current status of solid breeder tbm in china

27
Current Status of Solid Breeder TBM in China Presented at CBBI-16 meeting Sep. 8 -10, 2011, Red Lion on the River , Portland, OR, USA Presented by: Kaiming Feng (On behalf of Chinese HCCB TBM Team) Co-Institutes: 1). China Academy of Engineering Physics (CAEP), Mianyang, P.R. China 2). Chinese Institute of Atomic Energy (CIAE) , Beijing, 100084, P.R. China. 3). Chinese Institute of Nuclear Power CINP), Chengdu 610043, P.R. China 4). Shanghai Ceramic Institute, Chinese Academy of Science (SCICAS), P.R. China

Upload: eldora

Post on 03-Feb-2016

40 views

Category:

Documents


0 download

DESCRIPTION

Current Status of Solid Breeder TBM in China. Presented by: Kaiming Feng (On behalf of Chinese HCCB TBM Team). Co-Institutes: 1). China Academy of Engineering Physics (CAEP), Mianyang, P.R. China 2). Chinese Institute of Atomic Energy (CIAE) , Beijing, 100084, P.R. China. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Current Status of Solid Breeder TBM in China

Current Status of Solid Breeder TBM in ChinaCurrent Status of Solid Breeder TBM in China

Presented at CBBI-16 meeting

Sep. 8 -10, 2011, Red Lion on the River , Portland, OR, USA

Presented by: Kaiming Feng

(On behalf of Chinese HCCB TBM Team)

Co-Institutes:1). China Academy of Engineering Physics (CAEP), Mianyang, P.R. China 2). Chinese Institute of Atomic Energy (CIAE) , Beijing, 100084, P.R. China.3). Chinese Institute of Nuclear Power ( CINP), Chengdu 610043, P.R. China4). Shanghai Ceramic Institute, Chinese Academy of Science (SCICAS), P.R. China

Page 2: Current Status of Solid Breeder TBM in China

OUTLINEOUTLINE

11. Introduction

2. Progress on Updated Design

3. Progress on Relevant R&D

4. Test Plan and Cooperation

5. Summary

Page 3: Current Status of Solid Breeder TBM in China

1. Introduction1. Introduction

ITER is an unique opportunity to test tritium breeding blanket mock-ups in an integrated tokamak operating conditions;

Helium-cooled ceramic breeder (HCCB) test blanket module will be the primary option of the Chinese ITER TBM program;

China has the position of Port Master (PM) in port number 2 and is leading the HCCB concept as the TBM Leader (TL). CN HCCB TBM will be tested at different phases of ITER operation;

In order to reduce the effects of magnetic field ripple, the TBM design was updated with reduced RAFM mass;

Related R&D on key components, materials, fabrication and mock-up test have being implemented in China.

Page 4: Current Status of Solid Breeder TBM in China

It was assumed that DEMO is a next step after ITER. DEMO will demonstrate the integration technology, materials, economics, safety, and

environment for the fusion energy applications. TBM testing on ITER is an important approach toward to DEMO.

Roadmap to DEMORoadmap to DEMO

HL-2A

ITER

DEMO

Power Plant

Fusion Breeder?

ITER -TBM

IFMIF

2020 2035 20502010

EAST

CTF? FNST?

Page 5: Current Status of Solid Breeder TBM in China

5

As one options of breeding blanket with the Helium-cooled solid breeders/RAFM steel (HCSB-DEMO) will be chosen as China’s DEMO blanket concepts.

HCCB TBM will demonstrate the functions required for Chinese HCSB-DEMO blanket under at ITER operation condition.

HCSB-DEMO Blanket ConceptHCSB-DEMO Blanket Concept

HC-SB DEMO Blanket

3-D View of HCSB DEMO blanket

.K.M.Feng, et.al., J. Fusion Eng.& Desgn, 84(2009)2109-2113.

