delayed coker advanced process control at …©2010 petroliam nasional berhad (petronas), page 3...

10
Delayed coker advanced process control at Petronas Melaka refinery Seung-Yun Nam Y. Zak Friedman Petrocontrol, New York, USA Prakash Kumar Azura Bt. Azahar PETRONAS, Malaysia Overview Delayed coking is a refinery unit that is difficult to run and to control. That said, it is also one of the most profitable refinery units because it converts unwanted vacuum residue into distillates. The desire is to maximize coker feed, and APC is a lucrative application as long as it is able to increase throughput. This paper is about an APC project implemented on PETRONAS Melaka refinery coker, with the aim to o Smooth out the periodic drum switch disturbances, o Maximize middle distillate production o And above all, maximize throughput. The APC implementation work was carried out jointly by Petrocontrol and PETRONAS engineers. The project main features include o Petrocontrol inferential modeling package GCC. This was used for product quality predictions as well as some drum condition monitoring. o An MVPC (multi-variable predictive controller) from Honeywell (RMPCT). Two RMPCT controllers were utilized, one for the fractionator and one for the furnace. o The controller was commissioned in December 2007, and has been operated with a controller uptime of 99.9%+. This paper will show how the APC is structured and how it performs, demonstrating by trends that the application works very well. The post project analysis concluded that the increased throughput and reduced drum switch time created benefits of $5 million annually. Introduction Delayed coking is one of the most profitable refinery units. It takes low value vacuum pitch and converts it to distillates. Why then there are not many reports of Delayed coking units employing APC (Advanced Process Control)? We only know of one recent reference [1]. The answer must be – because delayed coking is also one of the most difficult refinery units to operate and control. First, batch reactors (coke drums) are integrated, not very smoothly, into a continuous plant. And second, the unit operates at high temperatures and is prone to coking, fouling and corrosion. The number of incidents on coking units is generally higher than in other refinery units. Figure 1 is a simplified diagram of Melaka’s delayed coker. Vacuum pitch (fresh feed) is mixed with some HCGO (cracked heavy coker gasoil), heated and injected into the main fractionator bottom. Mixed feed is then heated again in the coker furnace to a high cracking temperature, and hot partially cracked feed flows from the coker furnace into coke drums, where cracking ©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 1

Upload: others

Post on 25-Apr-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Delayed coker advanced process control at Petronas Melakarefinery

Seung-Yun NamY. Zak FriedmanPetrocontrol, New York, USA

Prakash KumarAzura Bt. AzaharPETRONAS, Malaysia

OverviewDelayed coking is a refinery unit that is difficult to run and to control. That said, it is also one ofthe most profitable refinery units because it converts unwanted vacuum residue into distillates.The desire is to maximize coker feed, and APC is a lucrative application as long as it is able toincrease throughput. This paper is about an APC project implemented on PETRONAS Melakarefinery coker, with the aim to

o Smooth out the periodic drum switch disturbances, o Maximize middle distillate productiono And above all, maximize throughput.

The APC implementation work was carried out jointly by Petrocontrol and PETRONASengineers. The project main features include

o Petrocontrol inferential modeling package GCC. This was used for product qualitypredictions as well as some drum condition monitoring.

o An MVPC (multi-variable predictive controller) from Honeywell (RMPCT). TwoRMPCT controllers were utilized, one for the fractionator and one for the furnace.

o The controller was commissioned in December 2007, and has been operated with acontroller uptime of 99.9%+.

This paper will show how the APC is structured and how it performs, demonstrating by trendsthat the application works very well. The post project analysis concluded that the increasedthroughput and reduced drum switch time created benefits of $5 million annually.

IntroductionDelayed coking is one of the most profitable refinery units. It takes low value vacuum pitch andconverts it to distillates. Why then there are not many reports of Delayed coking unitsemploying APC (Advanced Process Control)? We only know of one recent reference [1]. Theanswer must be – because delayed coking is also one of the most difficult refinery units tooperate and control. First, batch reactors (coke drums) are integrated, not very smoothly, into acontinuous plant. And second, the unit operates at high temperatures and is prone to coking,fouling and corrosion. The number of incidents on coking units is generally higher than in otherrefinery units.

