correctors for the j-parc proton beam line

11
Correctors for the J- PARC Proton Beam Line Peter Wanderer BNL Superconducting Magnet Div. September 8, 2007 T2K US B280 Collaboration Mtg.

Upload: gage

Post on 14-Jan-2016

48 views

Category:

Documents


0 download

DESCRIPTION

Correctors for the J-PARC Proton Beam Line. Peter Wanderer BNL Superconducting Magnet Div. September 8, 2007 T2K US B280 Collaboration Mtg. N. 50GeV PS. 3GeV PS. Neutrino Beam Line. 600MeV Linac. FD. To SK. JHF project and neutrino beam line. JAERI@Tokai-mura (60km N.E. of KEK). - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Correctors for the J-PARC Proton Beam Line

Correctors for the J-PARC Proton Beam Line

Peter WandererBNL Superconducting Magnet Div.

September 8, 2007T2K US B280 Collaboration Mtg.

Page 2: Correctors for the J-PARC Proton Beam Line

600MeV Linac

3GeV PS

50GeV PS

N

FD

Neutrino Beam Line

To SKJHF NuMI(FNAL)

K2K

E(GeV) 50 120 12

Int.(1012ppp)

330 40 6

Rate(Hz) 0.27

0.53 0.45

Power(MW)

0.75

0.41 0.0052

JAERI@Tokai-mura(60km N.E. of KEK)

1021POT(130day)≡ “1 year”

Use Super Con.mag. in line

JHF project and neutrino beam line

Page 3: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 3

What’s Needed

Dipole correctors:– Corrector = vertical + horizontal

windings, one wound over the other– Three correctors to install + two spares– Overall Schedule:

• Prototype (= 1 spare) now at KEK• Remaining four at JAERI by Dec. 31, 2007

– three months earlier than previously stated.– Change in schedule is due to revised estimate of

installation plans

Page 4: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 4

Corrector Parameters

- NbTi superconducting wire, 0.33 mm Ø (used for RHIC correctors) Bdl = 0.1 T·m; Lmagnetic = 522 mm– Bpeak = 0.2 T, Bquench > 6T

Significant temperature margin for operation

– Iop = 43A– Inner diameter = 150 mm– Slot length = 800 mm– Located between main magnets

conduction cooling thick-walled Cu tube

Page 5: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 5

Coil Winding

Precision semi-automatic winding machine developed for other projects.

Page 6: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 6

Test Results of Prototype

• 4.5 K, liquid helium• Test coil only (yoke added by KEK)• Test to ± 90A to obtain same field as

will be produced at 43A with yoke on.• Reached 90A without quenching

excellent performance.• Measure integral fields, field

uniformity across aperture ok

Page 7: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 7

Cost

• Cost basis:– Prototype construction– Construction of similar magnets for

HERA collider at DESY and BEPC upgrade

• Correctors – four - production, testing, shipment to Japan: $500k– Includes 13% contingency, all

overheads.

Page 8: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 8

Progress Report

• “Early” (i.e., “just in time”) start made possible by Stony Brook:– Copper forgings (cylindrical support

tubes) ordered by Stony Brook• 1 forging rec’d by BNL, machining starts

Monday• 4 forgings shipped to BNL yesterday

– $120k advance funding to BNL from Stony Brook Research Foundation

– Thanks to Chang Kee and Joan!

Page 9: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 9

“Just in time”• Technical: BNL has two automatic

winding machines (not identical)– Had planned to use just one– Will use both to meet schedule

• Financial: “no delays due to $” – Advance for remainder of budget (DOE

requires “no working ahead of funding”)– Prompt billing by BNL– Prompt payment by Stony Brook/NY state

Page 10: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 10

Forging in BNL Lathe

Page 11: Correctors for the J-PARC Proton Beam Line

11 February 2005 T2K proton line correctors 11

Cost status

• Forgings– Estimated @ $3k each $15k total– Actual cost $28k

• BNL machine shop costs– Increased from $90/hr to $115/hr