Transcript
Page 1: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

BMDH PROJECT

WEEKLY UPDATE

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

CLEAN SWEEP IN

NEW STERILISING

DEPARTMENT

Page 2: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

BMDH PROJECT WEEKLY UPDATE

BLACKTOWN HOSPITAL

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BU

NG

AR

RIB

EE

Pedestrians

STAFF & SPECIAL PATIENT PARKING ONLY

P3

P12

HOSPITAL STREET

P2

Blacktown

Hospital

WESTERN SYDNEY UNI

BLACKTOWN ROAD

P11

PA

NO

RA

MA

PA

RA

DE

MEL

ALE

UC

A

EM

BA

RK

BUILDING C CLINICAL SERVICES

BUILDING

BUILDING B

ON SITE

THIS WEEK

Asphalting work on

loop road next

week. Traffic

restrictions are in

place so please

follow directions

from site staff.

Temporary walkway

from Emergency to

Atrium 16 - 19

August - follow

signs.

Emergency drop-off,

parking and entry

now open. Do not

drive over hatched

yellow areas - these

areas are for

emergency vehicles

only.

No parking in drop-

off zones. Please use

new parking area -

check local signs for

time limits and fees.

No staff drop-off or

parking in

Emergency area.

Staff please use

Entry 1 or 2 for

drop-off and

pick-up.

Please take extra

care while we all get

used to the changes.

Building A

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

MAIN VISITOR AND STAFF CAR PARK

Atrium now open

Renal & Admin

Monday 26 August -

Perioperative Services,

Birthing and Newborn Care

move to Building A

Wednesday 28 August -

Maternity and Women’s Health

move to Building A

19 - 20 October Blacktown

Relay for Life. For more info

visit the Cancer Council

website.

Diary

dates

CHECK OUT

THIS WEEK’S

JOBS http://

www.bmdhproject.

health.nsw.gov.au/

Temporary walkway

from Emergency to

Main Entry and

Atrium - follow signs

3 1

Entries 1

P

P

Parking

Staff/Special

parking

2

P

Emergency vehicles only

Asphalting here

Page 3: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Yellow means no go:

The new Emergency entry includes access for ambulances and other emergency vehicles. These are clearly marked with yellow hatching.

Please do not drive through these areas

Page 4: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BLACKTOWN HOSPITAL

SITE ALERT BLACKTOWN AND MOUNT DRUITT HOSPITALS EXPANSION PROJECT

Contractors will be

working on the

colonnade from

Emergency to the

Atrium from Friday 16

to Monday 19 August.

To get to the main entry

from the Emergency

Department, public

access is via the

temporary walkway

past the university.

The path will be clearly

signposted and staff will

be available to direct

you.

Thanks for your

patience while we

complete this work.

Temporary walkway from

Emergency to Atrium

Use temporary pathway from

Emergency to Main Entry

during works Friday 16 August

and Monday 19 August.

Page 5: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BMDH PROJECT WEEKLY UPDATE

BRAG BOOK

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

Fresh

new start

in CSSD Congratulations to our Central

Sterilising Services Department who

have successfully moved into their

new unit on level 4 of Building A.

The expanded service includes more

washers, automated systems and

room to expand in the future.

Front page

The team in the new CSSD: Rajiththa, Robert, Mary, Victoria,

Maristelle, Shadow, Nita and Anjani.

Victoria with one of the new plasma sterilisers.

Page 6: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BMDH PROJECT WEEKLY UPDATE

BRAG BOOK

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

Flashback Friday - above, Sterile Supply Dept in 1966, two years after Blacktown Hospital opened, and now.

Mary at a new pass-through washer.

Rajiththa scans a sterilised

tray ready for theatres.

“Modern” techniques in the Sterile Supply Dept in 1966

Page 7: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BMDH PROJECT WEEKLY UPDATE

BRAG BOOK

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

TOP QUALITY Thanks to everyone at Blacktown and

Mount Druitt who voted in the WSLHD

Quality awards this week.

We’re not biased (much), but our

hospitals have some great entries this

year, including the ODDS Project which

declared war on storeroom clutter and

waste. VOTE HERE

WORKING TOGETHER Women’s and Children’s Health are also getting ready to open their new clinical spaces on level 6, 7 and 8 of

Building A. Across the corridor from the patient units, spacious new activity based working area provides

contemporary space for non-clinical and support activities. Like Periop, they also completed their transition

program this week and are ready to move at the end of August.

The Women’s and Children's Health

team in one of their new studios.

Vote for Graeme! Melissa and Camille at the showcase.

Page 8: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

Blacktown and Mount Druitt Hospitals Expansion Project | BMDH Project | We’re Growing

@BMDHProject Facebook/BMDH Project bmdhproject.health.nsw.gov.au @BMDHProject

BMDH PROJECT WEEKLY UPDATE

BRAG BOOK

Periop gets ready Hot on the heels of our CSSD opening,

Perioperative Services is getting ready to

move into the new building at the end of

August. This week, they completed the last

session in their transition to activity based

working. Meanwhile, training continued in

the operating theatres with staff perfecting

the use of the sophisticated digital camera

systems. Congratulations, team!

Blacktown and Mount Druitt Hospitals Expansion Project | No. 330 | 16 August 2019

Training in theatres.

Periop team in a chat booth

Page 9: CLEAN SWEEP IN NEW STERILISING DEPARTMENT€¦ · THIS WEEK Asphalting work on loop road next week. Traffic restrictions are in place so please follow directions from site staff

For those of you wondering about the new tree you can see on the level 8 terrace when you drive down Blacktown Road, it’s a magnolia grandiflora. Have a great weekend.