designing smart grid for utilities - · pdf filedesigning smart grid ... planning for smart...

29
Confidential Designing SMART GRID for Utilities The BSES Experience Arun Kanchan, Member of the board, BSES Delhi 1

Upload: dinhminh

Post on 06-Mar-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Confidential

Designing SMART GRID for Utilities

The BSES Experience

Arun Kanchan, Member of the board, BSES Delhi

1

Confidential

Reliance Energy: Leader in Private Sector Reliance Energy: Leader in Private Sector Power DistributionPower Distribution

� Serving over 8 million customers in Mumbai, Delhi a nd Orissa.

� Powering 2 out of 3 homes in Mumbai & Delhi and 3 o ut of 4 homes in Orissa.

� Distributing nearly 7,500 MW – the largest in India .

� Employs more than 30,000 personnel.

� Mix of Industrial, commercial, residential, urban a nd rural consumers.

Largest customer base for a Private Sector Utility in India.

Mumbai Delhi Orissa

2

Confidential

Privatized Delhi Discoms – A Synopsis

SN Particulars Unit BSES Delhi

1 Area sq. km 950

2 Total Registered customers millions 2.66

3 Peak Demand MW 3100

4 Consumption per year MU 16000

5 Regular Employees Nos. 8000

6 Customer density Cons/ sq. km 2800

7 Revenue Million US $ 1800

NDPLNDPL

BRPLBRPLBYPLBYPL REL acquired 51% stake in July

2002 in two out of three Discoms

Business Inheritance Marred by Multiple Maladies

3

Confidential

Topics Covered

1. Understanding the needs

4. Designing the smart grid for

utilities

3. BSES Philosophy

2. Understanding the Challenges

5. The road map adopted by BSES

4

Confidential

Main Challenges for Power Utilities

Efficiency

Additional BusinessEnvironment

Investment Control

Energy Mix

Demand Side Management

Smart Grid to address all these challenges and more

Supply Security

Volatile Prices

5

Confidential

Key Challenges for BSES, Delhi

ABT Tariff

CollectionHigh Theft

loss levels 62% to 17%

Consumer Trust

Major Load Growth2800 MW to 4760 MW

Break-down

Tomorrow will bring new challenges

Power Availability –75% to 98.7%

Material Theft

6

Confidential

Present TechnologiesPresent TechnologiesPresent TechnologiesPresent Technologiesat Discomat Discomat Discomat Discom

The present scenario

OMS

AMR

SCADA

LT AB Cable

Advanced Meters

GISSAP

7

Does thepresent technology

meet consumer expectations

and concerns ?

Confidential

In Brief…The customers expectations and DISCOM concerns revolve

around cost, reliability & quality of supply and services to consumers.

Cost of Supply

Customer Services

Reliability of Supply

Quality of Supply

Let the data flowwith electricity

Involve

Consumers

The basic purpose of Smart Grid8

Confidential

SMART GRID – BSES Perspective

Key Criteria……….

SMART GRID should be able to resolve concerns and Challenges which could be either generic or utility specific.

Kick Start ………..

1. Based on the priorities, identify the challenges to be addressed.

2. Document the results expected from Smart Grid Technologies.

3. Evaluate the investment and commercial viability (ROI).

4. Upgradability – Maximum use of existing resources and future flexibility

9

Confidential

Break-downResponse

• Failure informationFailure informationFailure informationFailure information

• Alternate feedAlternate feedAlternate feedAlternate feed

• Fault isolationFault isolationFault isolationFault isolation

Cost of Energy

Key Challenges !!!

21

Backbone of the Smart Grid is the IT system

•High Loss

•ABT Tariff

•Home automation

10

Confidential

IT: Present StatusIT: Present StatusERP

SystemSAP R/3

SCADAGEMS

GIS

BILLINGSYSTEMS- LEGACY

(ORACLE)

OMSDMS

CISDOOR STEPPRE-PAID

NetworkPlanning(CYME)

Energy Audit

AMR

Project Planning

Eve

ntan

d

Me a

s ur a

nds

Ene

rgy

Logs

Loss

Da t

a

Topo

log y

Info

rma t

ion

Meter DataBilling Settlement

Not

ifica

tion

/

Ord

ers

Cus

tom

er

Re s

pon s

e

EventInformation

………….. indicates loosely integrated / manual interface.

