cont analysis
TRANSCRIPT
-
8/2/2019 Cont Analysis
1/17
Contingency Analysis
-
8/2/2019 Cont Analysis
2/17
AbstractIn this presentation the development of a simple and fast method to calculate a new
set of distribution factors using the sensitivity property of Newton Raphson load flow
of jacobian at a base operating point has been shown.
The accuracy of post outage results using these distribution factors has beenestablished with respect to full AC load flow results on IEEE14-bus system by using
Newton raphson method.
-
8/2/2019 Cont Analysis
3/17
Proposed Distribution Factors
In the voltage security or reactive power security studies, the effect of line/transformer or
generator outages on the system voltage profile and reactive power output of sources are
required to be computed.
Two groups of distribution factors have been suggested they are
The vo ltage distribution factors which can be used to compute the post-outage voltage profilein the system .
The reactive power distribution factors which can be used to compute the post-outage output ofthe reactive power sources.
For a line/transformer outage, these factors have been termed as Line outage voltagedistribution factors (LO VDFs) and Line outage reactive power d istribution factors (LOQ DFs),respectively.
In the case of a generator outage, they have been termed as theGenerator outage voltagedistribution factors (GO VDFs) and the Generator outage reactive power distribution factors(GOQDFs),respectively.
-
8/2/2019 Cont Analysis
4/17
Consider the outage of a line or a transformer-l carrying an average real power PlTand
reactive power QlTdefined as
-
8/2/2019 Cont Analysis
5/17
Line ou tage distribution factors
i) Line outage voltage distribution factors
ii) Line outage Reactive power distribution factors
-
8/2/2019 Cont Analysis
6/17
Generator outage distribution factors
i) Generator outage voltage distribution factors
ii) Generator outage reactive power distribution factors
i=1,,N & g=1,.,Ng
j=1,,Nq& g=1,.,Ng
-
8/2/2019 Cont Analysis
7/17
Post contingency voltage profile and reactive power output of the system
For line outage
For generator outage
-
8/2/2019 Cont Analysis
8/17
Calculation of distribution factors
-
8/2/2019 Cont Analysis
9/17
i) Line outage voltage distribution factors
-
8/2/2019 Cont Analysis
10/17
ii) Generator outage voltage distribution factors
iii) Line outage Reactive power distribution factors
iv) Generator outage reactive power distribution factors
-
8/2/2019 Cont Analysis
11/17
Results and discussion
The accuracy of post outage results using these distribution factors has been
established with respect to full AC load flow results on IEEE14-bus system by
using Newton raphson method.
LINE FLOWS
LINE FROM BUS TO BUS REAL REACTIVE
1.0000 1.0000 2.0000 1.5705 -0.1713
2.0000 1.0000 5.0000 0.7495 0.07073.0000 2.0000 3.0000 0.7588 -0.1556
4.0000 2.0000 4.0000 0.5544 0.0063
5.0000 2.0000 5.0000 0.4125 0.0399
6.0000 3.0000 4.0000 -0.2099 0.2754
7.0000 4.0000 5.0000 -0.5894 0.1669
8.0000 4.0000 7.0000 0.2734 0.0477
9.0000 4.0000 9.0000 0.1571 0.0672
10.0000 5.0000 6.0000 0.4536 0.1966
11.0000 6.0000 11.0000 0.0799 0.0739
12.0000 6.0000 12.0000 0.0799 0.030013.0000 6.0000 13.0000 0.1818 0.0924
14.0000 7.0000 8.0000 0.0000 -0.1109
15.0000 7.0000 9.0000 0.2734 0.1429
16.0000 9.0000 10.0000 0.0466 0.0055
17.0000 9.0000 14.0000 0.0889 0.0128
18.0000 10.0000 11.0000 -0.0434 -0.0527
19.0000 12.0000 13.0000 0.0181 0.0122
20.0000 13.0000 14.0000 0.0621 0.0414
1.0000 2.0000 1.0000 -1.5259 0.2511
2.0000 5.0000 1.0000 -0.7210 -0.0037
3.0000 3.0000 2.0000 -0.7321 0.22194.0000 4.0000 2.0000 -0.5373 0.0076
5.0000 5.0000 2.0000 -0.4031 -0.0456
6.0000 4.0000 3.0000 0.2182 -0.2894
7.0000 5.0000 4.0000 0.5945 -0.1633
8.0000 7.0000 4.0000 -0.2734 -0.0320
9.0000 9.0000 4.0000 -0.1571 -0.0517
10.0000 6.0000 5.0000 -0.4536 -0.1423
11.0000 11.0000 6.0000 -0.0788 -0.0716
12.0000 12.0000 6.0000 -0.0791 -0.0282