Page 6: Current Status of Solid Breeder TBM in China

TBM Concepts and Port-Sharing

Six TBM Systems to be installed in ITER in different operation phases

Port No. and PM TBM Concept TBM Concept

A (PM : EU) HCLL (TL : EU) HCPB (TL : EU)

B (PM : JA) WCCB (TL : JA) PMG: US/KO, LLCB? TL?

C (PM : CN) HCCB (TL : CN) LLCB (TL : IN)

PM : Port Master, TL : TBM Leader

HCLL : Helium-cooled Lithium Lead HCPB : He-cooled Pebble Beds (Ceramic/Beryllium)

WCCB : Water-cooled Ceramic Breeder (+Beryllium) HCCB : He-cooled Ceramic Breeder (+Beryllium) LLCB : Lithium-Lead Ceramic Breeder (LiPb & He, Dual-Coolant type)

CN HCCB TBM will demonstrate the functions required for Chinese DEMO blanket in ITER condition

HCSB-DEMOITER cross-section

CN HCCB TBM

Relationship of ITER,TBM and DEMO

Page 7: Current Status of Solid Breeder TBM in China

7

A series of the Chinese HCCB TBM design have been carried-out since 2004 within the space limitation and technical requirements specified by ITER.

2. Progress on CN HCCB TBM Design2. Progress on CN HCCB TBM Design

Page 8: Current Status of Solid Breeder TBM in China

Outline of HCCB TBM Design

- TBM structure: Sub-module arrangement- Structure material: RAFM (CLF-1);- Tritium breeder: Li4SiO4 pebble bed, 80%Li-6 ;- Neutron multiplier: Be pebbles bed;- Coolant and purge gas: Helium gas - Coolant pressure: 8MPa- Coolant temperature: 300 OC(inlet) -500 OC (outlet)- Tritium production ratio (TPR): 0.0505g/d

Integration View of CN HCSB TBM

Cross-section of SB

Assembly scheme of Sub-Modules

Basic design characteristics:

Originally design of CN HCCB TBM have been completed before 2009.

Page 9: Current Status of Solid Breeder TBM in China

9

Updated Design of HCCB TBM for Reduction RAFM Mass

HCCB TBM Module TBM Sub-module arrangement Cross-section of SM

- The RAFM mass is reduced from 2.3t to 1.6t).

- TPR is increased by factor from 0.051g/day to 0.0798g/day.

Objectives of updated design:

- to simplify Sub-module structure;

- to reduce RAFM mass;

- to improve TPR performance;

Exploded view of sub-module

Main modification

An optimized all RAFM design with reduced mass of 1.3t is on going. A updated DDD report will be completed soon.

Results shown:

- Reduce radial dimension of the FW and sub-modules.- Bypass is introduced to TBM design to control the difference of

flow-rates .

- Arrangement of pebble beds in the sub-module is changed from the former transverse direction to the current vertical direction.

Page 10: Current Status of Solid Breeder TBM in China

10

Performance Analyses for Updated TBM Design

a) RAFM material b) Be pebble bed c) Li4SiO4 pebble bed

ParametersPrevious design

Updated design

RAFM mass, ton 2.31 1.63

Tritium Production Rate (TPR), (g/d)

0.051 0.079

Peak power density (MW/m3)

6.26 6.82

Total power deposit (MW)

0.587 0.642

Tmax= 517 OCTmax= 548 OC Tmax= 621 OC

Temperature and stress distribution of FW

Temperature Distribution of Sub-module

Main parameters meet design requirement. TPR is obviously increased.

Main calculation results

d)Sub-module

Page 11: Current Status of Solid Breeder TBM in China

thermal analysis model

RAFMs (CLF-1)

Li4SiO4

pebble bed

Be pebble bed

Thermal conductivity [W/(m·K)]

29.8(400

) ℃

1.0-1.2 (500-900 ℃)

5.4, 8.8, 10.6 (500, 600, 700

)℃

Max. allowable temperature [ ]℃

550 920 700

Thermal analysis results of sub-module

Primary stress Secondary stress

Stress analysis

Thermal analysis

Performance Analyses for Updated TBM Design

Page 12: Current Status of Solid Breeder TBM in China

13

CN HCCB TBM Auxiliary Sub-system Design

Page 13: Current Status of Solid Breeder TBM in China

Basic configuration BOT (Breeder Out of Tube) Modules: 2×6 Sub-modules

First wall area

Neutron wall loading

Surface heat flux

0.484 m(W)×1.660 m(H) 0.803 m2.

