designing a non-revenue water reduction strategy for ... · designing a non-revenue water reduction...
TRANSCRIPT
Designing a Non-Revenue Water
Reduction Strategy for Efficiency,
Resilience and Sustainablity
1Water Ideas 2016: Bologna, 20-21 October 2016
Malcolm Farley
Malcolm Farley Associates
Water Ideas 2016: Bologna, 20-21 October 2016 2
There are smart and capable engineers and
technicians in water utilities across the world
So, it follows that a NRW reduction strategy can
be introduced into any water utility network
But what causes a strategy to fail?
How can a strategy be sustained?
Some examples of failings and corrections!
Water Ideas 2016: Bologna, 20-21 October 2016 3
Smart technologies are not always the
answer because……….
In some utilities, the things that sustain smart or
advanced technologies are often lacking:
- A well developed infrastructure
- Funding for spare parts
- Awareness and focus on NRW
- An understanding of zoning and the DMA concept
- A ‘powerful’ NRW Department with experience and
know-how
Back to Basics
Water Ideas 2016: Bologna, 20-21 October 2016 4
Step 1Ask some questions about the volume of NRW:• How much is being lost? • is it from leaks in the pipe network?• Is it loss of income to the water company?
Step 2Examine the characteristics of the network and the company• What are the company’s operating policies and practices?• Identify the root causes of NRW and what can be done to reduce it
Step 3 Develop a relevant and appropriate NRW reduction strategy tailored to that particular water company
Ghana Water 2006-2011
Aqua Vitens Rand: Operators
Electromagnetic
system input meters
Pilot DMAs in Kumasi with
telemetered EM meters
Pilot DMAs in Accra with
mechanical meters
Water Ideas 2016: Bologna, 20-21 October 2016 5
In 2011 the NRW programme
was discontinued – why?
� No NRW Department
� Lack of capacity and know-how
� Lack of funding (and motivation) to maintain the NRW
programme
� No Active Leakage Control (no vehicle or equipment)
� Contractual issues – production meters never
commissioned
� Lack of spare parts
� Service contracts not renewed
Water Ideas 2016: Bologna, 20-21 October 2016 6
Ghana Water NRW Reduction
Programme 2013-2014
� 12 month programme to support Ghana Water with their
NRW Reduction Programme
� Funded by UK Government
� Managed by WSUP (Water and Sanitation for the Urban
Poor)
� Some limited funding for expert consultancy support and
equipment purchase
� Two pilot DMAs in Accra and Kumasi
� What can we do differently to sustain the programme in
future?
Water Ideas 2016: Bologna, 20-21 October 2016 7
So where did we start?Accra:
3 DMAs selected for pilot area
DMA chambers in place and
- well designed by AVRL
Some meters working
- others not!
Water Ideas 2016: Bologna, 20-21 October 2016 8
New ‘low cost’ equipment purchased
Water Ideas 2016: Bologna, 20-21 October 2016 9
New mechanical meters/replacement heads and sensorsBasic data loggers to measure night flows
DMAs
New ‘low cost’ equipment purchased
Water Ideas 2016: Bologna, 20-21 October 2016 10
Small meters for customer night use survey- Accuracy tests- Replacement programme- Unregistered and illegal use
New ‘low cost’ equipment purchased
Water Ideas 2016: Bologna, 20-21 October 2016 11
Portable clamp-on ultrasonic meter- Measure production volumes- Check flow rates of installed meters
New ‘low cost’ equipment purchased
Water Ideas 2016: Bologna, 20-21 October 2016 12
Leak detection• Basic listening sticks (20 euros)• Advanced leak detection equipment not
yet appropriate• Improving network infrastructure:
pipes, valves and contact points
Basic data logger and sensor
Water Ideas 2016: Bologna, 20-21 October 2016 14
Night flow measurement and data analysiscombined with customer night use survey
Kumasi – Telemetered DMAs
(high cost, high maintenance)
• Good chamber design• EM meters all working• Battery failure• Data logger problems• Service contract lapsed• Telemetry discontinued
Water Ideas 2016: Bologna, 20-21 October 2016 15
New equipment purchased
Water Ideas 2016: Bologna, 20-21 October 2016 16
Kumasi:- Audit of all meter sites by company engineers- List of spare parts needed - Lithium batteries purchased- Spares for meter data loggers and communication units- Reinstated service contract (first year only – written undertaking by Ghana Water to renew for next 4 years)
Results and Successes!� NRW Manager appointed to head new NRW Department
� Highly motivated and knowledgeable
� Working pilot DMAs in Accra and Kumasi
� Night flow data being collected from Accra DMAs
� Customer night use surveys ongoing –unregistered and illegal
connections
� Meter tests leading change out policy
� Leak detection training for all regions completed
� Network being strengthened by re-furbishing valves and
installing contact points
� Portable ultrasonic meter used continuously for production
measurement (and water balance)
� More abandoned DMAs being ‘discovered’ and refurbished
Water Ideas 2016: Bologna, 20-21 October 2016 17
Water Ideas 2016: Bologna, 20-21 October 2016 19
Training workshops, awareness seminars and field
training are essential for motivation, capacity building
and skills development
Water Ideas 2016: Bologna, 20-21 October 2016 20
Review of company operating practices
and DMAs
GIS and Hydraulic Analysis departments
(cooperation)?
