LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number : 2.1
Type Of Work : Excavation for The Drainage Ditch and Waterways
Payment unit : M3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) jam 0.0748 7,150.00 534.82
2. Mandor (L03) jam 0.0374 9,500.00 355.302. Mandor (L03) jam 0.0374 9,500.00 355.30
890.12JUMLAH HARGA TENAGA 890.12
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
- JUMLAH HARGA BAHAN
C. PERALATAN
1. Excavator (E10) jam 0.0222 320,462.53 7,114.271. Excavator (E10) jam 0.0222 320,462.53 7,114.27
2. Dump Truck (E08) jam 0.0374 241,830.76 9,044.47
3. Alat Bantu Ls 1.0000 100.00 100.00
16,258.74
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 17,148.86
E. KEUNTUNGAN 5 % x D 857.44
JUMLAH HARGA PERALATAN
E. KEUNTUNGAN 5 % x D 857.44
F. HARGA SATUAN PEKERJAAN ( D + E ) 18,006.30
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri PT. Perapen Prima Mandiri
Ir. MawardiDirektur UtamaDirektur Utama
-
Type Of Work : Excavation for The Drainage Ditch and Waterways 0
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Excavation for The Drainage Ditch and Waterways 0
Payment unit : M3
Pay Item Number : 2.1 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Faktor pengembangan bahan Fk 1.20 -5 Faktor pengembangan bahan Fk 1.20 -
II. URUTAN KERJA
1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil2 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
3 Dump Truck membuang material hasil galian keluar3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 0.10 Km
4 Sekelompok pekerja akan merapikan hasil galian
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Tidak ada bahan yang diperlukanTidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.800 M3Kapasitas Bucket V 0.800 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.75 -Faktor Efisiensi alat Fa 0.75 -
Waktu siklus Ts1 menit
- Menggali / memuat T1 0.500 menit- Menggali / memuat T1 0.500 menit
- Lain-lain T2 0.100 menit
Ts1 0.600 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 45.00 M3 / jam
Ts1 x FhTs1 x Fh
Koefisien Alat / M3 = 1 : Q1 - 0.0222 Jam
2.b. DUMP TRUCK (E08)
Kapasitas bak V 15.00 M3
Faktor efisiensi alat Fa 0.75 -Faktor efisiensi alat Fa 0.75 -
Kecepatan rata-rata bermuatan v1 40.00 Km/Jam
Kecepatan rata-rata kosong v2 60.00 Km/JamKecepatan rata-rata kosong v2 60.00 Km/Jam
Waktu siklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 0.15 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 0.10 menit- Waktu tempuh kosong = (L : v2) x 60 T2 0.10 menit
- Muat = (V : Q1) x 60 T3 20.00 menit
- Lain-lain T4 0.80 menit- Lain-lain T4 0.80 menit
Ts2 21.05 menit
Berlanjut ke halaman berikutBerlanjut ke halaman berikut
-
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Excavation for The Drainage Ditch and Waterways 0
Payment unit : M3Payment unit : M3
Pay Item Number : 2.1 URAIAN ANALISA HARGA SATUAN
LanjutanLanjutan
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
Kapasitas Produksi / Jam = V x Fa x 60 Q2 26.72 M3 / Jam Kapasitas Produksi / Jam = V x Fa x 60 Q2 26.72 M3 / Jam
Fk x Ts2
Koefisien Alat / M3 = 1 : Q2 - 0.0374 Jam
2.c. ALAT BANTU
Diperlukan alat-alat bantu kecil Lump SumpDiperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Keranjang + Sapu- Keranjang + Sapu
3. TENAGA
Produksi menentukan : Dump Truck Q2 26.72 M3/JamProduksi menentukan : Dump Truck Q2 26.72 M3/Jam
Produksi Galian / hari = Tk x Q2 Qt 187.05 M3