0.78 MW/m2

0.3 MW/m2 (normal condition)

0.5 MW/m2 (extreme condition)

Total heat deposition NT-TBM PI-TBM 0.642 MW

Tritium production rate ITER operation condition 0.079g/FPD

TBM module dimension (P)× (T) × (R) 1660mm×484mm×675mm

Ceramic breeder (Li4SiO4) Single size

Thickness

Max. Temperature

D = mm, pebble bed

90 mm (four zones)

699℃

Neutron multiplier

(Beryllium)

Two size

Thickness

Max. Temperature

Diameter: 0.5~1 mm, Pebble bed

200 mm (five zones)

537℃

Structure Material Ferritic steel

Max. Temperature

CLF-1

538 ℃

Coolant helium (He)

Pipes size

Pressure

Pressure drop

Temperature range (inlet/outlet)

Mass flow

Diameter (OD/ID)

8 MPa

0.08 MPa

300/500 ℃1.36kg/s

101.6/85.5 mm

He purge flow (He) Pressure

Pressure drop

Mass Flow

Diameter (OD/ID)

0.12 MPa

0.02 MPa

0.6 g/s

35/30 mm

Design Parameters for the HCCB TBMDesign Parameters for the HCCB TBM

Page 14: Current Status of Solid Breeder TBM in China

CN TBS Integration with ITER (Con’t)CN TBS Integration with ITER (Con’t)

C5CN-HCCB

C6IN-LLCB

15

2 half-ports

View of Pipe Forest and TBM-Sets in Port #2

Page 15: Current Status of Solid Breeder TBM in China

16

Port Cell area

Tokamak Coolant Water System vault

L2 of Tritium building for TES

Interface 1 Interface 2a Interface 2bInterface 3

India part

China part

Port 2#(Port Plug)

Interspace(Pipe forest)

Port Cell(AEU)

Space reserved for CN TBS has been identified. Arrangements of CN TBS have been considered. Investigation of components which selected for CN TBS has been done. Strategy for Pipe Forest maintenance has been coordinated with IO people.

Space arrangementSpace Arrangement Identification of CN TBS

CN TBS Integration with ITERCN TBS Integration with ITER

Page 16: Current Status of Solid Breeder TBM in China

17

500kg Ingot of CLF-1

1-ton Ingot of CLF-1

3. Progress on R&D:3. Progress on R&D: Structural Materials-CLF-1

Consumable electrode furnace Two RAFM alloys are being developed in China; CLF and CLAMA 500kg and 1-ton ingots of CLF-1 steel were recently produced by vacuum induction melting and electro-slag remelting method. The optimization of the melting technique for the larger ingots to

is underway.

Tensile strength of CLF-1 DBTT of CLF-1

Remelting facility

Page 17: Current Status of Solid Breeder TBM in China

18

3. Progress on R&D:3. Progress on R&D: Ceramic Breeder Pebbles

Relative density 94% TD

Li4SiO4 phase content 90%

Closed porosity 0.72%

Open porosity 5.2 %

Average crush load 7.0 N

Specific surface area 1.092 m2/gLi2TiO3 Pebbles (D=1mm)@CAEP

Li4SiO4 Pebbles (D=1mm) by

extrusion–sintering method @CIAE

Two kinds of ceramic breeders (Li4SiO4, Li2TiO3) for TBM are being developed at different institutions in China;

Lithium orthosilicate (Li4SiO4 ) pebbles will be the primary option in the CN HCCB TBM.