- Is there a calibrated model?
- How are DMAs designed?
- Are DMAs installed?
- Are there meter chambers (condition)?
- Are the meters still in place (fixed or temporary)?
- Are boundary valves in place (boundary closed)?
- Are there pressure monitoring points installed?
Egypt Real Losses Reduction Strategy: 2014-2016
Leak Detection
Water Ideas 2016: Bologna, 20-21 October 2016 22
All ACs practise leak detection surveys and have:
• A leak detection department with staff that are motivated to
find leaks
• A range of leak detection equipment
• Portable ultrasonic flow meters to measure DMA flows
• But staff only gather total flow data and make no use of night
flow data as a guide to ‘leaky’ areas
DMA Management
Water Ideas 2016: Bologna, 20-21 October 2016 23
Not all ACs have DMAs installed. There is a
wide range of DMA development:
• Some ACs have DMAs that are in the design stage only, needing
network model support
• Some DMAs are fully functional with working fixed flow meters and
closed boundary valves (and SMS data transfer)
• Some DMAs have meter chambers with meters removed
• Some chambers are buried and/or flooded
• Very few pressure monitoring points
Previous DMA Projects
Water Ideas 2016: Bologna, 20-21 October 2016 24
Several ACs have had DMA pilots implemented in earlier programmes
Most of these are no longer being used or are defunct – why?
- Portable flow meters have been taken for other uses
- Boundary valves have been opened
- No funding for spare parts
- Night flow monitoring and analysis not fully understood, only
total flows measured
- DMAs remain at the design and implementation stage
So how can this programme be more successful in implementing
and operating DMAs?
Sustaining DMAs
Water Ideas 2016: Bologna, 20-21 October 2016 25
Sound design using validated data and a calibrated
network model
Education and awareness training so that all staff
understand the DMA concept
Permanent fixed flow meters (A DMA without a meter is
not a DMA!)
Boundaries that are ‘tight’ and permanent
Regular operation and maintenance
Success in using night flow data to prioritise areas of
leakage
Water Ideas 2016: Bologna, 20-21 October 2016 26
• Assess the awareness, motivation and capability of the staff
• Review the network characteristics and the utility’s operating
practices
• Get as much data and information from the network as
possible
• Work with the information we have within these parameters
and accept the limitations of the network
• Do as much as we can to gradually improve the data
• ‘Drip feed’ technology and systems at the right time
• Use ‘appropriate’ technology until the utility is ready for
‘smart’ technology
Lessons for Future Projects?
Roland’s* 12 Key Mistakes
Water Ideas 2016: Bologna, 20-21 October 2016 27
• No Water Balance
• Wrong PIs
• Unrealistic targets
• Poor strategy (ask the four questions!)
• Underestimation of budget needed
• No monitoring in place to measure success
• Insufficient time for preparatory phase
• Failure to ensure institutional changes (eg NRW
department)
• Lack of full-time, dedicated NRW staff
• Lack of experience (all levels)
• No staff incentives
• Reluctance to outsource NRW management
*Roland Liemberger: Water Loss 2014, Vienna