Figure 1 is a simplified diagram of Melaka’s delayed coker. Vacuum pitch (fresh feed) is mixedwith some HCGO (cracked heavy coker gasoil), heated and injected into the main fractionatorbottom. Mixed feed is then heated again in the coker furnace to a high cracking temperature, andhot partially cracked feed flows from the coker furnace into coke drums, where cracking

©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 1

Page 2: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

continues. Cracked distillate vapor ascends in the coke drum and flows into the fractionator forseparation. Coke remains in the drum.

Figure 2 shows the coke drums in more detail. One drum operates at a time, accumulating cokeuntil it is almost full, and then the coke is removed. About every 15 hours, the filled coke drumis switched off for coke removal and the empty drum is connected. The drum that was just filledgoes then through a cycle of steaming out, cooling, opening, coke removal, closing, steaming,pressure testing, heating, and finally re-connecting to the furnace and fractionator. Heating ofcold drums creates significant disturbances because the heating is done by sending hot crackedvapor through the cold drum, depriving the fractionator of both heat and material. The maindisturbance, however, comes later upon connecting the warm empty drum. Drum temperatureneeded for cracking is around 500 ºC, but the new empty drum cannot practically be heated up tosuch a level. Drums are typically switched in at 400 ºC, which quenches the reaction almostcompletely, causing a major disturbance that lasts about two hours, until the newly connecteddrum reaches normal operating temperature.

All and all, figure 1 presents a fairly typical delayed coker, the main exception being that there isno fractionator internal recycle of HCGO to the bottom, and instead some fuel-oil is produced tosupply local demand.

At steady state operation, when the drum is at normal temperature, the APC challenge is tomaximize feed and minimize fuel-oil, while controlling overhead naphtha and LCGO (lightcoker gasoil) products on specifications. During drum switch operation the APC goal isprimarily to manage the inventory of liquid in the fractionator until the coke drum heats up andvapor supply re-established. Product specification constraints are usually inactive at that timebecause inventory control dictates quality giveaways. However, the economic drive forthroughput maximization is still there. To compound inventory control difficulties, downstreamconsideration dictate some draw of LCGO at all times, and during drum switch, when LCGO isnot available, APC must divert some naphtha down with LCGO to respect the low draw target.

Control matrix structureWe have made a decision to structure the APC as two separate controllers because there is littleinteraction between the two controllers. The furnace RMPCT performs temperature control, passbalancing and constraint pushing. The coking furnace feed is maximized to furnace constraints,whereas the fractionator is required to handle the load, relaxing product quality targets ifnecessary. There is only one important point of communications between the two applications:at drum switch time the furnace outlet temperature target is temporarily stepped up to speed therecovery to normal cracking conditions.

We proceed to discuss the fractionator control structure. The key handles used are

i) Handles for controlling naphtha and LCGO cutpoints

ii) Pumparound duties

iii) Pumpdown and recycles

These handles are used to control/constrain the following

i) Naphtha and LCGO 90% inference

ii) Pumparound flows

iii) Pan levels

©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 2

Page 3: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

iv) Flash zone temperatures

v) Charge pump current

Inferential model discussionCoker units are never at steady state. Drum switches occur every 15 hours and each switch isassociated with two major disturbances: drum warm-up and drum switch. In addition to thosemajor events, cracking conditions drift gradually as drum level increases. For a unit at steadystate, a 6:00 morning sample typically yields lab results at about 09:00, at which point theoperator might correct unit conditions. But when a unit is not at steady state the meaning of asample taken at 06:00 is partially lost at 09:00. Hence, coming up with reasonable inferentialmodels is a prerequisite to successful coker APC.

The advantage of GCC being a first principle model is that there is no frequent need to bias themodel to correct it against lab reading. Not that biasing can be completely avoided, becauseeven if the model were perfect, instruments are not ideal and their readings occasionally drift, butas compared to regression models GCC is more stable.

Figures 3 and 4 show a two months trend of ASTM 90 % point, inference versus lab data, forNaphtha, LCGO and HCGO. The predictions vary at the frequency of drum switches, andamplitudes of 15 – 20 °C. That is to be expected on a coker, where quality targets aretemporarily relaxed during disturbances. Lab samples are taken at different times of the drumcycle and they also exhibit variability. These trends demonstrate how well the inferences work.The predictions have tracked the lab well and there was no need to change inferential biasesduring the two months period.

