cpm & pert excercises - bu
TRANSCRIPT
-
8/10/2019 Cpm & Pert Excercises - Bu
1/211
Project Management
-
8/10/2019 Cpm & Pert Excercises - Bu
2/211
PROJECT MANAGEMENT
Times of India dt 29thoct 2007.
An air port in Assam,a bridge in Orissa, a
highway in Karnatakawhat they have incommon?all running behind schedule.
-
8/10/2019 Cpm & Pert Excercises - Bu
3/211
PROJECT MANAGEMENT.
Total no of projects (Rs 20crores &above)
866.
No of delayed projects=297.
Cost over-run=Rs 24,389 cr
Total anticipated cost=3,75,888cr
Expenditure till Dec 2006 =1,38,905 cr
Scale of time over run =1-196 months.
-
8/10/2019 Cpm & Pert Excercises - Bu
4/211
PROJECT MANAGEMENT.
Out of a total of 866 projects, each costingRs 20cr or more ,297 projects- spawned by13 ministries GOVT of Indiaare running
badly behind schedule. More than 24,000 crwill be spent additionally, because of delayan amount sufficient for many more
projects.
---- Quarterly report by the ministry ofstatistics and program implementation.
-
8/10/2019 Cpm & Pert Excercises - Bu
5/211
PROJECT MANAGEMENT.
By the time we build the airports, theyhave become obsolete.
By the time we build the roads, theyhave already become over crowded.
- Mr Ratan Tata.
-
8/10/2019 Cpm & Pert Excercises - Bu
6/211
PMBOK GUIDE
Project body of knowledge (PMBOK), is the sum ofknowledge within the profession of project
management.
-
8/10/2019 Cpm & Pert Excercises - Bu
7/211
PURPOSE OF PMBOK
The primary purpose of the PMBOK guide is toidentify that subset of project management body ofknowledge that is generally recognized as good
practice.
PMBOK Guide provides guide lines for managing
individual projects. It defines project management
and related concepts and describes projectmanagement life cycle and related processes.
-
8/10/2019 Cpm & Pert Excercises - Bu
8/211
PROJECT MANAGEMENT Project Management Institute, USA
(PMI) was founded in 1969 to provide ameans for project managers to
associate, share information, anddiscuss common problems.
Making project managementindispensable for business results.
www. pmi.org.
-
8/10/2019 Cpm & Pert Excercises - Bu
9/211
PROJECT MANAGEMENT
Project management is application ofknowledge, skills, tools & techniques toproject activities to meet projectrequirements.
-
8/10/2019 Cpm & Pert Excercises - Bu
10/211
PROJECT MANAGEMENT
PMI standards are developed, by teamsof hundreds of volunteers from around
the world with expertise, enthusiasmand dedication to advancing thepractice of project management and the
profession.
-
8/10/2019 Cpm & Pert Excercises - Bu
11/211
PROJECT MANAGEMENT
Over its almost 40 years history, PMI hascreated standards and practices that areglobally recognized.
Through its credential programs andpublications, which include A guide to theproject management body of knowledge
(PMBOK Guide), PMI identifies, defines,documents, and champions valuedapproaches.
-
8/10/2019 Cpm & Pert Excercises - Bu
12/211
PURPOSE OF PMBOK
The PMBOK guide also provides and promotes acommon lexicon for discussing,writing and applyingproject management. Such a standard lexicon is anessential element of a profession.
-
8/10/2019 Cpm & Pert Excercises - Bu
13/211
PURPOSE OF PMBOK
Generally recognizedmeans the knowledge and
practices described are applicable to most projects,most of the time, and there is consensus about theirvalues and usefulness.
Good practicemeans that there is general
agreement that the correct application of theseskills, tools and techniques can enhance the
chances of success over a wide range of differentprojects.
-
8/10/2019 Cpm & Pert Excercises - Bu
14/211
PROJECT MANAGEMENT.
Does project control the project manager? Or project
manager controls the project?
-
8/10/2019 Cpm & Pert Excercises - Bu
15/211
PROJECT MANAGEMENT A project is a temporary endeavor undertaken to
create a unique product, service or result.
-
8/10/2019 Cpm & Pert Excercises - Bu
16/211
Two Major Risks come to forewhile talking about Projects
Time Slippage / Delay
Cost Overrun
-
8/10/2019 Cpm & Pert Excercises - Bu
17/211
Mega ProjectsUnderground
Railways in Calcutta 20 years
Moonidih Coal Mine 25 years
Salal Power Project in
J&K > 18 years
Vizag Steel Plant 8 years
Like these 135 projects have been delayed
-
8/10/2019 Cpm & Pert Excercises - Bu
18/211
Projects successfully completed
Nehru Stadium in Chennai Abu Dhabi Airport
Bahai Temple in Delhi
Vijaipur Project was completed on Time
NTPC Projects, Asian Games in 1982.DELHI METRO
General Elections
-
8/10/2019 Cpm & Pert Excercises - Bu
19/211
When projects are
considered failure?
-
8/10/2019 Cpm & Pert Excercises - Bu
20/211
In your opinion
why do projects
often fail?
-
8/10/2019 Cpm & Pert Excercises - Bu
21/211
-
8/10/2019 Cpm & Pert Excercises - Bu
22/211
Project mgt & operation mgt.
Projects can interact with operations at variouspoints during product life cycle:
At close out.
When developing a new product, upgrading aproduct, or expanding outputs; or
Until the divestment of the operations at the endof the product life cycle.
-
8/10/2019 Cpm & Pert Excercises - Bu
23/211
Project management
Examples of project include, but are
not limited to:
Developing a new product or service.
Effecting a change in structure, staffing, or styleof an organization.
Designing a new transportation vehicle.
Developing or acquiring a new or modified
information system. Constructing a building or facility.
Building a water supply system for a community.
-
8/10/2019 Cpm & Pert Excercises - Bu
24/211
Project management
Running a campaign for a political office.
Implementing a new business procedure or process.
Responding to contract solicitation.
Conducting a wedding ceremony. Project to facilitate payments of tax through internet.
Service to collect garbage from homes.
Presenting a budget papers to the board.
-
8/10/2019 Cpm & Pert Excercises - Bu
25/211
Ongoing
and
Repetitive
Operation work is: Project work is:
temporary endeavor
undertaken to create a
uniqueproduct, serviceor result
What are the basic characteristics ofoperation & project work
-
8/10/2019 Cpm & Pert Excercises - Bu
26/211
1. Temporary endeavor means
project is having: Definite beginning Definite end, and Clear defined Project Objectives
Or when it becomes clear that the projectobjectives will or cannot be met, or the needfor the project is no longer exists and theproject is terminated
Milestone is an agreed end or starting of aspecific event or deliverable and has a duration ZERO
-
8/10/2019 Cpm & Pert Excercises - Bu
27/211
Projects creates unique deliverables, i.e.,
products, services, or results that has not
been done exactly the same way before and
which is, therefore, unique and distinct
2. Unique Product, Service
or Result means:
-
8/10/2019 Cpm & Pert Excercises - Bu
28/211
PROJECT MANAGEMENT
Uniqueness is an importantcharacteristics of project deliverables.
For example: many thousands of office buildingshave been developed, but each individual facilityis uniquedifferent owner, different design,different location, different contractors and so on.
The presence of repetitive elements does notchange the fundamental uniqueness of the projectwork.
-
8/10/2019 Cpm & Pert Excercises - Bu
29/211
High-level designRequirements
General
Detailed
Level
ofdetail
3. Progressive Elaboration
Progressive elaboration means developing in steps,and continuing steadily by increments
-
8/10/2019 Cpm & Pert Excercises - Bu
30/211
What is subproject?
Sub-projects are often contracted:
1.to an external enterprise, or
2.to another functional unit in theperforming organization
Project managers of the sub-projects areaccountable to the project manager of a project.
-
8/10/2019 Cpm & Pert Excercises - Bu
31/211
Performed by people
Constrained by limited resources
Planned, executed&
controlled
What is common to both
operation and project work?
-
8/10/2019 Cpm & Pert Excercises - Bu
32/211
PROJECT MANAGEMENT
The purpose of a project to attain its objectives andthen terminate.
Conversely, the objective of an ongoing operation isto sustain the business.
-
8/10/2019 Cpm & Pert Excercises - Bu
33/211
ProjectQuality is
affected by
Triple constraints influence projects
Q
SCOPE constraints limits project team to define scope and manage
scopeTIME constraints limits team to determine & manage time lines
COST constraints limits team to estimate life cycle cost i.e., projectcost plus operating and implementation costs
balancingtriple
constraints
If any one of the triple constraint factors is affected, atleast one other factor is likely to be effected, e.g.,Deliver high quality product, service or result within scope, time and budgetIf scope is increased, it has a likely effect on time, and cost as wellIf time or scope is increased, cost is most likely to be effected
Organizational Project
-
8/10/2019 Cpm & Pert Excercises - Bu
34/211
35
Organizational ProjectManagement (OPM)
Implementations should fit theOrganizational Environment: the
structure, policies, processes and culture of
the organization.
Right combination of right projects,
done right.
Portfolio: projects and programsgrouped for effective management andfocused on meeting specific strategicobjectives
Program: related projects grouped and
managed to optimize benefits, control
and outcomes, not available from
managing individually.
Projects: temporary endeavorsundertaken to create a unique product,
service or result
-
8/10/2019 Cpm & Pert Excercises - Bu
35/211
PROJECT MANAGEMENT
The projects or programs of the portfolio may notnecessarily be interdependent, or directly related.
