customer Satisfaction: Room supplies; Food
variety, quality & service
2. Upgrade facility and guest amenities for improved guest
perception of VFM
3. Reduce procurement lead time & delivered item cost
4. Reduce % Operating Cost (Food, Energy, R&M)
5. Improve employee morale and engagement in
continuous improvement
4KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Management Priorities & Challenges
Customer value• Improved customer experience, satisfaction• Reduced Room turnaround time /Smooth Guest check-in• Improved Room Service delivery -quality performance• Timely availability of Room supplies• Timely approval, procurement & product availability• Service delivery for short-notice events
Shareholder/ Management value• Reduced % Food cost• Reduced Repairs & maintenance bill• Lower overall operating cost• Reduced energy bills• Replacement of aged equipment & infrastructure
Employee engagement (issues)• Improved safety & security• Ownership, flexibility, openness to new learning• Availability of buses• Team deployment and efficiency• “One voice” in THTSL
Other issues• Management of traffic flow and parking• Training & support for IT• Reduction in “left behinds”• Real time guest feedback
9KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Highlights: Some overall observations
Strengths:1. Clarity of Top Management OE vision and direction2. Strong customer orientation and focus3. Open, progressive management team4. Excellent property, great potential
Challenges & opportunities:• Lack of “modern” guest amenities (wi-fi, TV, phone ..)• Need for room/ hotel infrastructure upgrade• Employee morale needs urgent address
10KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Some Gemba Observations
11KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Stores
Disorderly storage; difficult to retrieve material
12KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Kitchen and Laundry
Cluttered Workspace; difficult to maintain FIFO (First-in First-out) in cold-store
13KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Operating Cost Break Up
Operating Cost Break-Up
Operating Cost Break-Up as a % of revenue
27%
24%19%
11%
10%
8%
2%
PAYROLL COSTOTHER EXPENSESINSURANCE, MGMT FEE AND OTHERSFOOD COSTREPAIR AND MAINTENANCE COSTENERGY COSTBEVERAGE COST
16%
14%11%
6%
6%
5%
1%
OTHER EXPENSESINSURANCE, MGMT FEE AND OTHERSFOOD COSTREPAIR AND MAINTENANCE COSTENERGY COSTBEVERAGE COST
14KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Cost Break Up - Utilities
Energy Cost Break-Up
32%
63%
6%
FUELELECTRICITYWATER
15KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
F&B Revenue Break Up
Food Revenue Break-Up.
35% - Food cost as a % of revenue
15%
27%58%
1% 0% 3%
BREAKFAST FOOD REVENUELUNCH FOOD REVENUEDINNER FOOD REVENUESUPPER REVENUECOFFEE BREAKS REVENUEOTHER FOOD REVENUE
Beverage Revenue Break-Up.
19.5% - Beverage cost as a % of revenue
14%
11%
26%
50%
BEER REVENUEWINE REVENUELIQUOR REVENUEOTHER BEVERAGE REVENUE
16KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Food and Beverage – Daily Covers
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Total
Dinner
Lunch
High day-to-day variation in Lunch-Dinner covers (42 data points)
Note: This trend needs to be viewed with Actual Lead Time for “short notice” banquets/ events (data recording needs to be initiated)
17KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Customer Complaints
BQT/Events Business Center Laundry Housekeeping Engineering Concierge Room Service0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
38.19%
28.95%
11.01%7.28% 6.57%
4.80% 3.20%
Internet X Luggage Down Safe Witness Internet Cable Chair Delivery Chair Removal 0.00%
5.00%
10.00%
15.00%
20.00%
25.00%
30.00%
35.00%
40.00%
45.00%
50.00%45.12%
21.40%18.60%
11.16%
1.86% 1.86%
Source of customer complaints
BTQ/Events customer complaints
18KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Customer Complaints
Internet Down/Slow Internet Cable0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%71.17%
28.83%
0.00%5.00%
10.00%15.00%20.00%25.00%30.00%35.00%40.00% 35.48% 33.87%
16.13%
9.68%4.84%
Business centre complaints
Laundry complaints
Amenities Room Make Up 0%
10%
20%
30%
40%
50%
60%
70%
80%
Housekeeping complaints
19KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Guest Waiting/ Room Turnaround Time (Room TAT)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1821:36