Li4SiO4 Pebbles (D=1mm)

by metl spraying method @SWIP Li4SiO4 Pebbles (D=1mm)

by freeze-sintering method @CAEP

Ceramic breeder (Li4SiO4) pebbles fabricated by melt spraying method have good sphericity, and high density.

Ceramic breeder (Li4SiO4) pebbles prepared by Freeze-sintering process have good mechanical properties (the average crush load is 50N) ;

Li2TiO3 Pebbles have good surface

feature by using sol-gel method.

XRD pattern of Li4SiO4 pebbles

Main properties (Li4SiO4) by melt spraying method

15 20 25 30 35 40 45 50 55 60 65 700

1000

2000

3000

4000

5000

Inte

rnsity (C

ounts

)

2

Li4SiO

4

Li2SiO

3

Li2CO

3

Page 18: Current Status of Solid Breeder TBM in China

3. Progress on R&D:3. Progress on R&D: Fabrication of Be Pebbles

ChineseVHP-Be

Be BeO% Al C Fe Mg SiOther metallic

elements

1# ≥99% 0.750 0.006 0.060 0.050 0.003 0.009 <0.04

Be metal of high performance was developed in China .

Be pebbles have been produced by Rotating Electrode Process (REP) method in China. Related performance tests are on going.

A new project to develop higher quality Be pebbles in China is being implemented for the ITER project.

Main chemical composition of Chinese Be 1#

Be Pebbles (D=1mm)

Micrographs of Be Pebbles (D=1mm) REP Facility at HBSM Co.

Be (wt%) 98.3

BeO (wt%) 1.67

Al (ppm) 235

Si (ppm) 18

Mn (ppm) 58

Mg (ppm) ≤10

Co (ppm) ≤10

Sample of Be Pebbles(D=1mm)

Chemical Composition of Be pebble

Page 19: Current Status of Solid Breeder TBM in China

3. Progress on R&D3. Progress on R&D: Helium Coolant Test Loop

Flow diagram of He Loop Layout of He Loop

The construction of a small He Test Loop to validate circulator technology will be completed soon.

- The He test loop has two impellers. It uses aerostatic bearings to avoid oil lubricating.

Flow diagram of small He loop

Parameters Maximum flow rate /kg-1s

Inlet pressure /MPa

Maximum pressure head /MPa He inlet/outlet temperature /℃

Circulator ~0.35 8 0.4 ~50/65

A prototyped Helium Test Loop to validate TBM components and design is also to be built in SWIP. The circulator will use magnetic bearings. The flow rate will up to 1.3kg/s.

3-D view of circulator Impeller of circulator

Cross-section view

Main parameters of circulator design

Page 20: Current Status of Solid Breeder TBM in China

21

Fabrication of Key Components of He Test Loop

Page 21: Current Status of Solid Breeder TBM in China

22

3. Progress on R&D:3. Progress on R&D: Fabrication Process of U-Shaped FWFabrication Process of U-Shaped FW

A small-sized mock-up (1:3) of U-shaped first wall is completed; Two kinds of fabrication method of U-shaped FW have been considered;

Page 22: Current Status of Solid Breeder TBM in China

23

3. Progress on R&D:3. Progress on R&D: Fabrication of Small Sized Mock-up Fabrication of Small Sized Mock-up A full-sized mock-up with 2X2 sub-modules arrangement using the RAFM steel (CLF-1)

as structure material will be completed in this year.

Page 23: Current Status of Solid Breeder TBM in China

4. TBS R&D and Delivery Plan4. TBS R&D and Delivery Plan

1. CN HCCB TBS qualification activities– Helium experimental loop (1:3) construction (2010.01-2011.06)– Conceptual design of CN HCCB TBM(2010.01-2012.12)– CN TBM testing and update design (2011.06-2013.12)– Preliminary design of CN HCCB TBM (2013.01-2013.12)– Prototype helium loop construction (2012.01-2014.06)– Large scale TBM mock-up tests (2014.06-2015.12)– Final design of CN HCCB TBM (2014.01-2015.12)

2. CN HCCB TBS delivery activities.– Main TBS components fabrication (2016.01-2017.06)

Final TBS design in ITER. Main TBS components fabrication. TBS function tests (domestic).

