counterfeit or fraudulent parts - atoms for peace and ... · • counterfeit or fraudulent parts...
TRANSCRIPT
Technical Meeting on Procurement Activities and on
Counterfeit, Fraudulent and Substandard Items
Vienna, 19–21 July
Samvel Ghazaryan
WANO Technical Programme Manager
Analysis of Events Caused by
Counterfeit or Fraudulent parts
WANO developed the report Analysis of Events Caused by Deficient Parts in May
2016.
� In total, 53 event reports were extracted from the WANO OE database for the
period 2012 to early 2016 and binned in three categories:
• incorrect part or material selection – 22 events
• manufacturing deficiencies – 21 events
• counterfeit or fraudulent parts -10 events
� The report includes event details and the lessons learned to help other plants
prevent similar events.
� Counterfeit components are a significant concern because the lower quality
and unexpected failure can reduce the margin of safety and introduce
unrecognised common mode failures. Counterfeit parts may function initially,
but then fail unexpectedly well before the expected end of life.
Analysis of Events Caused by counterfeit or
fraudulent parts
3
� Only 10 counterfeit part related event reports were submitted to
WANO. However, potential consequences from events are a large
vulnerability to nuclear safety and plant reliability when compared to
the other part related events.
� Eight of the 10 event reports are from WANO-Atlanta Centre plants. It
is likely that plants in other WANO regional centres have experienced
similar issues with counterfeit parts that have not been reported.
� Two of the counterfeit parts events were categorised as significant
and one as noteworthy based on the potential impact to nuclear
safety and common cause failure potential.
� Counterfeit items from recent operating experience included circuit
breakers, valves, O-rings, cables, electrolytic capacitors and pressure
gauges. Digital devices and software components are also vulnerable to
counterfeiting but events have not been reported to date.
Analysis of Events Caused by counterfeit or
fraudulent parts
4
The consequences from the 53 part related events fall into five categories: scram,
degraded operating condition, safety system impact, outage extension and other.
About 44% of the part quality related OE events reported to WANO involved
safety-related systems and 10% resulted in either an automatic or a manual
reactor scram.
Analysis of Events Caused by counterfeit or
fraudulent parts
5
Analysis of Event Causes
Weaknesses contributed to some of the counterfeit part issues.
� Some manufacturers knowingly produced fraudulent counterfeit products
indicating a lack of safety culture.
� In several events, quality assurance programmes were ineffective in
preventing the procurement and use of counterfeit parts.
� In one plant, inadequate supervision of contractors during maintenance
performed in a vendor shop led to not identifying the installation of
counterfeit injector O-rings in an emergency diesel generator (EDG), which
resulted in fuel leaks and EDG inoperability. This was a potential common
mode failure for a second EDG.
� Falsified documents contributed to four events. In one significant event,
falsified test reports were discovered for installed safety-related cables in
several operating units. The testing agency manipulated the test results to
show passing results for components that had failed the test. In another
event, the test certificates for 1,228 valves and components were found to be
counterfeit. 6
Analysis of Event Causes
� At one station, 16 counterfeit circuit breakers were identified. Fortunately, the
fraudulent breakers were identified during the receipt inspection process. The
breakers were not purchased through a certified OCM/OEM distributor.
� Pressure gauges installed in a plant were identified to be counterfeit. The
gauges had an unauthorised modification performed by the distributor.
� During an inspection, counterfeit circuit breakers were found installed at
seven electrical panels at a plant’s emergency power supply station.
Counterfeit breakers were installed during initial construction in 1991.
� During construction of a new unit, counterfeit lashing hooks were used for
transporting plant equipment. Although the certificates showed the hooks
were load tested and acceptable, further investigation found the hooks to be
counterfeit material. The suspect hooks had the potential to fail while in use
and could have resulted in personnel injury or damage to the equipment.
7
Significant Industry Events
WER ATL 14-0817, Segments of Installed Emergency Diesel Generators Power Packs with
Different Material than Indicated in Vendors Manual
What happened?
� During an outage, an evaluation identified that materials used in components
installed in emergency diesel generators (EDGs) were different from those
specified in the vendor manual.
Why it happened?
� 13 new components (power packs) were installed in EDGs during an outage
which had a composition of lead and bronze instead of lead and silver.
� There was no administrative process to establish the requirements for
identifying and managing fraudulent spare parts, as well as the technical
requirements for spare parts acquisition for quality control of components
installed in critical equipment.
Why a significant event?
� Because it resulted in the inoperability of EDGs I and III and a 23-day
extension of the refuelling outage. 8
Significant Industry Events
What happened?
� In November 2012, two units were shut down and
experienced extended outages to replace many
parts supplied with fraudulent certifications. The
items had been procured over the preceding 10
years. Some suppliers had provided commercial-
grade items with a certification fraudulently
stating that they had been successfully dedicated.
Items included fuses, relays, diodes and switches.
� In May 2013, two additional nuclear units were
shut down due to falsified test reports for installed
safety-related control cables. Outages at four
additional reactors were extended to replace
installed cables that failed the testing.