For ex: An infrastructure company that has the strategic
objective of maximizing the return on investmentmay put together a portfolio that includes a mix ofprojects in oil and gas, power, roads, rail, andairports.
From this mix, the firm may choose to managerelated projects as one program. All of the powerprojects may be grouped together as a powerprogram.Similarly , all of the water projects may begrouped together as water program.
-
8/10/2019 Cpm & Pert Excercises - Bu
36/211
Projects and strategic planning
Projects are often utilized as a means of
achieving an organizations strategic plan: Market demand.
Strategic opportunity/business need.
Customer request.
Technological advance.
Legal requirement.
Social need
-
8/10/2019 Cpm & Pert Excercises - Bu
37/211
ROLE OF PROJECT MANAGER
PM is the person assigned by the performingorganization to achieve the project objectives.(S.M.A.R.T.)
The role of PM is distinct from a functional manager,or operation manager.
Typically the functional manager is focused on
providing management oversight for anadministrative area, and operations managers areresponsible for a facet of the core business.
-
8/10/2019 Cpm & Pert Excercises - Bu
38/211
ROLE OF PROJECT MANAGER In addition to any area-specific skills and general management
proficiencies required for the project, effective project
management requires that the PM possess the followingcharacteristics:
Knowledge:- this refers to what the PM knows about project management.
Performance:- this refers what PM is able to do or accomplish while applying
their project management knowledge.
Personal:-
this refers to how the PM behaves when performing theproject. The personal effectiveness encompasses attitudes,core personality characteristics and leadership.
-
8/10/2019 Cpm & Pert Excercises - Bu
39/211
Why do we
undertake Projects?
Project Characteristics
NEED
-
8/10/2019 Cpm & Pert Excercises - Bu
40/211
NEED
-
8/10/2019 Cpm & Pert Excercises - Bu
41/211
Projects are undertaken tosuccessfully implement organizational
strategies under uncertainties andsuccessfully meet the
expectations as visualized
NEED
-
8/10/2019 Cpm & Pert Excercises - Bu
42/211
C = f (Q, T, S)
COSTis a function of
QUALITY, TIME, & SCOPE
How project objectives are related?
1. Triple constraints influence projects
-
8/10/2019 Cpm & Pert Excercises - Bu
43/211
Knowledge of project mgmt.,processes to initiate, plan,execute, control, & closeprojects does influence thesuccess of projects
Effective communicationLeadershipInfluencing the organizationMotivationNegotiating & conflict mgmt.
Problem solving
1. Cultural & social environmentfactors
2. International & politicalenvironmental factors
3. Physical environmentalfactors
1. A standard is a documentedestablished by consensus andapproved by the recognizedbody
2. A regulation is a government-imposed requirement
General managementencompasses planning,organizing, staffing,executing, and controlling theoperations of the ongoing organd project operations.
PMBOKProject Mgmt.Methodology
Areas ofexpertiseby project
team
2. Project teams areas of expertiseinfluence projects
-
8/10/2019 Cpm & Pert Excercises - Bu
44/211
Product life cycle includes following projects:1. Curtain Raiser, Idea Generation
2. Market Research
3. Research and Development
4. Feasibility Analysis -5. Product Development
6. Marketing of a project product -
7. Installation of a User friendly product
8. Operation and Maintenance of a product
9. Disposition of product -
3. Product-life-cycle expectationsinfluence project
-
8/10/2019 Cpm & Pert Excercises - Bu
45/211
The Internal-Business-Process
CustomerNEEDIdentified
CustomerNEED
SatisfiedProject Life Cycle Phases
Need to upgradeOperation
Needto
Discard
BusinessPLAN
need
PROJECT LIFE CYCLE
-
8/10/2019 Cpm & Pert Excercises - Bu
46/211
What is importance of project phase?
Project phases are the description of
What project or technical work need to bedone, and describes what deliverables are
to be planned and managed in each project
phase of the project-life-cycle?
PROJECT MANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
47/211
CHARACTERISTICS OF PHASES
The completion and approval of one or moredeliverables characterizes a project phase.
A project phase is not a project managementprocess group.
-
8/10/2019 Cpm & Pert Excercises - Bu
48/211
Project Phases.
The phases:- Example:
Requirements gathering.
Design.
Construction.
Testing.
Implementation.
-
8/10/2019 Cpm & Pert Excercises - Bu
49/211
Project Phases.
Design documents. Deliverables at kill points.
Test plans. Exit gates.
Architectural design.
Low level design.
Coding standards
User interface approvals.
Planning phase Construction phase
-
8/10/2019 Cpm & Pert Excercises - Bu
50/211
Characteristics of project life cycle Projects vary in size and complexity.
No matter, how large or small, simple or complex, allprojects can be mapped to the following life cyclestructure:
Starting the project. Out put: charter. Organizing and preparing. Out put: project mgt
plan.
Carrying out the project work. Out put: accepted
deliverables Closing the project. Out put: archived
project documents.
-
8/10/2019 Cpm & Pert Excercises - Bu
51/211
Characteristics of project life cycle
A DELIVERABLE IS A MEASURABLE, VERIFIABLEWORK PRODUCT, SUCH AS A SPECIFICATION,FEASIBILITY STUDY REPORT, DETAILED DESIGNDOCUMENT, OR WORKING PROTOTYPE.
-
8/10/2019 Cpm & Pert Excercises - Bu
52/211
Characteristics of project life cycle
Entry criteria & exit criteria (kill points).
Each phase contains all the five process groups.
If project has five phases, the closing is done sixtimes.
-
8/10/2019 Cpm & Pert Excercises - Bu
53/211
Characteristics of project life cycle
Life cycle is from start to end.
All projects have a purpose or objective, but in thosecases where the objective is a service or result,there may be life cycle for the service or result, not aproduct life cycle.
-
8/10/2019 Cpm & Pert Excercises - Bu
54/211
Phase to phase relationships.
Sequential relationship:
A phase can only start once the previous phase iscomplete.
Step by step approach reduces uncertainty, but
may eliminate options for reducing the schedule.
Over lapping relationship:
A phase can start, prior to the completion of theprevious one. Fast tracking. Reduces theschedule, quality may be the victim.
-
8/10/2019 Cpm & Pert Excercises - Bu
55/211
Phase to phase relationships.
Iterative relationship.
Is used where one phase is planned at any givenpoint of time and the planning for the next iscarried out as the work progresses on the current
phase and deliverables.
This is useful in largely undefined, uncertain , orrapidly changing environment, such as research.
-
8/10/2019 Cpm & Pert Excercises - Bu
56/211
High
LowProject Life Cycle (Time)
Cost to make change, and
Amount of stake
Influence of Stakeholders,Opportunity to add Value, andUncertainty of success
PROJECT MANAGEMENT
Project Cost and staffing levels
-
8/10/2019 Cpm & Pert Excercises - Bu
57/211
Project Cost and staffing levels
-
8/10/2019 Cpm & Pert Excercises - Bu
58/211
Project Management Life Cycle describes whatwe need to deliver in order to
successfully manage, integrate the
project life cycle deliverables tomeet customer expectations.
Project management life cycle include:
Initiating, Planning, Executing, Controlling, and Closingprocess groups. Process groups are also known as
project life cycle phases
PROJECT MANAGEMENTLIFE CYCLE
-
8/10/2019 Cpm & Pert Excercises - Bu
59/211
A stakeholder is someonewhose interests may bepositively or negatively
impacted by the project.
They may also include thosewho may exert influenceover the project but wouldnot otherwise be consideredstakeholders.
Performanceorganization
Proj. Team
sponsor
Projectmgmt team
Proj.
Mgr
STAKE HOLDES INFLUENCE ON PROJECT
Sponsor is a person orgroup that provides thefinancial resources, in
cash or kind, for theproject
Project managementteam are the membersof the project team whoare directly involved inthe project managementactivities
Project manager isresponsible to:
1. Accomplish project objectives,2. Identify & quantify risks,
response to the uncertainties, &
control risks during execution3. Continuously utilize
progressive elaborationtechnique throughout theproject life cycle,
4. Adhere to code of professional
conduct
-
8/10/2019 Cpm & Pert Excercises - Bu
60/211
Values, norms, beliefs, & expectations
Policies & Procedures,
View of Authority relationships Work ethic & Work hours
Organizationculture
Performanceof
work
7. Organization culture & style influences project
Project Management knowledge areas
-
8/10/2019 Cpm & Pert Excercises - Bu
61/211
Supports the variouselements of the project
mgmt, which areidentified, defined,
combined & coordinated
To ensure that the projectincludes all the work
required, and only work tocomplete the project
successfully
To ensure timelycompletion of project
Planning, controlling, &
managing costs so thatproject is completedwithin the approved
budget
To ensure that the projectwill satisfy the NEEDS forwhich it was undertaken
To make the mosteffective use of the peopleinvolved with the project
To ensure timely andappropriate generation,
collection, dissemination,storage & disposition of
project information
Concerned withidentifying, analyzing, and
responding to projectrisks
To acquire material, goodsand services from outsidethe performingorganization
Project Scope mgmt
Project Time mgmt
Project Quality mgmt
Project H.R mgmt
Project Risk mgmt
Project Procurement mgmt
Project Management knowledge areas
Project Cost mgmt Project Comm. mgmtProject Integration mgmt
Project Management knowledge areas
-
8/10/2019 Cpm & Pert Excercises - Bu
62/211
Develop project charter
Develop project mgt plan
Direct & manage project execution
Monitor & control
Perform intergated change control
Close project /phase
Collect requirements
Define scope
Create WBS
Verify scope
Control scope
Define activities
Sequence activities
Estimate activity resources
Estimate activity durations
Develop schedule
Control schedule
Estimate costs
Determine budget
Control costs
Plan Quality
Perform Quality assurance
Perform quality control
Develop Human resourceplan
Acquire project team
Develop project team
Manage project team
Identify stakeholders
Plan communications
Distribute information
Manage stakeholder expecations
Report Performance
Plan risk management
Identify risks
Perform qualitative risk analysis
Perform quantitative risk analysis
Plan risk responses
Monitor and control risks
Plan procurementsConduct procurements
Administer procurements
Close procurements
Project Scope mgmt
Project Time mgmt
Project Quality mgmt
Project H.R mgmt
Project Risk mgmt
Project Procurement mgmt
Project Management knowledge areas
Project Cost mgmt Project Comm. mgmtProject Integration mgmt
-
8/10/2019 Cpm & Pert Excercises - Bu
63/211
Introduction toProject Management
Processes
Project management
-
8/10/2019 Cpm & Pert Excercises - Bu
64/211
Project managementprocesses
Project Integration Management:-
Develop project charter:- is the process ofdeveloping a document that formally authorizes aproject or a phase and documenting initial
requirements that satisfy the stakeholders needsand expectations.
