cook - nrc activities related to the fukushima task force flooding and seismic hazard...
DESCRIPTION
Reactor Session, 21.03.2012TRANSCRIPT
NRC Activities Related to the
Fukushima Task Force Flooding and
Seismic Hazard Recommendations
Christopher Cook, Ph.D.
Chief, Geoscience and Geotechnical Engineering Branch
Division of Site Safety and Environmental Analysis
Office of New Reactors
21 March 2012
2
Outline
• Background
• Scope
• Overall Approach
• Hazard Reevaluation
• Walkdowns
• Schedules
3
Background
• NRC established the Near-Term Task Force (NTTF) in response to events at Fukushima Dai-ichi in March 2011
• NTTF developed a set of twelve overarching recommendations
• Recommendation Two included:
– Flooding Hazard Reevaluations and Walkdowns
– Seismic Hazard Reevaluations and Walkdowns
4
Scope: NTTF Recommendation 2.1
• Reevaluate hazards at all operating reactor sites
• Collect information to facilitate NRC’s determination if there is a need for additional regulatory actions
• Gather information to address ongoing Generic Issues related to:
– Updated seismic hazards since the plant was licensed (GI-199)
– New information on plant safety following upstream dam failures (GI-204)
5
Scope: NTTF Recommendation 2.3
• Develop seismic and flooding walkdown procedures
• Perform walkdowns using NRC-endorsed walkdown methodology
• Identify and address degraded, non-conforming or unanalyzed conditions
• For flooding hazards only, identify and address any cliff-edge effects
NTTF defined “Cliff-Edge” effect: safety consequence of a flooding event may increase sharply with a small increase in flooding level.
6
Overall Approach: R2.1
• Recommendation 2.1 will be implemented in two phases: – Phase 1:
• Licensees reevaluate flooding and seismic hazards using present-day regulatory guidance and methodologies
• If necessary, perform an integrated/risk assessment following the hazard reevaluation
– Phase 2:
• Based on results of Phase 1, NRC will determine if further regulatory actions are necessary to protect against the updated hazard
7
Recommendation 2.1 Evaluation
Licensees Conduct
Hazard Reevaluation
NRC & Stakeholders
Interact on
Integrated/Risk
Assessment Guidance
NRC Reviews Hazard
Reevaluation and Near-
Term Actions
Licensees Conduct
Integrated/Risk
Assessment, as needed
NRC Reviews
Integrated/Risk
Assessment and
Additional Actions
NRC to make Regulatory
Decisions, as needed:
* Safety Enhancements
* Backfit Analysis
* Modify Plant License
PHASE 1
STAGE 1 STAGE 2
PHASE 2
8
R 2.1: Flooding Hazard Reevaluation • Hazard reevaluation should be consistent with
regulatory guidance and methodologies used for Early Site Permit (ESP) and Combined License (COL) reviews – NUREG-0800, “Standard Review Plan” Section 2.4
– NUREG/CR-7046, “Design Basis Flood Estimate for Site Characterization of Nuclear Power Plants in the USA”
• Evaluation should discuss all flood-causing mechanisms.
• Mechanisms that are not applicable at a site may be screened-out; however, a justification should be provided.
Use this elevation for this
causal mechanism in Step 3 Yes
Is the reevaluated flood
hazard elevation greater
than the current design
elevation?
No
No
No
Yes
Yes
Re-evaluate flood hazard based on present day guidance and methodology
(HHA) for each flood causing mechanism (e.g. local intense precipitation)
2a
1
2
Select one flood causing mechanism for analysis
2b
Develop conservative estimate for site-related parameters using simplifying
assumptions for a flood causing mechanism
Can parameter and/or
variables in analysis be
further refined?
Use site-specific data to refine
analysis
Compile data for site flood hazard
To Page 2
Have all flood causing
mechanisms identified in
Step 2 been addressed?
9
10
3
Submit the final report
No
Yes
Compare the final flood
elevations for all re-evaluated
flood causing mechanisms to
current design basis flood.
Does the design basis flood
elevation bound the
reevaluated flood hazard for all
mechanisms?
Submit hazard re-evaluation reports and plan for
conducting an integrated assessment
Perform an integrated assessment of the plant
performance
Identify vulnerabilities, if any, and actions planned
or taken during the re-evaluation
Submit hazard re-evaluation results
Phase 2
6
7
8
4
5
9
10
From Page 1
No further action
10
R2.1: Seismic Hazard Reevaluation
• Determine Ground Motion Response
Spectrum (GMRS) for Site
– Use Probabilistic Method (PSHA)
• Seismic Source Models
• Seismic Ground Motion Models
• Site Response Evaluation
• Compare GMRS with Safe Shutdown
Earthquake (SSE) with Plant
Spectrum 11
R2.1 Seismic Hazard Reevaluation
• New seismic source models for Central
and Eastern United States of America
(CEUS) developed jointly by NRC, Dept
of Energy, and Electric Power Research
Institute (EPRI)
www.ceus-ssc.com
• EPRI (2004, 2006) ground motion
prediction equations for CEUS
12
R2.1: Seismic Risk Evaluation
• Depending on Screening Criteria perform
– Seismic Margin Analysis (SMA) or
– Seismic Probabilistic Risk Assessment (SPRA)
• SMA method is NRC SMA (NUREG/CR-
4334) with enhancements.
• SPRA approach is Level 1 with estimate of
Large Early Release Frequency (LERF)
described in RG 1.200.
13
R2.1 Seismic
14
15
Overall Approach: R2.3 Walkdowns • Licensees and staff interact to develop walkdown methodology
– Procedures
– Training
– Staffing
• Integrate the combined effects of flooding along with other adverse weather conditions, such as high winds, hail, lightning, etc, that could simultaneously occur.
• Integrate insights from any new and relevant flood hazard information, as well as recent flood-related walkdowns.
• Identify any changes since the original licensing (security improvements/temporary structures) and review flood protection/mitigation features.
16
Overall Approach: R2.3 (continued)
• Licensees perform the walkdowns using NRC-endorsed walkdown methodology
• Identify and address degraded, non-conforming or unanalyzed conditions addressed by licensee’s corrective action program
• Identify and address cliff-edge effects for flooding only. Addressed by licensee’s corrective action program.
17
Flooding Recommendations Schedules
• Recommendation 2.1: hazard – Develop approach for Integrated Assessment by
approximately November 2012.
– Complete Hazard Evaluations within 1 to 3 years. Include plans for Integrated Assessment, if necessary.
– Complete Integrated Assessment within 2 years following Hazard Evaluation, if necessary.
• Recommendation 2.3: walkdown – Inform within 90-days of walkdown procedure.
– Complete and submit walkdown response by approximately November 2012.
All dates are from 12 March 2012
18
Seismic Recommendations Schedules
• Recommendation 2.1: hazard – Develop approach for Risk Assessment by approximately
November 2012.
– Complete Hazard Evaluations within 1.5 years for Central and Eastern USA sites. For Western USA sites, complete within 3 years. Include plans for Risk Assessment, if necessary.
– Complete Risk Assessment within 3-4 years following Hazard Evaluation, if necessary.
• Recommendation 2.3: walkdown – Inform within 120-days of selected walkdown procedure.
– Complete and submit walkdown response by approximately November 2012.
All dates are from 12 March 2012
19
Questions ?