EHV, HV, LT

11

Confidential

SCADA - DMSSupervisory Control and Data Acquisition-Distribution Transformer Management

GEMS Grid Energy Management System

AMI Advanced Metering Infrastructure

GIS Geographical Information System

AMR Automatic Meter Reading

SAP SAP- R/3

Building Blocks of the Smart GridBuilding Blocks of the Smart Grid

SCADA Centre

AMR

12

Confidential

Challenge 1 – Break -Down ResponseReduced power off : 20.1% to 1.2% - now target 0.2% .

Local fault – big source of break down – Overloading .

Load Growth – 100% in 5 years .

Revenue loss –Sale of 120 MU/yr .

Saving if ‘Power Off’ becomes 0.2% - 5 M$/ year .

Desired – immediate information, alternate feed, fault

isolation, network health

Solution:

• DT Automation System• Pole Metering

13

Confidential

� Network capacity vs. loading pattern.

� Concept of Predictive Maintenance desirable.

� Regular & prompt DT meter maintenance.

� Reliable energy accounting.

� GIS integration of FPIs to identify faulty section on GIS map.

� Response time for HT fault isolation to be brought down to approx 1 hour with the

help of FPIs.

� Auto Decision – alternate feed and fault isolation.

� Event notification via SMS and email to concerned person.

� Reduction in T & D loses via Reactive Power Management.

Sub Station Monitoring System - Advantages

14

Confidential

Pole Metering

• Principle:-– Energy Meter installed on pole to measure the

flow of energy and to monitor the electrical parameters. It also acts as a ‘check energy meter’ for consumers.

• Salient Features:a) Thread through technology.b) Special anomaly recording features viz. high/low

voltage, over and under load conditions etc.c) Improves revenue protection.d) Easy to install & download.e) Up-gradable for remote connect/disconnect

feature.

Same features as that in AMI forInteroperability. 15

Confidential

Challenge 2 – High Loss LT Transformer

Company loss reduced from 62% to 19% - Target 12% .

Loss is never uniform - Few transformers (DT) have very high loss.

Typical energy on a DT – 1.2MU/ year.

Typical Consumers on DT – 200 nos.

A loss reduction by 30% on a DT - 36000 US$/year .

For an expense of 300 US$/consumer,ROI is 20 months.

Solution:

Advanced MeteringInfrastructure (AMI)

16

Confidential

Loss Reduction - AMIEnergy Gap Analysis

� Energy Gap calculated between two nodes. Nodes can be defined as:

– Transformer to Feeder– Feeder to Pole– Pole to Consumer

� Alarm raised in case of high energy gap.

� Adjustable polling frequency – energy integration time.

� Helps to pin-point the area of loss.

Loss Reduction

• Theft detection by Online Energy Audit/ Gap Analysis.

• Pre-paid and post paid options.

• Facility to remote connect/disconnect.• Meter not accessible – separate

consumer display.

• Identification of improper load.

• To find technical loss.• Identification and reporting of

abnormal/ tampered conditions.

Interactive display will also help consumer

17

Confidential

Challenge 3 – ABT Tariff - Consumer Engagement

Generation – own 20% only.

Spot rate varies with availability.

Availability is defined –deviation in frequency.

Time when Spot rate is morethan highest Billing Rate ---- 30%.

When “ Non availability” is more,then Rates are high. Additionally need to

pay penalty.

Solution:

• Green Club – Demand Response• Consumer Interactive Display

18

Confidential

Other Options …… .