Develop project management plan:- is the process ofdocumenting the actions necessary to define,prepare, integrate, and coordinate all subsidiaryplans.
Direct and manage project execution:- is the processof performing the work defined in the projectmanagement plan to achieve project objectives.
Project management
-
8/10/2019 Cpm & Pert Excercises - Bu
65/211
Project management Monitor and control project work:- is the process of
tracking , reviewing, and regulating, the progress tomeet the performance objectives defined in theproject management plan.
Perform integrated change control :- is the processof reviewing all change requests, approvingchanges, and managing changes to the deliverables,organizational process assets, project documents,and the project plan.
Close project or phase: is the process of finalizing
all activities across all of the project managementprocess groups to formally to complete the projector phase.
Project scope mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
66/211
Project scope mgt Collect requirements:- is the process of defining and
documenting stake holders needs to meet the
project objectives. Define scope:- is the process of developing a
detailed description of the project and product.
Create WBS:- is the process of subdividing projectdeliverables and project work into smaller, moremanageable components.
Verify scope:- is the process of formalizingacceptance of the completed project deliverables.
Control scope:- Is the process of monitoring thestatus of the project and product scope and
managing changes to the scope base line
Project time mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
67/211
Project time mgt Define activities:- is the process of identifying the
specific actions to be performed to produce theproject deliverables.
Sequence activities:- is the process of identifyingand documenting relationships among the projectactivities.
Estimate activity resources:- is the process ofestimating the type and quantities of material,people, equipment, or supplies, required to performeach activity.
Estimate activity durations:- is the process ofapproximating the no of work periods needed tocomplete individual activities with estimatedresources.
P j t ti t
-
8/10/2019 Cpm & Pert Excercises - Bu
68/211
Project time mgt Develop schedule:- is the process of analyzing
activity sequences, durations, resourcerequirements, and schedule constraints to create athe project schedule.
Control schedule:- is the process of monitoring the
status of the project to update project progress andmanaging changes to the schedule base line.
P j t t t
-
8/10/2019 Cpm & Pert Excercises - Bu
69/211
Project cost mgt Estimate costs:- is the process of developing an
approximation of monitory resources needed tocomplete project activities.
Determine budget:- is the process of aggregating the
estimated costs of individual activities or workpackages to establish an authorized cost base line.
Control costs:- is the process of monitoring the
status of the project to update the project budgetand managing changes to the cost base line.
Project quality mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
70/211
Project quality mgt Plan quality:- is the process of identifying quality
requirements and / or standards for the project andproduct, and documenting how the project willdemonstrate compliance.
Perform quality assurance:- is the process ofauditing the quality requirements and results fromquality control measurements to ensure appropriatequality standards and operational definitions areused.
Perform quality control:- is the process ofmonitoring and recording results of executing thequality activities to assess performance andrecommend necessary changes.
Project HR mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
71/211
Develop human resource plan :- is the process ofidentifying and documenting project roles,
responsibilities, required skills, reportingrelationships, and creating a staffing managementplan.
Acquire project team:- is the process of confirming
human resources availability and obtaining the teamnecessary to complete the project assignments.
Develop project team:- is the process of improvingthe competencies, team interactions, and the overallteam environment to enhance project performance.
Manage project team:- is the process of trackingteam member performance, providing feed back,resolving issues, and managing changes, tooptimize project performance.
Project communication mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
72/211
Project communication mgt Identify stakeholders:- is the process of identifying
all people, or organizations, impacted by the project,
and documenting relevant information regardingtheir interest, involvement, and impact on the projectsuccess.
Plan communications:- is the process of determining
the project stakeholders information needs anddefining a communication approach.
Distribute information:- is the process of makingrelevant information available to project stake
holders as planned. Manage stakeholder expectation:- is the process of
communicating and working with stakeholders tomeet their needs and addressing issues as they
occur.
-
8/10/2019 Cpm & Pert Excercises - Bu
73/211
Project communication mgt
Report performance:-
Is the process of collecting and distributingperformance information, including status reports,
progress measurements, and forecasts.
Project risk mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
74/211
Project risk mgt Plan risk management:- is the process of defining
how to conduct risk management activities for aproject.
Identify risks:- is the process of determining whichrisk may affect the project and document their
characteristics. Perform qualitative risk analysis :- is the process of
prioritizing risks, for further analysis or action byassessing and combining their probability and
impact. Perform quantitative risk analysis: - is the process of
numerically analyzing the effect identified risks onover all project objectives.
Project risk mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
75/211
Project risk mgt
Plan risk responses:- is the process of developing
options and actions to enhance opportunities andreduce threats to project objectives.
Monitor and control risks:- is the process of
implementing risk response plans, trackingidentified risks, monitoring residual risks, identifyingnew risks, and evaluating risk process effectivenessthrough out the project.
Project procurement mgt
-
8/10/2019 Cpm & Pert Excercises - Bu
76/211
Project procurement mgt
Plan procurement:- is the process of documentingproject purchasing decisions, specifying theapproach , and identifying potential sellers.
Conduct procurements :- is the process of obtainingsellers responses, selecting a seller, and awarding acontract.
Administer procurements :- is the process of
managing procurement relationships, monitoringcontract performance, and making changes andcorrections as needed.
Close procurements:- is the process completing
each project procurement.
PROJECT MANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
77/211
PROJECT MANAGEMENTPROCESS GROUPS
INITIATION. PLANNING.
EXECUTING.
MONITORING & CONTROLLING.
CLOSING.
Project management process groups are not projectphases.
Each phase will have these five process groups.
-
8/10/2019 Cpm & Pert Excercises - Bu
78/211
inputs outputs
PROCESS
tools &
techniques
information monitorplan
control
Project Management Process Groups
-
8/10/2019 Cpm & Pert Excercises - Bu
79/211
j g p
Initiation process group
-
8/10/2019 Cpm & Pert Excercises - Bu
80/211
DevelopProjectCharter
Identify stakeHolders.
p g p
Projectobjective
+40%ROI
Sponsor
Projectmgr.
Projectstake-holders
Planning process group
-
8/10/2019 Cpm & Pert Excercises - Bu
81/211
g p g p
Execution process group
-
8/10/2019 Cpm & Pert Excercises - Bu
82/211
Time
Controlling process group
-
8/10/2019 Cpm & Pert Excercises - Bu
83/211
Closing process group
-
8/10/2019 Cpm & Pert Excercises - Bu
84/211
g p g p
Interaction between
-
8/10/2019 Cpm & Pert Excercises - Bu
85/211
InitiatingProcess
PlanningProcess
ExecutingProcess
Closing
ProcessControllingProcess
Phase
Start PhaseFinishtime
Activities
Project mgmt. process groups
-
8/10/2019 Cpm & Pert Excercises - Bu
86/211
LINKS IN PROCESS GROUPS
-
8/10/2019 Cpm & Pert Excercises - Bu
87/211
PROJECT MANAGEMENT
Project Management Office :
A PMO is an organizational unit to centralize andcoordinate the management of projects under itsdomain.
PMO
-
8/10/2019 Cpm & Pert Excercises - Bu
88/211
PMO
The responsibilities of PMO, can range fromproviding project management support functions toactually being responsible for the directmanagement of a project.
A primary function of a PMO is to support projectmanagers in a variety of ways which may include,but are not limited to:
Managing shared resources across all projects. Identifying and developing project management
methodology, best practices, and standards.
PMO
-
8/10/2019 Cpm & Pert Excercises - Bu
89/211
PMO
Coaching, mentoring, training and oversight.
Monitoring compliance with project managementstandards policies, procedures, and templates via
project audits.
Developing and managing project policies,procedures, templates, and other shareddocumentation.
Coordinating communication across projects.
