4 Storied building construction ProposalSuper Structure

Page 2: 4 storied building superstructure construction proposal

Site Overview

Page 3: 4 storied building superstructure construction proposal

Introduce

Client –Mr. Zakir Hossain Suman

Address -House36,Road-13

Nikunja-1,Khilkhat

Dhaka-1205

Company -TASK J MHM Ltd.

Address -House-5,Road-9,

Sector-7,Uttara,

Dhaka-1230

Page 4: 4 storied building superstructure construction proposal

Site location

Page 5: 4 storied building superstructure construction proposal

Proposed Drawing

Page 6: 4 storied building superstructure construction proposal

Room layout plan

Page 7: 4 storied building superstructure construction proposal

Plan of Floor Beam

Page 8: 4 storied building superstructure construction proposal

Details drawing

Page 9: 4 storied building superstructure construction proposal

Specification of Structure

Page 10: 4 storied building superstructure construction proposal
Page 11: 4 storied building superstructure construction proposal

SUPER STRUCTURE

Superstructure

Related

Items

Column

Beam

Floor Slab

Brick Wall

Superstructure of a building is the portion of the structure above the foundation. It provides the necessary utility of the building with comfort, structural safety ,ventilation etc.

Page 12: 4 storied building superstructure construction proposal

Outlines

Resources Proposed Budget

Management Time Schedule

Financial Ability

Page 13: 4 storied building superstructure construction proposal

•Materials & Products

•Equipment items

• Labor service

Resources

Page 14: 4 storied building superstructure construction proposal

Management

Planning

Project Controlling

Quality Control

Laboratory Section

Mechanical Section

Safety Team

Page 15: 4 storied building superstructure construction proposal

Time Schedule

Mobilization-----------------05.12.2014 – 11.12.2014

R.C.C Casting

Ground Floor

Column-------------------12.12.2014 – 20.12.2014

Roof Beam & Slab------21.12.2014 – 8.01.2015

1st Floor -------------10.01.2015 – 10.02.2015

2nd Floor ------------12.02.2015 – 10.03.2015

3rd Floor ------------12.03.2015 – 10.04.2015

4th Floor ------------12.04.2015 – 10.05.2015

Page 16: 4 storied building superstructure construction proposal

Time-Table

Brick Work

Ground Floor-------01.02.2015 – 10.02.2015.

1st Floor -------------06.03.2015 – 15.03.2015.

2nd Floor ------------03.04.2015 – 12.04.2015.

3rd Floor ------------04.05.2015 – 13.05.2015.

4th Floor ------------03.06.2015 – 12.06.2015

De-Mobilization-------13.06.2015 – 19.06.2015.

Hand Over--------------20.06.2015.

Total Completion the Project – 6 Month 15 Days.

Page 17: 4 storied building superstructure construction proposal

Test of Materials

Page 18: 4 storied building superstructure construction proposal

Sand Test

Test FM Analysis

Page 19: 4 storied building superstructure construction proposal

Reinforcement

All reinforcement steel to be used shall be the steel(ISO-9002 certified) 60-grade deformed bars.

Page 20: 4 storied building superstructure construction proposal

Brick

Page 21: 4 storied building superstructure construction proposal

Aggregates Test

Page 22: 4 storied building superstructure construction proposal

Slump of Concrete

Instrument Test

Page 23: 4 storied building superstructure construction proposal

Concrete test

Page 24: 4 storied building superstructure construction proposal

Site Safety Issue

Page 25: 4 storied building superstructure construction proposal
Page 26: 4 storied building superstructure construction proposal

Safety In Site

Page 27: 4 storied building superstructure construction proposal
Page 28: 4 storied building superstructure construction proposal

Shuttering Work

Page 29: 4 storied building superstructure construction proposal
Page 30: 4 storied building superstructure construction proposal

Proposed Budget

Page 31: 4 storied building superstructure construction proposal

Financial Ability

Page 32: 4 storied building superstructure construction proposal

General Terms & Conditions

PAYMENTS- All payments of earnest money, installments, additional works and other

charges shall be made by bank draft or A/C payee cheque in favor of TASKJMHM for which respective receipts will be issued. Details payment schedule will submit at the agreement.

PANALTY-If the payment is delayed beyond 30 days TASKJMHM shall

have the right to cancel the allotment.

REFUND- If ,for any reason beyond the control of TASKJMHM Ltd the implementation of the project is abandoned, company will refund to the Earnest Money and all installments deposited within 30 days from the announcement made to this effect.

LIABILITY- Our company are fully liable for construction procedure overall the projects. We are also responsible for all materials we are supplied.

MONITORING AND EVALUATION- Monitoring and Evaluation is an important part of the project proposal. We are responsible for overall project first to up to handover to the Client.

Page 33: 4 storied building superstructure construction proposal

Conclusion and Recommendation

Our all projects implemented by following Bangladesh national building code(BNBC) for safer living of city dwellers.

Our the experienced team are tasked in ensuring that the project is completed on time and within budget.

Construction of 4 storied residential building of super structure part will be cost approximately 6.894 million.

The proposed project is capable to bring a good atmosphere to the residents.