9
WER TYO 13-0053, Plants Shutdown due to Use of Cables with Fabricated Equipment
Qualification Test Report
Significant Industry Events
Why it happened?
� The test results for equipment qualification were falsified by local certified
testing institutes.
� The test results were manipulated in the reports to show passing results for
control cables that had failed the test.
Why a significant event?
� The units restarted in January 2014. The event is Significant because of its
widespread interest to WANO members potential impact to nuclear safety
and its effect on operation/construction of four units.
10
Significant Industry Events
WER MOW 15-0188, Counterfeit Material Test Certificates
What happened?
� Test certificates for 1,228 valves and components were discovered to be
counterfeit. In 204 cases, specifications could not be guaranteed due to
fabricated certificates. Four valves could not be verified after additional
checks. Two valves assembled at the plant were replaced and two valves were
quarantined. Another two hundred valves were verified to fulfil the
specifications.
Why it happened?
� Weaknesses in the supply chain. Gaps in approval of suppliers – insufficient
onsite audits and not verifying the management system under which they
operate, relying on certificates issued by third parties.
Why a noteworthy event?
� Because of safety significance and widespread interests related to counterfeit
certificates.
11
Strategies for prevention, early detection and mitigation of
component failures related to counterfeit parts.
� Based on the events reported to WANO, stations found weaknesses in quality
programmes and training related to counterfeit parts. Some stations have a weak or no
policy to provide sufficient focus on preventing counterfeit parts in the supply chain.
� Procurement personnel are challenged by obsolete equipment and sometimes rely on
commercial grade items from various suppliers for replacements. Items from the
original component or equipment manufacturer (OCM/OEM) may no longer be
available or the manufacturer might not be willing to support the required rigorous
testing and documentation.
� As the number of replacement parts from new sources increase, unaware and
unsuspecting suppliers can unknowingly purchase and use substandard or counterfeit
materials or subcomponents in the manufacture of larger components.
Lessons Learned
12
Key elements to guard against counterfeit items
� A proactive approach should be used for prevention and early detection of
counterfeit component.
� Establish process and governing procedures with requirements for detecting and
managing counterfeit spare parts. Revise existing guidelines or procedures that
address counterfeit items, to include inspection requirements and actions to be
performed when a counterfeit item is identified.
� Train applicable station personnel on counterfeit item prevention techniques,
including personnel from the utility’s supply chain, procurement, engineering and
work planning departments. Also train personnel that prepare technical
specifications and procurement documentation for new units before and during
construction. Training should be conducted on the requirements to look for
counterfeit parts and the impact on nuclear safety and reliability. Sources of
training materials regarding counterfeit item prevention are publically available.
Lessons Learned
13
� Obtain parts directly from the original component manufacturer
(OCM)/original equipment manufacturer (OEM) whenever possible as this will
result in the lowest risk of purchasing counterfeit components.
� OCM/OEM authorised distributors typically have documented agreements
with a manufacturer to sell their items.
� Improve the component procurement process to prevent the installation
of substandard and counterfeit items.
� Key elements for effective procurement include engineering involvement in
procurement and product acceptance, effective source inspection,
thorough receipt inspection and testing, and rigorous programmes for the
testing and dedication of commercial-grade products that may be suitable
for use in both safety-related and critical applications.
Lessons Learned
14
� Counterfeit part detection – know the warning signs.
� Item coming from a source other than the OCM or authorised
sources, or from suspect locations
� Price seems too low
� Scarce or obsolete items are suddenly available
� Chain of ownership unverifiable
� No certificate of conformance or other authenticity documentation
� Item does not exactly match similar items
� Packaging is nonstandard
� Item appears to be reworked, repaired or refurbished
� Quality is suspect
Lessons Learned
15
� Minimising potential plant impact – If using a supplier that is not the
OCM/OEM or is not OCM/OEM authorised (and there is no other alternative
than to use a third party supplier) then notify procurement personnel for
direction and approval. Quarantine parts from potentially high risk suppliers
until required testing and verification is complete. Treat these items as
suspect until authenticated. Obtain traceability or chain of custody
information, or authenticity testing records associated with the suspect part.
� Counterfeit parts identified – If the item is suspected to be counterfeit,
quarantine and identify it as non-conforming. Do not return the item to the
supplier to prevent resale to another customer. Notify appropriate legal
authorities. Submit an event report to WANO.
� Ensure operating experience personnel collect, evaluate and distribute
industry information and events regarding counterfeit parts.
Lessons Learned
� Many new nuclear units are planned or under construction and the number of counterfeit products are likely to continue to increase. Proactive strategies and processes are essential for detecting and preventing the introduction of counterfeit components into nuclear applications.
� Lessons learned from counterfeit or fraudulent events are important to share globally with all NPPs.
� So please ensure these events are reported to the WANO event database. The database is confidential and can only be used by WANO members.
In Closing…..
For more information please visit
www.wano.info
Thank you for listening