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0748 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0374 Jam- Mandor = (Tk x M) : Qt (L03) 0.0374 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN5. ANALISA HARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :Didapat Harga Satuan Pekerjaan :
Rp. 18,006.30 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKAN Memakai 6. WAKTU PELAKSANAAN YANG DIPERLUKAN Memakai
Masa Pelaksanaan : 206.00 Hari 2 Dump Truck
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 76,892.00 M3
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number : 2.2
Type Of Work : Mortared Stonework
Payment unit : M3
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) jam 1.9277 7,150.00 13,783.06
2. Tukang Batu (L02) jam 0.3213 11,500.00 3,694.952. Tukang Batu (L02) jam 0.3213 11,500.00 3,694.95
3. Mandor (L03) jam 0.3213 9,500.00 3,052.35
20,530.36JUMLAH HARGA TENAGA 20,530.36
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
1. Batu (M02) M3 1.0800 96,400.00 104,112.00
2. Semen (PC) (M12) Kg 161.0000 1,320.00 212,520.002. Semen (PC) (M12) Kg 161.0000 1,320.00 212,520.00
3. Pasir (M01) M3 0.4829 66,400.00 32,064.56
348,696.56JUMLAH HARGA BAHAN
C. PERALATAN
1. Conc. Mixer Jam 0.3213 98,123.55 31,527.101. Conc. Mixer Jam 0.3213 98,123.55 31,527.10
2. Alat Bantu Ls 1.0000 1,000.00 1,000.00
32,527.10
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 401,754.01
E. KEUNTUNGAN 5.0 % x D 20,087.70
JUMLAH HARGA PERALATAN
E. KEUNTUNGAN 5.0 % x D 20,087.70
F. HARGA SATUAN PEKERJAAN ( D + E ) 421,841.71
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri
Ir. MawardiIr. Mawardi
Direktur Utama
-
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Mortared Stonework
Payment unit : M3
Pay Item Number : 2.2 URAIAN ANALISA HARGA SATUANPay Item Number : 2.2 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSI
1 Menggunakan Tenaga Kerja (cara manual)1 Menggunakan Tenaga Kerja (cara manual)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaanseluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 25.00 KM
5 Jam kerja efektif per-hari Tk 7.00 jam5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 20 %
: - Volume Pasir Ps 80 %
7 Perbandingan Batu & Mortar :7 Perbandingan Batu & Mortar :
- Batu Bt 60 %
- Mortar (campuran semen & pasir) Mr 40 %- Mortar (campuran semen & pasir) Mr 40 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.67 ton/M3- Pasir D4 1.67 ton/M3
- Semen Portland D5 1.44 ton/M3
9 Faktor kehilangan bahan : - Batu Fh1 1.20 -
- Pasir / Semen Fh2 1.05 -- Pasir / Semen Fh2 1.05 -
II. URUTAN KERJAII. URUTAN KERJA
1 Semen, pasir dan air dicampur dan diaduk menjadi
mortar dengan menggunakan alat bantu
2 Batu dibersihkan dan dibasahi seluruh permukaannya2 Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
3 Penyelesaian dan perapihan setelah pemasangan
III. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x Fh1 (M02) 1.0800 M3
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x Fh2 (M12) 0.1120 M31.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x Fh2 (M12) 0.1120 M3
x {D5 x (1000)} (M12) 161.0000 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x Fh2 (M01) 0.4829 M31.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x Fh2 (M01) 0.4829 M3
2. ALAT
2.a. CONCRETE MIXER (E06)2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 3.00 menit
- Mengaduk T2 2.50 menit- Mengaduk T2 2.50 menit
- Menuang T3 1.50 menit
- Tunggu, dll. T4 1.00 menit- Tunggu, dll. T4 1.00 menit
Ts 8.00 menit
Kap. Prod. / jam = V x Fa x 60 Q1 3.113 M3
1000 x Ts
Koefisien Alat / M3 = 1 : Q1 (E06) 0.3213 jam