13.0000 13.0000 6.0000 -0.1792 -0.087214.0000 8.0000 7.0000 -0.0000 0.1130
15.0000 9.0000 7.0000 -0.2734 -0.1326
16.0000 10.0000 9.0000 -0.0466 -0.0053
17.0000 14.0000 9.0000 -0.0878 -0.0106
18.0000 11.0000 10.0000 0.0438 0.0536
19.0000 13.0000 12.0000 -0.0180 -0.0121
20.0000 14.0000 13.0000 -0.0612 -0.0394
-
8/2/2019 Cont Analysis
12/17
Considering the outage of heavily loaded line 3 connecting busses 2 and 3
Program Output :
CONTINGENCY ANALYSIS
Press 1 for line outage
Press 0 for generator outage
1
enter the line number where outage has occurred 3
ap =
-0.0022
0
0.0385
-0.0095
-0.0079
-0.0094
-0.0103
-0.0103
-0.0106
-0.0105
-0.0101
-0.0096
-0.0098
-0.0105
aq =
-0.0021
0
0.1099
-0.0145
-0.0106
-0.0136
-0.0150
-0.0150
-0.0150
-0.0149
-0.0143
-0.0140
-0.0141
-0.0150
v_profile =
1.0356
1.0230
0.9930
0.9391
0.9503
0.9446
0.9287
0.9287
0.9137
0.9106
0.9233
0.9265
0.9199
0.8956
c_p =
0.2008
0.2204
0.1471
0.4289
0.3069
0.00700.1913
0.0000
0.1173
0.0153
0.0123
0.0244
0.0567
0.0509
c_q =
0.2003
0.2247
0.1508
0.4349
0.3076
0.0070
0.1928
0.0000
0.1184
0.0155
0.0124
0.0246
0.0571
0.0513
post_reac =
0.1946
0.3418
0.3336
0.4174
0.3138
0.0818
0.1859
0.0000
0.2801
0.0729
0.0300
0.0397
0.1131
0.0994
-
8/2/2019 Cont Analysis
13/17
Average real power PlTand reactive power Ql
T are Computed from base load flow equations
Hence LOVDFS are calculated.
Using the new computed values of voltage magnitudes and angles, the reactive power output at
the source buses and hence, the change in their reactive power outputs from pre-outage to post-
outage condition can be computed. The change in reactive power output of the source-g due to
only real power and only reactive power outage of the line can be written as
Note that
Hence LOQDFs are calculated.
-
8/2/2019 Cont Analysis
14/17
Similarly for GOVDFs and GOQDFs are calculated by calculating appropriate power
mismatches and multiplying with sensitivity matrix.
In this presentation results are to be shown for outage of Generator at bus 1 which hasthe maximum generating capacity from base load flow.
GENERATION LOAD
BUS VOLTS ANGLE REAL REACTIVE REAL REACTIVE
1.0000 1.0400 5.1602 2.3200 -0.1006 0 0
2.0000 1.0230 0 0.4168 0.2687 0.2170 0.1270
3.0000 1.0253 -8.5783 0.0000 0.6874 0.9420 0.1900
4.0000 0.9915 -5.4450 0 0 0.4780 0.0000
5.0000 0.9925 -3.8653 0 0 0.0760 0.0160
6.0000 1.0240 -9.8830 0.0000 0.1289 0.1120 0.0750
7.0000 1.0056 -8.6601 0 0 -0.0000 -0.0000
8.0000 1.0250 -8.6601 -0.0000 0.1130 0 0
9.0000 0.9904 -10.3908 0 0 0.2950 0.1660
10.0000 0.9884 -10.6112 0 0 0.0900 0.0580
11.0000 1.0023 -10.3787 0 0 0.0350 0.018012.0000 1.0070 -10.8140 0 0 0.0610 0.0160
13.0000 1.0006 -10.8655 0 0 0.1350 0.0580
14.0000 0.9758 -11.7193 0 0 0.1490 0.0500
-
8/2/2019 Cont Analysis
15/17
Considering the outage of Generator at bus 1 which has the maximum generating
capacity from base load flow.
Program Output :
CONTINGENCY ANALYSIS
Press 1 for line outage
Press 0 for generator outage
0
enter the line number where outage has occurred 1
bgp =
-0.0123
-0.0099
-0.0010
-0.0021
-0.0025
-0.0028
-0.0023
-0.0023
-0.0023
-0.0024
-0.0026
-0.0028
-0.0028
-0.0026
bgq =
0
0
0
0
0
0
0
0
0
0
0
0
0
0
dgp =
0.0891
0.1031
0.0619
0.1851
0.1297
0.0029
0.0828
0.0000
0.0509
0.0066
0.0053
0.0105
0.0244
0.0220
dgq =
0
0
0
0
0
0
0
00
0
0
0
0
0
v_profile =
1.0090
1.0000
0.9356
0.9448
0.9529
0.9483
0.9346
0.9346
0.9197
0.9163
0.9281
0.9304
0.9241
0.9009
post_reac =
0.2068
0.3661
0.3336
0.4294
0.3169
0.0818
0.1922
0.00000.2840
0.0734
0.0303
0.0404
0.1147
0.1010
-
8/2/2019 Cont Analysis
16/17
LOVDFS & LOQDFS are calculated for line outage and they are used to calculate post
contingency voltage profile and reactive power outputs.
GOVDFS & GOQDFS are calculated and are used to calculate post contingency voltage
profile and reactive power outputs.
All the above calculations were carried out and they are to be compared with NR method in
terms of speed and accuracy.
-
8/2/2019 Cont Analysis
17/17