KNOWLEDGE AREAS TO PROCESSESKnowledge Initiatio Planning Executing Monitoring Closing
-
8/10/2019 Cpm & Pert Excercises - Bu
90/211
Knowledge
areas
Initiatio
n
Process
group
Planning
Process
group
Executing
Process
group
Monitoring
&
controlling
Process
group
Closing
Process
group
4.Project
Management
Integration
4.1Devel
op
Project
Charter.
4.2 Develop
Project
Management
plan.
4.3 Direct
& Manage
Project
execution
4.4 Monitor
& control
Project
work4.5
Perform
Integrated
Change
control
4.5 Close
project or
Phase.
5. Project
scope
management.
5.1 Collect
requirements.
5.2 Define
Scope.
5.3 Create
WBS
5.4 Verify
Scope.
5.5 Control
Scope.
6. ProjectTime
Management
6.1 Defineactivities.
6.2 Sequence
Activities.
6.3 Estimate
Activity
Resources.
6.4 Estimate
activity
durations.
6.5 Develop
Schedule.
6.6 Controlschedule
7. ProjectCost
Management.
7.1 EstimateCosts.
7.2 Determine
Budget.
7.3 ControlCosts.
8.Project
Quality
Management
8.1 Plan
Quality.
8.2
Perform
Quality
assurance.
8.3
Perform
Quality
Control
9. Project
Human
Resource
Management.
9.1 Develop
Human
resource plan.
9.2 Acquire
Project
Team.
9.3Develop
Project
Team
9.4 Manage
KNOWLEDGE AREAS TO PROCESSES
-
8/10/2019 Cpm & Pert Excercises - Bu
91/211
KNOWLEDGE AREAS TO PROCESSES10. Project
Communicati
on
Management
10.1
Identif
y
Stakeholder
s.
10.2 Plan
Communicatio
ns
10.3
Distribute
Information
.10.4
Manage
Stake
holder
Expectation
s.
10.5 Report
Performanc
e
11. Project
Risk
Management.
11.1 Plan Risk
Management.
11.2 IdentifyRisks.
11.3 Perform
Qualitative
Risk Analysis.
11.4 Perform
Quantitative
Risk Analysis.
11.5 Plan Risk
Responses.
11.6
Monitor
and ControlRisks.
12. Project
Procurement
Management.
12.1 Plan
procurements.
12.2
Conduct
procuremen
ts
12.3
Administer
procuremen
ts
12.4 Close
Procuremen
ts.
2 20 8 10 2
Total = 42 processes.
Process group
-
8/10/2019 Cpm & Pert Excercises - Bu
92/211
1. Initiation process group: 2 processes2. Planning process group: 20 processes3. Execution process group:
8processes
4. Controlling process group: 10 processes5. Closing process group: 2 processes
TOTAL PROJECT MGMT. PROCESSES 42
g pbreak up
-
8/10/2019 Cpm & Pert Excercises - Bu
93/211
Chief Executive
Functionalmanager
Functionalmanager
Functionalmanager
staff
staff
staff
staff
staff
staff
staff
staff
staff
Chief Executive
Functionalmanager
Functionalmanager
Functionalmanager
staff
staff
staff
staff
staff
staff
staff
staff
staff
Chief Executive
Functionalmanager
Functionalmanager
Functionalmanager
staff
staff
staff
staff
staff
staff
staff
staff
P.Mgr
Function organization Weak Matrix Org.
Balanced Matrix Org.
People havethe loyalty
towards theirfunctionmanager & notto the projects
People splitfocus between
project andfunctionalresponsibilitiesin weak matrix
In balancedmatrix, the
power isbalancedbetween PMs &functional mgrs
Organization culture & style influences project
-
8/10/2019 Cpm & Pert Excercises - Bu
94/211
Chief Executive
Functionalmanager
Functionalmanager
Functionalmanager
staff
staff
staff
staff
staff
staff
staff
staff
staff
Projecthead
P.Mgr
P.Mgr
P.Mgr Strong matrix organization
Projectized organization
Chief Executive
Projectmanager
Projectmanager
staff
staff
staff
staff
staff
staff
Projectmanager
staff
staff
staff
In strong
matrix, thepower isbalanced restswith the projectmanagers
In projectized
organizationpeople develoployalty to theproject & not toa function mgr.
Organization culture & style influences project
Composite Organization
-
8/10/2019 Cpm & Pert Excercises - Bu
95/211
Project Roles
-
8/10/2019 Cpm & Pert Excercises - Bu
96/211
j Project Manager:
Is the person ultimately responsible for the outcome of the project.
Found in balanced, strong matrix and projectized organization.
Project coordinator: Is weaker than project manager, may not be allowed to make
budget decisions or over all project decisions, but may have someauthority to reassign resources.
Usually found in weak matrix or functional organizations
Project expeditor: Is the weakest among the project roles. Is staff assistant who has little or no formal authority. Reports to the executive who ultimately has responsibility of the
project. Responsibility lies in making sure that things arrive in time and thetasks are completed on time.
Part time role --- found in functional organizations.
Project Selection Methods
-
8/10/2019 Cpm & Pert Excercises - Bu
97/211
Project Selection Methods
Benefit Measuring Methods:
BCR
Pay Back Period
Discounted Cash Flow
IRR
ROI
Economic Value Added Method
PROJECT SELECTION
-
8/10/2019 Cpm & Pert Excercises - Bu
98/211
METHODS
Mathematical methods: Constrained optimization methodslinear, dynamic,
integer, non linear, and/or multi objective programming.
Benefit measuring methods:
Benefit cost ratio: is the ratio of benefits to costs.
For example: if you expect a construction project to cost$10 million and you expect to be able to sell that completedbuilding for $15 million, then your BCR is 1.5
SCORING MODEL
-
8/10/2019 Cpm & Pert Excercises - Bu
99/211
SCORING MODEL
SCORING MODEL:
criteria weight proj-A proj-B proj-C
profit potential 5 5 5 3marketability 3 4 3 4
ease to produce 1 4 3 2
weighted score 41 37 29
project -A is the obvious choice.
PAY BACK PERIOD
-
8/10/2019 Cpm & Pert Excercises - Bu
100/211
PAY BACK PERIOD EXAMPLE: say initial investment on a project is
$200,000, with expected cash inflows of $25,000 perquarter for the first two years and $ 50,000 perquarter then on. What is the pay back period?
Initial investment=$200,000.
Cash inflows=($25,000)*(4) /year.=$100,000.
Pay back period = initial investment/ cash inflow peryear.=($200,000)/($100,000)=2 years.
Pay back period does not consider time value ofmoney-- serious draw back.
DISCOUNTED CASH FLOWS
-
8/10/2019 Cpm & Pert Excercises - Bu
101/211
DISCOUNTED CASH FLOWS
FV= future value of money.
PV= present value of money.
i=interest rate. n= no of years.
PV=FV/(1+i)^n.
Rs1,three years from now is worth
1/(1+0.09)^3=1/(1.09)^3=1/1.29=0.77 Rs.
NET PRESENT VALUE
-
8/10/2019 Cpm & Pert Excercises - Bu
102/211
NET PRESENT VALUE With NPV, you bring the value of the future money
into todays dollars.
12% is cost of capital.
Project A:
Year. inflows. P V
1 10,000 8,929 2 15,000 11,958 3 5,000 3,559 Total 30,000 24,446
Less investment 24,000 NPV 446
-
8/10/2019 Cpm & Pert Excercises - Bu
103/211
NET PRESENT VALUE
Project B: Year inflows PV
1 7,000 6,250
2 13,000 10,364
3 10,000 7,118
Total 30,000 23,732
Less investment 24,000
NPV
NET PRESENT VALUE
-
8/10/2019 Cpm & Pert Excercises - Bu
104/211
Project A has NPV greater than zero and should beaccepted.
Project B has NPV less than zero and should berejected.
When NPV >0 means that the project will earn at
least or greater than the cost of capital.
-
8/10/2019 Cpm & Pert Excercises - Bu
105/211
DISCOUNTED CASH FLOWS Project A is expected to make $100,000 in two years. Project B is expected to make $120,000 in three
years.
If the rate interest is 12%, which should you
choose?. Using the PV formula:
The PV of project A=$79,719.
The PV of project B=$85,414.
The project B is the project that will return highestinvestment to the company and should be chosenover Project A.
INTERNAL RATE OF RETURN
-
8/10/2019 Cpm & Pert Excercises - Bu
106/211
INTERNAL RATE OF RETURN
IRR is the discount rate when the PV of the cashinflows equals original investment.
For the exam, you need three things concerning IRR:
IRR is the discount rate when NPV=0
IRR assumes the cash inflows are reinvested at theIRR.
You should choose project with highest IRR value.
-
8/10/2019 Cpm & Pert Excercises - Bu
107/211
RETURN ON INVESTMENT
Is a % that shows what return you make by makingin something.
Ex: a company invests in a project that costs$200,000. The benefits of doing the project save the
company $230,000 in the first year alone.
ROI = (benefit-cost)/cost=30,000/200,000
15%.
For the exam: ROI , bigger is better.
BEP
-
8/10/2019 Cpm & Pert Excercises - Bu
108/211
BREAK EVEN POINT: BEP analysis is done for a predefined for future time
periods ( years, months, or weeks ).
It evaluates the time period when total cash inflowequals fixed cost.
If calculated BEP value is less than expected value,investment is considered justified.
BEP
-
8/10/2019 Cpm & Pert Excercises - Bu
109/211
A club is planning a dance party for its members.
The tickets will be sold for $30 each. Fixed costs (band & hire hall etc, ) $1500.