Berlanjut ke halaman berikut
-
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Mortared Stonework
Payment unit : M3
Pay Item Number : 2.2 URAIAN ANALISA HARGA SATUANPay Item Number : 2.2 URAIAN ANALISA HARGA SATUAN
Lanjutan
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
2.b. ALAT BANTU2.b. ALAT BANTU
Diperlukan :
- Sekop = 2 buah
- Pacul = 2 buah- Pacul = 2 buah
- Sendok Semen = 2 buah
- Ember Cor = 6 buah- Ember Cor = 6 buah
- Gerobak Dorong = 2 buah
3. TENAGA
Produksi Pasangan Batu dengan Mortar dalam 1 hari Qt 21.79 M3Produksi Pasangan Batu dengan Mortar dalam 1 hari Qt 21.79 M3
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Batu Tb 1.00 orang- Tukang Batu Tb 1.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.3213 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.3213 jam- Tukang = (Tk x Tb) : Qt (L02) 0.3213 jam
- Pekerja = (Tk x P) : Qt (L01) 1.9277 jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :Didapat Harga Satuan Pekerjaan :
Rp. 421,841.71 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKAN6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 12.00 Hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 241.00 M3
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number : 2.3. 3
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 80 cm) 75 - 85 cm
Payment unit : M1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) Jam 16.3333 7,150.00 116,783.10
2. Tukang (L02) Jam 4.6667 11,500.00 53,667.052. Tukang (L02) Jam 4.6667 11,500.00 53,667.05
3. Mandor (L03) Jam 2.3333 9,500.00 22,166.35
192,616.50
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
1. Beton K-300 M3 0.2062 1,191,672.38 245,722.84
2. Baja Tulangan Kg 22.6784 12,397.50 281,155.462. Baja Tulangan Kg 22.6784 12,397.50 281,155.46
3. Urugan Porus M3 0.2205 100,000.00 22,050.00
4. Mat. Pilihan M3 1.5523 25,000.00 38,807.504. Mat. Pilihan M3 1.5523 25,000.00 38,807.50
587,735.81
C. PERALATAN
JUMLAH HARGA BAHAN
C. PERALATAN
1. Tamper Jam 0.2484 38,223.09 9,494.62
2. Flat Bed Truck Jam 0.4861 164,585.50 80,005.012. Flat Bed Truck Jam 0.4861 164,585.50 80,005.01
3. Alat Bantu Ls 1.0000 1,000.00 1,000.00
90,499.63JUMLAH HARGA PERALATAN 90,499.63
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 870,851.93
E. KEUNTUNGAN 5.0 % x D 43,542.60
JUMLAH HARGA PERALATAN
E. KEUNTUNGAN 5.0 % x D 43,542.60
F. HARGA SATUAN PEKERJAAN ( D + E ) 914,394.53
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuranNote : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri PT. Perapen Prima Mandiri
Ir. Mawardi
Direktur UtamaDirektur Utama
-
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 80 cm) 75 - 85 cm
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 80 cm) 75 - 85 cm
Payment unit : M1
Pay Item Number : 2.3. 3 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSII. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 0.80 m
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 25.00 Km
5 Jam kerja efektif per-hari Tk 7.00 Jam5 Jam kerja efektif per-hari Tk 7.00 Jam
6 Tebal gorong-gorong tg 7.50 Cm
II. URUTAN KERJA
1 Gorong-gorong dicetak di Base Camp
2 Flat Bed Truck mengangkut gorong-gorong jadi2 Flat Bed Truck mengangkut gorong-gorong jadi
ke lapangan
3 Dasar gorong-gorong digali sesuai kebutuhan dan ma-3 Dasar gorong-gorong digali sesuai kebutuhan dan ma-
terial backfill dipadatkan dengan Tamper
4 Tebal lapis porus pada dasar gorong-gorong pipa tp 0.12 M Sand bedding
5 Material pilihan untuk penimbunan kembali (padat)5 Material pilihan untuk penimbunan kembali (padat)
