Page 1: Green Recycling Network Toward a Greener Tomorrow... Today!

Green Recycling Network

Toward a Greener Tomorrow... Today!

Page 2: Green Recycling Network Toward a Greener Tomorrow... Today!

Outline

• A brief introduction

• Markets primer

• Greening office renovations

• Deconstruction case study

• Best practices

• Future

Page 3: Green Recycling Network Toward a Greener Tomorrow... Today!

Deconstruction

The Deconstruction process is cost effective relative to traditional demolition because we avoid costly land disposal by leveraging off the expertise of our affiliated, integrated companies. Thus, no matter the job or the mix of materials, clients get great green results even when a project involves a diverse mix such as salvage, drywall (including painted), unusable furniture, carpet, ceiling tile, and even mixed debris.

Page 4: Green Recycling Network Toward a Greener Tomorrow... Today!

Deconstruction

Deconstruction’s approach allows maximum diversion of materials from landfills disposal as the goal no matter the client or certification being sought. This standardized approach, coupled with market development capabilities focused on finding outlets for problem materials and with highly trained crews capable of consistently beating expected timelines, allows outstanding results every time (typical diversion rates routinely exceed 90%).

Page 5: Green Recycling Network Toward a Greener Tomorrow... Today!

So where does it all go?

Page 6: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: aggregate

Page 7: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: cardboard / paper

Page 8: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: carpet / pad

Page 9: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: ceiling tile

Page 10: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: metal

Page 11: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: plastic

Page 12: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: wallboard

Page 13: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: wood

Page 14: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: salvage (residential)

Page 15: Green Recycling Network Toward a Greener Tomorrow... Today!

Market: salvage (commercial)

Page 16: Green Recycling Network Toward a Greener Tomorrow... Today!

Deconstruction: greening office renovations

• Selective demolition; construction in reverse

• More labor intensive than traditional demolition

• Has highest diversion capability

• Costlier than demolition? NO!

• More time consuming? NO!

• How? PLANNING!

Page 17: Green Recycling Network Toward a Greener Tomorrow... Today!

Case study

Page 18: Green Recycling Network Toward a Greener Tomorrow... Today!

Getting started

Page 19: Green Recycling Network Toward a Greener Tomorrow... Today!

Following the hierarchy

Page 20: Green Recycling Network Toward a Greener Tomorrow... Today!

Cleaning house

Page 21: Green Recycling Network Toward a Greener Tomorrow... Today!

Creating value

Page 22: Green Recycling Network Toward a Greener Tomorrow... Today!

Project results

• Completed 1 week AHEAD of schedule

• Approach saved owner > 50% of budget

• Consignment contract returns $$

• Clean space drastically reduces cost of

remediation and final demolition

• Avoided cost of temporary shoring

• Landfill diversion rate exceeded 75%

Page 23: Green Recycling Network Toward a Greener Tomorrow... Today!

Recent office fit-out results

• Slightly more expensive than typical due to

building constraints and drywall logistics,

however….

• Total diversion = 90.1%

• 6.3 tons salvage (doors, lights, ceiling

tile); 28.6 tons recycled (drywall, carpet,

metal); 3.84 tons went to landfill.

Page 24: Green Recycling Network Toward a Greener Tomorrow... Today!

Best practices

• Specify

• Design for recycling

• Innovate

• Look to the future

Page 25: Green Recycling Network Toward a Greener Tomorrow... Today!

Get what you want: specifyDEMOLITION WASTE MANAGEMENT SPECIFICATIONS1.THIT IS A REQUIREMENT FOR THIS PROJECT THAT THE GENERAL CONTRACTOR RECYCLE, REUSE AND/OR SALVAGE AS MUCH MATERIAL AS POSSIBLE. ALL CONSTRUCTION DEMOLITION OF EXISTING BUILT CONDITIONS SHALL BE RECYCLED AS NECESSARY TO MEET MINIMUM REQUIREMENT OF AT LEAST 50% DEMOLITION DEBRIS.2.THE PATH FOR ALL DEMOLISHED MATERIALS SHOULD BE FIRST TO REUSE, SECOND TO RECYCLE, AND LASTLY TO LANDFILL. THE BID BREAKDOWN SHALL INCLUDE A WASTE HANDLING PLAN THAT IDENTIFIES HOW THE WASTE STREAMS WILL BE SEPARATED AND MANAGED, AND SHALL INCLUDE THE FOLLOWING CATEGORIES:

