Transcript
Page 1: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 1

Controls for Linac Parallel Session 2/6/07

John Carwardine

ANL

Page 2: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 2

Controls from RDR to EDR…

• Develop RDR models into engineering design.• Validate/prototype key concepts in RDR models, eg

– Network architecture.– Front-end model, technical system interfaces.– Synchronous 5Hz feedback infrastructure.– Standards, standardization, QA.– Diagnostic Interlock Layer.

• Perform targeted R&D where it is needed, eg– RF field regulation (phase & amplitude).– High availability implementation.– Fault detection and recovery.

• Controls & LLRF support for test facilities.

Page 3: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 3

Linac specific issues

• Data archiving and collection model.• Distribution of RF phase reference• Feedback infrastructure.

Page 4: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 4

Physical model from RDR

Some items of note:• Physical model identifies some

technology (eg ATCA), but is not technology dependent.

• No software framework selected, but we assume derivation from an existing framework.

• Assessments indicate that future ‘commodity computing’ will meet performance requirements.

• Some design concepts require validation during EDR phase.

Page 5: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 5

Unknowns…

• Level of effort available from each region– Controls RDR related effort has been small, and largely

focused in Americas region.– Looking to expand participation. Must find overlap

between needs of ILC EDR efforts and interests of collaborating institutions.

– Actual work package content could change depending on the participation.

• Americas planning for FY08 identified a need for 10+ FTEs for controls on EDR and related R&D– Assumes similar participation from other regions.– Does not adequately cover all anticipated work

packages, eg for RDR validation & protypying RDR design concepts.

Page 6: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 6

Controls work packages “To Do”• We have a list of top-level objectives, and we have some work

packages identified.• Have not collected input from all regions and/or all interested

parties.• Does not take credit for related activities (XFEL, ITER, etc).• How best to apportion work packages…? So far, we have not

substantially apportioned specific work to specific labs/regions/groups.

• How to incorporate needs and interests of potential collaborators…?

Page 7: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 7

Integration with test facilities

• WPs to provide controls & LLRF for NML, XFEL, etc will presumably come from facility project managers.

• Using beam-based test facilities, but they also provide a necessary test bed for controls R&D.

Page 8: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 8

WP model…

• Topic: High Availability Control Systems

• Top-down objectives and initiatives, eg– Investigate, evaluate, and demonstrate candidate high

availability design techniques.– Investigate ATCA as a candidate platform for instrumentation

electronics.

• Bottom-up work packages can come from many sources:– Controls or ILC leadership– Lab proposals– Collaborative contributions– Overlapping interests with other activities.

Page 9: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 9

Examples of bottom-up WPs• Controls leadership

– MOU between SLAC and University of Illinois (UIUC) for investigating ATCA analog & digital performance, cabling, shelf manager, etc.

• Proposal driven– Proposal from LBNL to develop prototype RF phase distribution

system.– Proposal for x-ray based alignment system.– Implement bpm electronics in ATCA crate.– Port EPICS to ATCA, implement fail-over of IOC from machine to

machine.

• Coincidence of needs with other activities– XFEL LLRF developments.– Precision timing and RF phase distribution for APS picosecond x-ray

source.– ITER remote access / remote control needs.

Page 10: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 10

High Availability• HA is a requirement for all the technical systems.• Need to investigate techniques, implications, and cost-benefit for

meeting reliability requirements.

• Control system hardware & software are both impacted.

• Methodology component:– Design techniques, robust design.– Quality Control / extensive testing.– Standardization.

• Engineering component:– Reliably detect and then recover from faults.– Introspection, diagnostic tools,…– Redundancy, hot spares, remote power on/off,…

Page 11: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 11

HA technical working group…?

• HA issues apply to multiple technical systems.• We should attempt to solve the issues collectively.• Technical groups need to address HA in their R&D.• An HA Technical Working Group would serve to

guide and collect HA related activities.

Page 12: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 12

WP example: HA control systems• Investigate high availability design approaches, implications, and cost-

benefit for the ILC control system.

• Example work package items:– Develop & evaluate controls failure modes and machine impact. Determine

priorities for meeting overall availability.– Explore techniques such as virtual machine migration (Xen), clustering

(heartbeat), redundant I/O controllers, etc. using [EPICS, DOOCS, Tango, …] on ATCA.

– Evaluate and prototype second-tier HA techniques, eg: automated diagnosis, configuration management, coding standards.

– Build vertical demonstration of all tiers of control system with HA techniques applied. Perform fault injection to test and evaluate.

– Evaluate and prototype “Shelf-manager’ functionality in control system infrastructure for technical system fault management.

Page 13: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 13

WP example: ATCA evaluation• Investigate suitability of ATCA as a high availability compliant

electronics platform for ILC control system.

• Example work package items:– Prototype a precision instrumentation digitizer for beam position

monitors. Evaluate analog & digital performance.– Prototype electronics functions to the AMC mezzanine card, and

integrate with the IPMC diagnostic module. Write software drivers.

– Evaluate cabling options for ATCA and AMC cards– Port [EPICS, DOOCS, Tango,…] to the ATCA platform, integrate

and evaluate “Shelf Manager” functionality.

Page 14: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 14

WP example: diagnostic processor• The diagnostic processor (DP) is conceived as the key element

in the Diagnostic Interlock Layer (DIL).

• Work package example items:– Continue development of DP hardware for Marx and 4+1

supplies. Develop generic family of DP hardware (including chip-level) suitable for integration into various technical systems.

– Develop on-board software to integrate DP with IPMI-based relay rack monitoring. Client software will be developed/acquired to provide a uniform management interface to all relay racks based on current standards.

Page 15: 1 Global Design Effort Beijing GDE Meeting, February 2007 Controls for Linac Parallel Session 2/6/07 John Carwardine ANL

Beijing GDE Meeting, February 2007 Global Design Effort 15

WP example: RF phase distribution• Perform essential R&D on distribution techniques for the 1300

MHz timing distribution system.

• Example work package items:– Investigate & evaluate strategies for phase stabilizing long

fiber links modulated at 1.3 GHz.– Demonstrate critical time of arrival stabilization at a dummy

Interaction Point using NML beam test facility.– Investigate feasibility of using a beam-derived reference for

locking a local phase reference. – Prototype a redundant phase reference receiver with decision

logic to auto-switch upon detected failure.


Top Related