0:00
2:24
4:48
7:12
9:36
12:00
14:24
Chart Title
18 data points from front office Average 05:12Median 05:02
Min 00:41
Max 11:47Large variation observed
Room TAT for Last guest check-out time Next guest check-in time for a specific room
20KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
21KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Inventory and Consumption Analysis - Food
NGNTOTAL CONSUMPTION (2012) 800,539,217AVE DAILY CONSUMPTION 2,193,258INVENTORY ON HAND (AS ON MAY 31ST 2013) 41,036,811INVENTORY COVER (DAYS) AT 2012 CONSUMPTION RATE 19 Days
No.of ItemsInventory Value
(NGN)
NON-MOVING ITEMS
Items with no consumption in Jan-Dec 2012 55 1024958 2%
SLOW MOVING ITEMS
Items with stock of >365 Days 25 4038938 10%
Items with stock between 100 to 365 Days 41 2358256 6%
Items with stock between 30 to 100 Days 82 16818764 41%
MOVING STOCK
Items with stock between 7 to 30 Days 77 14548844 35%
Items with stock between 2 to 7 Days 18 2147828 5%
Items with stock between 1 to 2 Days 16 197233 0%
Items with no inventory in stock 123 0 0%
Total Items 437 41,134,821
57%
22KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Inventory and Consumption Analysis – General Store
TOTAL CONSUMPTION (MAY 2013) NGN 28,705,807
AVE DAILY DONSUMPTION (MAY 2013) NGN 925,993
INVENTORY ON HAND (AS ON MAY 31st 2013) NGN 130,757,095INVENTORY COVER (DAYS) AT MAY 2013 CONSUMPTION RATE
141 Days
No. of Items
Inventory Value (NGN)
% of Total Inv Value
SLOW-MOVING ITEMS
Items in stock, but no demand in May 2013 232 44,642,826 34%
Items with stock > 365 Days 43 33,628,698 26%
Items with stock between 100 to 365 Days 82 27,878,186 21%
Items with stock between 30 to 100 Days 71 20,408,989 16%
MOVING ITEMS
Items with stock between 7 to 30 Days 33 4,063,518 3%
Items with stock between 2 to 7 Days 8 134,696 0%
No Inventory 31 182 0%
Total 500 130,757,095
23KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Technical Services
24KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
“Ageing Infrastructure”
SURVEY OF AREAS & TECHNICAL INSTALLATIONS: ‘A’ ITEMS ARE THOSE THAT HAVE EXCEEDED THEIR EXPECTED LIFE BY HILTON / INDUSTRY STANDARDS
AREA ‘A’ PRIORITY ITEMS 1. SAFETY EQUIPMENT & SYSTEM 92. SECURITY: CCTV – TV, MUSIC SYSTEM 203. ELECTRICAL SYSTEM & EQUIPMENT4. ROOF TOP 135. EXECUTIVE FLOOR 76. GUEST ROOMS / CORRODOR 97. FRONT OF HOUSE (Health Centre) 18. PUBLIC AREAS 89. F&B OUTLETS 1210. BACK OF HOUSE 511. LANDSCAPE & FAÇADE 9
Source: Study conducted by Chief Engineer
25KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Hotel: Critical Equipment (“Show Stoppers”)
1. GENERATORS2. CHILLERS3. STEAM BOILER / WATER CALORIFIER4. MAIN WATER SUPPLY PUMP5. FIRE PUMPS6. WATER TREATMENT UNIT7. FUEL SUPPLY PUMPS8. BUSES
9. FUEL / GAS STORAGE TANKS10.RELATED PIPING (etc) INSTALLATIONS
26KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
LAUNDRY
1. DRY CLEANING EQUIPMENT2. WASHING MACHINES3. FLAT BED DRYER
Laundry, Kitchen: Critical Equipment
KITCHEN(Data being listed by team)
27KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Buses: Maintenance Expense Jan-May 2013 and Forward Estimate
Note: Excludes 5 new buses
No. BUS NUMBER Exp: Jan-May 2013(NGN)
% of Total Jan-May Exp
STATUS Est Repair Cost(NGN)
1 329 (MBO1721) 3,353,854 19.0
2 458 (MBO 1418) 2,564,260 14.5 . UNDER REPAIR
3 310 (MBO1721) 2,480,284 14.1 . UNDER REPAIR
4
911 (MBO1721) 2,162,660 12.3 . Needs New Engine. Body work
4,800,000
5 922 (MBO1721) 1,883,920 10.7
6 351 (MBO1721) 1,779,715 10.1
7 685 (MBO 1418) 1,075,894 6.1
8 424 (MBO1721) 975,955 5.5
9 459 (MBO 1418) 867,686 4.9 . Needs New Engine 4,200,000
10 352 (MBO1721) 257,250 1.5 . Needs New Engine 4,200,000
11 456 (MBO 1418) 232,455 1.3 . ON SCRAP LIST
12 687 (MBO 1418) Out of Operation . Needs New Engine 4,200,000
TOTAL 17,633,931 17,400,000
57KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Key Initiatives – Phase 1
• Implement 5S in Stores, Kitchen, Laundry, Utilities and Parking
• Streamline flow of Purchasing & Procurement process
• Reduce Room Turn-around Time
• Improve Delivery-Quality of Short-notice Events
• Initiate TPM through Autonomous Maintenance of critical equipment in Technical Service, Kitchen, Laundry
• Reduce Energy Consumption
• Reduce F&B Costs as a percentage of F&B Revenue
• Reduce inventory of slow moving items
58KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Roadmap & Benefits
59KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
TENTATIVE ROADMAP – PHASE 1 (1/3)
START UP ACTIVITIES
INITIATIVES AREA MEANS OUTCOME Month 1
Month 2
Month 3
Month 4
Month 5
Month 6
Month 7
Month 8
Month 9
Month 10
Month 11
Month 12
Month 13
Month 14
Month 15
Month 16
Month 17
Month 18
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
START UP
TOP & SENIOR MANAGEMENT CONCLAVE
THTSL, Abuja Top/ Sr Mgmt Conclave
Alignment and role clarity of key stakeholders in continual improvement journey
1
ESTABLISH OE INFRASTRUCTURE THTSL, Abuja
. Kaizen Coordinator
. Kaizen Promotion Office
ESTABLISH HOTEL STEERING COMMITTEE THTSL, Abuja
Senior Management
+KPO
Top/Sr Mgr Sponsoship established for direction, support & review of improvement activities
KAIZEN BASICS TRAINING THTSL, Abuja
Class Room + On the job
taining
All participants those who will be part of execution team
18 Month engagement, consisting of:1. Start-up Activities2. Transformation Actions (Implementation in Gemba)3. Actions to Sustain improvements
60KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
TENTATIVE ROADMAP – PHASE 1 (2/3)
TRANSFORMATION ACTIONS
INITIATIVES AREA MEANS OUTCOME Month 1
Month 2
Month 3
Month 4
Month 5
Month 6
Month 7
Month 8
Month 9
Month 10
Month 11
Month 12
Month 13
Month 14
Month 15
Month 16
Month 17
Month 18
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
TRANSFORM (Theme)
REDUCE PROCUREMENT LEAD TIME
GENERAL STORES:- Approval process- Order to Delivery process
TFM Tool Box . Current State Map . Future State Map. Specific projects
IMPROVE STORE ITEMS AVAILABILITY
. Food store
. Gen store
. Room supplies
Inventory Management
(PFEP). Reduced stock outs. Controlled nventory
IMPROVE WORKPLACE
. Stores: Gen, Food, Wine. Kitchen, Laundry. Utilities, Car Parking
5S. Reduced Search time. Space freed up. Improved productivity
IMPROVE MACHINE UTILISATION
. Kitchen
. Laundry
. (Utilities)
Autonomous Maintenance (Steps 1 & 2)
. Reduced downtime
. Reduce Maintenance cost
REDUCE ENERGY CONSUMPTION . Hotel LOSS TREE
ANALYSIS . Reduced Energy Cost
REDUCE ROOM TURNAROUND TIME . Housekeeping TFM Toolbox . Reduced Customer Wait
time
REDUCE FOOD COST AS % OF FOOD REV . Food LOSS TREE
ANALYSIS . Reduced Food Wastage
61KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
TENTATIVE ROADMAP – PHASE 1 (3/3)
ACTIONS TO SUSTAIN CONTINUOUS IMPROVEMENT
INITIATIVES AREA MEANS OUTCOME Month 1
Month 2
Month 3
Month 4
Month 5
Month 6
Month 7
Month 8
Month 9
Month 10
Month 11
Month 12
Month 13
Month 14
Month 15
Month 16
Month 17
Month 18
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
SUSTAIN
INITIATE DAILY MANAGEMENT
ALL OPERATING AREAS NGK
. Consistancy of results
. Quick Response to Problems. Daily Accountability
Certified Kaizen Practitioner ALL FUNCTIONS CKP Training . 25 Kaizen Trained Internal
Resources
PHASE I PROGRESS REVIEW KI + Co Kaizen Audit . Phase II Roadmap
KAIZEN PROMOTION KI + Co. Setup KPO. Setup Obeya Room
. Communication
. R&R
62KAIZEN and GEMBAKAIZEN
are the trademarks of KAIZEN Institute
Potential Benefits (First estimates)
No. Particulars Current State Future State/Benefits Annualised Savings (Est)
1 5S - Workplace Organisation Cluttered . Reduced Search Time. Improved Productivity. Space Freed Up
2 Purchase & Procurement process flow improvement
(TBD) . Reduced Lead Time. Improved item availability. Lower Inventory
3 Food & General Stores Inventory Management
31-May-13 Stock ~ NGN 170,000,000
. 35% Reduction in Wrkg Cap
. Freshness: First-in, First-out
. Space released
. Improved productivity
$55,000
4 Autonomous Maintenanace (Steps 1&2)
High Breakdowns, Low Utilisation
. Improved Equipment Availability. 10% cost reduction
$472,000
5 Spares Inventory Management Non-Availability Of Critical Spares
. Quicker Mean Time to Repair (MTTR)
6 Improve Service Response Time Low Customer Sat . Repeat Customers
7 Reduce Energy Costs (% of overall Rev)
5% of Revenue . 5% lower cost $195,000
8 Reduce F&B Costs (% of F&B Rev) Food:35.5% of Food RevBeverage:19.5% of Bev Rev
F:33.3% & B:18.9% $350,000
9 Steering Committee and KPO Sponsorship, Direction and Support10 Obeya Room KPI Management and Control
11 Certified Kaizen Practitioner Internal Expertise for KaizenSavings: ~ US$1,072,000
PROCESS & SYSTEM IMPROVEMENTS
SUSTENANCE & INTERNAL CAPABILITY BUILDING