a. WHAT ITEMS WILL BE SALVAGED VS RECYCLED VS LANDFILLEDb. HOW THEY WILL BE SALVAGED OR RECYCLEDc. WHAT PERCENTAGE OF TOTAL DEMOLITION IS BEING SALVAGED VS RECYCLED VS LANDFILLEDd. WHERE WILL THE SALVAGED AND RECYCLED ITEMS BE DIVERTED TO

3.UNLESS OTHERWISE INDICATED, DECONSTRUCTION WASTE BECOMES THE PROPERTY OF THE CONTRACTOR.4.SCHEDULE OF DECONSTRUCTION ACTIVITIES: INDICATE THE FOLLOWING:

a. DETAILED SEQUENCE OF DECONSTRUCTION AND REMOVAL WORK, WITH STARTING AND ENDING DATES FOR EACH ACTIVITY.

b. INTERRUPTION OF UTILITY SERVICES IF REQUIRED. INDICATE HOW LONG UTILITY SERVICES WILL BE INTERRUPTED.

c. COORDINATION FOR SHUTOFF, CAPPING AND CONTINUATION OF UTILITY SERVICES.d. USE OF ELEVATOR AND/OR STAIRS.e. LOCATIONS OF PROPOSED DUST- AND NOISE-CONTROL TEMPORARY PARTITIONS AND MEANS OF

EGRESS.f. MEANS OF PROTECTION FOR ITEMS TO REMAIN AND ITEMS IN PATH OF MATERIAL REMOVAL FROM

BUILDING.5.DOCUMENT GENERAL CONDITION OF MATERIALS TO BE SALVAGED PRIOR TO REMOVAL. CONDUCT PRE-DECONSTRUCTION CONFERENCE ONSITE. REVIEW METHODS AND PROCEDURES RELATED TO DECONSTRUCTION. DESIGNATE AREA(S) ON SITE FOR SEGREGATED OR COMMINGLED COLLECTION OF RECYCLABLE MATERIALS.6.DOCUMENTATION BY THE DEMOLITION CONTRACTOR IS REQUIRED TO VERIFY ALL REUSED AND/OR RECYCLED MATERIALS. HAUL TICKETS AND RECEIPTS SHALL BE PROVIDED BY THE RECIPIENTS OF SALVAGED AND RECYCLED MATERIALS; RECEIPTS SHALL BE MAINTAINED AND MADE AVAILABLE UPON REQUEST.

Page 26: Green Recycling Network Toward a Greener Tomorrow... Today!

Plan for end of life

• Do markets exist?

• Are outlets local?

• Forecast infrastructure changes

• Examine installation practices

Page 27: Green Recycling Network Toward a Greener Tomorrow... Today!

Think outside of the box

Reusing just Reusing just 1010 doors doors at a 5,000 SF office fit-at a 5,000 SF office fit-out completely pays for out completely pays for the deconstruction the deconstruction expense!expense!

New 10 doors: $10,000New 10 doors: $10,000Salvage 10 doors: Salvage 10 doors: $2,000$2,000Savings: $8,000Savings: $8,000 Vs.Vs.Avg. Demo:Avg. Demo: $7,500 $7,500

Page 28: Green Recycling Network Toward a Greener Tomorrow... Today!

Future: green-to-green facilities

Page 29: Green Recycling Network Toward a Greener Tomorrow... Today!

Huge capacity

Page 30: Green Recycling Network Toward a Greener Tomorrow... Today!

End product capability

Page 31: Green Recycling Network Toward a Greener Tomorrow... Today!

THANK YOU!

Contact Information:

Scott Shepard

O. (703) 880-8428

C. (703) 819-5558 [email protected]

www.GreenRecyclingNetwork.com