To reduce the peak deficit:� Energy Conservation� Demand Shift

� Additional Generation� Consumer Load Control

� Energy Source shift

BRPL Green Club – A DSM measure

19

Confidential

Demand Response - BRPL Green Club

20 KW load reduction duringpeak time by 10000 consumers

is equivalent to a virtual power plant of 200 MW

meant only for peak duration.

Load Reduction of consumerswho voluntarily join the Green Club as

part of the DSM initiatives:Remote Connection/ Disconnection

of non essential load(declared by consumer)during power shortage

Kick Start ……… ..

1. Motivation and awareness – to inform about Non Ava ilability.

2. Incentives & regulatory mechanism – To install re mote control connect and disconnect devices.

3. Legislation: Auto disconnection of few typical lo ads.

20

Confidential

Green Club can be extended toMan-less Site Load Management

• Pumping – Utility controlled pump switching.

• DG Sets – Operation of DG when power purchase cost is high.

• Battery Charging – Discontinuation of charging during peak load period.

And for many more activities

21

Confidential

Consumer can log onto Power MeterGmail ID and password is required

Google Power Meter allows access to electricity usage fromany Google Power meter enabled device and to learn and

understand more about how to use electricity throughout the day

Customer Interactive Display – Google Power Meter

22

Confidential

Customer Interactive Display - Advantages

� Analyze:To give better insight of the energy bill and consumer awareness about energy conservation.

� Save:Reduce energy bills and carbon footprint by making smart decisions about energy use.

� Share:Strike up a little friendly competition to see how energy consumption compares to that of friends and neighbors.

Additionally• Local Intelligence• Interactive Graph

23

Confidential

IT Strategic Road Map : Planning for Smart Grid

The overall strategic intent for operations in IT, is to:-�� Build world class communication and infrastructure.�� Implement internationally established packaged software.�� Enhance computer literacy and ensure complete usage.�� Improve/Integrate legacy systems for immediate gains.

24

Confidential

IT: Our Forward PathIT: Our Forward Path -- Planning for Smart GridPlanning for Smart Grid

ERPSystemSAP R/3

SCADAGEMS

GIS

BILLING SYSTEMS: ISU-SAP

OMSDMS

CIS

NetworkPlanning(CYME)

EnergyAudit

AMR and AMI

Project Planning

Eve

ntan

d

Mea

sura

nds

Ene

rgy

Logs

Loss

Dat

a

Topo

logy

Info

r mat

ion

Customer / DataNetwork

Meter DataBilling Settlement

Cus

tom

e rH

isto

ry

B illi

ngD

ata

Not

ifica

tion

/

Ord

ers

Out

age

Trig

gers

Cu s

tom

er

Res

pons

e

EventInformation

Complete integration of all major functions.

25

Confidential

Smart Network – Phase One Components

Distribution Transformer

Pole Consumer

AMI Technology

DT Automation &Pole Metering

Green Club &Consumer InteractiveDisplay

� Concentrator� Meter� Communication

� Pole Meter� Communication

� Consumer Meter� Communication� Load On-Off� KWh Display

� AMR� I/O� LT ACB automation� Sensors

� Pole Meter� Communication

� Interactive Display� Communication� Load On-Off� Frequency based Off

Component design should be flexible, modular and scalable.

26

Confidential

Future Components – Smart Grid� Small Renewable Energy Generators.� Volatile prices – Demand Response – Consumer level intelligent units.� Grid Interactive Generators.� Network Health Sensors.� LT Fault Path Indicators.� LT Fault Isolators.� Interactive Consumer Display.� Home Area Network.� Additional Business – Non tariff income.

And More.........................

While finalizing Phase one components, it is planne d to ensure seamless integration of future components also.

27

Confidential

Miles to go before…..� BSES is ready with its phaseone plan.

� BSES already has all the ingredients of smart grid in place.

� Govt. of India has approved the grant to BSES for AMI project .

� BSES believes SMART GRIDis more suitable for Indian utilities due to the faster ROI.

28

Confidential

Contact detail

Email: [email protected]

[email protected]

Thank You

29