6 Sekelompok pekerja akan melaksanakan pekerjaan
dengan cara manual dengan menggunakan alat bantudengan cara manual dengan menggunakan alat bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Untuk mendapatkan 1 M' gorong-gorong diperlukanUntuk mendapatkan 1 M' gorong-gorong diperlukan
- Beton K-300 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1 (EI-714) 0.2062 M3
- Baja Tulangan (asumsi 100kg/m3) (M39) 22.6784 Kg
- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05} (EI-241) 0.2205 M3- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05} (EI-241) 0.2205 M3
- Material Pilihan = ((2*tg/100+d+0.3)*(0.4+2*tg/100+d+0.4) (Vp) 1.5523 M3
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2. ALAT
2.a. TAMPER (E25)
Kecepatan V 0.50 Km / JamKecepatan V 0.50 Km / Jam
Efisiensi alat Fa 0.75 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 6.00 lintasanBanyak lintasan n 6.00 lintasan
Tebal lapis hamparan tp 0.25 M
Kap. Prod. / Jam = v x 1000 x F ax tp x Lb x 60 Q1 6.2500 M3 / Jam
n n
Koefisien Alat / m' = 1 : Q1 x Vp (E25) 0.2484 jamKoefisien Alat / m' = 1 : Q1 x Vp (E25) 0.2484 jam
2.b. Flat Bed Truck (E08)
Kapasitas bak sekali muat V 4.00 BuahKapasitas bak sekali muat V 4.00 Buah
Faktor efisiensi alat Fa 0.75
Kecepatanrata-rata bermuatan v1 40.00
Kecepatan rata-rata kosong v2 60.00
Waktu siklus : TsWaktu siklus : Ts
- Waktu tempuh in si = (L : v1 ) x 60 T1 37.50 menit
- Waktutempuh kosong = (L : v2) x 60 T2 25.00 menit- Waktutempuh kosong = (L : v2) x 60 T2 25.00 menit
- Muat, bongkar dan lain-lain T3 25.00 menit
Ts 87.50 menit
Berlanjut ke halaman berikutBerlanjut ke halaman berikut
-
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 80 cm) 75 - 85 cm
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 80 cm) 75 - 85 cm
Payment unit : M1
Pay Item Number : 2.3. 3 URAIAN ANALISA HARGA SATUAN
LanjutanLanjutan
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
Kapasitas Produksi / Jam = V x Fa x 60 Q2 2.0571 M' / Jam Kapasitas Produksi / Jam = V x Fa x 60 Q2 2.0571 M' / Jam
Ts
Koefisien Alat / m' = 1 : Q2 (E08) 0.4861 jam
2.c. ALAT BANTU
Diperlukan alat-alat bantu kecil Lump SumpDiperlukan alat-alat bantu kecil Lump Sump
- Sekop = 3 buah
- Pacul = 3 buah
- Alat-alat kecil lain- Alat-alat kecil lain
3. TENAGA 3. TENAGA
Produksi Gorong-gorong / hari Qt 3.00 M'
Kebutuhan tenaga :
- Pekerja P 7.00 orang- Pekerja P 7.00 orang
- Tukang T 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M' :
- Pekerja = (Tk x P) : Qt (L01) 16.3333 jam- Pekerja = (Tk x P) : Qt (L01) 16.3333 jam
- Tukang = (Tk x T) : Qt (L02) 4.6667 jam
- Mandor = (Tk x M) : Qt (L03) 2.3333 jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN5. ANALISA HARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :
Rp. 914,394.53 / M1
6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 2.00 hariMasa Pelaksanaan : 2.00 hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 4.00 M1
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number : 2.3 (4)
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 100 cm) 95 - 105 cm
Payment unit : M1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja Jam 4.6667 7,150.00 33,366.67
2. Tukang Jam 2.3333 11,500.00 26,833.332. Tukang Jam 2.3333 11,500.00 26,833.33
3. Mandor Jam 1.1667 9,500.00 11,083.33
71,283.33JUMLAH HARGA TENAGA 71,283.33
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
1. Beton K-300 M3 0.2897 1,191,672.38 345,227.49
2. Baja Tulangan Kg 31.8707 12,397.50 395,117.002. Baja Tulangan Kg 31.8707 12,397.50 395,117.00