The variable costs (food etc, ) will be $10, for each
ticket sold.
(x)*(30)= (x)*(10)+1500.
X=75
no of tickets to be sold for BEP.
Economic value add (EVA)
-
8/10/2019 Cpm & Pert Excercises - Bu
110/211
It takes into account the fact that there are opportunity costs toevery financial expenditure, and that if a project does not makemore money than those opportunity costs, it has not trulyadded economic value to the organization.
A company XYZ, invested $175,000 in a project, and that projectreturned a net profit of $10,000 in the first year operation.
Assume cost of capital 6%.
If the organization could have put the same $175,000 in thebank and earned 6% return.
$10,000-(06*175,000)=-$500.
$ 10,000-10,500 = -$500.
They would have earned $10,500 in interest if they had investedin the bank, instead of project.
Project Management
-
8/10/2019 Cpm & Pert Excercises - Bu
111/211
Project Management
Charter.
Scope Statement.
Work Break Down Structure.
Project Scope Management
-
8/10/2019 Cpm & Pert Excercises - Bu
112/211
j p g Manages the work involved in the project.
Understand requirements.
Define the scope.
Break down the scope in the form of WBS. Control the scope of the project.
Verify that the project is completed correctly.
Scope Management Processes
-
8/10/2019 Cpm & Pert Excercises - Bu
113/211
p g
Collect requirements:-
This is the process of understanding what is needed tosatisfy the stakeholders and creating a document to reflectthat understanding, for both product and the project.
Deliverables :-
Requirements documentation.
The root business problem being solved.
The source of the requirements.
The way each requirement addresses the problem.
How business processes interact with the requirements.Associated measurements for each requirement.
Business, legal, ethical compliance.
Constraints and assumptions.
Anticipated impact of the requirement on other.
Scope Management Processes
-
8/10/2019 Cpm & Pert Excercises - Bu
114/211
g
Requirements management plan:
Defines what activities the team will perform to gather andmanage project requirements.
Shows how requirements will be gathered, how decisionswill be made, how changes to the requirements will behandled, and how the requirements will be documented.
Requirements trace ability matrix:
It is important to identify the source of the requirement.
The source could originate from a stake holder or
departmental request, a legal, contractual, or ethical need,an underlying requirement.
Who owns the requirement so that it is fulfilled.
Status of the requirements.
Define scope
-
8/10/2019 Cpm & Pert Excercises - Bu
115/211
p
.
Product analysis.
Product breakdown.
System analysis.
Requirement analysis.
System engineering.
Value engineering.
Define scope
-
8/10/2019 Cpm & Pert Excercises - Bu
116/211
Define scope
Alternatives identification:
Brainstorming.
Lateral thinking. (Shift in paradigm)
-
8/10/2019 Cpm & Pert Excercises - Bu
117/211
-
8/10/2019 Cpm & Pert Excercises - Bu
118/211
-
8/10/2019 Cpm & Pert Excercises - Bu
119/211
Scope Management Processes
-
8/10/2019 Cpm & Pert Excercises - Bu
120/211
Define scope:
Defines the total work and only the work to be executed bythe project team , so that all the requirements of the projectare fulfilled and the final deliverable is created.
Scope of the project. Scope of the product.
The scope statement.
Product scope description, product acceptance criteria, projectdeliverables, project exclusions, project constraints, projectassumptions.
Scope Management Processes
-
8/10/2019 Cpm & Pert Excercises - Bu
121/211
Create WBS:- Is the process of subdividing project deliverables and project work
into smaller, more manageable components.
Is deliverable oriented hierarchical decomposition of the work tobe executed by the project team, to accomplish the projectobjectives and create the required deliverables.
Each descending level of the wbs, representing an increasinglydetailed definition of the project work.
Organizes and defines the total scope of the project. Planned work is contained within the lowest level WBS component
, which are called work packages.
A work package can be scheduled, cost estimated, monitored andcontrolled.
Work packages contain the deliverables, i.e the result of the effortand not the effort it self.
Travel Abroad
Create WBSFirst we need to organize project work
-
8/10/2019 Cpm & Pert Excercises - Bu
122/211
Passport Visa Ticketing &Boarding
GetPassport
ObtainPolice
verification
Apply forPassport
SubmitApplication
Form
GetApplication
Form
FillApplication
Form
Travel Abroad
Passport
Apply forPassport
Work Breakdown Structureorganizes and defines the
total scope of the project
WBS subdivides the project deliverables into smaller, moremanageable deliverables, with each descending level of WBSrepresenting an increasingly detailed definition of the projectwork. Lowest level of WBS components or deliverables are
called work packages.
WPs can be scheduled, cost estimated,monitored, & controlled
-
8/10/2019 Cpm & Pert Excercises - Bu
123/211
Identify stake holders.
The process of identifying all people or organizationsimpacted by the project, and documenting relevantinformation regarding their interests, involvement,
and impact on project success.
Identify stake holders.
-
8/10/2019 Cpm & Pert Excercises - Bu
124/211
What it is?
Keep in mind that a stakeholder may be any one with aninterest in the project.
And that interest may be positive or negative.
Why it is important?.
If the stakeholders are not properly identified on the projectand their needs are understood, then there is little chance ofmeeting their expectations.
Many projects are derailed because they did not understand
the needs of stakeholders and address them on the project.
Identify stakeholders
-
8/10/2019 Cpm & Pert Excercises - Bu
125/211
de t y sta e o de s
power
high
Interest. high
low
low
Manage
closely.Keep
satisfied.
Monitor(mini
mum effort).
Keep
informe
d.
Stake holder analysis
tool.
Scope Management Processes
-
8/10/2019 Cpm & Pert Excercises - Bu
126/211
Group Exercise:-
Using Mind Map & M.S.Words
Create a WBS for wedding ceremony.
Create a WBS for a house construction.
Create a WBS for cycle.
Stake holder analysis of these projects?
VERIFY SCOPE.
-
8/10/2019 Cpm & Pert Excercises - Bu
127/211
Verifying the project scope includes reviewingdeliverables with the customer or sponsor, to ensurethat they are completed satisfactorily and obtainingformal acceptance of deliverables by the customer
or sponsor.
VERIFY SCOPE
-
8/10/2019 Cpm & Pert Excercises - Bu
128/211
If the project is terminated early, the project scopeverification process should establish and documentthe level and extent of completion.
Control Scope
-
8/10/2019 Cpm & Pert Excercises - Bu
129/211
Control scope:
Is the process of monitoring the status of the project
and product scope and managing changes to thescope base line.
It ensures all requested changes and recommended
corrective or preventive actions are processedthrough the perform integrated change controlprocess.
Control Scope.
-
8/10/2019 Cpm & Pert Excercises - Bu
130/211
Is also used to manage actual changes when theyoccur and is integrated with other change controlprocesses.
Uncontrolled changes are termed as Scope Creep:
Avoid scope creeps.
PROJECT TIME MANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
131/211
PROJECT TIME MANAGEMENT
INCLUDES THE PROCESSES
REQUIRED TO ACCOMPLISH TIMELYCOMPLETION OF THE PROJECT.
PROJECT TIME MANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
132/211
PROJECT TIME MANAGEMENT
Fundamentals:
ACTIVITY ON ARROW DIAGRAM (AOA)/ADM.Dummy activity. Finish to start relationship.
ACTIVITY ON NODE DIAGRAM(AON)/PDM.
FS, SS, FF & SF RELATIONSHIPS Lead & lag between activities. Early start, early finish & late start, late finish Float , free float, critical path.
Forward pass and back ward pass. Project float. Crashing and fast tracking.
ESTIMATIONS
-
8/10/2019 Cpm & Pert Excercises - Bu
133/211
Analogous estimation:
top down estimate. It is a form of expert judgment.
Parametric estimating / Quantitative method : it uses a mathematical model to calculate projected
times for an activity based on historical records fromprevious projects. Such as time per line of code,time per linear meter or time per installation.
Learning curve: the 100throom painted will take less time than the
first room because of improved efficiency.
Project Time Management
-
8/10/2019 Cpm & Pert Excercises - Bu
134/211
Define activities:-
The process of identifying the specific actions to beperformed to produce the project deliverables.
Sequence activities:-
The process of identifying and documentingrelationships among the project activities.
Estimate activity resources:-
The process of estimating the type, and quantities ofmaterial, people, equipment, or supplies, required toperform each activity.
Project Time Management
-
8/10/2019 Cpm & Pert Excercises - Bu
135/211
Estimate activity durations:-
The process of approximating the number of workperiods needed to complete individual activities withthe estimated resources.
Develop schedule:-
The process of analyzing activity sequences,durations, resource requirements, and scheduleconstraints to create the project schedule.
Control schedule:-
The process of monitoring the status, of the projectto update the project progress, and managingchanges to the schedule base line.
Scheduling Techniques
-
8/10/2019 Cpm & Pert Excercises - Bu
136/211
Activity on arrow (AOA) also known as ADP( arrowdiagramming method).
Activity on Node (AON) also known as PDM (predecessor diagramming method).
CPM & PERT.
CPM-EXERCISE-1
-
8/10/2019 Cpm & Pert Excercises - Bu
137/211
Sl.no act dur pred.
1.Estimate cost to complete project. 7 d ---- 2.Bid job& get order. 15 d 1
3.Build system 7d 2 4.Dev-training 4d 2 5.Implement. 5d 3,4 Find critical path, float/slack, free float/free
slack for each activity.