– CN TBS delivery (2016.12-2017.06)– CN TBS acceptance tests in ITER site (2017.06-2017.12)– EM TBM delivery (2018.01-2018.06)– EM-TBM System acceptance tests(2018.06-2019.06)

3. EM-TBM will be installed in ITER port after the first plasma shutdown (2019)24

High flux test reactor

Page 24: Current Status of Solid Breeder TBM in China

25

Domestic and Intl. Cooperation Domestic and Intl. Cooperation

CAEP: China Academy of Engineering Physics; CIAE: China Institute of Atomic Energy;SJTU: Shanghai Jiao Tong University; ASIPP: Institute of Plasma Physics; Academy of Sciences ;NCEPU: North China Electric Power University; NECB: Nuclear Engineer Corporation , BeijingNPIC: Nuclear Power Institute, China; IMPCAS: Institute of Modern Physics, Chinese Academy of Sciences;TUINET: Tsinghua University, Institute of Nuclear Energy Technology; XJTU: Xi’an Jiao Tong University;SICCAS: Shanghai Institute of Ceramics, Chinese Academy of Sciences ; HBSMC: Haibao special metal materials Co.

SWIP CAEPCIAE ASIPPXJTU NCEPUNCIRD IMPCASNPIC TUINETSICCAS SJTU

SWIP CAEPCIAE ASIPPXJTU NCEPUNCIRD IMPCASNPIC TUINETSICCAS SJTU

Design Team R&D Team Safe & QA Team

SWIP CAEPCIAE SJTUASIPP NCEPUXJTU IMPCASNPIC TUINETSICCAS HBSMC

SWIP CAEPCIAE SJTUASIPP NCEPUXJTU IMPCASNPIC TUINETSICCAS HBSMC

SWIP CAEPCIAE NCEPUASIPP TUINETNPIC TUINETNCIRD SICCAS

SWIP CAEPCIAE NCEPUASIPP TUINETNPIC TUINETNCIRD SICCAS

CN HCCB TBMCN HCCB TBM

A lot of domestic units are joined into CN HCCB TBM program, including universities, institutes and industry company

Page 25: Current Status of Solid Breeder TBM in China

CN HCCB TBM will be operated and tested on ITER through international cooperation under the frame of partnership with ITER parties.

China is interested in other TBM concepts as a partner in HCPB-TBM, WCCB-TBM and LiPb-based TBMs.

China HCCB TBM is open to cooperation with other ITER parties. Some informal discussions, for instance, CN-EU,CN-JA, CN-KO, has been started.

CN-US bilateral cooperation meeting on TBM program will held on Nov.7-9, 2011.

Intl. Cooperation and Partnership

Domestic and Intl. CooperationDomestic and Intl. Cooperation

Page 26: Current Status of Solid Breeder TBM in China

5. Summary5. Summary

HCSB TBM with the Solid Breeder/Helium coolant/ RAFM material is the primary option of the Chinese TBM program.

Updated design, current progress on R&D, test and delivery plan up to the installation in ITER (2019) are presented.

Relevant R&D on key techniques for the HCSB TBM concept are supported by the Chinese ITER- DA domestic agency (2009-2012) , including:

– TBM optimization design and validation of key technologies;– Fabrication of Li4SiO4 pebbles and Be pebbles to large-scaled level;– Fabrication of structure material RAFM to ton level;– Construction of High Heat Flux Test Facility (Power:400kW);– Construction of small-scale and prototyped Helium Test Loop.

Testing HCSB TBM on ITER will be implemented with the cooperation of domestic and international institutions and industries.

Page 27: Current Status of Solid Breeder TBM in China

Thanks for your Attention !Thanks for your Attention !