3. Urugan Porus M3 0.3103 100,000.00 31,030.00
4. Mat. Pilihan M3 1.9114 25,000.00 47,785.004. Mat. Pilihan M3 1.9114 25,000.00 47,785.00
819,159.49JUMLAH HARGA BAHAN 819,159.49
C. PERALATAN
JUMLAH HARGA BAHAN
C. PERALATAN
1. Tamper Jam 0.3058 38,223.09 11,688.62
2. Flat Bed Truck Jam 0.3426 164,585.50 56,386.992. Flat Bed Truck Jam 0.3426 164,585.50 56,386.99
3. Alat Bantu Ls 1.0000 1,000.00 1,000.00
69,075.61
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 959,518.44
JUMLAH HARGA PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 959,518.44
E. KEUNTUNGAN 5.0 % x D 47,975.92
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,007,494.36F. HARGA SATUAN PEKERJAAN ( D + E ) 1,007,494.36
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri
Ir. Mawardi
Direktur Utama
-
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 100 cm) 95 - 105 cm
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 100 cm) 95 - 105 cm
Payment unit : M1
Pay Item Number : 2.3 (4) URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Diameter bagian dalam gorong-gorong d 1.00 m
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 25.00 Km
5 Jam kerja efektif per-hari Tk 7.00 Jam5 Jam kerja efektif per-hari Tk 7.00 Jam
6 Tebal gorong-gorong tg 8.50 Cm
II. URUTAN KERJA
1 Gorong-gorong dicetak di Base Camp
2 Flat Bed Truck mengangkut gorong-gorong jadi2 Flat Bed Truck mengangkut gorong-gorong jadi
ke lapangan
3 Dasar gorong-gorong digali sesuai kebutuhan dan ma-3 Dasar gorong-gorong digali sesuai kebutuhan dan ma-
terial backfill dipadatkan dengan Tamper
4 Tebal lapis porus pada dasar gorong-gorong pipa tp 0.15 M Sand bedding
5 Material pilihan untuk penimbunan kembali (padat)5 Material pilihan untuk penimbunan kembali (padat)
6 Sekelompok pekerja akan melaksanakan pekerjaan
dengan cara manual dengan menggunakan alat bantudengan cara manual dengan menggunakan alat bantu
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Untuk mendapatkan 1 M' gorong-gorong diperlukanUntuk mendapatkan 1 M' gorong-gorong diperlukan
- Beton K-300 = (22/7*((2*tg/100+d)/2)^2)-(22/7*(d/2)^2))*1 (EI-714) 0.2897 M3
- Baja Tulangan (asumsi 100kg/m3) (M39) 31.8707 Kg
- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05} (EI-241) 0.3103 M3- Timbunan Porus = {(tp*(0.4+2*tg/100+d+0.4)*1)*1.05} (EI-241) 0.3103 M3
- Material Pilihan = ((2*tg/100+d+0.3)*(0.4+2*tg/100+d+0.4) vp 1.9114 M3
-(22/7*(0.5*(2*tg/100+d))^2))*1*1.05 -(22/7*(0.5*(2*tg/100+d))^2))*1*1.05
2. ALAT
2.a. TAMPER (E25)
Kecepatan V 0.50 Km / JamKecepatan V 0.50 Km / Jam
Efisiensi alat Fa 0.75 -
Lebar pemadatan Lb 0.40 M
Banyak lintasan n 6.00 lintasan
Tebal lapis hamparan tp 0.25 M
Kap. Prod. / Jam = v x 1000 x Fa x Lb x 60 Q1 6.2500 M3 / Jam
n x tp n x tp
Koefisien Alat / m' = 1 : Q1 x Vp (E25) 0.3058 jamKoefisien Alat / m' = 1 : Q1 x Vp (E25) 0.3058 jam
2.b. Flat Bed Truck (E08)
Kapasitas bak sekali muat V 6.00 Buah/M'Kapasitas bak sekali muat V 6.00 Buah/M'
Faktor efisiensi alat Fa 0.75
Kecepatanrata-rata bermuatan v1 40.00Kecepatanrata-rata bermuatan v1 40.00
Kecepatan rata-rata kosong v2 60.00
Waktu siklus : Ts
- Waktu tempuh in si = (L : v1 ) x 60 T1 37.50 menit- Waktu tempuh in si = (L : v1 ) x 60 T1 37.50 menit
- Waktutempuh kosong = (L : v2) x 60 T2 25.00 menit
- Muat, bongkar dan lain-lain T3 30.00 menit- Muat, bongkar dan lain-lain T3 30.00 menit
Ts 92.50 menit
Berlanjut ke halaman berikut
-
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Reinforced Concrete Pipe Culverts Inside Diameter (nominal 100 cm) 95 - 105 cm 0