Monitoring of drum conditions is part of the inferential package. The following conditions aredetected automatically

o Start of drum warm-upo End of drum warm-up and start of drum switcho Drum stripping steam going into the fractionator (affects the inferences)o Stop of drum steam to fractionatoro End of drum switch and start of normal operation

Feed maximization Once we succeed in controlling product qualities, the main coker APC benefit is achieved byfeed maximization, and figure 5 demonstrate this achievement. The figure upon commissioningthe application throughput has gone up by 5 M3/Hr, about 3%. Figure 6 shows that much of thethroughput increase happened during drum switches.

Conclusions

©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3

Page 4: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Against the challenge of the coker being a difficult unit, with part of the unit operated in batchwhile the other part is continuous, plus high temperatures and many constraints and restrictions,we have demonstrated that coker APC can be made to work. Key to such success are:knowledge of the process, good quality inferences and attention to details. The Melaka cokerhigh value APC application not only improves the unit economics but also makes operator lifemore comfortable, and in our opinion reducing the chance of incidents. In addition to thedelayed coker knowledge within the APC team we are grateful for help from Melaka processengineering, as well as from the coker operation department. We would not recommend thatanyone begin coker APC work without such support as the coker is a demanding unit, andincorrectly implemented APC is liable to damage the unit, or at least the APC team reputation.

Literature1. Volker Haseloff, Sean G. Goodhart and Y Zak Friedman “Coker advanced process control at

BP Gelsenkirchen refinery”, Hydrocarbon Processing Journal, July 2007

©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 4

Page 5: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 1: C

oker u

nit sim

plified

diag

ram

FC

TC

PC

FC

LC

FE

ED

FC

LC

LC

FC

LC

GO

PA

FC

LC

GO

PD

LC

GO

FC

HC

GO

PA

FC

FC

HC

GO

PD

RE

CY

CL

E

LI

FU

EL

OIL

LC

FC

FC

QU

EN

CH

TC

FC

FC

TC

FC

TC

TC

PC

PC

FC

FC

LC

LC

FE

ED

FC

FC

LC

LC

LC

LC

FC

LC

GO

PA

FC

FC

LC

GO

PD

LC

GO

FC

LC

GO

FC

HC

GO

PA

FC

FC

FC

HC

GO

PD

RE

CY

CL

E

LI

LI

FU

EL

OIL

LC

LC

FC

FC

FC

QU

EN

CH

TC

TC

FC

FC

FC

TC

TC

Page 6: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 2

: C

oke d

rum

s con

figu

ration

FE

ED

HC

GO

PC

450°C420°C

Qu

ench

Pu

mp

do

wn

Fu

eloil

Recycle

FC

FC

FC

PC

Fu

elgas

FC

TC

Page 7: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 3: N

aph

tha 90%

po

int in

ference (N

AP

90_M) versu

s lab (N

AP

90_L)

120

130

140

150

160

170

180

15-Sep-07

25-Sep-07

05-Oct-07

15-Oct-07

25-Oct-07

04-Nov-07

NA

P90_M

NA

P90_L

Page 8: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 4: L

CG

O 90%

po

int in

ference (L

CG

90_M) versu

s lab (L

CG

90_L)

340

350

360

370

380

390

400

410

420

430

440

15-Sep-07

25-Sep-07

05-Oct-07

15-Oct-07

25-Oct-07

04-Nov-07

LCG

90_LLC

G90_M

Page 9: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 5: C

oker fresh

feed flo

w b

efore an

d after co

mm

ission

ing

of A

PC

613545

477409

341273

205137

691

200

195

190

185

180

175

170

Ob

serv

ation

Individual Value

_X=189.27

UCL=198.83

LCL=179.70

10

10

111

11

1

111

11

1

1

1

11

1

1

I Chart of 3

2FC

10

2 by Condition

Page 10: Delayed coker advanced process control at …©2010 PETROLIAM NASIONAL BERHAD (PETRONAS), Page 3 Against the challenge of the coker being a difficult unit, with part of the unit operated

Fig

ure 6: F

resh feed

flow

du

ring

dru

m sw

itches

Fresh Feed (32FC102) reduction during drum sw

itch

50.00

70.00

90.00

110.00

130.00

150.00

170.00

190.00

210.00

230.00

020

4060

80100

120140

160180

BeforeBefore

AfterAfter

After