Page 1: Diversion head work

UNIT 3

DIVERSION AND IMPOUNDING STRUCTURES

Page 2: Diversion head work

HEADWORKA hydraulic structure which supplies water to the off taking canal is called a head work.

Functions• A headwork raises the water level in the river• It regulates the intake of water into the canal• It also controls the entry of silt into the canal• A headwork can also store water for small

periods of time.• Reduces fluctuations in the level of supply in

river

Page 3: Diversion head work

TYPES OF HEADWORK• Storage headwork• Diversion headwork

Storage headwork• Stores water - the period of excess

supplies - releases when demand.• It comprises the construction of a dam on

the river.

Page 4: Diversion head work

Diversion Head Work• Weir or Barrage – across perennial river – to

raise the water level – water is diverted to canal

Objectives• Raises the water level on the U/S side• Regulates the supply of water into canals• Controls the entry of silt into the canal• Helps in controlling fluctuations in the river

Page 5: Diversion head work

Site Selection for a diversion head work• River section @ site – narrow and well defined• River – inerodable, non- submersible, well

defined – cost of the work is minimum• Canals – taking off – large commandable area

– economical• Arrangement for diverting river during

construction• Weir aligned along right angle to direction of

flow

Page 6: Diversion head work

• It should not submerge costly land• Good foundation should be available at the site• Materials – should be available near site• Site – easily accessible by rail and road• Overall cost - minimum

Page 7: Diversion head work

Component parts of Diversion Headwork• Weir or Barrage• Divide Wall• Fish Ladder• Undersluices• Silt Excluder• Canal head regulator• River training works (Marginal Bund)

Page 8: Diversion head work
Page 9: Diversion head work

Weir

• A weir is a raised concrete crest wall constructed across the river. It may be provided with small shutters (gates) on its top.

• In the case of weir, most of the raising of water level or ponding is done by the solid weir wall and little by the shutters.

Advantages:

The initial cost of weirs is usually low.

Page 10: Diversion head work

Disadvantages:• There is a large afflux during floods which

causes large submergence.• Because the crest is at high level, there is great

silting problem• The raising and lowering of shutters on the crest

is not convenient. Moreover, it requires considerable time and labor.

• The weir lacks an effective control on the river during floods.

Page 11: Diversion head work
Page 12: Diversion head work
Page 13: Diversion head work

Barrage• A barrage has a low crest wall with high gates. As the

height of the crest above the river bed is low most of the ponding is done by gates.

• During the floods the gates are opened so afflux is very small.

Advantages• The barrage has a good control on the river during

floods. The outflow can be easily regulated by gates.• The afflux during floods is small and, therefore, the

submerged area is less.• There is a good control over silt entry into the canal.

Page 14: Diversion head work

• There is a good control over flow conditions, crosscurrents on the upstream of the barrage.

• There are better facilities for inspection and repair of various structures.

• A roadway can be conveniently provided over the structure at a little additional cost.

Disadvantage: • The initial cost of the barrage is quite high.

Page 15: Diversion head work
Page 16: Diversion head work

BARRAGE

Page 17: Diversion head work
Page 18: Diversion head work

Divide Wall• A divide wall is a wall constructed parallel to

the direction of flow of river to separate the weir section and the undersluices section to avoid cross flows.

• If there are undersluices at both the sides, there are two divide walls.

Page 19: Diversion head work

Divide Wall

Page 20: Diversion head work

Fish Ladder• A fish ladder is a passage provided adjacent to

the divide wall on the weir side for the fish to travel from the upstream to the downstream and vice versa.

• Fish migrate upstream or downstream of the river in search of food or to reach their sprawling places. In a fish ladder the head is gradually dissipated so as to provide smooth flow at sufficiently low velocity.

• Suitable baffles are provided in the fish passage to reduce the flow velocity.

Page 21: Diversion head work
Page 22: Diversion head work

Undersluices

Undersluice sections are provided adjacent to the canal head regulators.

The undersluices should be able to pass fair weather flow for which the crest shutters on the weir need not be dropped.

The crest level of the undersluices is generally kept at the average bed level of the river.

Page 23: Diversion head work
Page 24: Diversion head work

Silt Excluder• A silt excluder is a structure in the undersluices

pocket to pass the silt laden water to the downstream so that only clear water enters into the canal through head regulator.

• The bottom layer of water which are highly charged with silt pass down the silt excluder an escape through the undersluices.

Page 25: Diversion head work

Canal Head Regulator• A canal head regulator is provided at the head

of the canal offtaking from the diversion headworks.

• It regulates the supply of water into the canal, controls the entry silt into the canal, and prevents the entry of river floods into canal.

Page 26: Diversion head work
Page 27: Diversion head work

Guide Banks and Marginal Bunds• Guide banks are provided on either side of the

diversion headwork for a smooth approach and to prevent the river from outflanking.

• They protect the land and property which is likely to be submerged during ponding of water in floods.

Page 28: Diversion head work

Marginal Bund

Page 29: Diversion head work