D GROUNDWORK
D20 Excavating and filling
Excavating by machine
To reduce levels, maximum depth not exceeding
a 0.25 m 12.02 m3 3.20 38 46
Trenches, width over 0.30 m, maximum depth not
exceeding
b 1.00 m 6.87 m3 11.50 79 01
Excavating by machine in confined spaces
Trenches, width over 0.30 m, maximum depth not
exceeding
c 1.00 m 1.29 m3 10.45 13 48
Pits, maximum depth not exceeding
d 1.00 m 0.44 m3 7.26 3 19
Breaking out
Existing materials
e concrete (existing GF slab) 1.58 m3 120.50 190 39
f concrete (existing foundations) PROVISIONAL
QUANTITY 1.37 m3 120.50 165 09
Disposal
On site by hand
g to skips. (Skips measure elsewhere) 17.17 m3 84.00 1,442 28
D21 Ground gas venting
Excavation of radon sump
by hand, depth not exceeding
h 1.00m 5.40 m3 92.40 498 96
Construction of radon sump using
900 x 900mm PC slab
i as base and lid. 3.00 nr 9.70 29 10
100mm dense concrete blocks loose laid
j as side walls. 3.00 nr 24.00 72 00
Excavation of trench
by hand
k for radon pipe (Disposal measure in disposal item
above) 8.00 m 30.00 240 00
100mm PVCu pipe
laid in trench as radon extract pipe
l including building into radon sump and wall. 8.00 m 6.09 48 72
2 Trevarthian Cottages, Kestle Mill, Newquay EXCAVATION & FILLING
B G Helps A Building Design & Estimating Page 8 To Collection £ 2,820 68
Qty Unit Rate £ p
F MASONRY
F10 Brick/Block walling
Precast concrete dense aggregate blocks to BS 6073
in gauged mortar 1:1:6
skins of hollow walls
a 100 mm solid 73.24 m2 41.13 3,012 36
walls and partitions
b 100 mm solid (this wall is a new wall to the
ground floor only there is no indication to say the
wall is to be extended to the first floor level). 10.70 m2 26.78 286 55
E IN SITU CONCRETE/LARGE PRECAST CONCRETE
E10 Mixing/casting/curing in$situ concrete
Site mixed in*situ concrete
Plain in situ concrete 1:2:4 * 20 mm aggregate
c filling to hollow walls 0.53 m3 346.16 183 46
C EXISTING SITE/BUILDINGS/SERVICES
C90 Alterations $ spot items
Block up openings in walls
Blockwork in gauged mortar 1:1:6
d 100 mm 7.41 m2 41.97 311 00
Cut pockets and bond blockwork to existing
e 100 mm wide 10.00 m 10.00 100 00
Precast concrete lightweight aggregate loadbearing
blocks to BS 6073 in gauged mortar 1:1:6
skins of hollow walls
f 100 mm 54.88 m2 27.47 1,507 55
F30 Accessories/Sundry items for brick/block/stone
walling
Forming cavities
50 * 100 mm cavities in hollow walls with 200 mm
wall*ties at 5 per m2 using
g 0.6 mm stainless steel pressed ties with
insulation retaining clips 62.59 m2 5.55 347 37
Closing cavities
Thermabate cavity closers
h 100mm cavity 20.46 m 25.44 520 50
using Rockwool TCB cavity barrier,
i 100mm 16.80 m 13.25 222 60
2 Trevarthian Cottages, Kestle Mill, Newquay BRICKWORK, BLOCKWORK & MASONRY
B G Helps * Building Design & Estimating Page 14 To Collection £ 6,491 39
Qty Unit Rate £ p
P BUILDING FABRIC SUNDRIES
P10 Sundry insulation/proofing work/fire stops
Insulating boards
Celotex insulation board, for ground floor
construction, laid level
a 80mm thick 44.00 m2 15.92 700 48
J WATERPROOFING
J40 Flexible sheet tanking/ damp proof
membranes
Tanking and damp proofing
Polythene medium weight sheet underlay lapped
150 mm at joints
b horizontally 44.00 m2 0.85 37 40
K LININGS/SHEATHING/DRY PARTITIONING
K20 Timber board
flooring/sheathing/linings/casings
Flooring
Plywood flooring in 1500 x 600mm panels tongued
and grooved all edges, width exceeding 300 mm,
thickness
c 6mm 44.00 m2 19.71 867 24
G STRUCTURAL/CARCASSING METAL/TIMBER
G20 Carpentry/Timber framing/First fixing
Impregnated sawn softwood , SC3 Grade
Floor members
d 38 x 175mm 29.70 m 4.72 140 18
Metalwork
Galvanised steel joist hangers , built in
e 38 x 175mm 18.00 nr 4.71 84 78
30 x 2.5mm galvanised steel holding down straps,
twice bent, one end drilled and screwed to timber,
the other end built in
f 1200mm girth 4.00 nr 11.83 47 32
Herringbone strutting (size 50 x 50 mm) to joists,
(measured over joists)
g 175 mm deep 3.30 m 9.24 30 49
Noggings between joists
h 50 x 50mm 19.20 m 4.56 87 55
2 Trevarthian Cottages, Kestle Mill, Newquay WOODWORK & JOINERY
B G Helps , Building Design & Estimating Page 20 To Collection £ 1,995 44
Qty Unit Rate £ p
Collection
Total from Page 20 £ 1,995 44
Total from Page 21 £ 2,064 88
Total from Page 22 £ 1,848 82
Total from Page 23 £ 4,070 15
Total from Page 24 £ 1,574 47
2 Trevarthian Cottages, Kestle Mill, Newquay WOODWORK & JOINERY
B G Helps 3 Building Design & Estimating Page 25 To Summary £ 11,553 76
Qty Unit Rate £ p
Summary
PRELIMINARIES Page 3 £ 11,360 00
DEMOLITIONS & REMOVALS Page 7 £ 3,971 01
EXCAVATION & FILLING Page 10 £ 3,756 38
CONCRETE WORK Page 13 £ 3,566 59
BRICKWORK, BLOCKWORK & MASONRY Page 17 £ 8,449 31
ROOFING & RAINWATER DISPOSAL Page 19 £ 5,376 25
WOODWORK & JOINERY Page 25 £ 11,553 76
FLOOR, WALL & CEILING FINISHES Page 28 £ 5,419 12
DECORATION Page 30 £ 2,728 97
DRAINAGE Page 33 £ 1,540 11
EXTERNAL WORKS Page 35 £ 292 37
SPECIALIST INSTALLATIONS Page 38 £ 25,966 15
PROVISIONAL & PC ITEMS Page 40 £ 2,394 32
2 Trevarthian Cottages, Kestle Mill, Newquay
B G Helps 7 Building Design & Estimating Page 41 Total for Bill £ 86,374 34
Qty Unit Rate £ p