CPMEXERCISE-2
-
8/10/2019 Cpm & Pert Excercises - Bu
138/211
SL. NO. ACTIVITY. DUR. PRED.
1 A 2 DAYS.
2 B 6 DAYS. 1
3 C 8 DAYS. 1
4 D 4 DAYS. 2,3
FIND CRITICAL PATH . FLOATS. , OF ALLACTIVITIES.
CPM-3
-
8/10/2019 Cpm & Pert Excercises - Bu
139/211
SL Activity Dur(Hrs) Pred.
A Remove & dis mantle motar. 8 ----
B. Clean & Paint frame. 7 A.
C. Rewind armature. 12 A.
D. Replace armature. 9 A.
E. Assemble & Install
Motar. 4 B,C,D
Calculate the total time of the ovehaul.
CPM-Exercise.
-
8/10/2019 Cpm & Pert Excercises - Bu
140/211
Sl no activity dur pred.
1 Get equipment. 5 d 2. hire people. 4 d 3. develop system. 15 d 1,2
4. training. 3 d 3 5. documentation. 6 d 3 6. install system. 9 d 4,5
Find critical path. What are floats for each activity?.
CPMEXERCISE-3
-
8/10/2019 Cpm & Pert Excercises - Bu
141/211
Sl no. Act dur pred.
1. project dels 12 d ----
2.procure h/w 2 1
3.test h/w 8 2
4.procure s/w tools. 10 1
5.write programs 45 4
6.test & debug 22 5
7.install 8 3,6
8.training 3 7
9.acceptance 1 8.
Find critical path, float/slack, free float/free slack foreach activity.
CPM-EXERCISEHOUSECONSTRUCTION.
-
8/10/2019 Cpm & Pert Excercises - Bu
142/211
CONSTRUCTION. Sl.no activity duration pred
1 lay foundation 3w nil 2 erect frame 4w 1 3 install mill works 3w 2
4 install wiring 1w 2 5 install plumbing 1w 2 6 plaster walls 4w 2 7 decorate interior 1w 3,4,5,6 8 install siding 3w 2 9 finish exterior 4w 8 10 finish 0 7,9
CPM EXERCISE-6
-
8/10/2019 Cpm & Pert Excercises - Bu
143/211
Sl no act dur pred
1 specs 15d nil
2 design data base part. 45d 1
3 design GUI part. 30d 1 4 code data base part. 105d 2
5 code GUI part. 45d 3
6 integrate & test. 120d 4,5
7 write user manual. 60d 1
8 finish. 0d 7,6
CPM
-
8/10/2019 Cpm & Pert Excercises - Bu
144/211
Sl no activity Dur Predecessor.
1 Remove & Dismantle motar. 8hrs ------
2 Clean & paint frame. 7hrs 1
3 Rewind armature. 12 hrs 1
4 Replace bearing. 9 hrs 1 5 Assemble & Install motar. 4 hrs 2,3,4
CRASHING Sl no activity duration pred
-
8/10/2019 Cpm & Pert Excercises - Bu
145/211
Sl no activity duration pred
A. Get import license. 5 days. ----- B. Ship 7days A
C. Train users. 11days ----
D. Train on system. 2 days B,C.
You have agreed to get the system running in 12 days. If youare late, you will pay penalty $500/day, beyond 12 days.
Options for activity B :
Slow boat: 7days. (current option). $100.
Fast boat: 6days. $300.
Air plane: 5days. $400.
CRASHINGTask Pred Nor Crash Crashing cost/day
-
8/10/2019 Cpm & Pert Excercises - Bu
146/211
Task Pred Normaldur
Crashtime
Crashing cost/day
1 A 3 1 4$/D
2 B 1 7 3 1$/D
3 C 1 4 2 4$/D
4 D 3 5 2 2$/D
5 E 2,4 0 0 COST OF OVERHEAD$4.5/D
CPM-7
A small engineering company intends to produce a batch of machines
-
8/10/2019 Cpm & Pert Excercises - Bu
147/211
to be used by a shoe manufacturer in the mass production of shoes.
The activities required in the design and manufactures of themachines are
listed below: A. Draw up estimate. --- 2w. B. Agree estimate. A 1w. C. Purchase internal m/c. B. 4w.
D. Prepare design drawings. B. 6w. E. Construct main frame. D. 3w. F. Assemble machinery. C,E 3w. G. Test machinery. F 4w. H. Determine model type. D 2w. I. Design outer casing. D 3w.
J. Construct outer casing. H,I, 8w. K. Final assy. G,J, 2w. L. Final check. K. 2w.
Find duration of the project. What would be the effect of strike at the factory supplying the internal
machinery, there by delaying its delivery by 4 weeks?
PERT FORMULA. Pert duration: p+(4)*(M)+0 divided by 6
-
8/10/2019 Cpm & Pert Excercises - Bu
148/211
Pert duration: p+(4) (M)+0 divided by 6.
Standard deviation of an activity of
an activity=(p-o)/6.= s.d.
Variance of an activity = (s.d) squared.
Confidence = NORMDIST(D, PERT TIME, SD, TRUE ).Duration needed at a confidence level = NORMINV
(PROB, PERT DUR, SD ).
PERTEXERCISE-1
-
8/10/2019 Cpm & Pert Excercises - Bu
149/211
SL.NO pred O M P 1 ESTIMATE 5 7 15
2 BID 1 10 15 25
3 BUILD 2 4 7 10
4 TRAIN 2 4 4 4
5 IMPLEMET. 3,4 3 5 10
Find PERT duration of the project.
Probability of completing the project?
PERTEXERCISE- 2
-
8/10/2019 Cpm & Pert Excercises - Bu
150/211
Sl no Activity OMP Pred. pert dur
1 A 2 4 6 nil 4 2 B 5 13 15 1 12
3 C 13 18 35 2 20
PERTEXERCISE- 2
-
8/10/2019 Cpm & Pert Excercises - Bu
151/211
Project PERT duration :36 days.
Project std dev:4.08
36+/- 1 std dev=36+/-4.08=40.08 to 31.92 days.
There is 68% chance (0.68 prob ) of completing the
project in 31.92 to 40.08 days. There is 34% chance (0.34 prob ) of completing the
project in 36 days to 40.08 days.
There is 34% chance (0.34 prob ) of completing the
project in 31.92 days to 36 days.Duration needed at a confidence level = NORMINV
(PROB, PERT DUR, SD )= ((0.34+0.50), 36, 4.08 )
PERTEXERCISE- 2
-
8/10/2019 Cpm & Pert Excercises - Bu
152/211
If two tail statistical table is referred:
68% confidence = 68/2 = 34% confidence for 36 daysto 40.08 days.
34% confidence for 31.92 to 36 days.
So for confidence of 0.34 , z= 1.0
Z= (x- pert dur of project )/ s.d = 1= (x-36)/4.08 , x=40.08 days.
If single tail statistical table is referred:
Add 0.5 to 0.34 i,e 0.84 that corresponds to z valueof 1.0 x=40.08 days.
If excel is used prob =0.84 excel uses single tail
PERTEXERCISE: 3 Sl no Act dur (d) pred
-
8/10/2019 Cpm & Pert Excercises - Bu
153/211
Sl no. Act dur (d) pred. 1. project dels 10- 12 -14 ----
2.procure h/w 2 -2 -2 1 3.test h/w 8 -8 -8 2 4.procure s/w tools. 8 -10 -14 1 5.write programs 38 -45 -57 4 6.test & debug 20-22 -30 5
7.install 5-8-10 3,6 8.training 3-3 -3 7 9.acceptance 1 -1-1 8. Find critical path, float/slack, for each activity. There is 68% chance that write program activity will be
completed in ------ days to -------- days.
Variance of the project? Standard deviation of the project? Project dur=103 days. Variation of project=14.98 s.d= 3.87
PERTEXERCISE: 3
-
8/10/2019 Cpm & Pert Excercises - Bu
154/211
PERT duration of activity write program =
(p+4*m+o)/6 = (38+4*45+57)/6 = 45.83 Standard deviation = (p-o)/6 = (57-38)/6 =3.17
Now we can say:
There is 68% chance that write program activity
will be completed in 42.66 days to 49 days
-
8/10/2019 Cpm & Pert Excercises - Bu
155/211
Monitor & Control Schedule
-
8/10/2019 Cpm & Pert Excercises - Bu
156/211
Tracking:
Set project review date.
Project update.
Show progress line at status date.
Save base line.
Project progress reports.
Critical chain
-
8/10/2019 Cpm & Pert Excercises - Bu
157/211
Critical chain method:
Dr Goldratt.
Managing systems through constraints: TOC
Weakest link is the strongest, because it can breakit.
1. Identify the constraint of the system.
2. Decide how to exploit the constraint of the system.
3. Subordinate every thing else to the decision taken
regarding the constraint. 4. Elevate the constraint.
5. Go back to focusing step-1
Critical chainP j t t i TOC
-
8/10/2019 Cpm & Pert Excercises - Bu
158/211
Project management using TOC:-
Students syndrome --- Law of Murphy.
Law of Parkinson.
Multitasking.
Feeding buffers.
Project buffer.
Critical chain:
In addition to task dependent, is resource dependent
longest path.
RESOURCE LEVELLING
-
8/10/2019 Cpm & Pert Excercises - Bu
159/211
Sl.no activity duration pred Reso. 1 A1 3 D nil. Ram.
