Spring Creek SouthHazard Mitigation Grant Program (HMGP) Update

Presentation to Jamaica Bay Task ForceState of the Bay Meeting

Venetia LannonR2 Regional DirectorOctober 29, 2015

Page 2: Fall 2015--DEC Upated on Spring Creek Restoration Project

2

FEMA Hazard Mitigation Grant

Federal Funds: 75% Local Funds: 25%

Goal: Reduce future disaster damages

Page 3: Fall 2015--DEC Upated on Spring Creek Restoration Project

3

Project Area: National Park Service Gateway National Recreation Area Jamaica Bay Unit – Spring Creek

Page 4: Fall 2015--DEC Upated on Spring Creek Restoration Project

4

Project Area: Spring Creek

Page 5: Fall 2015--DEC Upated on Spring Creek Restoration Project

5

Project Goals

• Natural/nature-based features to manage coastal storm risk

• Improve sustainability and resilience of area

• Integrated approach to provide storm protection and ecosystem restoration benefits

• Consistent with NPS management goals

Page 6: Fall 2015--DEC Upated on Spring Creek Restoration Project

6

HMGP Award: Two Phases

Phases• I: Engineering & DesignTotal: $3.3M (Share: $2.5M + $0.8M)

• II: ConstructionTotal: $65.8M (Share: $49.3M + $16.5M)Schedule: 18-month build

Page 7: Fall 2015--DEC Upated on Spring Creek Restoration Project

7

Phase 1 Status Progress

• Agreements between USACE and NYSDEC executed and sampling permits obtained• Scope of Work and contract awarded to Consultant TeamPrinceton HydroParsons BrinckerhoffHDR

• Field work for Baseline Conditions and Concept Design development over the next 2-3 months

Page 8: Fall 2015--DEC Upated on Spring Creek Restoration Project

8

Baseline Data CollectionOctober- November

Wetland Delineation

Bathymetry

Page 9: Fall 2015--DEC Upated on Spring Creek Restoration Project

9

Baseline Data Collection: Geotechnical Investigation - Soil BoringsNovember-December

Delivery of ATV Rig and Water Truck to remain on-site

Work Hours: 7AM-3PM +/- One Pick-up Truck on 165th

Street (at 7AM and 3PM) Duration: 2-3 weeks from

start

Page 10: Fall 2015--DEC Upated on Spring Creek Restoration Project

10

Baseline Data Collection: Contaminant Characterization - Soil SamplingNovember-December

Delivery of Geoprobe and brush hog on-site

Operational hours and traffic same as Geotech

Duration: 5-6 weeks from start

Page 11: Fall 2015--DEC Upated on Spring Creek Restoration Project

11

Baseline Data Collection: October-December

Biological surveys

Aerial surveys

Tide gauges and current meters

Page 12: Fall 2015--DEC Upated on Spring Creek Restoration Project

12

Previous USACE Ecosystem Restoration Conceptual Design

Concept Plan Development

Page 13: Fall 2015--DEC Upated on Spring Creek Restoration Project

13

Conceptual Designs

Page 14: Fall 2015--DEC Upated on Spring Creek Restoration Project

14

Concept Designs Evaluated

Coastal Storm Modeling Cost Estimates

Concept Plan Selected Designs National Environmental Policy Act (NEPA) Environmental Assessment

Page 15: Fall 2015--DEC Upated on Spring Creek Restoration Project

15

Detailed Designs and Cost Estimates and NEPA Compliance

Cost Benefit Analysis Detailed designs Detailed cost estimates Plans and specifications Updated NEPA Environmental Assessment

and Compliance

Page 16: Fall 2015--DEC Upated on Spring Creek Restoration Project

16

Complementary Projects: USACE Rockaway Reformulation Study

Page 17: Fall 2015--DEC Upated on Spring Creek Restoration Project

17

Complementary Projects: Spring Creek North and New York Rising

Spring Creek North (USACE/NYC Parks Restoration Project)

NY RisingPriority Projects

Page 18: Fall 2015--DEC Upated on Spring Creek Restoration Project

18

Community and Partner Input

Adjacent landowner requirements Partner agencies considerations Complementary projects Public access & amenities Community Involvement:

Information sessions Draft Environmental Assessment Review/Comment Potential outreach portals (webpage, library, press, signage, info sheets, email updates)

Page 19: Fall 2015--DEC Upated on Spring Creek Restoration Project

19

FEMA Approval of Phase 1

Advancement to Phase 2 Final plans and specifications for construction Construction

Page 20: Fall 2015--DEC Upated on Spring Creek Restoration Project

20

Page 21: Fall 2015--DEC Upated on Spring Creek Restoration Project

21

Thank You

Lisa BaronProject Manager, USACE [email protected]

Joanna FieldMarine Resources BiologistRegion 2, [email protected]