Payment unit : M1
Pay Item Number : 2.3 (4)Pay Item Number : 2.3 (4)
Lanjutan
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
Kapasitas Produksi / Jam = V x Fa x 60 Q2 2.9189 M' / Jam
Ts Ts
Koefisien Alat / m' = 1 : Q2 (E08) 0.3426 jam
2.c. ALAT BANTU2.c. ALAT BANTU
Diperlukan alat-alat bantu kecil Lump Sump
- Sekop = 3 buah
- Pacul = 3 buah- Pacul = 3 buah
- Alat-alat kecil lain
3. TENAGA
Produksi Gorong-gorong / hari Qt 6.00 M'
Kebutuhan tenaga :Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Tukang T 2.00 orang- Tukang T 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M' :Koefisien tenaga / M' :
- Pekerja = (Tk x P) : Qt (L01) 4.6667 jam
- Tukang = (Tk x T) : Qt (L02) 2.3333 jam
- Mandor = (Tk x M) : Qt (L03) 1.1667 jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :Didapat Harga Satuan Pekerjaan :
Rp. 1,007,494.36 / M'
6. WAKTU PELAKSANAAN YANG DIPERLUKAN6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 159.00 hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 950.00 M'
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAHLocation : KABUPATEN ACEH TENGAH
Pay Item Number : 2.3.9.1
Type Of Work : U Ditch Type DS 1
Payment unit : M1
PERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A. TENAGA
1. Pekerja (L01) jam 2.0000 7,150.00 14,300.00
2. Mandor (L03) jam 0.5000 9,500.00 4,750.002. Mandor (L03) jam 0.5000 9,500.00 4,750.00
19,050.00JUMLAH HARGA TENAGA 19,050.00
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
1. Beton K 250 M3 0.3240 1,008,486.44 326,749.61
2. Baja Tulangan Polos Kg 25.6830 12,397.50 318,404.992. Baja Tulangan Polos Kg 25.6830 12,397.50 318,404.99
645,154.60 JUMLAH HARGA BAHAN
C. PERALATAN
1. Trailer (E10) jam 0.1000 224,844.25 22,484.431. Trailer (E10) jam 0.1000 224,844.25 22,484.43
2. Crane jam 0.1111 302,220.25 33,576.67
3. Alat Bantu Ls 1.0000 100.00 100.00
56,161.09
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) 720,365.69
E. KEUNTUNGAN 5 % x D 36,018.28
JUMLAH HARGA PERALATAN
E. KEUNTUNGAN 5 % x D 36,018.28
F. HARGA SATUAN PEKERJAAN ( D + E ) 756,383.98
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri
Ir. MawardiIr. Mawardi
Direktur Utama
-
Type Of Work : U Ditch Type DS 1 0
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : U Ditch Type DS 1 0
Payment unit : M1
Pay Item Number : 2.3.9.1 URAIAN ANALISA HARGA SATUAN
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Jarak rata-rata Base Camp ke lokasi pekerjaan L 25.00 Km5 Jarak rata-rata Base Camp ke lokasi pekerjaan L 25.00 Km
II. URUTAN KERJA
1 Sekelompok Pekerja Merapikan dinding saluran yang digali
2 beton praetak Type DS 1 dicetak di base camp 2 beton praetak Type DS 1 dicetak di base camp
3 beton pracetak diangkut kelokasi pekerjaan dengan menggunakan trailer
4 beton pracetak dipasang dan disusun dengan menggunakan crane4 beton pracetak dipasang dan disusun dengan menggunakan crane
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
1.a Beton K 250 M3 0.3240 M31.a Beton K 250 M3 0.3240 M3
1.b Baja Tulangan Polos Kg 25.6830 Kg
2. ALAT
2.a TRAILER (E29)
Kapasitas bak sekali muat V 15.000 M1Kapasitas bak sekali muat V 15.000 M1
Faktor efisiensi alat Fa 0.75
Kecepatanrata-rata bermuatan v1 40.00 Km/JamKecepatanrata-rata bermuatan v1 40.00 Km/Jam
Kecepatan rata-rata kosong v2 60.00 Km/Jam
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 37.50 menit- Waktu tempuh isi = (L : v1 ) x 60 T1 37.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 25.00 menit
- Lain-lain (bongkar dan muat) T3 5.00 menit
