correctors for the j-parc proton beam line
DESCRIPTION
Correctors for the J-PARC Proton Beam Line. Peter Wanderer BNL Superconducting Magnet Div. September 8, 2007 T2K US B280 Collaboration Mtg. N. 50GeV PS. 3GeV PS. Neutrino Beam Line. 600MeV Linac. FD. To SK. JHF project and neutrino beam line. JAERI@Tokai-mura (60km N.E. of KEK). - PowerPoint PPT PresentationTRANSCRIPT
Correctors for the J-PARC Proton Beam Line
Peter WandererBNL Superconducting Magnet Div.
September 8, 2007T2K US B280 Collaboration Mtg.
600MeV Linac
3GeV PS
50GeV PS
N
FD
Neutrino Beam Line
To SKJHF NuMI(FNAL)
K2K
E(GeV) 50 120 12
Int.(1012ppp)
330 40 6
Rate(Hz) 0.27
0.53 0.45
Power(MW)
0.75
0.41 0.0052
JAERI@Tokai-mura(60km N.E. of KEK)
1021POT(130day)≡ “1 year”
Use Super Con.mag. in line
JHF project and neutrino beam line
11 February 2005 T2K proton line correctors 3
What’s Needed
Dipole correctors:– Corrector = vertical + horizontal
windings, one wound over the other– Three correctors to install + two spares– Overall Schedule:
• Prototype (= 1 spare) now at KEK• Remaining four at JAERI by Dec. 31, 2007
– three months earlier than previously stated.– Change in schedule is due to revised estimate of
installation plans
11 February 2005 T2K proton line correctors 4
Corrector Parameters
- NbTi superconducting wire, 0.33 mm Ø (used for RHIC correctors) Bdl = 0.1 T·m; Lmagnetic = 522 mm– Bpeak = 0.2 T, Bquench > 6T
Significant temperature margin for operation
– Iop = 43A– Inner diameter = 150 mm– Slot length = 800 mm– Located between main magnets
conduction cooling thick-walled Cu tube
11 February 2005 T2K proton line correctors 5
Coil Winding
Precision semi-automatic winding machine developed for other projects.
11 February 2005 T2K proton line correctors 6
Test Results of Prototype
• 4.5 K, liquid helium• Test coil only (yoke added by KEK)• Test to ± 90A to obtain same field as
will be produced at 43A with yoke on.• Reached 90A without quenching
excellent performance.• Measure integral fields, field
uniformity across aperture ok
11 February 2005 T2K proton line correctors 7
Cost
• Cost basis:– Prototype construction– Construction of similar magnets for
HERA collider at DESY and BEPC upgrade
• Correctors – four - production, testing, shipment to Japan: $500k– Includes 13% contingency, all
overheads.
11 February 2005 T2K proton line correctors 8
Progress Report
• “Early” (i.e., “just in time”) start made possible by Stony Brook:– Copper forgings (cylindrical support
tubes) ordered by Stony Brook• 1 forging rec’d by BNL, machining starts
Monday• 4 forgings shipped to BNL yesterday
– $120k advance funding to BNL from Stony Brook Research Foundation
– Thanks to Chang Kee and Joan!
11 February 2005 T2K proton line correctors 9
“Just in time”• Technical: BNL has two automatic
winding machines (not identical)– Had planned to use just one– Will use both to meet schedule
• Financial: “no delays due to $” – Advance for remainder of budget (DOE
requires “no working ahead of funding”)– Prompt billing by BNL– Prompt payment by Stony Brook/NY state
11 February 2005 T2K proton line correctors 10
Forging in BNL Lathe
11 February 2005 T2K proton line correctors 11
Cost status
• Forgings– Estimated @ $3k each $15k total– Actual cost $28k
• BNL machine shop costs– Increased from $90/hr to $115/hr