2 A2 2 D 1 Lax.
3 B1 2 D nil Lax. 4 B2 2 D 3 Lax.
5 C1 3 D nil Sita.
6 C2 3 D 5 Sita. 7 C3 2 D 2,4,6 Sita.
Project Cost Management Includes processes that make the project completion within
d b d t
-
8/10/2019 Cpm & Pert Excercises - Bu
160/211
approved budget.
Estimate cost:
The process of developing an approximation of the monetaryresources needed to complete project activities.
Determine budget:
The process of aggregating the estimated costs of individualactivities or the work packages to establish an authorized costbase line.
Control costs:
The process of monitoring the status of the project to update
the project budget, and managing changes to the cost baseline.
Earned Value 4-fences. Each fence/day. Rs1000/fence. One fence
-
8/10/2019 Cpm & Pert Excercises - Bu
161/211
after another.
Report at Day-3.
Completed one wall. spent Rs1000.(D-1)
Completed one wall. Spent Rs1200(D-2)
Completed 50%wall.spent Rs600 (D-3)
Pv=1000+1000+1000=3000
Ev=1000+1000+500=2500 Ac=1000+1200+600=2800
Earned Value BAC =Rs4000.
-
8/10/2019 Cpm & Pert Excercises - Bu
162/211
Cost variance = EV-AC=2500-2800=-300
Cost performance index =EV/AC=2500/2800=0.893
Over budget. Getting 89 paise for every rupee.
Schedule variance =EV-PV=2500-3000=-500
Schedule performance index=SPI=2500/3000=0.833
Behind schedule & progressing @83% of the rateoriginally planned.
Exercise - EV Problem
-
8/10/2019 Cpm & Pert Excercises - Bu
163/211
164
The project: 5 software package installs on 5 existingPCs in 5 weeks (1 installation /week ) for a totalconsulting fee of $5,000. After two weeks only 1 installhas been done for a cost of $1,500.
Determine PV, AC, EV.
Calculate SV, CV, SPI, CPI.
Assume the rate of progress continues and calculateEAC .
Exercise Solution
-
8/10/2019 Cpm & Pert Excercises - Bu
164/211
165
Earned Value You have planned for a project to write a software
-
8/10/2019 Cpm & Pert Excercises - Bu
165/211
application to take 1 year. The costs to this project
are budgeted at $12,500 per month.
Six months into the project, you find that softwareapplication is 50% completed, & spent $70,000
Calculate CV, CPI, SV, SPI, VAC.
Earned Value BAC =(12 MONTHS)*($12,500/MONTH)= $150,000
-
8/10/2019 Cpm & Pert Excercises - Bu
166/211
PV=(6MONTHS)*($12,500)/MONTH=$75,000.
EV= SW IS 50% COMPL = $75,000. AC=$70,000
CV=EV-AC=$75,000-$70,000=$5000.
SV=EV-PV=$75,000-$75,000=$0.
CPI=EV/AC=75,000/70,000=1.O7 SPI=EV/PV=75,000/75,000=1
EAC=BAC/CPI=$150,000/1.07=$140,186.91
ETC=EAC-AC=$140,186.91-$70,000=$70,186.91
VAC=BAC-EAC=$150,000-$140,186.91=$9813.09
Earned Value Management
-
8/10/2019 Cpm & Pert Excercises - Bu
167/211
168
EVM
Consider a company that took earned value
-
8/10/2019 Cpm & Pert Excercises - Bu
168/211
Consider a company that took earned value
measurements at monthly intervals for the past threemonths:
EV AC
Month-1 $22,000 $13,700
Month-2 $151,000 $ 137,900
Month-3 $ 107,000 $98,400
CPI cum? At the end of 3-months.
EVM
EV EV AC AC CPI CPI
-
8/10/2019 Cpm & Pert Excercises - Bu
169/211
EV EVc AC ACc CPI CPIc
Month-1, 22000 22000 13,700 13700 1.61 1.61
Month-2, 151000 173000 137,900 151,600 1.09 1.14
Month-3, 107,000 280,000 98,400 250,000 1.09 1.12
PROJECT HUMAN RESOURCE
-
8/10/2019 Cpm & Pert Excercises - Bu
170/211
PROJECT HUMAN RESOURCE
MANAGEMENT
INCLUDES THE PROCESSES THAT ORGANIZE ANDMANAGE THE PROJECT TEAM.
Project human resourceprocesses
Develop human resource plan:
-
8/10/2019 Cpm & Pert Excercises - Bu
171/211
Develop human resource plan:
Identifying, and documenting project roles,responsibilities, and required skills, reportingrelationships, & creating staffing managementplan.
Acquire project team:
Confirming human resource availability and
obtaining the team necessary to complete projectassignments.
.
Project human resourceprocesses
Develop project team:
-
8/10/2019 Cpm & Pert Excercises - Bu
172/211
Develop project team:
The process of improving the competencies, teaminteraction, and the overall team environment to enhanceproject performance.
Manage project team:
The process of tracking team member performance,providing feed back, resolving issues, and managingchanges to optimize project performance
RACI
-
8/10/2019 Cpm & Pert Excercises - Bu
173/211
174
RACI Chart Person
Act iv ity Krishna Ram
Define A R I I I
Design I A R C C
Develop I A R C C
Test A I I R I
Legend: R = Responsible, A = Accountable, C = Consult , I Inform
Sita Karthik Vinay
PROJECT QUALITYMANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
174/211
INCLUDES ALL THE ACTIVITIES OF THEPERFORMING ORGANIZATION THAT DETERMINE
QUALITY POLICIES, OBJECTIVES, ANDRESPONSIBILITES SO THAT THE PROJECT WILLSATISFY THE NEEDS FOR WHICH IT WASUNDERTAKEN.
QUALITY
-
8/10/2019 Cpm & Pert Excercises - Bu
175/211
Quality is the degree to which a set of inherentcharacteristics fulfill requirements.
Stated and implied needs are inputs to developing
project requirements.
QUALITYPlan quality:
-
8/10/2019 Cpm & Pert Excercises - Bu
176/211
The process of identifying quality requirements and how
the project will demonstrate compliance /or standardsfor the project and product, and documenting.
Perform quality assurance:The process of auditing quality requirements and the
results from quality control measurements to ensureappropriate quality standards and appropriateoperational definitions are used.
Perform quality control:
The process of monitoring and recording results ofexecuting the quality activities to assess performanceand recommend necessary changes.
Project communication management
Identify stake holders:
-
8/10/2019 Cpm & Pert Excercises - Bu
177/211
Identify stake holders:
The process of identifying all people, or organizationsimpacted by the project and documenting relevantinformation, regarding their interest, involvement, andimpact on the project success.
Plan communications:The process of determining the project stakeholder
information needs and defining a communication approach.
Distribute information:The process of making relevant information available to the
project stakeholders as planned.
Project communication management
Manage stakeholder expectation:
-
8/10/2019 Cpm & Pert Excercises - Bu
178/211
Manage stakeholder expectation:
The process of communicating and working withstakeholders, to meet their needs and addressing theirissues.
Report performance:
The process of collecting and distributing performanceinformation, including status reports, progressmeasurements, and forecasts.
-
8/10/2019 Cpm & Pert Excercises - Bu
179/211
Project RiskManagement.
-
8/10/2019 Cpm & Pert Excercises - Bu
180/211
probability isthe languageof uncertainty
Risk management is
-
8/10/2019 Cpm & Pert Excercises - Bu
181/211
Risk management isthe means by which
uncertainty issystematic managed
Key word is systematic
Uncertain
Project Risk management
-
8/10/2019 Cpm & Pert Excercises - Bu
182/211
Uncertainevent
or
conditionthat if
occurs
effect on the Project Objectives
Risk
+ ve - vehas
Project Risk Management
Includes the processes of conducting riskt l i id tifi ti l i
-
8/10/2019 Cpm & Pert Excercises - Bu
183/211
management planning, identification, analysis,
response planning, and monitoring and control on aproject.
The objective:
To increase the probability and impact of positive events,and decrease the probability and impact of negative eventsin the project.
Project Risk Management Project risk is always in the future.
-
8/10/2019 Cpm & Pert Excercises - Bu
184/211
Risk is an uncertain event or condition, that if it occurs, has an
effect on at least one project objectives.
Objectives can include scope, schedule, cost, and quality.
A risk may have one or more causes and if it occurs, it mayhave one or more impacts.
A cause may be a requirement, assumption, constraint, orcondition that creates a possibilityof negative or positiveoutcomes.
Risk --- cause--- event/condition ---- impact (on projectobjectives)
Project Risk Management Project risks can be substantially decreased.
-
8/10/2019 Cpm & Pert Excercises - Bu
185/211
j y
Some studies quote a 90% decrease in projectproblems, through the use of risk management.
Through the process of risk management, wechange from the project controlling PM, to PMbeing in control of the project.
It focuses on proactively preventing things that cango wrong and helping things to go right.
Project Risk Management Individuals and groups adopt attitudes towards risk that
-
8/10/2019 Cpm & Pert Excercises - Bu
186/211
influence the way they respond.
These risk attitudes are driven by perception, tolerances, andother biases.
These factors must be made explicit whenever possible.
Risk responses reflect an organizations perceived balance
between risk - taking and risk - avoidance .
Moving forward on project, without a proactive focus on riskmanagement can potentially lead to project failure.