Ts1 67.50 menit
Kapasitas Produksi / Jam = V x Fa x 60 Q1 10.00 M1Kapasitas Produksi / Jam = V x Fa x 60 Q1 10.00 M1
Ts1
Koefisien Alat / m3 = 1 : Q1 (E29) 0.1000 JamKoefisien Alat / m3 = 1 : Q1 (E29) 0.1000 Jam
2.b CRANE (E07)2.b CRANE (E07)
Kapasitas V2 1.00 M1
Faktor Efisiensi alat Fa 0.75 -
Waktu siklusWaktu siklus
- Waktu memuat dan membongkar T1 4.00 menit
- dan lain-lain ( termasuk mengatur, menggeser dan memasang) T2 1.00 menit- dan lain-lain ( termasuk mengatur, menggeser dan memasang) T2 1.00 menit
Ts2 5.00 menit
Kap. Prod. / jam = V x Fa x 60 Q2 9.00 M1Kap. Prod. / jam = V x Fa x 60 Q2 9.00 M1
Ts2
Koefisien Alat / m = 1 : Q2 (E07) 0.1111 jamKoefisien Alat / m = 1 : Q2 (E07) 0.1111 jam
Berlanjut ke halaman berikutBerlanjut ke halaman berikut
-
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : U Ditch Type DS 1 0
Payment unit : M1Payment unit : M1
Pay Item Number : 2.3.9.1 URAIAN ANALISA HARGA SATUAN
LanjutanLanjutan
No. U R A I A N KODE KOEF. SATUAN KETERANGAN
2.c. ALAT BANTU
Diperlukan alat-alat bantu kecil Lump SumpDiperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Cangkul, dan alat bantu lainnya- Cangkul, dan alat bantu lainnya
3. TENAGA
Produksi menentukan : Crane Q2 2.00 M1/JamProduksi menentukan : Crane Q2 2.00 M1/Jam
Produksi Galian / hari = Tk x Q2 Qt 14.00 M1
Kebutuhan tenaga :Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.0000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.5000 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN5. ANALISA HARGA SATUAN PEKERJAAN
Didapat Harga Satuan Pekerjaan :Didapat Harga Satuan Pekerjaan :
Rp. 756,383.98 / M1
6. WAKTU PELAKSANAAN YANG DIPERLUKAN Memakai 6. WAKTU PELAKSANAAN YANG DIPERLUKAN Memakai
Masa Pelaksanaan : 12.00 Hari 2 Dump Truck
7. VOLUME PEKERJAAN YANG DIPERLUKAN7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 312.00 M1
-
LAMPIRAN 2 PENAWARAN
ANALISA HARGA SATUAN MATA PEMBAYARAN
Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)Project : ACEH RECONSTRUCTION PROJECT, ROAD SUB - PROJECT (JICA LOAN IP - 545)
Contract Package : No. 3 (Three)
Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)Package Name : KABAYAKAN - SP. KRAFT (STA. 3 + 850 - STA. 56 + 032)
Location : KABUPATEN ACEH TENGAH
Pay Item Number : SS 2.4.3.b
Type Of Work : Perforated or porous Pipe for subsurface Drainage WorkType Of Work : Perforated or porous Pipe for subsurface Drainage Work
Payment unit : M1
PERKIRAAN HARGA JUMLAHPERKIRAAN HARGA JUMLAH
NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)(Rp.) (Rp.)
A. TENAGAA. TENAGA
1. Pekerja Jam 2.8000 7,150.00 20,020.00
2. Tukang Jam 0.7000 11,500.00 8,050.00
3. Mandor Jam 0.7000 9,500.00 6,650.00
34,720.00
B. BAHAN
JUMLAH HARGA TENAGA
B. BAHAN
1. Pipa Porous M' 1.0500 85,000.00 89,250.001. Pipa Porous M' 1.0500 85,000.00 89,250.00
2. Semen (PC) Kg 0.0900 1,320.00 118.80
3 Mortar M3 0.0003 1,000,000.00 300.00
4 Pasir M3 0.0002 66,400.00 13.284 Pasir M3 0.0002 66,400.00 13.28
5 Filter Stripe, dll Ls 1.0000 15,000.00 15,000.00
104,682.08JUMLAH HARGA BAHAN
C. PERALATAN
1. Alat Bantu Ls 1.0000 1,000.00 1,000.001. Alat Bantu Ls 1.0000 1,000.00 1,000.00
1,000.00
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 140,402.08
JUMLAH HARGA PERALATAN
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 140,402.08
E. OVERHEAD & PROFIT 5.0 % x D 7,020.10
F. HARGA SATUAN PEKERJAAN ( D + E ) 147,422.18F. HARGA SATUAN PEKERJAAN ( D + E ) 147,422.18
Note : 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.berat untuk bahan-bahan.
2 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang3 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN yang
dibayar dari kontrak) dan biaya-biaya lainnya.
Banda Aceh, 20 Juni 2012
PT. Perapen Prima Mandiri PT. Perapen Prima Mandiri
Ir. MawardiIr. Mawardi
Direktur Utama
-
Type Of Work : Perforated or porous Pipe for subsurface Drainage Work
ANALISA TEKNIS SATUAN PEKERJAAN
Type Of Work : Perforated or porous Pipe for subsurface Drainage Work
Payment unit : M1
Pay Item Number : SS 2.4.3.b
No. U R A I A N KODE KOEF. SATUAN KETERANGANNo. U R A I A N KODE KOEF. SATUAN KETERANGAN
I. ASUMSII. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan terpengaruh oleh aliran air tanah
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Diameter dalam pipa d 0.10 M5 Diameter dalam pipa d 0.10 M
6 Material penyaring terdiri dari material porus
7 Penyangga sambungan pipa dengan mortar7 Penyangga sambungan pipa dengan mortar
II. URUTAN KERJA
1 Semua material diterima di lokasi pekerjaan1 Semua material diterima di lokasi pekerjaan
2 Pekerjaan dilakukan secara manual dengan
menggunakan alat bantu kecil
3 Pekerjaan galian dibayar tersendiri.
III. PEMAKAIAN BAHAN, ALAT DAN TENAGAIII. PEMAKAIAN BAHAN, ALAT DAN TENAGA
1. BAHAN
Diperlukan material :
- Pipa Porous (M25) 1.0500 M'- Pipa Porous (M25) 1.0500 M'
- Mortar (penyangga sambungan pipa) = 2 x (0.05x0.05x0.05) Mr 0.0003 M3
- Semen = 20% x Mr x Bj Mortar 1.8 T/m3 (M12) 0.0900 Kg- Semen = 20% x Mr x Bj Mortar 1.8 T/m3 (M12) 0.0900 Kg
- Pasir = 80% x Mr (M01) 0.0002 M3
- Filter stripe dan lain2 (pada sambungan) - 1.0000 Ls
2. ALAT 2. ALAT
2.b. ALAT BANTU Lump Sump
Diperlukan alat-alat bantu kecilDiperlukan alat-alat bantu kecil
- Sekop = 2 buah
- Pacul = 2 buah
- Alat-alat kecil lain- Alat-alat kecil lain
3. TENAGA
Produksi yang dapat diselesaikan / hari Qt 10.00 M'Produksi yang dapat diselesaikan / hari Qt 10.00 M'
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Tukang T 1.00 orang- Tukang T 1.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M1 :
- Pekerja = (Tk x P) : Qt (L01) 2.8000 Jam
- Tukang = (Tk x T) : Qt (L02) 0.7000 Jam
- Mandor = (Tk x M) : Qt (L03) 0.7000 Jam- Mandor = (Tk x M) : Qt (L03) 0.7000 Jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.Lihat lampiran.
5. ANALISA HARGA SATUAN PEKERJAAN
Lihat perhitungan dalam FORMULIR STANDAR UNTUKLihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :Didapat Harga Satuan Pekerjaan :
Rp. 147,422.00 / M'Rp. 147,422.00 / M'
6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : 19.00 HariMasa Pelaksanaan : 19.00 Hari
7. VOLUME PEKERJAAN YANG DIPERLUKAN
Volume pekerjaan : 183.00 M'Volume pekerjaan : 183.00 M'