PROJECT RISK MANAGEMENT
-
8/10/2019 Cpm & Pert Excercises - Bu
187/211
A cause :
May be requiring an environmental permit to dowork.
Risk event: (probability)
Is permitting agency may take longer time thanplanned to issue a permit.
Project objective:( impact) Time over run.
PROJECT RISK MANAGEMENT A cause:
-
8/10/2019 Cpm & Pert Excercises - Bu
188/211
Having limited personnel assigned to designa project.
Risk event / condition: The design personnel available and assigned
may not be adequate for the activity. Impact on project objective: Cost, schedule ,or performance (quality).
Risk score=(probability)*(impact) forprioritization.
Definition conditions for Impact Scales of a Risk onFour Major Project Objectives
(examples are shown for negative impacts only)
Risk management planning
-
8/10/2019 Cpm & Pert Excercises - Bu
189/211
Very low.05
Low.1
Moderate.2
High.4
Very high.8
Projectobjective
Cost
Schedule
Scope
Quality
Insignificantcost increase
Insignificantsch slippage
Barely scopechange affect
noticeable
Low quality
barelynoticeable
20%sch slippage
Effectsprojectproduct
Effects
projectproduct
(examples are shown for negative impacts only)
probability and impact matrix
Risk management planning
-
8/10/2019 Cpm & Pert Excercises - Bu
190/211
Low impact Moderate impact High impact
Risk score (probability x impact) for a specific risk
0.18 0.36 0.72
0.28 0.56
0.20 0.40
0.24
0.04
0.03
0.02 0.03
0.01 0.01 0.02 0.04
0.05 0.09
0.07 0.14
0.05 0.10
0.06 0.12
0.08
0.05 0.10 0.20 0.40 0.80
ThreatsProbability0.9
0.7
0.5
0.3
0.1
Impact (Ratio scale) on an objective - cost, time, scope of quality
0.18 0.09 0.05
0.07 0.04
0.05 0.03
0.02
0.56
0.40
0.24 0.12
0.08 0.04 0.02 0.01
0.72 0.36
0.28 0.14
0.20 0.10
0.06 0.03
0.01
0.80 0.40 0.20 0.10 0.05
Opportunities
RISK SCORE
-
8/10/2019 Cpm & Pert Excercises - Bu
191/211
Risk event : govt may increase commercial tax. Likely Impact on the project objective: cost increase
-
8/10/2019 Cpm & Pert Excercises - Bu
192/211
Risk event: there may be strike on port.
Likely impact on the project objective: cost . Thecost of out put of the project may increase >20%.
Ref impact scale : very high (0.8)
The team assess the prob of this event happening=
0.4 The risk score of this event =(0.8)*(0.4)=0.32
This score is on RED. To be taken on top priorityfor response planning.
Risk Breakdown Structure(RBS)Project
-
8/10/2019 Cpm & Pert Excercises - Bu
193/211
Organizational Project Mgmt
Requirements
Technology
Complexity &Interfaces
Quality
Performance& Reliability
Subcontractors& Suppliers
Regulatory
Market
Weather
Customer
Projectdependencies
Resources
Funding
Prioritization
Estimating
Planning
Controlling
Communication
ExternalTechnical
Project Risk Management
The major steps of risk management are:-
-
8/10/2019 Cpm & Pert Excercises - Bu
194/211
The major steps of risk management are:
Creating a risk management plan. Identifying risks.
Analyzing risks.
Creating a risk response plan.
Monitoring and controlling risks through out theproject.
Project Management Risk can be threat or opportunity.
-
8/10/2019 Cpm & Pert Excercises - Bu
195/211
Responses for threat: Avoid, transfer, mitigate.
Responses for opportunity: Accept, enhance, share.
Passive acceptance and active acceptance.
Contingency plans.
Risk monitoring & control:
Work around plan to deal with secondary risks.
Project procurement management Plan procurements:
The process of documenting project purchasing decisions,
-
8/10/2019 Cpm & Pert Excercises - Bu
196/211
The process of documenting project purchasing decisions,
specifying the approach, and identifying potential sellers.
Conduct procurements:
The process of obtaining seller responses, selecting a seller,and awarding a contract.
Administer procurements:
The process of managing procurement relationships,monitoring contract performance, and making changes, andcorrections as needed.
Close procurements:
The process of completing each project procurement.
RFP Guide lines for drafting a formal request for proposal
for an contractor:
-
8/10/2019 Cpm & Pert Excercises - Bu
197/211
for an contractor:
An RFP must provide statement of work. Customer requirements.
What deliverables the customer expects the contractor orthe project team to provide.
Should list any customer- supplied items.
RFP might state approvals required by the customer.
Some RFP mention the type of contract the customer
intends to use.
An RFP might state the payment terms the customer
intends to use. Should state the required schedule for completion of the
project.
RFP
Should provide instruction for the format and the content ofthe contractors proposal
-
8/10/2019 Cpm & Pert Excercises - Bu
198/211
the contractor s proposal.
Should indicate the due date by which the customer expectspotential contractors to submit proposals.
May include evaluation criteria.
In rare cases an RFP will indicate the funds the customerhas available to spend on the project.
Preparing proposal Ensure that the proposal process is competitive.
A customer uses RFP to solicit competing proposals from
-
8/10/2019 Cpm & Pert Excercises - Bu
199/211
A customer uses RFP to solicit competing proposals from
contractors.
Submitting a proposal that meets the SOW of work andrequirements in the RFP is not sufficient to guarantee selection as thewinning contractor.
The customer will select the one that it expects will provide the bestvalue.
A proposal is a selling document.
In the proposal the contractor must convince the customer that thecontractor :
Understands what the customer is looking for. Can carry out the proposed project. Is the best contractor to solve the problem. Will provide the greatest value to customer. Will capitalize on its successful experience with previous related projects.
Preparing proposal
Will do the work professionally.
Will achieve intended results
-
8/10/2019 Cpm & Pert Excercises - Bu
200/211
Will achieve intended results.
Will complete the project within budget and on schedule.
Will satisfy the customer.
In the proposal the contractor must highlight the
unique factors that differentiate it from competingcontractors.
Must stress the benefits to the customer if the
customer selects the contractor to execute theproject.
Preparing proposal Proposal contents:
Technical.
-
8/10/2019 Cpm & Pert Excercises - Bu
201/211
Management. Cost.Technical section:
Objective is to convince the customer that the contractor understandsthe need or problem and can provide least risky and most beneficialsolution.
Understand the problem.
Proposed approach / solution.Benefits to the customer.
Management section:Description of work tasks.Deliverables.Project schedule.
Project organization.Related experience.Equipment and facilities.
Preparing proposal Cost section: The objective is to convince the customer that the contractors
price for the proposed project is realistic and reasonable
-
8/10/2019 Cpm & Pert Excercises - Bu
202/211
price for the proposed project is realistic and reasonable.
In some cases, the customer may want only the bottom line totalcost of the project.
Some customers also want to see the cost of optional items. Government RFP s usually require contractors to provide a
detailed breakdown of various costs. Labor. Materials. Subcontractors and consultants. Equipment and facilities rental. Travel. Documentation.
Overhead costs. Escalation. Contingency. Fee or profit.
Now I havean authorityto direct the
assigned
-
8/10/2019 Cpm & Pert Excercises - Bu
203/211
ProjectCHARTER,
resources on
project to:
manage
milestonesBudget
scope
Triple
Constraints
Project Integration Management
-
8/10/2019 Cpm & Pert Excercises - Bu
204/211
CONSISTS OF:
Develop project charter.
Develop project management plan.
Direct and manage project execution.
Monitor and control project work.
Integrated change control.
Close project.
Global project management
Globalization adds a unique dimension on projectmanagement
-
8/10/2019 Cpm & Pert Excercises - Bu
205/211
management. Cultural differences.
Multinational economic transactions.
Currency fluctuations and exchange rates.
Country-specific work codes and regulations, such as hoursper day, holidays, religious observances.
Interdependence of economies.
Corporate joint ventures and partnerships creating entitieswith a presence and facilities in multiple countries.
Political relations between countries.
Availability of high-demand work force skills.
Global project management Requires additional set of competencies:
To have foreign language skills.
-
8/10/2019 Cpm & Pert Excercises - Bu
206/211
Knowledge and understanding of other countries and cultures,geography, world history, and international economics (currencies, exchange rates, export /import transactions ).
Culture and customs ( meal times, eye contact, possible differing
roles of men and women, dress codes, religious practices, lines ofauthority, communication protocol etc. )
Etiquette (in some countries sitting with crossed leg is consideredas insult, or shaking hand, or touching some one of the oppositesex is frowned upon )
To have awareness of geo- political environment of the countriesof various project participants, in particular the country of thecustomer.
Global project management
Learning and understanding the culture and
-
8/10/2019 Cpm & Pert Excercises - Bu
207/211
customs of other project participants demonstratesrespect, helps build trust, aids in developing aneffective project team.
It is critical for the successful global projectmanagement.
Benefits of Project management
Project management is essential to business results.
-
8/10/2019 Cpm & Pert Excercises - Bu
208/211
Having a satisfied customer.
If youre a PM, you have the satisfaction of knowing you led asuccessful project effort.
You have enhanced your reputation as successful project managerand positioned your self for expanded career opportunities.
If you are a team member, you feel satisfaction of being on a winningteam.
You not only contributed to the projects success, but also probablyexpanded your knowledge and enhanced your skills along the way.
When th